Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2004Division BenchAppeal allowed; remitted to High Court for fres...

MIS. Jai Durga Finvest Pvt. Ltd. v. State of Haryana and Ors.

Case / Petition Number:
Civil Appeal No. 9267 of 2003

Case Synopsis & Summary

This appeal concerns a mining lease granted by the State of Haryana for extraction of mineral sand in the Bega Murtha area. Jai Durga Finvest Pvt. Ltd. (the appellant) bid successfully in an auction held on 6 April 1998, with a per‑annum bid of Rs 1.48 crore and entered into an agreement on 30 October 1998, including clauses that required the contractor to pay compensation to landowners (clause 9) and to secure compensation with government assistance if landowners refused consent (clause 27 of Form L). The landowners did not permit operation, and the appellant sought to have compensation determined by the District Collector; no response ensued. Consequently, performance of the contract became allegedly impossible, and the contract was terminated in March 2000 for non‑payment of contract money, with the security forfeited. The High Court partly allowed relief but did not resolve the central issue of whether the contract could have been performed given the statutory obligations and non‑compliance by respondents. The Supreme Court allowed the appeal, noting that the award is governed by Punjab Minor Mineral Concession Rules, 1964, and that Clause 27 and Rule 33 of Form L required consideration of whether the contract could be performed; it remitted the matter to the High Court for fresh consideration in light of the doctrine of frustration. The Court held that non‑compliance by the authorities could affect performance and require reconsideration of the contractual obligations under the doctrine of frustration.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • V. N. Khare
  • S. B. Sinha
  • A. R. Lakshmanan
Judgment Date
2004-01-05
Court Decision / Holding
Appeal allowed. The matter is remitted to the High Court for fresh consideration in light of the observations on the doctrine of frustration and the statutory framework.
Final Disposition
Appeal allowed; remitted to High Court for fresh consideration in light of observations on doctrine of frustration.

Parties to the Case

Appellants / Petitioners

  • Jai Durga Finvest Pvt. Ltd.

Respondents

  • State of Haryana
  • and others

Legal Representation & Advocates

Counsels for Petitioners

  • • Dr. Vikas Vashishth

Counsels for Respondents

  • • Aditya K. Choudhary
  • • Sanjay Singh
  • • Ms. Kavita Wadia

Provisions of Law Cited

Punjab Minor Mineral Concession Rules, 1964Rule 33Form LClause 9Clause 27Land Acquisition Act, 1894

Legal Doctrines & Maxims

  • Doctrine of frustration

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the contract became impossible to perform due to non‑payment of compensation to landowners arising from non‑enforceability of Clause 27. The State did not respond to the District Collector’s direction, leaving the landowners uncompensated and obstructing mining operations. The appellant deposited substantial security and contract money but faced termination for non‑payment. It argues that the High Court erred in not addressing whether the contract’s non‑enforcement and the government’s omissions render performance impossible, invoking the doctrine of frustration. The contract could not be relied upon to compel payment when non‑performance by the State prevented extraction; the appellant should not be penalized for circumstances beyond its control. The plea that the contract was entered voluntarily should not defeat relief where statutory obligations were not fulfilled by the authorities; the remedy lies in applying the doctrine of frustration and re‑evaluating the obligations. respondents: The respondents contend that the appellant entered the contract voluntarily and that it remains bound by its terms, including payment of contract money and interest. They argue there was no coercion or undue influence; the contract money obligations and interest were validly recoverable as arrears of land revenue, and termination for non‑payment was proper. The landowners’ failure to consent cannot absolve the appellant of its contractual duties; non‑extraction cannot negate the contractual payments, and the State’s obligations do not erase the appellant’s liabilities. The High Court’s partial relief was correct in limiting relief to specific period and claims.

Contentions of Respondents

(see applicants)

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
MD. Army Welfare Housing Organisation v. Sumangal Service Pvt Ltd.(2003) 8 Scale 424PositiveCited to illustrate that the doctrine of frustration should be considered where performance is hindered due to omissions/commissions by the other party; the Court recognizes the need to evaluate frustration in this case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,535 words•~12 min read

In The Court Record

MIS. Jai Durga Finvest Pvt. Ltd. v. State of Haryana and Ors.

