Supreme Court of IndiaSupreme Court · 1996Division BenchPetitions dismissed.

MIS. SHAPERS CONSTRUCTION (P) LTD. AND ANR. v. AIRPORT AUTHORITY OF INDIA AND ANR.

Case / Petition Number:
Special Leave Petition (Civil) No. 1811-22 of 1996

Case Synopsis & Summary

Mis. Shapers Construction (P) Ltd. and Anr. v. Airports Authority of India concerns eligibility for tenders on national highways. Tender Condition No. 2 requires that the tenderer have satisfactorily completed at least two runway or national highway works and one work of Rs. 600 lakhs in the last five years, with an annual turnover of Rs. 500 lakhs in the three most recent years, and possess a computerised hot-mix plant and a concrete batching plant. The petitioners argued that they had substantial experience and had executed major portions of two highway contracts; they contended that this demonstrated capability and compliance with the overall spirit of the condition. They submitted tenders following an interim directive from the Madhya Pradesh High Court but, at final hearing, the writ petitions were dismissed. They argued that completion of works should be viewed in light of past performance and that failure to issue tender forms at the initial stage would deprive them of bidding for subsequent contracts. The High Court dismissed, and the Supreme Court upheld that the completion as of the date of application is a pre-condition. The court rejected the petitioners’ assertion that previous experience could be counted before tender submission, distinguishing the earlier ruling in New Horizons Ltd. & Ors. v. Union of India & Ors. and affirming that the pre-condition was not satisfied on the date of application.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • G. B. Pattanaik
Judgment Date
1996-09-17
Court Decision / Holding
The petitions are accordingly dismissed.
Final Disposition
Petitions dismissed.

Parties to the Case

Appellants / Petitioners

  • Mis. Shapers Construction (P) Ltd.
  • Anr.

Respondents

  • Airport Authority of India
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • G. C. Gupta
  • • Shiv Sagar Tiwari

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contended that their prior experience and performance in highway works should satisfy Tender Condition No. 2 and that they should be allowed to compete for the contract. They asserted they had two highway projects of substantial value, had completed major portions of the works within the contract period, and that their interim tender submissions were properly made. They argued that completion of works is not required at the inception stage and relied on the principle that previous experience can influence award decisions after tender submission, citing New Horizons Ltd. & Ors. v. Union of India & Ors. as clarifying the timing of consideration of experience.

Contentions of Respondents

The respondents maintained that Condition No. 2 explicitly requires completion of the specified works as of the date of application. They argued the tender process must ensure contractors have demonstrable completion or substantial readiness, and that the petitioners’ failure to complete on the relevant date justifies denial of tender forms, despite interim directions. They emphasized the High Court’s proper reading of the condition as a pre-condition and rejected the notion that past performance alone could govern eligibility at the pre-application stage.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
New Horizons Ltd. & Ors. v. Union of India & Ors.[1995] 1 SCC 478DistinguishedThe Court cited this case to discuss whether prior experience should be considered before tender submission. It distinguished the ruling on the ground that the present facts concern completion as a pre-condition for application, not pre-tender evaluation.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,057 words•~5 min read

In The Court Record

MIS. SHAPERS CONSTRUCTION (P) LTD. AND ANR. v. AIRPORT AUTHORITY OF INDIA AND ANR.

