High Court of KeralaSingle JudgeWrit petition dismissed (disposed of on merits)

Mohamed Sali Kasim & Jameela Beevi Aneez v. State of Kerala and Others

Case / Petition Number:WP(C).No. 27767 of 2014 (U)

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K. Vinod Chandran
Judgment Date
2014-10-30
Court Decision / Holding
Writ petition is dismissed.
Final Disposition
Writ petition dismissed (disposed of on merits)

Parties to the Case

Appellants / Petitioners

  • Mohamed Sali Kasim
  • Jameela Beevi Aneez

Respondents

  • State of Kerala, represented by Secretary to Government Labour Department, Thiruvananthapuram - 695 001
  • The Assistant Labour Officer Grade-I, (Assessing Officer), Thozhil Bhavan, Opp: Vikas Bhavan, K.S.R.T.C. Depot, Post Master General Office Thiruvananthapuram - 695 001
  • The Deputy Tahsildar (Revenue Recovery), Taluk Office, Chirayinke Zu, Attingal - 695 101
  • Lal Kumar N, M/S. Zion Engineers and Builders Pvt. Ltd, Attingal - 695 101
  • The Secretary, Building & Other Construction Workers Welfare Board, Thiruvananthapuram - 695 001

Legal Representation & Advocates

Counsels for Petitioners

  • • T. M. Abdul Latheef
  • • A. Mohammed Rasheed

Counsels for Respondents

  • • Sri. Biju Meenattur

Case Synopsis & Summary

This writ petition (WP(C)) challenges an assessment under the Kerala Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996, arising from the construction of a commercial complex undertaken via a contractor. The petitioners admitted receipt of a pre-assessment notice, filed objections, and the assessment was issued on 5 April 2013 (Ext. P2). A show-cause notice followed (Ext. P3). On 15 April 2014, the petitioners filed an application before the Assistant Labour Officer Gr. I asserting they bore no liability under the Cess Act because a contractor employed the workers. The court notes the absence of any provision for such an application or for review by the assessing officer, and points out that a remedy exists under Section 11 of the Act, with Rule 14 of the Kerala Rules requiring filing within three months from the order. The petitioners did not pursue the appellate remedy. The court emphasizes that under Article 226 of the Constitution, writ jurisdiction cannot override statutory remedies when available; it cites Panopharam v. Union of India (2010 (3) K.L.T. 149) and Assistant Commissioner of Central Excise v. Krishna Poduval (2005 (4) K.L.T. 947) to that effect. The court also discusses the inclusive definition of “employer” under the 1996 Act, concluding that liability cannot be exonerated merely because a contractor was engaged, but notes the petitioner may pursue remedies against the contractor in the appropriate forum. Writ petition is dismissed.

Provisions of Law Cited

Kerala Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 - Section 11Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Kerala Rules, 1998 - Rule 14Kerala Cess Act - Section 2(d) (definition of 'employer')Kerala Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 - Section 2(i) (definition of 'employer')

Legal Doctrines & Maxims

  • Doctrine of availability of alternate remedy (writ jurisdiction under Article 226 should not be exercised where an adequate statutory remedy exists)
  • Inclusive interpretation of the term 'employer' to include owner or contractor under the Act
  • No condonation of delay under the Act; only a prescribed appellate remedy within three months

Submissions & Arguments

Contentions of Appellants / Petitioners

Petitioners contended that, as a building owner, they could not be treated as 'employers' under the Cess Act if a contractor is employed, and that the Assessing Officer had no power to review; they pointed to the lack of provision for condonation of delay and argued for the appellate remedy under Section 11 and Rule 14 within three months.

