High Court of KeralaSingle JudgeWrit petition disposed; recovery for arrears of...

M.P.M.MUNAWAR v. KOZHIKODE DISTRICT TOURISM PROMOTION COUNCIL & ORS

Case / Petition Number:WP(C).No. 5906 of 2011 (K)

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • A.K.JAYASANKARAN NAMBIAR
Judgment Date
2014-10-07
Court Decision / Holding
The court held that the Kerala Revenue Recovery Act can cover only amounts found due after adjudicatory processes or admitted payable. It found that the Rs. 20 lakhs demanded as the boat’s value could not be recovered through revenue recovery since it was quantified unilaterally by one party without adjudication. It directed the computation of the remaining licence-fee arrears and interest under Ext. P1, with the possibility of issuing a fresh recovery notice for that portion. It set aside the Rs. 20 lakhs demand and advised that any further recovery actions related to that amount should proceed only after appropriate adjudicatory proceedings. Disposal of the writ petition followed accordingly.
Final Disposition
Writ petition disposed; recovery for arrears of licence fees and interest allowed; Rs. 20 lakhs claim set aside; fresh legitimate notices may be issued for the remaining admissible arrears; adjudicatory proceedings required for any damages claim.

Parties to the Case

Appellants / Petitioners

  • M.P.M.MUNAWAR

Respondents

  • Kozhikode District Tourism Promotion Council
  • District Collector, Kozhikode
  • Special Deputy Tahsildar/Authorised Officer, Revenue Recovery, Kannur
  • State of Kerala

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri B. Krishnan
  • • Sri R. Parthasarathy
  • • Smt. Seema

Counsels for Respondents

  • • Special Government Pleader Sri A.K. John

Case Synopsis & Summary

The petitioner M.P.M. Munawar, a proprietor operating a boat under a licence agreement dated 15 February 2005 with the Kozhikode District Tourism Promotion Council, challenges two notices under the Kerala Revenue Recovery Act (Exts. P4 and P5) issued after Ext. P2 by the District Collector for defaulting on licence fees and other contractual obligations. Ext. P1 is the licence agreement, under which the Council was to receive Rs. 4,68,000 in licence fees over the term. Ext. P2 demanded arrears and additionally claimed Rs. 20 lakhs as the value of the boat not returned after expiry of the contract. The petitioner contends that the Kerala Revenue Recovery Act can recover only amounts determined by an adjudicatory process or admitted payable, and that the quantification of Rs. 20 lakhs was unilateral. The respondents argue that the arrears under Ext. P1 are due and that the Rs. 20 lakhs reflect damages for the boat’s non-return. The High Court held that under the Revenue Recovery Act, only amounts found due post-adjudication or admitted can be recovered; the Rs. 20 lakhs claim cannot be recovered via this route. It directed computation of the remaining arrears (licence fees with interest) and suggested issuing fresh notices if needed, while setting aside the Rs. 20 lakhs claim, and permitted recovery only to the extent of the admitted/arbitrated arrears. The writ petition was disposed accordingly.

Provisions of Law Cited

Kerala Revenue Recovery ActSection 7Section 34

Legal Doctrines & Maxims

  • Amount due under the Kerala Revenue Recovery Act can be recovered only after an adjudicatory process or when admitted to be payable by the party.
  • Quantification of damages (e.g., for the boat) requires a formal adjudicatory process in a court of competent jurisdiction.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner submitted that Exts. P4 and P5 notices under the Kerala Revenue Recovery Act were issued without the required prior adjudication of the amounts due and that the term 'amount due' should reflect only those sums determined after adjudicatory processes or admitted by the petitioner in terms of the contract. They relied on precedents that the amount recoverable under the Act must be adjudicated or admitted.