\ "f A # _MIS._ JAi DURGA FINVEST PVT. LTD. _v._ # STATE OF HARYANA AND ORS. JANUARY 5, 2004 [V. N. KHARE, CJ, S.B. SINHA AND DR. AR. LAKSHMANAN, JJ.] _Punjab Afinor Mineral Concession Rules, 1964-Rule 33-Contractfor mining operation-Non-performance of contract by the contractor due to noncompliance of statutOIJ' obligation on part of concerned authority-Demand_ C _of contract amount by authority-Demand held justified by High Court-On appeal, held: Demand nut justified in view of non-compliance of statutory obligation on part of the authority-However, case remitted back to High Court for determination of doctrine of frustraiion._ ... Respondent got a confract for mining operation for extraction of D mineral sand in an auction. In furtherance of acceptance of his bid he entered into an agreement. According to clause 9 of the agreement appellant approached the land owners for settlement of compensation. When the land owners did not permit him to operate, he requested respondent No.3 as per clause 27 of the agreement to get the compensation E determined by the District Collector, but no response thereto was made. As a result, performance of the contract by the appellant became impossible despite having paid a large amount. Appellant also did not seek any relief in payment of contract money on the plea of non-extraction of sand in view of condition No.ISA of the contract agreement. Respondent F No.2 terminated the contract of the appellant on 9.3.2000 for not having paid the contract money from Septetnber 1999 to January 2000 and his security amount was also forfeited. In appeal against the order terminating the contract, Appellate Authority directed adjustment of security amount against the outstanding amount of contract money and upto date interest thereon. Thereafter respondent No.3 demanded the alleged balance G amount, which was paid by appellant, but he submitted that contract money for the period 10.3.2000 to 7.4.2000 was wrongly raised in view of the fact that the contract was terminated on 9.3.2000. Appellant filed writ petition, which was partly allowed by High H Court regarding the amount for the period 10.3.2000 to 7.4.2000 and it 157 158 SUPREME COURT REPORTS (2004) I S.C.R. A further held that appellant was obliged to deposit the amount in terms of the contract, as he had entered into the contract voluntarily without any coercion and undue influence. In appeal to this Court, appellant contended that the contract became impossible to be performed as the compensation was not paid to the land owners due to non-enforceability of Clause 27 of the agreement on the part of respondent No.3. B Allowing the appeal and remitting the case to the High Court, the Court c HELD: Grant of mining lease in favour of the appellant for the extraction of mineral sand by the respondents is governed by the provisions of Punjab Minor Mineral Concession Rules, 1964. In terms of Rule 33, the bidder is required to execute a deed in Form 'L'. Clause 27 of the agreement in Form 'L' obligates the respondent to comply with the D request made in terms thereof. The Appellant Authority had not considered this aspect of the matter. High Court also did not apply its mind in this behalf. As the High Court has merely proceeded on the basis that the appellant had entered into the contract with his eyes wide open; but, the same would not mean that they were bound to pay the contract E[amount, get ][its ][security amount forfeited, ][as ][also ][pay ][interest at the rate ] of 24 per cent, although it could not, by reason of acts of omission and commission on the part of the respondents, carry out the mining operation as per the terms of the agreement. Whether in such a situation the doctrine of frustration will be invoked or not should have been considered by the High Court. 1162-F-H; 163-A-BI F _i_ ' .. CIVIL APPELLATE JURISDICTION: Civil Appeal No. 9267 of2003. . .... G From the Judgment and Order dated 7. I 0.2002 of the Punjab and Haryana High Court in C.W.P. No. 12114 of 2000. Dr. Vikas Vashishth for Kuldip Singh for the Appellant. ~ Aditya K. Choudhary, Sanjay Singh for Ms. Kavita Wadia for the Respondents. H The Judgment of the Court was delivered by 159 .IAI DURGA FINVEST PVT. LTD. v. STATE [SINHA. J.] D S.B. SINHA, J. The writ petitioner before the High Court is appellant herein. ## Admitted fact of the matter is as under: An auction for grant of mining operation that is for extraction of mineral sand in Bega Murtha! comprising 56 villages in the district of Sonepat in the B State of Haryana was held on 6.4.1998. The reserved price therefor was fixed Rs. 83,23,000 (Rupees eighty three lacs twenty three thousand only). The appellant herein became the highest bidder, the bid amount being Rs. 1,48,00,00 (Rupees on crore forty eight lacs) per annum for the period I Ith October, 1998 to 31st March, 200 I. The said bid was accepted and pursuant to and in furtherance thereof an agreement was entered into by and C between the parties on 30th October, 1998. The appellant herein deposited an amount of Rs. 37,00,000 (Rupees thirty seven lacs) as security. The relevant clauses of the said agreement are as under : "9. Payments of Compensations to land owners: The contractor shall make and pay reasonable satisfaction and compensation for all damages or disturbance which may be done by him in exercise of the powers granted by this contract and shall indemnify and keep indemnify fully and completely the Government E against all claims which may be made by any. person or persons in respect of any such damage, injury or disturbance 'and costs any ·expenses in connection therewith. 