Contentions of Respondents

The respondents argued for adherence to the statutory framework, stressing the availability of the appellate remedy under the Act and the remedy’s timing; the writ petition should be dismissed for non-exhaustion of the alternative remedy.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Panopharam v. Union of India2010 (3) K.L.T. 149PositiveCited to support the proposition that there is no condonation for delay and that a remedy under the Act must be pursued within the prescribed period.
Assistant Commissioner of Central Excise v. Krishna Poduval2005 (4) K.L.T. 947PositiveCited as authority for the principle that delay cannot be condoned and the legal remedy lies in the statutory appellate route.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Mohamed Sali Kasim & Jameela Beevi Aneez v. State of Kerala and Others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT:** ## **THE HONOURABLE MR.JUSTICE K.VINOD CHANDRAN** ## **THURSDAY, THE 30TH DAY OF OCTOBER 2014/8TH KARTHIKA, 1936** ## **WP(C).No. 27767 of 2014 (U)** ## **------------------------------** ## **PETITIONER(S) :** **-------------------------** ## **1. MOHAMED SALI KASIM,** **S/O.MOHAMMED SALI, P.M.J.MANZIL, I.T.I.ROAD ATTINGAL - 695 101.** ## **2. JAMEELA BEEVI ANEEZA, AGED 81 YEARS** **W/O.MOHAMMED SALI KSAIM, P.M.J.MANZIL, I.T.I.ROAD ATTINGAL - 695 101. PETITIONERS ARE REPRESENTED BY THEIR POWER OF ATTORNEY HOLDER SALAHUDEEN YOUSAF MOHAMMED S/O.YOUSUF LEBBA, P.M.J.MANZIL,** **I.T.I.ROAD, ATTINGAL - 695 101** ## **BY ADVS.SRI.T.M.ABDUL LATHEEF SRI.A.MOHAMED RASHEED** **RESPONDENT(S) :** **---------------------------** **1. STATE OF KERALA, REPRESENTED BY SECRETARY TO GOVERNMENT LABOUR DEPARTMENT, THIRUVANANTHAPURAM - 695 001.** ## **2. THE ASSISTANT LABOUR OFFICER GRADE-I,** - **(ASSESSING OFFICER), THOZHIL BHAVAN, OPP: VIKAS BHAVAN, K.S.R.T.C. DEPOT., POST MASTER GENERAL OFFICE THIRUVANANTHAPURAM - 695 001.** **VS** **-2** **3. THE DEPUTY TAHSILDAR (REVENUE RECOVERY), TALUK OFFICE, CHIRAYINKEEZHU, ATTINGAL - 695 101.** **4. LAL KUMAR. N,** - **M/S.ZION ENGINEERS AND BUILDERS PVT. LTD, ATTINGAL - 695 101.** **5. THE SECRETARY,** - **BUILDING & OTHER CONSTRUCTION WORKERS WELFARE BOARD THIRUVANANTHAPURAM - 695 001.** **BY GOVERNMENT PLEADER SRI. BIJU MEENATTUR** **THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 30-10-2014, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **VS** **-3** ## **WP(C).No. 27767 of 2014 (U)** **----------------------------** ## **APPENDIX** **PETITIONER(S)' EXHIBITS** **-------------------------------------** **EXHIBIT P1. TRUE COPY OF THE AGREEMENT DATED 17.08.2000 EXECUTED BETWEEN THE 1ST PETITIONER AND THE 4TH RESPONDENT.** **EXHIBIT P2. TRUE COPY OF THE ORDER NO.C2-CH2-30/25/12 DATED 05.04.2013 ISSUED BY THE 2ND RESPONDENT.** **EXHIBIT P3. TRUE COPY OF THE NOTICE NO.C2-CH2-30/25/12 DATED 04.03.2014 ISSUED BY THE 2ND RESPONDENT.** **EXHIBIT P4. TRUE COPY OF THE NOTICE NO.C2-CH2-30/25/12 DATED 01.03.2014 ISSUED BY THE 2ND RESPONDENT.** **EXHIBIT P5. TRUE COPY OF THE REPRESENTATION DATED 15.06.2012 SUBMITTED BY THE PETITIONERS TO THE 2ND RESPONDENT, THROUGH THEIR POWER OF ATTORNEY HOLDER.** **EXHIBIT P6. TRUE COPY OF THE DEMAND NOTICE NO.G2-2476/14 DATED 19-00-2014 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONERS.** **EXHIBIT P7. TRUE COPY OF THE REPRESENTATION DATED 10.10.2014 SUBMITTED BY THE PETITIONERS BEFORE THE HONOURABLE MINISTER FOR LABOUR, THROUGH THEIR POWER OF ATTORNEY HOLDER.** **RESPONDENT(S)' EXHIBITS NIL** **---------------------------------------** **/TRUE COPY/** **PA TO JUDGE** **VS** ## **K. Vinod Chandran, J.** ==================================== W.P.(C)No.27767 of 2014 ==================================== Dated this the 30[th] day of October, 2014. ## **JUDGMENT** 1. Petitioners are aggrieved with the assessment passed under the Kerala Building and other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996. Proceedings were initiated with respect to the construction of a commercial complex. The petitioners allegedly employed a contractor, who is the fourth respondent herein, to carry out the construction. The petitioners admit to having received the pre-assessment notice and also filed an objection produced at Ext.P13. The assessment was passed as per Ext.P2 on 5.4.2013. A show cause notice, raising the demand, was also issued as per Ext.P3. 