MIS. EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS.

Case / Petition Number:
Civil Appeal Nos. 7184 of 2008 and 7185 of 2008
Neutral Citation:[2016] 5 S.C.R. 503

Case Synopsis & Summary

MIS. EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS. is a Supreme Court decision interpreting the ambit of Section 11 of the Arbitration and Conciliation Act, 1996. The appellants, a contractor, challenged an order of the Chief Justice of the Punjab and Haryana High Court dismissing their Section 11 application to refer disputes to arbitration. The factual backdrop is a government contract for security fencing completed in 2000; the final bill was prepared in February 2001 and paid in April 2001, with the undisputed portion settled. On February 23, 2005, the contractor served a notice claiming that additional items, listed in Appendix A, remained due for payment, i.e., disputed amounts. The government rejected the claim as time-barred, citing the two-year defect liability period under the contract and the three-year period for limitation under Article 137 of the Limitation Act. The High Court, following the line of authority, held that the claim was not a live claim and rejected the application. The Supreme Court held that the Chief Justice, while deciding preliminaries under Section 11, may determine whether a claim survives or is dead; such a claim can be rejected if patently time-barred, but otherwise the dispute requires examination of documents and evidence by an Arbitral Tribunal. The matter was remitted to a designated judge for appointment of the arbitrator, with consent of the parties or by the Court if necessary, to decide the disputes. The appeals were allowed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Abhay Manohar Sapre
  • Ashok Bhushan
Judgment Date
2016-06-29
Court Decision / Holding
Appeals allowed. The High Court Chief Justice’s order rejecting the Section 11 application is set aside. The matter is remitted to the High Court (designated Judge) to pass consequential orders for appointment of an arbitrator to decide the disputes, allowing initial appointment by mutual consent and, if not possible, appointment by the Court, to be completed within one month of appearance.
Final Disposition
Appeals allowed; remitted to High Court (designated Judge) for appointment of arbitrator

Parties to the Case

Appellants / Petitioners

  • MIS. EMM ENN ASSOCIATES

Respondents

  • Commander Works Engineer & Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • 0. P. Gupta (Partner, appellant)

Counsels for Respondents

  • • Yashank Adhyaru, Sr. Adv.; Krishna Prasad; Rashmi Malhotra, Advs.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 11Limitation Act, 1963 - Article 137Clause 67 of General Conditions of Contract (Recovery from Contractor)

Legal Doctrines & Maxims

  • Live claim (doctrine)
  • Dead claim (doctrine)
  • Chief Justice's jurisdiction under Section 11 to decide preliminaries including existence of arbitration agreement and live claim

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the disputed claim was not barred by time since the final bill dated 10.04.2001 covered only undisputed amounts; other claims remained disputed and were not adjudicated. The two-year defect liability period cannot extinguish the right to pursue the disputed amounts, especially where the notice of 23.02.2005 was within the contract's framework for arbitration. The appellant asserts that the Chief Justice may determine whether a claim is live or dead by examining the pleadings and relevant documents; if the claim is not evidently time-barred, it must be referred to arbitration. The final settlement certificates and annexures produced to prove undisputed portions were not conclusive, and the matter required scrutiny by the Arbitral Tribunal to ascertain the scope of recovery and the status of disputed items.

Contentions of Respondents

The respondents argued that the final bill was paid in 2001 and the notice was issued in 2005, well beyond the period of three years under Article 137 of the Limitation Act; hence the claim was time-barred and not a live claim. They submitted that the Chief Justice was correct to reject the application under Section 11 and that limitation issues should be decided by the statute, not the arbitral tribunal. They also relied on the No-Liability certificate and the two-year remedy period under the contract to assert no live claim existed.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
SBP & Co. v. Patel Engineering Ltd. & another2005 (4) Suppl. SCR 688; (2005) 8 SCC 618PositiveCited as authority on Chief Justice’s power under Section 11 and the live/dead claim concept in arbitrations.
Indian Oil Corporation Limited v. SPS Engineering Limited2011 (3) SCC 507; 2011 (2) SCR 512PositiveLays down what constitutes a live claim and the CJ’s jurisdiction under Section 11, guiding leave-to-arbitrate decisions.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,413 words•~21 min read

In The Court Record

MIS. EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS.

