Case Synopsis & Summary

This appeal concerns captive generation and the levy of an additional surcharge under Section 42(4) of the Electricity Act, 2003. The Maharashtra State Electricity Distribution Company Limited challenged an Appellate Tribunal for Electricity order that had held captive consumers not liable to pay the additional surcharge. The Court clarifies the statutory framework: Section 9 permits captive generation and the right to open access for transmission to the destination of the user’s own use, subject to transmission capacity determined by the Central or State Transmission Utility. Crucially, no license from the State Commission is required for a captive generating plant and its dedicated transmission lines, and the right to open access arises from the statute itself. Section 42(4) imposes an additional surcharge only when the State Commission permits a consumer or class of consumers to receive electricity from a person other than the distribution licensee and only to meet the fixed costs of the distribution licensee. Captive consumers, as a separate class under Section 2(15), obtain power for their own use and do not need such permission. Therefore, captive consumers are not liable to pay the 42(4) surcharge. The Supreme Court dismissed the appeals, with no costs, and directed that already collected surcharges be adjusted in future wheeling charges.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M. R. SHAH
  • SANJIV KHANNA
Judgment Date
2021-12-10
Court Decision / Holding
Appeals dismissed. The Court held that captive consumers/captive users are not liable to pay the additional surcharge under Section 42(4) of the Electricity Act, 2003. No order as to costs. The surcharge already recovered from captive consumers shall be adjusted in future wheeling charges; refunds to be facilitated accordingly.
Final Disposition
Appeals dismissed.

Parties to the Case

Appellants / Petitioners

  • MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD.

Respondents

  • M/S JSW Steel Limited and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • G. Saikumar
  • • Samir Malik
  • • Aman Malik
  • • Chandra Prakash

Counsels for Respondents

  • • C. S. Vaidyanathan
  • • Gopal Jain
  • • S. K. Rungta
  • • Dr. A. M. Singhvi
  • • Sajan Poovayya
  • • Mahesh Agarwal
  • • Rishi Agrawala
  • • Aman Anand
  • • Anshuman Srivastava
  • • Rishabh Parikh
  • • Aman Dixit
  • • Shivam Shukla
  • • E. C. Agrawala
  • • Ms. Pratiti Rungta
  • • Prashant Singh
  • • Ms. Amita Singh Kalkal
  • • Hemant Singh
  • • Lakshyajit Singh Bagdwal
  • • Rishabh Sehgal
  • • Pratibhanu Singh Kharola
  • • Ms. Raksha Agarwal
  • • Sharan Balakrishna
  • • Mridul Chakravarty
  • • Gaurav Mitra
  • • Hasan Murtaza
  • • Varun Pathak

Provisions of Law Cited

Electricity Act, 2003 – Section 2(15)Electricity Act, 2003 – Section 9Electricity Act, 2003 – Section 42(4)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant distributor contends that Section 42(4) surcharge is invoked when a consumer or class is permitted by the State Commission to receive supply from a person other than the distribution licensee, to meet the fixed costs of that licensee. It is argued that open access and the associated costs would justify a surcharge, and that the statutory framework allows recovery where the licensee bears fixed costs for supply to consumers. However, captive generation under Section 9—used for own consumption—does not require State Commission permission for supply to a licensee or to other consumers, and open access is subject to transmission facility availability determined by the Central or State Transmission Utility. As captive consumers form a separate class (Section 2(15)), they are not liable for the 42(4) surcharge. This statutory right to captive generation and the absence of requiring permission negate application of Sub-section (4).