17. Termination of the contract by State Government in public interest: Except as otherwise provided, the contract may be terminated by F Govt. if considerable by it to be in public interest, by giving one month's notice. Provided that in the state of national emergency or war contract may be terminated without giving such notice. G 18. Recovery of contract money as arrears of land revenue: Any sum from the contractors on account of contract money in respect of the contract, shall be recovered from him/them as arrears of land revenue. H I _"(_ 160 SUPREME COURT REPORTS (2004) I S.C.R. A B c D I SA The contractor shall have no right to seek any relief in payment of contract money on the plea that he was not able to extract sand from any village falling in the zone. 27. Acquisition of land of third parties and compensation thereof:- In accordance with provisions of clause 9 of this agreement the contractor shall offer to pay compensation to an occupier or owner of the surface of the land where from the minor mineral will be raised, including the land required for use as access to the quarry/mine, stracking of mineral and purpose subsidiary thereto for any damage or injury which may arise from the proposed mining operations of the contractor and in case the said occupier or owner refuses his consent to the exercise or the rights and powers reserved to the government and demised to the contractor under these presents the contractor shall report the matter to the Assistant Mining Engineer/Mining Officer posted in the District who shall request the collector of the District concerned to direct the occupier or the owners on such mining/ quarrying operations as may be necessary for the working of the mine/quarry on deposit with the collector to the occupier or the owner by the contractor subject to its final fixation by the collector under the Land Acquisition Act, 1894." E The contention of the appellant was that in terms of clauses 9 and 27, he approached the land owners of villages Nandnaur, Larsauli, Pipli Khera, Murtha( and Bhigan for settlement of compensation, but, they did not accede thereto. Thereafter, the appellant requested respondent No.3 to get the amount of compensation determined by the District Collector and pay the same to the land owners but no response thereto was made. Further contention of the F appellant is that although in the aforementioned situation he has not been able to extract and even for a day, he had deposited a huge sum of Rs. 2, 12,07,573 (Rupees two crores twelve lacs seven thousand five hundred seventy three only.) The appellant further urged that having regard to the said conduct on the part of the respondents, performance of contract on his part G became impossible. Despite the same, one month notice was issued by the 3rd respondent herein on or about 19th January, 2000, terminating the .contract on the ground that the contract money from September 1999 to January 2000 had not been paid; whereafter the Director, 2nd respondent terminated the contract by an order dated 9th March, 2000; as a result whereof the s.ecurity amount deposited by the appellant was also forfeited. _J_ ## H ,., JAi DURGA FINVEST PVT. LTD. _v._ STATE [SINHA, J.] **161** "- ~ Aggrieved by the said order, the appellant preferred an appeal which **A** was partly allowed by the Appellate Authority in tem1s of an Order dated I 0th July, 2000, whereby and whereunder the security amount deposited by the appellant was directed to be adjusted against the outstanding amount of contract money and upto date interest thereon, The 3rd respondent thereafter issued a notice to the appellant on 4th August, 2000 demanding the alleged **B** balance amount along with the interest at the rate of 24 per cent per annum which was worked out to Rs. 68,35,290 (Rupees sixty eight lacs thirty five thousand two hundred ninety only). The appellant deposited the said amount, but submitted a representation before the 2nd respondent _inter a/ia_ contending that the contract money for the period 10.3.2000 to 7.4.2000 has wrongly been raised having regard to the fact that the contract stood terminated on 9th c March, 2000. The appellant thereafter filed a Writ Petition before the Punjab and Haryana High Court which was marked as C.W.P. No. 12114 of2000, praying _inter alia_ therein th.e following