## A _MIS._ SHAPERS CONSTRUCTION (P) LTD. AND ANR. _v._ ## AIRPORT AUTHORITY OF INDIA AND ANR. ## SEPTEMBER 17, 1996 ## B ## [K. RAMASWAMY AND G.B. PATTANAIK, JJ.) _Tender Form-Condition enVisaging completion of particular type of work on the date of application-Party had done major part of such work but not completed on the date of application-Hence tender form refused-Party_ C _filing a writ petition and High Court ordering issue of tender form-On appeal held since on the date of application admittedly such work was not completed, the pre-condition is not satisfied-Hence the High Court was right in finally dismissing the writ petition._ _New Horiwns Ltd. & Ors._ v. _Union of India & Ors.,_ (1995] 1 SCC 478, D distinguished. CIVIL APPELLATE JURISDICTION : Special Leave Petition (C) No. 181~1-22 of 1996. From the Judgment and Order dated 8.8.96 of the Madhya Pradesh E High Court in W.P. No. 2164/96 and L.PA. No. 138of1996. G.C. Gupta and Shiv Sagar Tiwari for the Petitioners. > The following Order of the Court was delivered : ## F F The petitioners have filed these special leave petitions against the order of the Division Bench of the High Court of M.P. at Jabalpur made on August 14, 1996 in LPA No. 138/96. The learned single Judge as well as the Division Bench dismissed the writ petitions in which the petitioners had sought direction to the respondents to give the tender form on the G ground that they had satisfied Condition No. 2 of the Tender Conditions. Pursuant to the interim order passed by the High Court, the petitioner submitted their tender forms. But, at the final hearing, the writ petitions came to be dismissed. Thus, these special leave petitions. It is contended for the petitioners that they have past experience in H execution of the national highway. They have two contracts of more than 424 SHAPERS CON1N. (P) LTD. _v._ AIRPORT AUUIORITY OF INDIA 425 required amount specified in the tender conditions, 42% of Rs. 4 crores A and Rs. 6 crores respectively. The certificates issued by the competent engineers, namely Executive Engineer and the Superintending Engineer would show that the petitioners have been satisfactorily performing their duties in execution of the work. The petitioners, after securing the contracts, have executed major part of the work within the scheduled time granted under. the contracts. Therefore, the failure to give tender form at[B ] the inception and consideration thereof after the interim direction is violative of their fundamental right to compete in the tender for the further contract. The question is : whether the view taken by the High Court is wrong in law? Tender Condition No. 2 envisages as under: "The tenderer who wish to apply shall have satisfactorily completed[c ] at least two runway/ National highway, preferably rigid pavement works involving considerable earth filling each of value Rs. 400 lakhs or one work of Rs. 600 Ic.khs during the last five years and have annual turn over of Rs. 500 lakhs in each (1992-93, 1993-94 D & 1994-95) and should possess computerised hot mix plant and concrete batching plant for executing asphaltic and rigid pavement works." A reading of this condition would clearly indicate that the tenderers who wish to apply shall have satisfactorily completed at least two runE way/National highway, preferably rigid pavement works involving considerable earth filling, each valuing Rs. 400 lakhs and one work of Rs. 600 lakhs during the last five years and have annual turn over of Rs. 500 lakhs in each of the last three years {1992-93, 1993-94 and 1994-95). He should possess computerised hot mix plant and concrete batching plant for executing F asphaltic and rigid pavement works. It is true, as contended by the petitioners, that the Tender Condition would indicate that they had completed at least two runway/National highway, preferably rigid pavement works. He contends that the completion of the work is different from tendering the contracts for execution of G the work. They had two contracts as envisaged thereunder; though they had not totally completed the same, major part of the work had been completed. Therefore, they have fulfilled the conditions prescribed thereunder. The petitioners, thereby, could not be denied of their right to compete in, apply for and be considered for assignment of the work under H SUPREME COURT REPORTS [1996) SUPP. 6 S.C.R. 426 A the tenders now in dispute. We find no force in the contention. The condition envisages that he shall have satisfactorily completed. The word 'completed' would indicate that as on the date of application for the tenders, he should have completed at least two runway/National highway works, preferably rigid pavement works involving considerable earth B filling. In other words, the completion of the work of at least two runway/National highway ' is a pre-condition. On their own admission, they had not completed, though the major part of the work as professed by them is completed. Under these circumstances, the view taken by the High Court cannot be said to be unwarranted. c The learned counsel placed strong reliance on the judgment of this Court in _New H01izons Ltd. &_ 01:f. v. _Union of India & Ors.,_ [1995] 1 SCC 478, in particular, paragraphs, 21 and 22 in support thereof. This case relates to previous experience and the question therein was : whether the previous experience would be considered after submitting the tenders or D before submitting the tenders? This Court had held that the question would arise only after the submission of the tender. In support of consideration of the tender thereof, the previous experience would play an important role for awarding the -contract. In that case, this Court considered and held that at the inception, the tender forms cannot be refused on the ground that he had not proved the previous experience. That question has no relevance to E the facts in these petitions. Und<:;r these circumstances, as stated earlier, the completion of the work of at least two runway/National highway works is a pre-condition for submitting the application. On their own admission, since the petitioners had not completed the works in hand, we cannot find any illegality in respondents not giving the tender forms nor in non-conF sideration of their cases pursuant to the interim direction given by the High Court. E ·The petitions are accordingly dismissed. G.N. Petitions dismissed.
End of Judgment Record
Browse All Supreme Court of India (1996) Decisions
1996-08-16

Pfizer Ltd. v Mazdoor Congress and ors.