Contentions of Respondents

The respondents submit that captive generation is for self-use and that Section 42(4) applies only when a consumer chooses to receive supply from a third party with permission of the State Commission. Since captive users primarily depend on their own captive plants for power, and open access is regulated by the transmission facility, the surcharge should not apply. This aligns with the two-class framework (ordinary consumers versus captive consumers) and preserves the incentive for captive generation. The Appellate Tribunal’s interpretation that captive consumers are not liable to pay the surcharge should stand.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,467 words•~21 min read

In The Court Record

MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v. M/S. JSW STEEL LIMITED

404 SUPREME COURT REPORTS [2021] 9 S.C.R. 404 [2021] 9 S.C.R. ## A MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD. v. ## M/S. JSW STEEL LIMITED & ORS. B (Civil Appeal Nos. 5074-5075 of 2019) ## DECEMBER 10, 2021 ## **[M. R. SHAH AND SANJIV KHANNA, JJ.]** _Electricity Act, 2003 – ss.2(15), 42(4) – State Commission held captive consumers-respondents herein liable to pay additional_ C _surcharge – Appeals filed by the captive consumers – Allowed by Appellate Tribunal – On appeal by distribution licensee, held: Captive consumers incur huge expenditure/invest huge amount for construction, maintainance or operation of a captive generating plant and dedicated transmission lines – Such captive consumers/_ D _captive users who form a separate class other than the consumers defined u/s.2(15) are not liable to pay additional surcharge leviable u/s.42(4), as rightly held by the Appellate Tribunal._ _Electricity Act, 2003 – s.9 – Operation of – Discussed._ _Electricity Act, 2003 – Class of consumers under – Held: As_ E _per the scheme of the Act, there can be two classes of consumersordinary consumer and captive consumers._ _Electricity Act, 2003 – s.42(4) – Applicability of – Discussed._ ## **Dismissing the appeals, the Court** F **HELD : 1.1 On a fair reading of Section 9, it can be seen that captive generation is permitted under sub-section (1) of Section 9. As per subsection (2), every person, who has constructed a captive generating plant and maintains and operates such plant, shall have the right to open access for the purposes of carrying electricity from his captive generating plant to the** G **destination of his use, but of-course subject to availability of adequate transmission facility determined by the Central Transmission Utility or the State Transmission Utility, as the case may be. So, the captive generation / captive use is statutorily provided /available and for which a permission of the State** H 404 MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. 405 LTD. v. M/S. JSW STEEL LIMITED **Commission is not required. Construction and/or maintenance and operation of a captive generating plant and dedicated transmission lines is not subjected to any permission by the State Commission. As provided under Section 9 of the Act, 2003, any person may construct, maintain or operate a captive generating plant and dedicated transmission lines. Merely because the supply of electricity from the captive generating plant through the grid shall be regulated in the same manner as the generating station of a generating company or the open access for the purpose of carrying electricity from the captive generating plant to the destination of his use shall be subject to availability of the adequate transmission facility determined by the Central Transmission Utility or the State Transmission Utility, it cannot be said that for captive generation plant, the State Commission’s permission is required. Right to open access to transmit/carry electricity to the captive user is granted by the Act, and is not subject to and does not require the Sate Commission’s permission. The right is conditioned by availability of transmission facility, which aspect can be determined by the Central or State transmission utility. Only in case of dispute, the State Commission may adjudicate. [Para 9][412-A-G]** **1.2 Sub-section (4) of Section 42 shall be applicable only in a case where the State Commission permits a consumer or class of consumers to receive supply of electricity from a person other than the distribution licensee of his area of supply and only such consumer shall be liable to pay additional surcharge on the charges of wheeling, as may be specified by the State Commission. Captive user requires no such permission, as he has statutory right. As per the Scheme of the Act, there can be two classes of consumers, (i) the ordinary consumer or class of consumers who is supplied with electricity for his own use by a distribution licensee / licensee and; (ii) captive consumers, who are permitted to generate for their own use as per Section 9 of the Act, 2003. [Para 11][413-A-C]** A B C D E F G **1.3 The term “consumer” is defined in Section 2(15). Ordinarily, a consumer or class of consumers has to receive supply** H 406 SUPREME COURT REPORTS [2021] 9 S.C.R. - A **of electricity from the distribution licensee of his area of supply. However, with the permission