M/s ABCI Infrastructure Private Limited v. Union of India and Others

Case / Petition Number:
Civil Appeal a/o. SLP (C) No. 25394 of 2023

Case Synopsis & Summary

This Supreme Court Civil Appeal concerns a public procurement dispute arising from a complex highway/tunnel project at Shinkun La Pass. The Border Roads Organisation (BRO), under the Ministry of Defence, invited bids for design and construction of two-lane twin tunnels (~4.1 km) with extensive civil, electrical, and mechanical work. ABCI Infrastructure Private Limited (the appellant) submitted bids; it was declared L-1 with a quoted price of Rs. 1,569 crores, though the bid note displayed Rs. 1,569 only due to a claimed system glitch. ABCI informed BRO that the intended bid was Rs. 1,569 crores, not Rs. 1,569; however, BRO insisted on sticking to the apparent figure and sought a detailed price justification. Despite ABCI’s requests to withdraw, BRO, guided by the Evaluation Committee, pressed ahead, ultimately encashing the bank guarantee and inviting fresh bids. ABCI challenged this in a writ petition before the Himachal Pradesh High Court, which was dismissed. The core issue before the Supreme Court was whether BRO’s actions in accepting the erroneous bid and forfeiting the bank guarantee were justified, or whether equitable relief could be afforded to rectify a unilateral and obvious error in a public bid. The Court ultimately held that the error was self-evident but did not fall within established exceptions for equitable relief; instead, it directed a partial remedy, balancing fairness with procurement integrity.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Sanjiv Khanna
  • Sanjay Kumar
  • K. V. Viswanathan
Judgment Date
2025-02-14
Court Decision / Holding
The impugned judgment is set aside, and the appeal is allowed in the afore-said terms. The appellant is directed to pay Rs. 1 crore to BRO as a consequence of the error. Upon payment, BRO shall return the appellant’s original bank guarantee or demand draft of Rs. 15.04 crores within one week. There would be no order as to costs.
Final Disposition
Appeal allowed; impugned judgment set aside; appellant directed to pay Rs. 1 crore to BRO; BRO to return the bank guarantee of Rs. 15.04 crores within one week; no order as to costs.

Parties to the Case

Appellants / Petitioners

  • M/s ABCI Infrastructure Private Limited

Respondents

  • Union of India
  • Border Roads Organisation (BRO) under the Ministry of Defence

Provisions of Law Cited

Section 20 of the Indian Contract Act, 1872

Legal Doctrines & Maxims

  • Unilateral or mutual mistake (as a matter of fact) is typically unintentional; a mistake can render an agreement void.
  • Equitable relief may be available where a bidder makes a material mistake of fact in a public bid and acts promptly to withdrawal before contract formation.
  • Doctrine of proportionality in judicial review as applied to administrative/contractual actions.
  • Principle of transparency and fairness in public procurement; high standards for evident mistakes and avoidance of manipulation.

Submissions & Arguments

Contentions of Appellants / Petitioners

ABCi argued that the quoted price of Rs. 1,569 crores was the intended bid; the displayed Rs. 1,569 was a patent, self-evident clerical/technical error or system glitch. They stated they promptly informed BRO and sought withdrawal or rectification before contract liability attached; reliance on established equity principles (as in West Bengal State Electricity Board) to permit relief was urged. They contended that encashment of the bank guarantee and default declaration were unjust given the mistake was obvious and promptly disclosed.

Contentions of Respondents

BRO contended that the bid must stand as submitted; it argued that prize undervaluation would defeat fair competition and transparency; it maintained that the bank guarantee was rightly encashed and that only a contractual remedy (or re-bid) could be honored; the delay and failure to follow bidding rules justified forfeit/encashment; asserted that equitable relief was not warranted given procurement integrity.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
West Bengal State Electricity Board v Patel Engineering Co. Ltd. & Others2001 (2) SCC 451PositiveUsed to articulate exceptions to the general rule against relief in bids; the court acknowledges the principle and the exceptions from this decision, but finds the present case does not fall within those exceptions.
Moffett, H. & C. Co. v. Rochester178 U.S. 373 (1900)Mentioned OnlyCited as part of general authority on equitable relief for obvious mistakes, without being the primary basis for the decision.
Hearne v. New England Marine Ins. Co.22 L. Ed. 395Mentioned OnlyCited in context of general principles about mistakes and equitable relief; not a controlling factor in the outcome.
Spina Asphalt Paving Excavating Contractors, Inc. v. Borough of Fairview304 NJ Super 425Mentioned OnlyReferenced regarding rectification of bid specifications and the caution that price errors are generally material unless clearly obvious.
M/s Omsairam Steels & Alloys Pvt. Ltd. v. Director of Mines and Geology, BBSR & Ors2024 INSC 520PositiveUsed to discuss proportionality in the context of judicial review of contractual matters.
Coimbatore District Central Cooperative Bank v. Coimbatore District Central Cooperative Bank Employees Association and Another(2007) 4 SCC 669PositiveCited to elaborate the proportionality concept and balancing in decision-making.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,493 words•~12 min read