reliefs:- **D** ~- A '[/' ] - (a) issue a writ of certiorari quashing the impugned notice dated 4.8.2000 to the extent it demands contract money and interest thereon@ Rs. 24% P.A. after expiry of one month notice dated 19.1.2000 terminating the contract or in the alternative demand of contract money and interest thereon from 9.3.2000 to 7.4.2000, be declared _null and void_ and quashed; E - (b) issue an appropriate writ, order or directions declaring clause 19 of the agreement; (P/l) as _null and void_ to the extent it stipulates no11-payment of interest on the heavy amount of security deposited by the petitioner and that direction be issued to respondents to pay interest @ 24% P.A. on the amount of security till final F adjustment qua the outstanding contract money; - (c) issue further an appropriate writ, order or direction to the respondents not to charge interest on the amount of contract money being demanded from the petitioner vide order dt. 10.7.2000; P/3 and notice dated 4.8.2000." - G The High Court allowed the writ petition in part i.e. as regard the demand of the amount for the period 10.3.2000 to 7.4.2000 of the contract money. As regard the other contentions of the appellant, the High Court proceeded on the basis that as it was not coerced into bid by any of the representatives of the State nor the contract was signed under undue influence H I -.; 162 SUPREME COURT REPORTS (2004) I S.C.R. A[or ][pressure, ][the ][appellant ][cannot ][be ][discharged ][of ][its ][liability ][as ][it ][entered ] into the contract voluntarily and as in terms thereof it was obliged to deposit the amount in question. It appears to us that the High Court committed an error in not going into the principal issue involved in the matter. B We may notice that the second respondent in its order dated 10th July, 2000 held : "It is an admitted fact that the appellant did not operate the Bega Murtha! Sand Zone, even if by their own choice, but facts remain that they did not derive any benefit from the contract. On the other hand they had bound themselves by condition No. I SA of the contract agreement not to seek any relief in payment of conduct money on the plea of non extraction of sand". c The question, thus, which was required to be posed and answered was D as to whether Clause I SA of the agreement would remain enforceable despite the fact that the appellant allegedly could not extract any sand by reasons of omission and commission on the part of the concerned respondents. The appellant herein has raised a plea that the contract became impossible to be performed as the land owners of the area in question did not receive E[compensation ][and ][despite ][request ][the ][3rd ][respondent ][did ][not ][enforce clause ] 27 of the agreement. It is not in dispute that the grant of mining lease in favour of the appellant herein for the extraction of mineral sand by the respondents is governed by the provisions of Punjab Minor Mineral Concession Rules, 1964. F[In ][tenns of ][Rule ][33 ][the ][bidder ][is ][required ][to ][execute ][a ][deed ][in ][Form ]['L'. ] Clause 27 of the agreement in Form 'L' obligates the respondent to comply with the request made in terms thereof. The Appellate Authority had not considered this aspect of the matter. The High Court also did not apply its mind in this behalf. The first question that arises whether the respondents complied with their statutory obligations when the request.was made by the G appellant. If not, the second question would be the effect on non-compliance of the statutory obligation of the respondents which formed part of the contract insofar as they did not comply with the appellant's request as aforementioned which had a direct bearing to the right of the appellant to raise sand. As the High Cou11, as noticed here-in-before, has, merely proceeded on the basis H[that ][the ][appellant ][had ][entered ][into ][the ][contract ][with ][his ][eyes ][wide ][open, ][but, ] _)_ ""' '" J _f_ " 163 JAi DURGA FINVEST PVT.LTD. _v._ STATE [SINHA, J.] . < ' the same would not, in our opinion, mean that they were bound to pay the contract amount, get its security amount forfeited, as also pay interest at the rate of 24 per cent, although it could not, by reason of acts of omission and commission on the part of the respondents, carry out the mining operation as per the terms of the agreement. Whether in such a situation the doctrine of frustration will be invoked or not should have been considered by the High Court. (See _MD. Army Welfare Housing Organisation_ v. _Sumangal Service Pvt Ltd.,_ (2003) 8 Scale 424). For the reasons afore-mentioned, the impugned judgment cannot be sustained which is set aside accordingly. The appeal is allowed and the matter is remitted back to the High Court for consideration of the matter afresh in the light of the observations made herein on. an early date. No costs. K.K.T. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (2004) Decisions
2004-05-26