of the State Commission such a consumer or class of consumers may receive supply of electricity from the person other than the distribution licensee of his area of supply, however, subject to payment of additional surcharge on the charges of wheeling as may be specified by the State** - B **Commission to meet the fixed cost of such distribution licensee arising out of his obligation to supply. There is a logic behind the levy of additional surcharge on the charges of wheeling in such a situation and/or eventuality, because the distribution licensee has already incurred the expenditure, entered into purchase** - C **agreements and has invested the money for supply of electricity to the consumers or class of consumers of the area of his supply for which the distribution license is issued. Therefore, if a consumer or class of consumers want to receive the supply of electricity from a person other than the distribution licensee of his area of supply, he has to compensate for the fixed cost and** - D **expenses of such distribution licensee arising out of his obligation to supply. Therefore, the levy of additional surcharge under sub-section (4) of Section 42 can be said to be justified and can be imposed and also can be said to be compensatory in nature. However, sub-section (4) of Section 42 shall be applicable only in** - E **a case where the State Commission permits a consumer or class of consumers to receive supply of electricity from a person other than the person – distribution licensee of his area of supply. So far as captive consumers/captive users are concerned, no such permission of the State Commission is required and by operation of law namely Section 9 captive generation and distribution to** - F **captive users is permitted. Therefore, so far as the captive consumers / captive users are concerned, they are not liable to pay the additional surcharge under Section 42(4) of the Act, 2003. The Appellate Tribunal has rightly held that so far as the captive consumers/captive users are concerned, the additional surcharge** - G **under sub-section (4) of Section 42 of the Act, 2003 shall not be leviable. The consumers defined under Section 2(15) and the captive consumers are different and distinct and they form a separate class by themselves. So far as captive consumers are concerned, they incur a huge expenditure/invest a huge amount** H MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. 407 LTD. v. M/S. JSW STEEL LIMITED **for the purpose of construction, maintenance or operation of a captive generating plant and dedicated transmission lines. However, so far as the consumers defined under Section 2(15) are concerned, they as such are not to incur any expenditure and/or invest any amount at all. Therefore, if the appellant is held to be right in submitting that even the captive consumers, who are a separate class by themselves are subjected to levy of additional surcharge under Section 42(4), in that case, it will be discriminatory and it can be said that unequals are treated equally. Therefore, such captive consumers/captive users, who form a separate class other than the consumers defined under Section 2(15) of the Act, 2003, shall not be subjected to and/or liable to pay additional surcharge leviable under Section 42(4) of the Act, 2003. The additional surcharge already recovered from the captive consumers/captive users shall be adjusted in the future wheeling charges bills. [Paras 12-14, 16][413-C-H; 414-A-G; 415-C]** CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 50745075 of 2019. A B C D From the Judgment and Order dated 27.03.2019 of the Appellate Tribunal for Electricity, New Delhi in Appeal Nos.311 and 315 of 2018. G. Saikumar, Samir Malik, Aman Malik, Chandra Prakash for M/ s D.S.K. Legal, Advs. for the Appellant. C. S. Vaidyanathan, Gopal Jain, S. K. Rungta, Dr. A. M. Singhvi, Sajan Poovayya, Sr. Advs., Mahesh Agarwal, Rishi Agrawala, Aman Anand, Anshuman Srivastava, Rishabh Parikh, Aman Dixit, Shivam Shukla, E. C. Agrawala, Ms. Pratiti Rungta, Prashant Singh, Ms. Amita Singh Kalkal, Hemant Singh, Lakshyajit Singh Bagdwal, Rishabh Sehgal, Pratibhanu Singh Kharola, Ms. Raksha Agarwal, Sharan Balakrishna, Mridul Chakravarty, Gaurav Mitra, Hasan Murtaza, Varun Pathak, Advs. for the Respondents. E F The Judgment of the Court was delivered by ## **M. R. SHAH, J.** G 1. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the Appellate Tribunal for Electricity, Delhi in Appeal Nos. 311 and 315 of 2018 whereby the Appellate Tribunal has allowed H 408 SUPREME COURT REPORTS [2021] 9 S.C.R. - A the said appeals preferred by the respondents herein – the ‘captive consumers’ and has set aside the order passed by the Maharashtra Electricity Regulatory Commission (hereinafter referred to as the “State Commission”) in Petition No.195 of 2017 by which the State Commission has held that the group of ‘captive consumers’ are liable to pay additional surcharge, Maharashtra State Electricity Distribution Company Limited - B (hereinafter referred to as the “distribution licensee”), has preferred the present appeals. 