[2016] 5 S.C.R. 503 A ## M/S. EMM ENN ASSOCIATES v. ## COMMANDER WORKS ENGINEER & ORS. ## (Civil Appeal No.7184 of2008) ## JUNE 29, 2016 B [ABHAY MANOHAR SAPRE AND ASHOK BHUSHAN, JJ.) _Arbitration and Conciliation Act, 1996_ - _s. 11_ - _Work contract_ - _To appellant-contractor, by Government_ - _After completion of work, payment of undisputed part of final bill on 10.4.2001_ - _As per the contract defect liability period was two years, during which recovery could be made from the contractor_ - _On 23.2.2005 contractor served notice to the Government raising other claims which were disputed_ - _Claim denied_ - _Letter by contractor to Government for appoint111ent of arbitrator as per the contract_ - - _Thereafter application uls.11 filed Rejection of application by the Chief Justice of High Court on the ground that the clai111 was not a live clai111 and the notice dated 23.2.2005 was ti111e-barred_ - _On appeal, held: The Chief Justice since exercises judicial power while deciding application u/s. 11, can examine the question as to whether the claim survives or needs to be adjudicated_ - _But a clai111 can be held to be a dead claim only when the clai111 is evidently and patently long time-barred and there is no need for any detailed consideration of evidence_ - _Jn the present case there was a dispute which needed adjudication after looking into all relevant documents, which could have been appropriately exa111ined by Arbitral Tribunal_ - _Case remitted to Designated Judge for appointment of the arbitrator._ c D E F Allowing the appeals and remitting the matters to Designated Judge, the Court HELD: 1. The Chief Justice exercises the judicial power while passing an order under Section 11 of the Arbitration and Conciliation Act, 1996 and thus can examine the question as to whether the claim which has been raised before him survives and needs to he adjudicated. If Chief Justice finds that claim is a dead claim, he can exercise jurisdiction in rejecting the application. [Para 17] [ 509-B-C) G H 503 [2016) 5 S.C.R. 504 SUPREME COURT REPORTS A _SEP & CO. versus Patel Engineering Ltd and another_ 2005 (4) Suppl. SCR 688 : (2005) 8 SCC 618 - relied on. 2. An application under Section 11 of the Act is expected to contain pleading about the existence of a dispute and the applicant B is not expected to justify the claim or plead extensively in regard to limitation or production of document to demonstrate that claim is within time in proceeding under Section 11 and that issue should normally be left to the Arbitral Tribunal. Therefore, the Chief Justice may chose to hold a claim as a dead claim only when the claim is evidently and patently long time barred claim and there c is no need for any detailed consideration of evidence. [Paras 19 and 20] [510-C-D, H; 511-A) - _Indian Oil Corporation Limited v. SPS Engineering Limited_ 2011 (2) SCR 512 : 2011 (3) SC 507 - relied on. - D 3. In the present case, the appellant has also contended that there is a defect liability period of two years during which any recovery can be made from the contractor. Further the categorical case of the appellant was that final payment made at 10.04.2001 was the final payment of the undisputed claim and E there were other claims of the appellant which were disputed. There being no adjudication with regard to disputed claim, the claim raised by notice dated 23.02.2005 cannot be said to be barred by time or a dead claim. [Para 21] [511-B-C] 4. The examination of the additional materials brought on F this appeal, d.oes indicate that the case required consideration of relevant bills and certificates and determination on the question as to whether the claim laid by appellant was a dead claim and was not a live claim depended upon scrutiny of relevant documents. The pleadings in the proceeding under Section 11 by G the appellant were clearly to the effect that on 10.04.2001, he was paid only undisputed part and the appellant has reserved his right to raise claim to the disputed part. [Para 25] [513-A-B) 5. Thus, there was a dispute which needed an adjudication after looking into all relevant documents, bills and certificates which could have been appropriately examined by Arbitral H 505 ## MIS. EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS. Tribunal