Contentions of Respondents

The respondents argued that arrears due under the Ext.P1 contract were clearly payable and that the Rs. 20 lakhs claimed for the boat’s value was a legitimate estimate of damages not returned, which could be included in the recovery proceedings.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
P.V.Pally v. State of Kerala and OthersAIR 2000 Kerala 268PositiveCited to show that 'amount due' under the Revenue Recovery Act is confined to amounts determined after adjudication or admitted payable.
Shriram Engineering Construction Co. Ltd v. K.S.I.D.C.2007 (2) KLT 388PositiveCited to support the interpretation that 'amount due' requires adjudication or admission.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against M.P.M.MUNAWAR v. KOZHIKODE DISTRICT TOURISM PROMOTION COUNCIL & ORS and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT:** **THE HONOURABLE MR. JUSTICE A.K.JAYASANKARAN NAMBIAR** **FRIDAY, THE 7TH DAY OF OCTOBER 2014/15TH ASWINA 1933** **WP(C).No. 5906 of 2011 (K) ---------------------------** ## **PETITIONER(S):** - **--------------** **M.P.M.MUNAWAR, AGED 58 YEARS, S/O.DR.K.P.ABDUL KHADER, PROPRIETOR CLIFF EXOTEL INTERNATIONAL BEACH RESORT PAYYAMBALAM BEACH CANTONMENT AREA, KANNUR-670 001.** **BY ADVS.SRI.B.KRISHNAN** **SRI.R.PARTHASARATHY SMT.SEEMA** **RESPONDENT(S):** - **---------------** **1. THE KOZHIKODE DISTRICT TOURISM PROMOTION COUNCIL WITH ADDRESS FOR SERVICETHE CHAIRMAN, THE KOZHIKODE DISTRICT TOURISM PROMOTION COUNCIL, MANANCHIRA, KOZHIKODE KERALA-673 001.** **2. THE DISTRICT COLLECTOR, KOZHIKODE-673001** **3. THE SPECIAL DEPUTY TAHSILDAR/ AUTHORISED OFFICER, REVENUE RECOVERY, KANNUR-670001.** **4. STATE OF KERALA-WITH ADDRESS FOR SERVICE- THE CHIEF SECRETARY, SECRETARIAT THIRUVANANTHAPURAM-695001.** **BY SPECIAL GOVERNMENT PLEADER SRI.A.K.JOHN** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 07-10-2014, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **WP(C).No. 5906 of 2011 (K)** ## **APPENDIX** ## **PETITIONER'S EXHIBITS:** **EXT.P1: TRUE COPY OF THE DEED OF LICENCE EXECUTED BY THE LICENSOR & LICENSEE DATED 15TH FEB 2005** **EXT.P2: TRUE COPY OF THE PROCEEDINGS BY THE 2ND RESPONDENT DATED 29.11.2010** **EXT.P3: TRUE COPY OF THE REPLY DATED 10TH NOV 2010 BY THE WRIT PETITONER TO THE 1ST RESPONDENT.** **EXT.P4: TRUE COPY OF THE NOTICE U/S 7 BY 3RD RESPONDENT EXT.P5: TRUE COPY OF THE NOTICE U/S 34 BY 3RD RESPONDENT** ## **RESPONDENTS' EXHIBITS: NIL** **//TRUE COPY//** **P A TO JUDGE** ## **A.K.JAYASANKARAN NAMBIAR, J.** **.............................................................** W.P.(C).No.5906 of 2011 **.............................................................** Dated this the 7[th ] day of October, 2014 ## **J U D G M E N T** Exts.P4 and P5 notices issued under the Revenue Recovery Act are impugned in this writ petition. The aforesaid notices were issued to the petitioner pursuant to Ext.P2 proceedings of the District Collector, Kozhikode, wherein it was found that the petitioner had defaulted on payment of licence fees, under the agreement dated 15.02.2005 entered into between the petitioner and the 1[st] respondent. Ext.P1 is a copy of the said agreement. A perusal of the same would indicate that the agreement between the petitioner and the 1[st] respondent was to permit the petitioner to operate a boat, that was owned by the 1[st] respondent, for the period stipulated in the agreement. The boat was to be used by the petitioner for tourism related purposes and the 1[st] respondent was to get a licence fees of Rs.4,68,000/- over the period of the agreement. It would appear that the petitioner defaulted on payment of arrears of licence fees, and also in complying with some of the other obligations under the agreement, and this prompted the 2[nd] respondent District Collector, who was the Chairman of the 1[st] respondent, to issue Ext.P2 notice. In Ext.P2 notice, apart from demanding the arrears of licence fees that was due and payable to the 1[st] respondent, the 2[nd] respondent has also -2- W.P.(C).No.5906 of 2011 included an amount of Rs.20 lakhs towards the cost of the boat which, according to the 2[nd] respondent, was not returned to it by the petitioner after the period of the agreement. When no amounts were paid by the petitioner pursuant to Ext.P2 notice, steps were taken in terms of Exts.P4 and P5 notices under the Kerala Revenue Recovery Act. The said notices have been impugned by the petitioner inter alia on the ground that, prior to invoking the provisions of the Kerala Revenue Recovery Act, the respondents had not pursued any steps for getting the amounts due to it, from the petitioner, adjudicated and determined and in that view of the matter the proceedings under the Revenue Recovery Act were vitiated. Reliance has been placed on the decisions in **P.V.Pally v. State of Kerala and Others (AIR 2000 Kerala 268) and Shriram Engineering Construction Co.Ltd v. K.S.I.D.C. (2007 (2) KLT 388).