2. That the appellant as distribution licensee filed a petition before the State Commission for MYT approval for FY 2014-2015, provisional truing up of ARR for FY 2015-2016 and Multi Year Tariff for 3[rd] Control C Period FY 2016-2017 to FY 2019-2020. The said petition was numbered as Case No.48 of 2016. The State Commission held that the additional surcharge leviable under Section 42(4) of the Electricity Act, 2003 (hereinafter referred to as the “Act, 2003”) is not applicable to captive users to the extent of their self-consumption from such plants. The State D Commission also held that the additional surcharge shall be applicable to all consumers who have availed open access to receive supply from sources other than the distribution licensee to which they are connected. 3. The appellant – distribution licensee submitted its revised Review Petition being Case No.195 of 2017, for approval of final true up of E ARR for FY 2015-2016 and 2016-2017, provisional true up of ARR for FY 2017-2018 and approval for revised forecast of ARR for FY 20182019 and 2019-2020, inter alia, including the prayer “to approve additional surcharge for all open access consumers including those sourcing power from CPPS as proposed for FY 2018-2019 to FY 2019-2020”. The Captive Power Producers Association filed their objections including F the objections with respect to levy of additional surcharge on such captive users. That by order dated 12.09.2018, the State Commission passed the order holding that additional surcharge is leviable under Section 42(4) of the Act, 2003 on the captive consumers/captive users. 4. Feeling aggrieved and dissatisfied with the order passed by the G State Commission allowing the levy of additional surcharge from the captive consumers/captive users, the respondents herein – captive users/ captive consumers approached the Appellate Tribunal. By impugned order dated 27.03.2019, the Appellate Tribunal has allowed the said appeals and has set aside the order passed by the State Commission H ordering/permitting to levy the additional surcharge leviable under Section MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. 409 LTD. v. M/S. JSW STEEL LIMITED [M. R. SHAH, J.] 42(4) of the Act, 2003 and has held that the group of captive consumers A are not liable to pay additional surcharge to the distribution licensee. 5. Feeling aggrieved and dissatisfied with the impugned order passed by the Appellate Tribunal holding that the group of captive consumers/captive users are not liable to pay the additional surcharge leviable under section 42(4) of the Act, 2003, appellant – distribution licensee. 6. We have heard the learned counsel appearing for the appellant – distribution licensee as well as learned counsel appearing on behalf of the respective respondents – intervenors – the captive consumers/captive users at length. B C 7. The short question which is posed for the consideration of this Court is : “Whether the captive consumers/captive users are liable to pay the additional surcharge leviable under Section 42(4) of the Electricity Act, 2003? D 8. While deciding the aforesaid issue/question, the relevant provisions of Electricity Act, 2003 namely Sections 9 and 42 are required to be noted/visited, which reads as under:- **“9. Captive generation.-** (1) Notwithstanding anything contained in this Act, a person may construct, maintain or operate a captive generating plant and dedicated transmission lines: Provided that the supply of electricity from the captive generating plant through the grid shall be regulated in the same manner as the generating station of a generating company: Provided further that no licence shall be required under this Act for supply of electricity generated from a captive generating plant to any licencee in accordance with the provisions of this Act and the rules and regulations made thereunder and to any consumer subject to the regulations made under sub-section (2) of section 42. E F G (2) Every person, who has constructed a captive generating plant and maintains and operates such plant, shall have the right to open access for the purposes of carrying electricity from his captive generating plant to the destination of his use: H 410 SUPREME COURT REPORTS [2021] 9 S.C.R. A Provided that such open access shall be subject to availability of adequate transmission facility and such availability of transmission facility shall be determined by the Central Transmission Utility or the State Transmission Utility, as the case may be: Provided further that any dispute regarding the availability of B transmission facility shall be adjudicated upon by the Appropriate Commission. **42. Duties of distribution licensees and open access.