and the observation of the Chief Justice "As the appellant A has failed to _prinw facie_ show this court that there was a live claim of the appellant" is not correct. [Para 27] [513-D-E] 6. It is apposite to remit the case to the High Court (designated Judge) to pass consequential orders for appointment of the arbitrator for deciding the disputes which have arisen B between the parties. The appointment of the arbitrator may be made in the first instance with the consent of the parties and if, for any reason, it is not possible to do so then the Court will appoint the arbitrator in its discretion. (Para 29) (513-G-H] ## Case Law Reference C 2005 ( 4) Suppl. SCR 688 relied on Para 16 2011 (2) SCR 512 relied on Para 18 CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7184 of 2008. D From the Judgment and Order dated 12.03.2007 of the High Court of Punjab and Haryana at Chandigarh in Arbitration Case No. 184 of 2006. WITH C. A. No. 7185 of 2008. E Petitioner-in-person. Yashank Adhyaru, Sr. Adv., 8. Krishna Prasad, Ms. Rashmi Malhotra, Advs. for the Respondents. The Judgment of the Court was delivered by F ASH OK BHUSHAN, J. 1. These two appeals raising identical questions oflaw have been heard together and are being decided by this common judgment. For deciding both the appeals, it shall be sufficient to refer to facts and pleadings in Civil Appeal No. 7184 of2008. Appeal No. 7184 of 2008 has been filed against judgment of Chief Justice of Punjab & Haryana High Court in Arbitration Case No. 184 of2006 by which judgment learned Chief Justice has dismissed the application, filed by appellant for referring the dispute to an arbitrator in exercise of power under Section 11 of the Arbitration and Conciliation Act 1996 (hereinafter referred to as 'Act'). G H 506 [2016] 5 S.C.R. SUPREME COURT REPORTS A 2. Civil Appeal No. 7185 of2008 has also been filed against the identical judgment ofleatned Chief Justice in Arbitration Case No. 89 of 2006 by which the application filed by the appellant for appointing an arbitrator has been dismissed. 3. Brief facts giving rise to Appeal No. 7184 of2008 now need to B be noted. The appellant a partnership firm was allotted a contract on I 0.11.1998 for providing additional security fencing at Mullanpur. The work was completed on 10.7.2000. Work completion certificate was issued. Final bill was prepared on 20.2.2001 and the payment of final bill c was made to the petitioner on 10.04.2001. Payment of the undisputed part of the final bill was made by cheque dated 10.04.2001. D 4. Although Clause 67 of general conditions of contract contemplated for recovery from contractor in several contingencies one of which as referred in sub-Clause (t) was that if as a result of any audit and technical examination, any over payment is discovered in respect of work done under this contract, the contractor shall on demand make payment of a sum equal to the amount of over-payment. Sub-Clause (g) further provided that the Government shall not be entitled to recover any over-payment beyond a period of two years from the date of payment of the undisputed portion of the final bill. E F 5. Even though, two years period expired after payment of final bill, no demand for any recovery was issued by the Government. Contractor by letter dated 23.02.2005 served a notice stating that final bill amount as paid during April, 2001 did not include the payments due to contractor against several items which were claimed as per appendix A annexed to the notice. > 6. It was further stated that the decision be communicated within thirty days failing which it shall be assumed that the claim is disputed and contractor shall be left with no remedy except to seek adjudication by an arbitrator appointed in terms of the contract. G 7. The Garrison Engineer issued a letter dated 22.03.2005 informing that contractor had signed the final bill without any protest and had given 'No Further Claim' certificate. Hence no arbitrable dispute exists. The claim now intimated after the lapse of a period of approx four years is baseless and hence denied. H 507 ## _MIS._ EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS. [ASHOK BHUSHAN, J. ] 8. A letter dated 24.03.2005 was written by the contractor to the chief engineer in reference to notice dated 23.02.2005 with a prayer that arbitrator under condition 70 of the Contract may kindly be appointed to adjudicate the dispute. The appeilant thereafter filed an application under Section 11 of the Arbitration Act before District Judge, Ropar. The application was ultimately taken by Chief Justice of the High Court and by an order dated 12.03.2007, the application was rejected taking the view that appel !ant's claim is not a live claim. Aggrieved against the above judgment dated 12.03 .2007 in Arbitration Case No. 184 of2006, Appeal No. 7184 of 2008 has been filed. 