Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Single JudgeWrit petition dismissed; no interference with M...

MANAGING DIRECTOR, KERALA STATE ROAD TRANSPORT CORPORATION, THIRUVANANTHAPURAM vs REGIONAL TRANSPORT AUTHORITY, KOTTAYAM & OTHERS

Case / Petition Number:
WP(C).No.37228/2008

Case Synopsis & Summary

This writ petition challenges Exts.P2 and P3 judgments of the State Transport Appellate Tribunal (MVAA Nos.91/2008 and 93/2008) which allowed respondents 3 and 4 to obtain a regular permit as Super Deluxe Service on a route of approximately 454 km (Pulppally–Changanassery), despite KSRTC’s objections. The KSRTC contends that it was not impleaded in the MVAA appeals, that there were objections of overlapping on certain notified routes, and that the draft scheme notification dated 09/05/2007 should bar such grants. The first respondent rejected the application under Kerala Motor Vehicles Rules, holding that the permit could not be granted as Ordinary (Rule 2(oa)), as Fast Passenger (Rule 2(ea)), or as Super Fast (Rule 2(uc)). The STAT, however, allowed the petitions, directing grant of the regular permit as Super Deluxe, subject to counter signature by sister RTAs. The KSRTC argued that impleadment was necessary only if there was scheme violation and that objections regarding overlapping should have been adjudicated by the RTA. The court, finding no scheme violation and noting that the route did not fall within the notified routes, held there was no valid ground to interfere with the STAT judgments. The writ petition was disposed of accordingly, with directions to entertain counter-signature when appropriate.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • ANTONY DOMINIC
Judgment Date
2009-02-16
Court Decision / Holding
Writ petition disposed of. The court held that there was no sufficient ground to interfere with Exts.P2 and P3 and that impleadment of KSRTC was not necessary as there was no scheme violation. The route did not fall within the notified schemes, and objections based on overlapping were not fatal. The KSRTC will be given notice and its objections considered when counter signatures are sought. The petition was dismissed in effect, upholding the STAT judgments.
Final Disposition
Writ petition dismissed; no interference with MVAA judgments; Exts.P2 & P3 stand; counter-signature procedures to be followed when invoked.

Parties to the Case

Appellants / Petitioners

  • THE MANAGING DIRECTOR, KERALA STATE ROAD TRANSPORT CORPORATION, THIRUVANANTHAPURAM REPRESENTED BY LAW OFFICER, SRI,RANJITH JOSEPH

Respondents

  • THE REGIONAL TRANSPORT AUTHORITY, KOTTAYAM REPRESENTED BY ITS SECRETARY
  • THE SECRETARY, REGIONAL TRANSPORT AUTHORITY, KOTTAYAM
  • SMT.V.P.SUKUMARI, VALIYAPARAMBIL, NADAKKAVU P.O. ERNAKULAM
  • SMT.MARIAMMA THOMAS, KUMBALAMTHANATHU HOUSE, AYARKUNNAM KOTTAYAM
  • THE STATE TRANSPORT APPELLATE TRIBUNAL ERNAKULAM

Legal Representation & Advocates

Counsels for Petitioners

  • • MR.K.PRABHAKARAN, SC, K.S.R.T.C.

Counsels for Respondents

  • • MR.P.DEEPAK
  • • MR.K.V.GOPINATHAN NAIR (by Government Pleader SMT.M.R.SREELATHA)

Provisions of Law Cited

Rule 2(oa) Kerala Motor Vehicles RulesRule 2(ea) Kerala Motor Vehicles RulesRule 2(uc) Kerala Motor Vehicles RulesSection 99(2) Motor Vehicles Act

Legal Doctrines & Maxims

  • The emphasis is on the intermediate points, and not on the intermediate places.
  • What is prohibited is overlapping over the nationalised route and not inter-section of any nationalised route or touching a station as terminus.