In The Court Record

M/s ABCI Infrastructure Private Limited v. Union of India and Others

2025 INSC 215 **REPORTABLE** **==> picture [72 x 72] intentionally omitted <==** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. OF 2025** **(Arising out of Special Leave Petition (Civil) No. 25394 of 2023)** M/S. ABCI INFRASTRUCTURES PVT. LTD. ..... APPELLANT VERSUS UNION OF INDIA AND OTHERS ..... RESPONDENTS ## **J U D G M E N T** ## **SANJIV KHANNA, CJI.** Leave granted. 2. This is an avoidable litigation. No doubt, there was a mistake on the part of the Appellant – M/s ABCI Infrastructure Private Limited, _albeit,_ instead of taking a pragmatic approach, Respondent No. 2 - Border Signature Not Verified Digitally signed by babita pandey Date: 2025.02.14 16:33:26 IST Reason: _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 1 of 12**_ Road Organisation[1] under the Ministry of Defence, Union of India, adopted an obdurate and overly legalistic stance, causing a delay in the project's execution. 3. We begin by briefly discussing the facts of the case: - On 23.02.2023, BRO invited bids for the design and construction of two-lane twin tunnels, approximately 4.1 kilometres long, at Shinkun La Pass, including civil, electrical, and mechanical work, with approaches connecting the Darcha-Padam Highway to NHDL specifications in Himachal Pradesh and Ladakh. The estimated cost of the project was Rs.15,04,64,00,000/- (Rs. 1,504.64 crores). The project was to be completed within 48 months. The bid security amount was Rs.15,04,64,000/- (Rs. 15.04 crores) - Ten bidders, including the Appellant, had submitted their online Technical and Financial Bids on 03.06.2023. The Appellant, like others, had furnished a bank guarantee of Rs.15,04,64,000/-. - On 05.06.2023, technical bids were opened and seven bidders, including the Appellant, were declared technically qualified. - On 24.08.2023, the financial bids of seven bidders, including the Appellant, were opened and the results were declared. > 1 Hereinafter, “BRO.” _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 2 of 12**_ - The Appellant was ranked as L-1 bidder, with the bid price of Rs.1,569/- (Rupees One thousand five hundred and sixty-nine only). According to the Appellant, they had quoted a bid price of Rs.1,569 crores. However, due to what they claim was a system error, the quoted amount appeared as just Rs.1,569. - The Appellant claims that they discovered the mistake on 24.08.2023 when the financial bids were opened and announced, and therefore, on the next day, 25.08.2023, they informed the authorities that their actual bid was Rs.1,569 crores, not Rs.1,569. They attributed the error to a typographical mistake or a critical technical issue with the server. While we would not accept the plea of system error, the figure quoted was clearly unrealistic, a patent error and a mistake given the scale and nature of the work tendered. Though the mistake was bald-faced, what followed is incomprehensible, with BRO, insisting on accepting the bid, in spite of letters from the Appellant wanting to withdraw from the tender. - BRO, guided by the Evaluation Committee, instead of accepting the obvious, _vide_ letter dated 26.08.2023, called upon the Appellant to justify the quoted amount of Rs.1,569 by providing a detailed price analysis, including the scope of work, completion _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 3 of 12**_ schedule, risk allocation, safety requirements, and proof of capability to complete the project, by 31.08.2023. - On 30.08.2023, the Appellant reiterated that their intended bid was Rs.1,569 crores, not Rs.1,569, attributing the error to a technical or typographical mistake. - On 07.09.2023, the Appellant sent another letter stating they should not be considered the L1 bidder, and the bank guarantee of Rs.15,04,64,000 may be returned to them without encashment. - On 12.09.2023, the Appellant again wrote emphasizing that the bid was an error and that the bid security should not be forfeited. - _Vide_ letter 16.09.2023, BRO, unmoved, wrote to the Appellant’s bank, the State Bank of India, stating that the Appellant had been declared a defaulter, and their bid security was to be forfeited. The bank was asked to encash the bank guarantee and remit Rs.15,04,64,000 to BRO. - The Appellant filed a writ petition before the High Court of Himachal Pradesh at Shimla, which stands dismissed by the impugned judgment dated 07.10.2023. 4. The short question before us is whether BRO was justified in accepting the bid of Rs.1,569, and on the failure of the Appellant to execute the _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 4 of 12**_ agreement asking for forfeiture _vide_ encashment of bank guarantee of Rs.15,04,64,000. 