9. Arbitration Case No. 89 of 2006 has also been filed by the appellant seeking appointment of an arbitrator under Section 11 of the Act in the said case and also the work was completed on 23.09.2000 and the final bill was paid on 10.04.200 I. Notice along with list of claim was sent by the appellant on 23.02.2005 i.e. on the same day when notice in Arbitration Case No. 184 of2006 has been sent. I 0. Hon 'hie Chief Justice giving the same reasons rejected the application in Arbitration Case No. 89 of 2006 holding that the claim made by the appellant is not a live claim. Hon'ble Chief Justice by order dated 12.03.2007 took the view that final bill has been paid on 10.04.2001, the notice having been given only on 23.02.2005 the period oflimitation was over. With regard to the Clause 67 of the contract, it was observed by the Chief Justice that Embargo of two years as per sub-Clause (f) and (g) is with regard to the right of the Government for effecting recovery from the contractor which clause does not extend the period of limitation in favourofthe contractor. 11. Shri 0. P. Gupta, the partner of the appellant firm has appeared in-person and made his submission. We have also heard the learned counsel appearing for the respondents. 12. The appellant's case is that the claim raised by contractor by notice dated 23.02.2005, was not barred by time and was a live claim which ought not to have been rejected by the Chief Justice in exercise of his power under Section 11 of the Act. It is contended that the issues as to whether the claim is barred by time are the issues which ought to have been left for decision of arbitrator. It is contended that payment in respect to the final bill made on 10.04.2001, was payment with regard to undisputed amount. Apart from undisputed amount there were other A B c D E F G H 508 SUPREME COURT REPORTS [2016] 5 S.C.R. - A claims of the contractor and the 'No Liability' certificate given by the appellant was only with regard to undisputed claim. Payment made on 10.04.2001 was the payment only in reference to undisputed claim and that in no manner precluded the appellant from raising claim. 13. As per Clause 67 of the contract, there was two years period B for effecting any recovery from the contractor and when no claim against the contractor was raised during the aforesaid period, the appellant raised the claim for disputed amount which was not paid. The period of two years is defect liability period and it was clearly open for the appellant to raise the claim for disputed amount after expiry of the aforesaid period of two years. - c 14. The respondents never adjudicated the disputed part of the final bill and after serving notice the appellant had rightly sought for adjudication by an arbitrator which application has been rejected by Hon'ble Chief Justice not on valid considerations. D E 15. Learned counsel appearing for the respondents supported the judgment of the Chief Justice and contends that for filing any application limitation is three years as per Article 137 of the Limitation Act, 1963. Final bill had been paid on I 0.04.2001, any application for any claim in respect to final bill ought to have been raised within three years. It is contended that the respondents have raised the preliminary objections in replyobjectingthe application for arbitration filed by the appellant, which has rightly been rejected by the Chief Justice. F G H 16. We have considered the submissions of both the parties and have perused the record, what is the nature of jurisdiction of the Chief Justice while deciding an application under Section 11 of the Act has elaborately been considered by Seven Judge Bench of this court in _SBP & CO. versus Patel Engineering Ltd and another (2005) 8 SCC 618._ In para 4 7 of the judgment, conclusions were recorded by the larger Bench. Conclusion IV is relevant for the present case which is quoted as below: _"4_ 7. _We, therefore, sum up our conclusio11s as follows:_ _(iv) Tile Chief Justice or the designated Judge will /lave tile right to decide tile prelimillary aspects as indicated in tile earlier part of this judgment. T/lese will be /tis own jurisdiction to entertain tlte request, tlte existence of a valid arbitration agreement, tlte existence or otherwise of a live claim, tlte_ 509 ## _MIS._ EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS. [ASHOK BHUSHAN, J.] - _existence of tire condition for tire exercise of liis power and_ A _on tire qualifications of tlte arbitrator or arbitrators. Tire Cltief Justice or tire designated Judge would be entitled to seek tire opinion of an institution in tlte matter of nominating an arbitrator qualified in terms of Section 11 (8) of tlte Act if tlte need arises but tlte order appointing tlte arbitrator could only_ B - _be tliat of tire Cltief Justice or tlte designated Judge."_ 17. The Chief Justice exercises the judicial power while passing an order under Section 11 of the Act thus can examine the question as to whether the claim which has been raised before him survives and needs to be adjudicated. It goes without saying that if Chief Justice finds that claim is a dead claim, he can exercise jurisdiction in rejecting the application. 18. A two Judge Bench of this court in _Indian Oil Corporation_ . _Limited vs. SPS Engineering Limited, 2011 (3) SCC 507,_ had occasion to· consider what is a 'live claim' within the meaning of Section 11 of the Act. Elaborating the jurisdiction of the Chief Justice, under Section 11 of the Act following was laid down by this court in para 14 of the judgment: _"14 ........ Tlte Chief Justice or llis designate may ltowever clroose to decide wlretlrer tire claim is a dead (long-barred) claim or wlretlter tlte parties !rave; by recording satisfaction, exhausted all riglrts, obligations and remedies under tlte contract, so tltat neither tile contract nor tlte arbitration agreement survived. Wiren it is said tllat tile Cllief Justice or llis designate may clloose to decide wltetller tile claim is a dead claim, it is implied tlrat Ile will do so only wllen tile claim is evidently and patently a long time-barred claim and tllere is no need for any detailed consideration of evidence. We may elucidate by an illustration: if tile contractor makes a claim a decade or so after completion of t/1e work wit/tout ref erring to any acknowledgment of a liability or otlter factors tltat kept tile claim alive in law, and tile claim is patently long timebarred, tile Cllief Justice or llis designate will examine wltetller tlte claim is a dead claim (tllat is, a long time-barred claim). On tile otlter lland, if tile contractor makes a claim for payment, beyond tllree years of completing of tile work but say wit/tin jive years of completion of work, and alleges_ c D E F G H 510 [2016] 5 S.C.R. SUPREME COURT REPORTS A B _that tile final bill was drawn up and payments were made within three years before tile claim, the Court will not enter into a disputed question whether tile claim was barred by limitation or not. Tile Court will leave tile matter to the decision of the Tribunal. If tile distinction between apparent and obvious de(l(/ claims, and claims involving disputed issues of limitation is not kept in view, tile Chief Justice or his designate will end 11p deciding tile question of limitation in all applications under Section 11 of tile Act."_ 19. Further this court has observed that an application under Section 11 of the Act is expected to contain pleading about the existence c of a dispute and the applicant is not expected to justify the claim or plead extensively in regard to limitation or production of document to demonstrate that claim is within time in proceeding under Section 11 and that issue should normally be left to the Arbitral Tribunal. Following was observed in para 15: D _"15. An 11pplicatio11 111uler Section 11 of tile Act is expected to ctmtain ple11di11gs about the_ exi.