State of West Bengal v. Haresh C. Banerjee and Ors.

This appeal concerns the constitutional validity of Rule 10(1) of the West Bengal Services (Death-cum-Retirement Benefit) Rules. The Calcutta High Court had previously held the rule ultra vires the Constitution and had struck down the power to conduct a departmental inquiry against a retired employee. The Supreme Court granted special leave and noted that even if the appeal were to succeed, the benefit already due to respondent No. 1 in the High Court’s order would not be recalled; arrears would be paid by the State within the time prescribed. The sole question before the Court is the validity of Rule 10(1) and its relation to the West Bengal (Classification, Control and Operation) Rules, 1971, including sub-rule (1) of Rule 10, which governs classification and control of service. The Court observed that the issue raises a larger question of operation that could affect a large number of employees, and therefore it is appropriate to refer the matter to a larger Bench for authoritative adjudication. The matter is thus directed to be placed before a larger Bench, and the judgment does not finally decide the vires of Rule 10(1). In short, the Court stayed further adjudication on the matter of validity and opted for an expeditious reference to a larger judicial forum. The background also includes the Court’s directive in leave proceedings that arrears, if any, would be payable according to the High Court’s order, not recalled pending appellate resolution.

2004-05-05

Commissioner of Customs & Central Excise & Ors. v Charminar Nonwovens Ltd.

The case concerns the proper classification and duty liability of Floor G Coverings and Filter Fabrics under the Central Excises and Salt Act, 1944, specifically whether these goods fall under Tariff sub-headings 5703.90 (30% ad valorem) or 5703.20 (5% ad valorem). The respondent, Charminar Nonwovens Ltd., received a detention memo and a show-cause notice challenging the classification and the related duty. An appellate authority had previously upheld the assessee's classification on a similar adjudication, and the Andhra Pradesh High Court later quashed the show-cause notice on the ground that the appellate order had become final. The petitioners challenged this, arguing that classification must be decided on facts arising in each case and that new facts or changes in law may warrant re‑examination, not interference by the High Court at the show-cause stage. The Supreme Court held that classification and the determination of duty are case-specific, and even if a decision was taken earlier, further investigation can reveal new facts or a change in law requiring re‑examination. The High Court's interference at the show-cause stage was improper. The Court then set aside the High Court order and remitted the matter to the Adjudicating Authority for fresh adjudication, with similar directions to related appeals. The overarching principle is that revenue classifications are not frozen by earlier judgments and must be reconsidered as facts or law evolve.

2004-08-16

G. B. LAHOTI v. S. J. CHOURASIYA

This Supreme Court decision concerns substitution of legal heirs in a pending appeal arising from a land-lord–tenant dispute. The landlord sued for possession; the trial court decreed possession due to unlawful sub-letting. The tenant’s successor-deceased Ganesh Prasad Lahoti’s heirs sought substitution under Order XXII Rule 11 after the defendant’s death; the first substitution application Exh. 22 was rejected on a technical ground, and three further applications followed (for setting aside abatement, for condonation of delay, and for interim relief). The appellate court dismissed these on merits and on the ground of res judicata, and the High Court dismissed revisions. The Court held that the doctrine of res judicata does not bar such subsequent applications where, as in this case, there was no inaction or negligence by the heirs and the delay was explained by the circumstances—knowledge of pendency arose only after a letter from the advocate confirming hearing. The Supreme Court allowed the appeal, set aside the lower orders, and directed the lower appellate court to hear the appeal on merits in accordance with law, with an award of costs (Rs. 10,000) within three months, and a fresh deadline for a merits decision by Aug. 31, 2005. The decision clarifies substitution rights in the context of pending appeals and limits of res judicata in substitution petitions.

2004-05-05

SHAKUNTALA BAI v. NARAYAN DAS

This Supreme Court decision arises from a long-drawn eviction suit under the Madhya Pradesh Accommodation Control Act, 1961, filed for bona fide landlord’s need to carry on business in a non-residential premises. The trial court decreed eviction; during appeal, the landlord died and his heirs sought to amend the plaint to plead their own bona fide need. The tenant urged amendment of his pleadings to claim that, after the landlord’s death, the personal need ceased. The High Court dismissed the suit on the ground that after the landlord’s death the personal need could not be pursued by heirs. The Supreme Court, allowing the appeals, held that the bona fide need of the landlord must be examined as on the date of institution of proceedings, and if a decree for eviction is passed, the death of the landlord during pendency of the appeal does not invalidate the Plaintiffs’ right to defend the estate. It clarified the law: the bar under s.12(1) prevents filing the suit except on listed grounds; the need may be tested with amended pleadings after remand; the object of the Act is expeditious disposal and not perpetual litigation. Citing earlier decisions, the Court ultimately restored the trial court’s decree, set aside the High Court’s dismissal, and granted four months for eviction with an undertaking. The decision reaffirms that heirs may defend the estate where a valid eviction decree has been issued.