Pfizer Ltd. v Mazdoor Congress and ors is a Supreme Court appeal arising from writ petitions under Article 227 challenging the Bombay High Court’s reversal of Labour Court and Industrial Court findings that Pfizer had not committed an unfair labour practice in terminating two security staff, Waman S. Surve and R.B. Sail. The matter centers on the terminations of Surve and Sail after arrests in a theft case involving Pfizer property and the company’s loss of confidence in their suitability as watch and ward personnel. The Labour Court dismissed the complaints under Section 28 of the MRTU & PULP Act, and the Industrial Court upheld that dismissal; the High Court, however, intervened in a petition under Article 227, allowing an unfair labour practice claim under Item 1(1) of Schedule IV on the grounds of undue haste and ordering reinstatement with back wages. The apex court reverses, holding that undue haste is a question of fact to be determined on evidence and that no case under Item 1(1) was pleaded or proven before the lower fora or the High Court. It stresses that new arguments cannot be introduced at the Article 227 stage absent prior pleadings and evidence. The Court restores the Labour Court’s and Industrial Court’s decisions and allows Pfizer’s appeals, clarifying the evidentiary and pleading boundaries for unfair labour practices in industrial relations law.

1996-01-09

Union of India v. S.S. Uppal and Anr.

This appeal concerns the fixation of seniority for an officer absorbed into the Indian Administrative Service (IAS) from a state civil service quota. Respondent No.1, S.S. Uppal, a Development Officer in Madhya Pradesh’s Commerce and Industry Department, was considered for IAS absorption under Rule 8(2) of the IAS (Recruitment) Rules, 1954. A panel of four officers was prepared for vacancies arising up to 1 February 1989, with Uppal placed at serial No.4, making him eligible only for the February 1989 vacancy. Although the vacancy arose earlier, he was not appointed until 15 February 1989, and on 3 February 1989 the IAS (Regulation of Seniority) Rules were amended to introduce a weightage-based method for determining Year of Allotment (YOA) for those appointed by selection. Uppal challenged Rule 2 of the 1989 Amendment Rules as ultra vires and argued his seniority should be determined by the rules in force on 1 February 1989. The Central Administrative Tribunal accepted that the vacancy occurred before the amendment, so unamended rules should apply. The Supreme Court held that seniority in the IAS is determined by the rules in force on the date of appointment, not the date of vacancy, and that weightage cannot be retrospective unless provided. It emphasized that mere inclusion in a panel does not guarantee appointment and that the Central Government may amend seniority rules from time to time. The appeal was allowed, and the Tribunal’s order set aside.

1996-03-29

Thimmappa v. Siddaramakka

Thimmappa v. Siddaramakka concerns a deed of reconveyance attached to a sale of land. The reconveyance deed provided that if the respondent vendor repaid Rs. 5,000 within eight years from the sale date (July 20, 1968), the sale deed would be executed and registered in her favor. The respondent contended she offered payment before the eight-year period expired and sought specific performance through reconveyance; the appellant allegedly refused. The trial court accepted the respondent's evidence of offer within the period; the appellate court reversed, holding time was the essence of the contract and thus the suit was barred by limitation. The Karnataka High Court then set aside the appellate decree and restored the trial court’s decree. The Supreme Court held that, unless the deed of agreement of sale fixes a date for performance, time is not necessarily the essence of the contract. It found that Thimmappa had agreed to reconveyance conditioned on repayment within eight years, and that the respondent offered payment before expiry while the appellant refused to reconvey. The cause of action arose on expiry of eight years from July 20, 1973, but the suit was filed on July 20, 1976, within the period from the date of refusal (July 19, 1976). The Court concluded the suit was not barred by limitation, dismissed the appeal, and upheld the High Court’s restoration of the trial court’s decree.

1996-11-19

STATE OF UTTAR PRADESH AND ORS. v. V.K. JAIN

State of Uttar Pradesh and Ors. v. V.K. Jain concerns the regulation of compounded entertainment tax for cinema theatres under the Uttar Pradesh Entertainments and Betting Tax Act, 1979 and related Rules. The respondent cinema proprietor sought to reduce seating capacity from 540 to 450 for the 1995-96 year and to opt for the compounded tax system under Rule 24-A. The District Magistrate rejected both applications; the Allahabad High Court quashed that rejection, holding that the District Magistrate had no power to ignore or alter the seating capacity indicated in the option application. The State appealed to the Supreme Court. The Court held that a proprietor cannot enter into a composite agreement indicating a reduced seating capacity from the maximum stated in the licence, and the District Magistrate cannot adopt any seating capacity other than the maximum in the licence for Rule 24-A purposes. To reduce seating capacity, the proprietor must approach the licensing authority under Rule 14 of the U.P. Cinematograph Rules, 1951 to amend the licence, and only then can the amended capacity be used for Rule 24-A calculations. The decision emphasizes that the maximum seats fixed in the licence, not ad hoc figures, determine the governing base for taxation and that post-composition adjustments require proper licensing amendments. The Government suggests a clarifying recast of sub-rule (4) for the post-composition period to avoid litigation.