~te11ce _of 11 dispute mu/ tile existence of <Ill arbitration agreement to decide suclt disp11te. Tlte applimnt is 1101 expected to justify tile claim or plead exhaustively in regard to limitlllion or produce documents to_ E _denwmtrate tli11t tile claim is wit/till time in a proceeding under Section 11 of tlte Act. Tll11t_ is~·ue _sl1011/d normally be left to tlieArbitral Tribunal. If tile Cltief Justice or his designate is of tile view that in addition to examining whether there is wi arbitration agreement between tile parties, lie should consider tile issue wlletller tlte claim is a dead one (long time-_ F _barred) or whether there has been satisfaction of mutual rights and obligation under the contract; lie should record his intention to do so and give aJI opportuJ1ity to tile parties to place their materials OJI such issue. UJ1less tile parties are put OJI notice that suclt an il·sue will be examined, they will be_ G _11J1der tlte impression that only questions of jurisdiction aJ1d existence of arbitratioJI agreement between tile parties will be considered in such proceedinJ:S."_ 20. From the above, it is clear that Chief Justice may chose to hold a claim as a dead claim only when the claim is evidently and patently long H time barred claim and there is no need for any detailed consideration of M/S. EMM ENN ASSOCIATES v. COMMANDER WORKS 511 ENGINEER & ORS. [ASHOK BHUSHAN, J. ] evidence. An illustration have been given in para 14 as extracted above. The above illustration becomes relevant for the facts of the present case. In the present case also, the appellant has raised the claim beyond the three years of completing of the work but within five years of completion of the work. 21. In the present case, the appellant has also contended that there is a defect liability period of two years during which any recovery can be made from the contractor. Further the categorical case of the appellant was that final payment made at 10.04.200 I was the final payment of the undisputed claim and there were other claims of the appellant which were disputed and the payment received on 10.4.2001 was with regard to undisputed claim. There being no adjudication with regard to disputed claim the claim raised by notice dated 23.02.2005 cannot be said to be barred by time or a dead claim. > 22. In the present appeal by IA No. 03 of2012, the appellant has brought certain additional materials for consideration of the Court. By annexure 16 certain certificates which were given by the contractor on 20.02.2001 that is when the final bill was prepared, has been brought on record. The payment was made by cheque dated I 0.04.200 I and para 3/4 of the certificate filed at the 2nd page of the annexure 16 states as follows: _"3. Printed Certificate signed by tlte petitioner at tlte time of receiving payment of tile undisputed part of tile Final Bill._ A B. c D E _Received Rs. 575321-. Tltis payment is in full and final settlement of all money due under C WE/AF CHD I CHD-51 98-99 and I have no f.urt/ier claim in respect of tlte_ F _Sd/-_ _Contractor"_ _"4. Payment by Clteque of tlte undisputed part of tile Final Bill made by tlte dispersing officer, mentio11ed-lierein-below:-_ _Clieq11e No. H_ - _916930 dated 10.4.2001 for Rs. 575321issued in favour of Mis Emm Emt Associates on SB/ AF Cllandigarli Treasury._ G _Sd/-_ _Signature of Dispersing Office"_ H 512 (2016] 5 S.C.R. SUPREME COURT REPORTS A _,_B .23. Para 04 of the above certificate as quoted above clearly mentions payment by cheque of the undisputed part of the final bill and above certificate also clearly indicates that payment on I 0.04.200 I was made of the undisputed part of the final bill which presupposes that there are certain other claims which are disputed. Clause 67 of the contract entered between the parties also uses expressions "undisputed portion of the Final Bill" 24. Appellant had relied on Clause 67 which contains a heading "Recovery From Contractor'' under sub-Clause (t) and (g) which is to the following effect: - c _(/) If, as a result of sucft audit and tecftnica/ examination, any over-payment is discovered in respect of tfte work done under tftis Contract, tfte contractor sftall on demand make payment of a sum equal to tfte amount of over-payment or agree for effecting necessary adjustment from any amounts due to ftim by Government. If