Submissions & Arguments

Contentions of Appellants / Petitioners

KSRTC argued that the writ petition should challenge Exts.P2 and P3 only on grounds of lack of impleadment and alleged overlapping, and on the effect of the draft notification dated 09/05/2007. It contended that the 1st respondent’s rejection of the application relied on Rule 2(oa), 2(ea) and 2(uc) of the Kerala Motor Vehicles Rules to deny Ordinary, Fast Passenger, and Super Fast permits, respectively. KSRTC asserted that there was no valid scheme violation, and that the appeals could not have been decided without the KSRTC’s involvement where rights could be affected. It also argued that overlapping concerns were not properly addressed, and that the route length (454 km) did not justify a grant of Super Deluxe service, absent proper counter signature by sister RTAs.

Contentions of Respondents

Respondents contended that the route length and public necessity permitted granting the permit as Super Deluxe Service, subject to counter signature by sister RTAs. They relied on the State Transport Appellate Tribunal’s interpretation that a route of 454 km could be regularized as Super Deluxe if fit for higher service upon verification. They defended the decision of the 1st respondent not to grant ordinary/fast service under the specified rules, and argued that KSRTC’s objections about overlapping were limited to certain notified schemes (Wayanad and Thiruvananthapuram–Payyannur) lying outside the 1st respondent’s jurisdiction, and that the draft notification dated 09/05/2007 did not bar consideration where the route did not fall within notified routes.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
K.S.R.T.C. v. The Regional Transport Authority and Others1991(3) ILR (Kerala) 40PositiveCited to support the proposition that overlapping on nationalised routes is governed by the Scheme; the court relied on the intermediate-points doctrine to reject the overlapping contention.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,666 words•~8 min read

In The Court Record

MANAGING DIRECTOR, KERALA STATE ROAD TRANSPORT CORPORATION, THIRUVANANTHAPURAM vs REGIONAL TRANSPORT AUTHORITY, KOTTAYAM & OTHERS