2. On 15.4.2014. an application was filed by the petitioner before the Assistant Labour Officer. The application indicated that the petitioner did not have the liability under the Cess Act for reason of the petitioner having employed a contractor, who alone employed the W.P.(C)No.27767 of 2014 -:2:- employees in the construction of the building. It is to be immediately noticed that, there is no provision for such an application, nor is the assessing officer under the Cess Act conferred with any powers of review. But an appeal is provided under Section 11 of the Act. Such appeal has to be filed under Rule 14 of the Building and other Construction Workers (Regulation of Employment and Conditions of Service) Kerala Rules, 1998, within a period of three months from the date of the order. The petitioner chose not to avail of the appellate remedy, but filed an application before the Assistant Labour Officer Gr.I, the Assessing Officer, who had, as noticed above, absolutely no power to consider the same. 3. In any event, the Assessing Officer considered the application and also found from the agreement produced that the contractor did not have any liability since the contract did not clearly include the payment of any cess with respect to the construction carried out. Petitioner rested contend with the order issued at Ext.P4 also. No W.P.(C)No.27767 of 2014 -:3:- appeal was filed therefrom. When recovery proceedings were initiated by Ext.P6, the petitioner approached this Court with the above writ petition. 4. It is trite that, this Court, under Article 226, cannot invoke the extraordinary jurisdiction, when an alternate remedy is available and the same is not availed of by the assessee within the period stipulated or within the time in which an appeal could be filed with a delay condonation application. The Act does not contain any provision for condonation of delay, but provides only for a period of three months from the date of the order; to file an appeal. The position is covered by two decisions of this Court in Panopharam v. Union of India (2010 (3) K.L.T. 149) and Assistant Commissioner of Central Excise - v. Krishna Poduval (2005 (4) K.L.T. 947). 5. Learned counsel appearing for the petitioner would urge another contention with respect to the owner of the building, not being included under the definition of 'employer' under the Cess Act; if a W.P.(C)No.27767 of 2014 ## -:4:- contractor is employed. The Cess Act by Section 2(d) incorporates the definition in the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 with respect to the words and expressions used in the Cess Act. The definition of 'employer' in the Act of 1996 is, as follows: “Section 2(i) “employer” in relation to an establishment, means the owner thereof, and includes.- (i) in relation to a building or other construction work carried on by or under the authority of any department of the Government, directly without any contractor, the authority specified in this behalf, or where no authority is specified, the head of the department; (ii) in relation to a building or other construction work carried on by or on behalf of a local authority or other establishment, directly without any contractor, the Chief Executive Officer of that authority or establishment; (iii) in relation to a building or other construction work carried on by or through a contractor, or by the employment of building workers supplied by a contractor, the contractor.” W.P.(C)No.27767 of 2014 -:5:- 6. A reading of the definition does not advance the case put forward by the petitioner, since, it is an inclusive definition where the owner is primarily mulcted with the liability, but extending the same to the contractor also by sub-clause (3) of Clause (i). In such circumstances, with respect to the liability of the petitioner under the Cess Act, it cannot be said that the petitioner is exonerated from the liability on account, only, of the petitioner, having employed a contractor to carry out the work. But, however, if the petitioner has a remedy against the contractor as per the terms of the contract, he shall be entitled to agitate the same before the appropriate forum. Writ petition is dismissed. ## **K. Vinod Chandran, Judge.** sl.