ftowever, lie ref uses or neglects_ - D _to make tfte payment on demand or does not agree for effecting adjustment from any amounts due to ftim, Government sltal/ be entitled to take action as in sub-para (a) ltereinbefore. If as a result of suclt audit and tee/mica/ examination any under payment is discovered, tlte amount_ - E _of under payment slta/l be duly paid to tlte Contractor by Government._ - _(g) Provided, tltat, not/ting ltereinbefore contained s/1a// entitled tlte Government to recover any over-payment in respect of any price agreed between tlte C. W.E or tlte G.E._ - F _and tlte Contractor under tfte circumstances specifically prescribed for suclt metftod of assessment and tltilt tlte said rigftt of tlte Government to adjust over-payment from any sum due or from any sum wlticlt may become due to tlte Contractor or from Security Deposit or Security Bond amount and adjust under payment, sltall not extend beyond a period of two years_ - G _from tlte date of payment of tfte undisputed portion of tile Final Bill or in tile case of minus Bill, from tile date, tile net amount of tile final bill is communicated to tlte Contractor._ " 25. In sub-Clause (g) the period of two years under which the Government is entitled to make recovery is "from the date of payment H 513 ## _MIS._ EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS. [ASHOK BHUSHAN, J. ] of the undisputed portion of the final bill". The examination of the additional materials brought on this appeal, does indicate that the case required consideration of relevant bills and certificates and determination on the question as to whether the claim laid by appellant was a dead claim and was not a live claim depended upon scrutiny of relevant documents. The pleadings in the proceeding under Section 11 by the appellant were clearly to the effect that on 10.04.200 I, he was paid only undisputed part and the appellant has reserved his right to raise claim to the disputed part. 26. In view of the Division Bench judgment in _Indian Oil Corporation Ltd._ supra para 14 as extracted above, the present was the case which ought to have been left for the decision by the Tribunal. We, however, have proceeded further to examine the claim raised by the appellant in his notice dated 23.02.2005. The pleadings of the appellant are categorical to the effect that the final payment made on 10.04.2001 was only with regard to undisputed portion and he has reserved his right to raise claim with regard to other disputed claims. 27. The disputed claims having never been adjudicated, we are of the view that there was a dispute which needed an adjudication after looking into all relevant documents, bills and certificates which could have been appropriately examined by Arbitral Tribunal and the observation of the Chief Justice "As the appellant has failed to prima facie show this court that there was a live claim of the appellant" does not commend us. 28. The claim raised by petitioner in the facts of the case could not have been said to be a dead claim. Especially in view of the additional documents which have been placed before us by IA No. 03 of2012. We are thus of the view that the order dated 12.03 .2007 passed in Arbitration Case No. 184 of 2006 and 89 of 2006 deserves to be set-aside. 29. As a consequence thereof, the application made by the appellant under Section 11 of the Act is allowed. We, however, consider it apposite to remit the case to the High Court (designated Judge) to pass consequential orders for appointment of the arbitrator for deciding the disputes which have arisen between the parties. The appointment of the arbitrator may be made in the first instance with the consent of the parties and if, for any reason, it is not possible to do so then the Court will appoint the arbitrator in its discretion. It be done within .one month from the date of the parties appearance. A B c D E F G H -- 514 SUPREME COURT REPORTS [2016] 5 S.C.R. A 30. Parties to appear before the designated Judge in the High Court on 25 .07 .2016 to enable the Court to pass appropriate consequential order as directed above. Both the appeals are accordingly allowed. Kalpana K. Tripathy Appeals allowed. B
End of Judgment Record
Browse All Supreme Court of India (2016) Decisions
2016-03-16