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE ANTONY DOMINIC** **MONDAY, THE 16TH FEBRUARY 2009 / 27TH MAGHA 1930** **WP(C).No. 37228 of 2008(F)** **---------------------------------------** **PETITIONER(S):** - **------------------------** **THE MANAGING DIRECTOR, KERALA STATE ROAD TRANSPORT CORPORATION, THIRUVANANTHAPURAM REPRESENTED BY LAW OFFICER, SRI,RANJITH JOSEPH.** **BY ADV. MR.K.PRABHAKARAN, SC, K.S.R.T.C.** **RESPONDENT(S):** - **--------------------------** **1. THE REGIONAL TRANSPORT AUTHORITY, KOTTAYAM, REPRESENTED BY ITS SECRETARY.** **2. THE SECRETARY, REGIONAL TRANSPORT AUTHORITY, KOTTAYAM.** **3. SMT.V.P.SUKUMARI, VALIYAPARAMBIL, NADAKKAVU P.O. ERNAKULAM.** **4. SMT.MARIAMMA THOMAS, KUMBALAMTHANATHU HOUSE, AYARKUNNAM KOTTAYAM.** **5. THE STATE TRANSPORT APPELLATE TRIBUNAL ERNAKULAM.** **R3 & R4 ADV. MR.P.DEEPAK** **MR.K.V.GOPINATHAN NAIR BY GOVERNMENT PLEADER SMT.M.R.SREELATHA** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 16/02/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** ## **W.P.(C) NO.37228/2008** ## **APPENDIX** ## **PETITIONERS EXHIBITS** **P1:- COPY OF THE PROCEEDINGS DT. 7.12.07.** **P2:- COPY OF THE JUDGMENT DT. 19.2.08 IN M.V.A.A. NO.91/2008.** **P3:- COPY OF THE JUDGMENT DT. 19.2.08 IN M.V.A.A NO.93/08.** **P4:- COPY OF THE PROCEEDINGS DT. 3.4.08.** **P5:- COPY OF THE JUDGMENT DT. 3.9.08 IN WPC. NO.23207/08.** **P6:- COPY OF THE JUDGMENT DT. 6.10.08 IN WPC. NO.29432/08. P7:- COPY OF THE JUDGMENT DT. 26.11.08 IN RP. NO.1249/08 IN WPC. NO.23207/08.** ## **RESPONDENT'S EXHIBITS** **R3(a):- COPY OF THE ROUTE ENQUIRY REPORT DT. 12.12.06.** **R3(b):- COPY OF THE SKETCH DT. 14.11.06.** **R3(c):- COPY OF THE AGENDA NOTES DT. 16.12.06.** **R3(d):- COPY OF THE PROCEEDING S OF THE IST RESPONDENT DT. 21.12.06.** **R3(e):- COPY OF THE JUDGMENT DT. 13.7.07 IN WPC. NO.14567/07. R3(f):- COPY OF THE OBJECTION FILED BY THE IST RESPONDENT DT. 5.12.07. R3(g):- COPY OF THE JUDGMENT IN WPC. NO.8458/08 DT. 25.3.08.** _**/**_ **TRUE COPY/** **P.A. TO JUDGE** **tss** ## ANTONY DOMINIC, J. ------------------------- W.P.(C.) No.37228 of 2008 --------------------------------- Dated, this the 16[th] day of February, 2009 **==> picture [108 x 13] intentionally omitted <==** Challenge in this writ petition is against Exts.P2 & P3 judgments of the STAT in MVAA Nos.91/2008 and 93/2008. 2. The facts of the case are that respondents 3 & 4 herein applied for two regular permits in the route PulppallyChanganassery in respect of stage carriages bearing Regn.Nos.KL- 7/AT-3739 and KL-13/E-2448 as Super Fast/Fast Passenger/LSOS subject to counter signature by the sister RTAs. Ext.R3(a) and R3(b) are the route enquiry report and the sketch respectively. It was reported that the route length is 454 Kms. and the route applied of is an inter-district route covering 7 districts. It was also reported that there is no objectionable overlapping in Kottayam district. Ext.R3(b) sketch shows that there is no overlapping through the notified routes in Kottayam district. 3. Ext.R3(c) is the agenda for the meeting that was held on 21/12/2006. Accordingly, the matter was considered and as is seen from Ext.R3(d), the matter was adjourned on the ground that WP(C) No.37228/2008 -2- concurrence of the sister RTAs is mandatory for considering the application, and directing the Secretary to seek concurrence of the sister RTAs. Ext.R3(d) was challenged by the aforesaid respondents 3 & 4 before this Court in WP(C) No.14567/2007. That writ petition was disposed of by Ext.R3(e) judgment dated 13/07/2007 directing the RTA, Kottayam to consider the application made by respondents 3 & 4 herein for grant of regular permit, if they are otherwise eligible for the same subject to counter signature by the sister RTAs. 4. The matter was accordingly placed before the RTA, Kottayam. Ext.R3(f) is the objection filed by the KSRTC. The KSRTC has given particulars of 11 notified routes. In so far as the Wayanad and Trivandrum-Payyannur schemes are concerned, KSRTC has stated that there is overlapping in the sector Kalpetta-Kozhikkode and Kozhikkode-Thrissur sectors respectively. Further, the KSRTC also stated that the route applied for was in violation of the draft notification dated 09/05/2007. 5. The matter was considered by the 1[st] respondent and by Ext.P1 proceedings, the application was rejected, taking the view that, in view of Rule 2(oa) of the Kerala Motor Vehicles Rules, permit WP(C) No.37228/2008 -3- cannot be granted as Ordinary service, and in view of Rule 2(ea) of the the Rules, permit cannot be granted as Fast Passenger service, and in view of Rule 2(uc) of the Rules, permits cannot be granted as Super Fast service. 