5. A mistake may be unilateral or mutual, but it is always unintentional. If it is intentional, it ceases to be a mistake. Mistakes or errors, though avoidable, are committed inadvertently. They have varied consequences in law. As per Section 20 of the Indian Contract Act, 1872[2] whereby both parties to an agreement are under a mistake as to matter of fact essential to an agreement, the agreement is void. The explanation to Section 20 says that an erroneous opinion as to the value of the thing which forms the subject matter of an agreement is not deemed to be a mistake as a matter of fact. This will not be a case covered by Section 20 of the Contract Act. However, this is not the first time that this question has arisen either before this Court or Courts outside of India. In _**West Bengal State Electricity Board**_ v. _**Patel Engineering Company Limited and Others[3]**_ , this Court referred to paragraph 84 of _American Jurisprudence_ (2[nd] Edition, Volume 64 at page 944), which reads: “As a general rule, equitable relief will be granted to a bidder for a public contract where he has made a material mistake of fact in the bid which he submitted, and where, upon the discovery of that mistake, he acts promptly in informing the public authorities and requesting withdrawal > 2 Hereinafter, “Contract Act.” > 3 (2001) 2 SCC 451. _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 5 of 12**_ of his bid or opportunity to rectify his mistake particularly when he does so before any formal contract is entered into.” 6. Thereafter, reference was made to two decisions of the Supreme Court of the United States in _**Moffett, H. and C. Co.**_ v. _**Rochester[4]**_ and _**Hearne**_ v. _**New England Marine Ins. Co.**_ **[5]** wherein it is observed that where the mistake is apparent and the party promptly informs the other as soon as it is discovered but before entering into a contract, equitable orders may be passed. However, the mistake should be clear, explicit, and undisputed. Further, a mistake on one side may be a ground for rescinding but not for reforming a contract where the minds of the parties have not met, yet there is no contract and hence none to be rectified. Relief may not be granted where it is inequitable. While accepting this legal position, this Court in _**West Bengal State Electricity Board**_ (supra) has propounded the following exceptions to the general principle on a person seeking relief in equity on account of mistake: “ **27.** …….. (1)Where the mistake might have been avoided by the exercise of ordinary care and diligence on the part of the bidder; but where the offeree of the bid has or is deemed to have knowledge of the mistake, he cannot be permitted to take advantage of such a mistake. > 4 178 U.S. 373 (1900). > 5 22 L. Ed. 395. _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 6 of 12**_ (2) Where the bidder on discovery of the mistake fails to act promptly in informing to the authority concerned and request for rectification, withdrawal or cancellation of bid on the ground of clerical mistake is not made before opening of all the bids. (3) Where the bidder fails to follow the rules and regulations set forth in the advertisement for bids as to the time when bidders may withdraw their offer; however where the mistake is discovered after opening of bids, the bidder may be permitted to withdraw the bid.” 7. This judgment also refers to a decision of the Superior Court of New Jersey in _**Spina Asphalt Paving Excavating Contractors, Inc.**_ v. _**Borough of Fairview**_ .[6] The said case is related to the rectification of mistakes in the bid specifications. Relief granted in the said case was upheld by the Superior Court with the caution that generally an error in the statement of a price would not be treated as immaterial and it is only when the case of error was patent and the true intent of the bidder obvious that such an error might be disregarded. 8. In _**West Bengal State Electricity Board**_ (supra), the private party, the bidder did not succeed for several reasons, including the factum that the error was not obvious and self-evident. Further, the correction of such mistakes after one and a half months after the opening of the bids would have violated the express clauses relating to the computation of > 6 304 NJ Super 425. _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 7 of 12**_ the bid amount. Thus, waiver of the rule or conditions in favour of the one bidder would have created unjustifiable doubts in the minds of others impairing the rule of transparency and fairness and providing room for manipulation for awarding contracts. 9. The decision in _**West Bengal State Electricity Board**_ (supra) was referred to and followed where a relief to the bidder was apparent before this Court in _**M/s Omsairam Steels & Alloys Pvt. Ltd.**_ **v.** _**Director of Mines and Geology, BBSR & Ors**_ .[7] This decision observes that while the Court must exercise a lot of restraint in exercising the power of judicial review in contractual commercial matters, the doctrine of proportionality nevertheless applies when the error or mistake is writ large and equity merits the grant of some relief. Reference was made to the decision in _**Coimbatore District Central Cooperative Bank**_ v. _**Coimbatore District Central Cooperative Bank Employees Association and Another**_[8] where discussing the question of proportionality or punishment imposed on the striking workmen it is observed: “ **18.