Union of India v. Mis. Ambica Construction

This judgment addresses whether an arbitrator can award pendente lite interest when a contract expressly bars such interest, within the framework of Indian arbitration law. The Union of India approached this dispute after two arbitrators failed to publish an award and after a long procedural history in the Calcutta High Court and various SLPs. The core issue is whether pendente lite interest can be awarded where the contract contains explicit clauses barring such interest, and how this interacts with the implied terms of arbitration under the Arbitration Act, 1940 and, for post-1996 matters, the Arbitration and Conciliation Act, 1996. The Court traces a lineage of decisions (GC Roy; NC Budharaj; Sayeed Ahmed; Harish Chandra; Balimela; Engineers-De-Space-Age; Tehri Hydro) and clarifies that while arbitrators are generally creatures of the contract, their power to award pendente lite interest is bounded by express contractual bars. It concludes that no pendente lite interest can be awarded if the contract expressly prohibits it. The judgment also recognizes Tehri Hydro’s reasoning and clarifies the status of earlier decisions, holding certain observations as overruled or limited prospectively. The result is that the High Court and the award are to be modified to reflect the absence of pendente lite interest, with a reference answered and no costs awarded.”

2016-08-29

Madhya Pradesh State Road Transport Corporation v. Manoj Kumar & Anr.

This is a civil appeal challenging the voluntary retirement scheme (VRS) introduced by the Madhya Pradesh State Road Transport Corporation (MPSRTC) to downsize its workforce as the company faced losses and declining business. The scheme opened on July 1, 2005 and closed on August 1, 2005, with employees permitted to submit their option for voluntary retirement (VRS) within that window. The scheme included a clause stating that once an employee’s option was submitted it could not ordinarily be withdrawn, yet the scheme was a funded, time-bound arrangement requiring the employer to create a fund and to lay out a process for acceptance and settlement. In October 2006, the Corporation issued an amendment extending the period to October 28, 2006, prompting questions whether this extension created a new scheme or was merely an extension of the original. Several employees who had submitted applications sought withdrawal after August 1, 2005, and in some cases after the extension, while the Corporation accepted their VRS applications and disbursed terminal dues. The High Court of Madhya Pradesh upheld the employees’ right to withdraw within the relevant periods, but the Supreme Court concluded that VRS schemes, being contractual and funded, are invitations to offer governed by the Indian Contract Act, and withdrawals are permissible only within the valid period; the extension does not automatically grant a right to withdraw beyond the original window. The Court accordingly set aside some reinstatement orders and disposed of the appeals in favor of the Corporation in most respects.

2016-07-01

Mahipal Singh Rana, Advocate v. State of Uttar Pradesh

The appeal arises from a High Court of Allahabad judgment (Criminal Contempt Petition No.16 of 2004) finding the appellant, an advocate, guilty of criminal contempt for intimidating and berating a Civil Judge, Etah, on two dates (16 April 2003 and 13 May 2003). The Allahabad High Court sentenced him to two months’ simple imprisonment and imposed a fine, with a direction to Bar Council authorities to consider disciplinary action for professional misconduct. On admission to this Supreme Court, the matter was referred to a larger bench to decide whether a case of criminal contempt by a lawyer could also implicate professional misconduct beyond the contempt regime, and whether the Court could exercise suo motu jurisdiction under the Advocates Act if Bar Councils fail to act. The Court examined the separation of powers between contempt proceedings and Bar Council disciplinary processes, the scope of Article 142/129, and the ability to regulate appearance in courts (including the right to practice vs. the right to appear). It held that contempt conviction was justified and upheld the High Court’s finding, but set aside the imprisonment sentence due to the appellant’s advanced age. It sustained a two-year enrollment suspension under Section 24A of the Advocates Act and directed the Bar Councils to suspend the licence for an additional five years, with further appearance restrictions until the contemnor purges himself of contempt. The judgment emphasizes reform of regulatory mechanisms governing the legal profession and the State Bar Councils’ failings in acting on earlier notices.

2016-03-10

CHARANJIT KAUR v. BIKRAM SINGH & ANR.

Charanjit Kaur, wife of Bikram Singh, faced dowry-related harassment under sections 498A and 406 IPC. The trial court convicted the husband and imposed a one-year RI for each offence, with the sentences to run concurrently and a fine of Rs. 1,000/- with default imprisonment. The wife appealed against the conviction and also sought enhancement of punishment; the husband cross-appealed. The mother-in-law was acquitted; the father-in-law had died. The Sessions Court at Kapurthala modified the sentence by permitting the husband to deposit Rs. 2,50,000 payable to the appellant within one month, so that he could obtain the benefit of probation under Section 4(1) of the Probation of Offenders Act, 1958. The wife’s revision before the High Court of Punjab & Haryana at Chandigarh was dismissed in a summary manner, reportedly influenced by the deposit. The Supreme Court, noting the summary disposal and the deposit-driven rationale, held that the impugned order required setting aside so that the matter could be re-heard on merits. It directed remand to the High Court for a fresh decision strictly in accordance with law, without entering into the merits of rival submissions in this order. The decision was delivered by a Single Judge, Justice Shiva Kirti Singh, on March 10, 2016.