6. Respondents 3 & 4 challenged Ext.P1 before the STAT by filing MVAA Nos.91/2008 and 93/2008. True, in these appeals, the KSRTC was not impleaded as a party. The STAT, by Exts.P2 & P3 judgments held that the route length being 454 Kms., permit cannot be granted as Super Fast service, but can be granted as Super Deluxe Service in view of Rule 2(ua) of the Kerala Motor Vehicles Rules. It was also held that depending on the route length, it is always open to the Primary Authority to grant a higher class permit than what was sought for by the applicant, provided the vehicle is operational for such service. On this basis, by Exts.P2 & P3, the appeals were allowed and Ext.P1 was set aside and the 1[st] respondent was directed to grant the regular permit applied for by respondents 3 & 4 subject to counter signature by the sister RTAs, as Super Deluxe Service, if the vehicles offered are fit for such higher class of service. It is these two judgments, which are sought WP(C) No.37228/2008 -4- to be challenged by the learned counsel for the KSRTC in this writ petition. 7. The learned counsel for the KSRTC raised three contentions: (1) That the KSRTC was not impleaded as a party in the appeals filed before the STAT, resulting in Exts.P2 & P3 judgments. (2) That there is objectionable overlapping pointed out in the objection, and neither the RTA nor STAT did consider the same. (3) That the draft notification scheme dated 09/05/2007 was in force and if so, permit could not have been granted. 8. So far as the impleadment of KSRTC in the Appeals is concerned, as already noticed, impleadment of the KSRTC is necessary only if there is scheme violation. In this case, as can be seen from Ext.R3(a) enquiry report and Ext.R3(b) sketch, there was material to the effect that in respect of the route applied for falling within the jurisdiction of the 1[st] respondent, there is no objectionable overlapping. A reading of Ext.P1 also shows that the rejection of the application made by respondents 3 & 4 was also not on the ground of objectionable overlapping, accepting the case of the KSRTC. If that be so, none of the rights of the KSRTC is WP(C) No.37228/2008 -5- questioned in the appeals and hence I cannot find fault with respondents 3 & 4 in not impleading KSRTC in the appeals resulting in Ext.P2 & P3 judgments. 9. In so far as the objectionable overlapping now canvassed by the KSRTC is concerned, as already noticed in Ext.R3(f) objection filed by the KSRTC before the 1[st] respondent, although they have mentioned 13 particulars of the notified routes, violation pointed out is only in respect of Wayanad and ThiruvananthapuramPayyannur schemes. These two violations certainly did not fall within the jurisdiction of the 1[st] respondent and if there is any scheme violation as contended, it is always open to the RTA of the concerned district to consider the case of scheme violation, in terms of the provisions contained under the Motor Vehicles Act and also the impugned judgments. Therefore, these two scheme violations pointed out could not stand in the way of the 1[st] respondent. In that manner, the STAT considered the claim of respondents 3 & 4 and that cannot be faulted. 10. Yet another contention raised is that in view of the draft scheme notification dated 09/05/2007, according to the learned WP(C) No.37228/2008 -6- counsel for the KSRTC, it was impermissible to grant any permit and all that was possible was to grant temporary permit under Section 99(2) of the Act. This contention again cannot be accepted for the reason that going by Ext.R3(a) enquiry report, and Ext.R3(b) sketch, it can be seen that the report is to the effect that the route applied for does not fall within any of the notified routes. If that be so, this notification also cannot stand in the way of respondents 3 & 4. 11. Then it was contended that even going by the sketch produced, the route applied for is touching two intermediate points on the notified route and therefore grant is illegal. This submission of the learned counsel for the petitioner is sought to be contradicted by the learned counsel for respondents 3 & 4 relying on the judgment of the Division Bench of this Court in K.S.R.T.C. v. The Regional Transport Authority and Others 1991(3) ILR (Kerala) 40, where it has been stated thus :- “The emphasis is on the intermediate points, and not on the intermediate places. Thus it is made clear by the Scheme that the notified area covers all the points between Quilon and Alleppey and between intermediate places specified in column (5) of Annexure 'A' to the Scheme. The clear effect of the scheme therefore is, the entire route Quilon-Alleppey being a nationalised WP(C) No.37228/2008 -7- route overlapping on this route between any two points has the effect of offending the Scheme. Therefore by merely avoiding Oachira as the terminus and fixing the District Border as the terminus, the Regional Transport Authority has not succeeded in preventing overlapping of the route between Kayamkulam and District Boarder.” Further, it was also held that what is prohibited is overlapping over the nationalised route and not inter-section of any nationalised route or touching a station as terminus. In my view, this judgment is a complete answer to the contention that is now raised. 12. On the whole, I am satisfied that the petitioner has not made out a case for interference. 13. Needless to say that as and when request for counter signature is made before the sister RTAs, the KSRTC will be issued notice and their objections will also be considered. The writ petition is disposed of as above. (ANTONY DOMINIC, JUDGE) jg
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.