** “Proportionality” is a principle where the court is concerned with the process, method or manner in which the decision-maker has ordered his priorities, reached a conclusion or arrived at a decision. The very essence of decision-making consists in the attribution of relative importance to the factors and considerations in the > 7 2024 INSC 520. > 8 (2007) 4 SCC 669. _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 8 of 12**_ case. The doctrine of proportionality thus steps in focus true nature of exercise—the elaboration of a rule of permissible priorities. **19.** de Smith states that “proportionality” involves “balancing test” and “necessity test”. Whereas the former (balancing test) permits scrutiny of excessive onerous penalties or infringement of rights or interests and a manifest imbalance of relevant considerations, the latter (necessity test) requires infringement of human rights to the least restrictive alternative. [ _Judicial Review of Administrative Action_ (1995), pp. 601-05, para 13.085; _see also_ Wade & Forsyth: _Administrative Law_ (2005), p. 366.] **20.** In _Halsbury's Laws of England_ (4th Edn.), Reissue, Vol. 1(1), pp. 144-45, para 78, it is stated: “The court will quash exercise of discretionary powers in which there is no reasonable relationship between the objective which is sought to be achieved and the means used to that end, or where punishments imposed by administrative bodies or inferior courts are wholly out of proportion to the relevant misconduct. The principle of proportionality is well established in European law, and will be applied by English courts where European law is enforceable in the domestic courts. The principle of proportionality is still at a stage of development in English law; lack of proportionality is not usually treated as a separate ground for review in English law, but is regarded as one indication of manifest unreasonableness.” Accordingly, in the said case the Appellant was directed to make a payment of Rs.3 crores within the stipulated period and on the said _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 9 of 12**_ payment the security deposit in the form of a bank guarantee of over Rs.9 crores was directed to be refunded. 10. The present case does not fall under any exception, for the error or mistake in quoting a price of Rs.1,569/-, does not require any argument and cannot be debated as it is self-evident. A contract of this nature for an estimated value of more than Rs.1,500 crores spread over 48 months requiring construction of roads and tunnels of the length of more than 4 kilometres in a hilly terrain can never be executed for a mere Rs.1,569/-. 11. At the same time, we agree with BRO, that the Appellant was at fault and had made the mistake, of having failed to add the required zeros in the financial bid. The plea of a system glitch should not be accepted, as others had successfully uploaded their bids without a problem. 12. BRO justified encashing the bank guarantee by citing delays caused by issuing a second notice inviting bids. This claim is baseless, as BRO was aware of the Rs.1,569/- error. Instead of declaring the bid _non est_ due to the clear mistake, BRO asked the appellant to justify the bid, cancelled the notice, declared the Appellant a defaulter, invoked the bank guarantee, and issued a fresh notice inviting bids. _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 10 of 12**_ 13. Thus, BRO’s claim that the delay was entirely due to the Appellant’s mistake is flawed, ignoring BRO’s own lapses. Mistakes, including by authorities, should be resolved through corrective steps. A practical approach could have avoided the delay, which was caused by BRO’s refusal to acknowledge the Appellant’s genuine error and the unwarranted cancellation of the bid. 14. The alleged two-month delay by the Appellant is incorrect. The error, submitted on 03.06.2023, became apparent only when financial bids were opened on 24.08.2023. The Appellant promptly acknowledged the mistake on 25.08.2023. 15. A fresh tender was issued, and financial bids opened on 09.01.2024 revealed the lowest bid of Rs.1,290 crores, lower than the earlier Rs.1,351 crores. Thus, while delayed, the contract was awarded at a lower cost. 16. In view of the aforesaid discussion, we direct the Appellant to pay Rs.1 crore to BRO, as a consequence of their error. Upon receiving this payment, BRO shall return the Appellant’s original bank guarantee or demand draft of Rs.15.04 crores within one week. _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 11 of 12**_ 17. The impugned judgment is set aside, and the appeal is allowed in the aforesaid terms. There would be no order as to costs. **......................................CJI. (SANJIV KHANNA) …......................................J. (SANJAY KUMAR) …......................................J. (K.V. VISWANATHAN)** **NEW DELHI; FEBRUARY 14, 2025** _**Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 12 of 12**_
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.