** 2. A statement has been filed on behalf of the 1[st] and 2[nd] respondents, wherein it is pointed out that the petitioner had defaulted on his obligation under Ext.P1 agreement and it was in view of this that the 1[st] respondent was constrained to take steps under the Revenue Recovery Act for realizing the amounts due to it. It is contended that the arrears of licence fees due to the 1[st] respondent were clearly discernible from the terms of the contract -3- W.P.(C).No.5906 of 2011 between the parties and in this sense there could not be any dispute with regard to the amount liable to be paid by the petitioner to the 1[st] respondent, towards license fees, in terms of the contract. The learned Government Pleader would also contend that the amount of Rs.20 lakhs, shown in Ext.P2 towards the value of the boat, is an estimation done by the 2[nd] respondent, taking into account relevant factors for arriving at the cost of the boat, which had not been returned to the 1[st] respondent despite the expiry of the period of the contract between the parties. 3. On a consideration of the facts and circumstances of the case as also the submissions made across the Bar, I am of the view that the proceedings initiated by the 1[st] and 2[nd] respondents under the Kerala Revenue Recovery Act can only cover such amounts as are found to be due and payable by the petitioner in terms of the contract. The decisions in **P.V.Pally v. State of Kerala and Others (AIR 2000 Kerala 268) and Shriram Engineering Construction Co.Ltd v. K.S.I.D.C. (2007 (2) KLT 388)** clearly indicate that the words “amount due” for the purposes of the Kerala Revenue Recovery Act can only be such amounts as have been arrived at after an adjudicatory process or such amounts as are admitted to be payable by the person, against whom the proceedings are initiated. In the instant case, the admitted amounts -4- W.P.(C).No.5906 of 2011 can only be in respect of the arrears of licence fees that was payable by the petitioner to the 1[st] respondent in terms of Ext.P1 agreement. It is seen from the file that, at the time of granting an interim stay against further proceedings against the petitioner, there was a condition requiring the petitioner to remit an amount of Rs.3,50,000/- within six weeks from 24.02.2011 either in lumpsum or in two equal monthly instalments. Counsel for the petitioner would submit that the said amount has since been paid. The respondent will therefore have to compute the amounts that remain to be paid towards arrears of licence fee and interest thereon in terms of Ext.P1 agreement and continue the recovery proceedings, initiated by Exts.P4 and P5 notices, only to the extent of demanding the balance licence fee and interest thereon, if need be by issuing a fresh recovery notice for the said purpose. 4. As regards the demand made by the 1[st] and 2[nd] respondents for an amount of Rs.20 lakhs towards the alleged cost of the boat, this amount, I feel, cannot be demanded by the said respondents as the quantification of damages has been done, unilaterally, by one of the contracting parties. In my view, the quantification of damages, for the boat that was allegedly not returned by the petitioner, has to be done pursuant to a formal adjudicatory process, initiated by the 1[st] and 2[nd] respondents -5- W.P.(C).No.5906 of 2011 against the petitioner, in a court of competent jurisdiction. It is only in such adjudicatory proceedings that an examination, of the factual aspects of the case and the evidence adduced by the parties, can be undertaken to ascertain the liability of the petitioner, if any, in respect of the boat in question. Accordingly, while I sustain the recovery steps initiated by the 1[st] and 2[nd] respondents against the petitioner to the limited extent of recovery of the arrears of licence fees payable by the petitioner to the 1[st] and 2[nd] respondents under Ext.P1 agreement, the recovery steps insofar as they relate to the amount of Rs. 20 lakhs, covering the value of the boat, are set aside. I make it clear that while I am not interfering with the steps initiated by the 1[st] and 2[nd] respondents for recovery of the arrears of licence fees, together with interest thereon, it may be in their interests for the 1[st] and 2[nd] respondents to issue a fresh notice for the recovery of the said amounts since Exts.P4 and P5 notices have been issued taking into account the amounts which have been held not recoverable, in terms of the Revenue Recovery Act, in this judgment. The writ petition is disposed as above. ## **A.K.JAYASANKARAN NAMBIAR JUDGE** mns W.P.(C).No.5906 of 2011 -6-