-** (1) It shall be the duty of a distribution licensee to develop and maintain an efficient, co-ordinated and economical distribution system in C his area of supply and to supply electricity in accordance with the provisions contained in this Act. (2) The State Commission shall introduce open access in such phases and subject to such conditions, (including the cross subsidies, and other operational constraints) as may be specified within one D year of the appointed date by it and in specifying the extent of open access in successive phases and in determining the charges for wheeling, it shall have due regard to all relevant factors including such cross subsidies, and other operational constraints: Provided that such open access shall be allowed on payment of a E surcharge in addition to the charges for wheeling as may be determined by the State Commission: Provided further that such surcharge shall be utilised to meet the requirements of current level of cross subsidy within the area of supply of the distribution licensee: F Provided also that such surcharge and cross subsidies shall be progressively reduced in the manner as may be specified by the State Commission: Provided also that such surcharge shall not be leviable in case open access is provided to a person who has established a captive G generating plant for carrying the electricity to the destination of his own use: Provided also that the State Commission shall, not later than five years from the date of commencement of the Electricity (Amendment) Act, 2003 (57 of 2003) by regulations, provide such H MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. 411 LTD. v. M/S. JSW STEEL LIMITED [M. R. SHAH, J.] open access to all consumers who require a supply of electricity A where the maximum power to be made available at any time exceeds one megawatt. (3) Where any person, whose premises are situated within the area of supply of a distribution licensee, (not being a local authority engaged in the business of distribution of electricity before the appointed date) requires a supply of electricity from a generating company or any licensee other than such distribution licensee, such person may, by notice, require the distribution licensee for wheeling such electricity in accordance with regulations made by the State Commission and the duties of the distribution licensee with respect to such supply shall be of a common carrier providing non-discriminatory open access. (4) Where the State Commission permits a consumer or class of consumers to receive supply of electricity from a person other than the distribution licensee of his area of supply, such consumer shall be liable to pay an additional surcharge on the charges of wheeling, as may be specified by the State Commission, to meet the fixed cost of such distribution licensee arising out of his obligation to supply. (5) Every distribution licensee shall, within six months from the appointed date or date of grant of licence, whichever is earlier, establish a forum for redressal of grievances of the consumers in accordance with the guidelines as may be specified by the State Commission. (6) Any consumer, who is aggrieved by non-redressal of his grievances under sub-section (5), may make a representation for the redressal of his grievance to an authority to be known as Ombudsman to be appointed or designated by the State Commission. B C D E F (7) The Ombudsman shall settle the grievance of the consumer within such time and in such manner as may be specified by the G State Commission. (8) The provisions of sub-sections (5), (6) and (7) shall be without prejudice to right which the consumer may have apart from the rights conferred upon him by those sub-sections.” H 412 SUPREME COURT REPORTS [2021] 9 S.C.R. - A 9. On a fair reading of Section 9, it can be seen that captive generation is permitted under sub-section (1) of Section 9. As per subsection (2), every person, who has constructed a captive generating plant and maintains and operates such plant, shall have the right to open access for the purposes of carrying electricity from his captive generating plant to the destination of his use, but of-course subject to availability of - B adequate transmission facility determined by the Central Transmission Utility or the State Transmission Utility, as the case may be. So, the captive generation / captive use is statutorily provided / available and for which a permission of the State Commission is not required. The submission on behalf of the appellant that the captive generation under - C Section 9 is subject to the regulations as per first proviso to sub-section (1) of Section 9 and that even open access for the purpose of carrying electricity from his captive generating plant to the destination of his use shall be subject to availability of the adequate transmission facility determined by the Central Transmission Utility or the State Transmission Utility, as the case may be, sub-section (4) of Section 42 shall be applicable - D and such captive users are liable to pay the additional surcharge leviable under sub-section (4) of section 42, has no substance and has to be rejected outright. Construction and/or maintenance and operation of a captive generating plant and dedicated transmission lines is not subjected to any permission by the State Commission. As provided under Section 9 of the Act, 2003, any person may construct, maintain or operate a - E captive generating plant and dedicated transmission lines. Merely because the supply of electricity from the captive generating plant through the grid shall be regulated in the same manner as the generating station of a generating company or the open access for the purpose of carrying electricity from the captive generating plant to the destination of his use - F shall be subject to availability of the adequate transmission facility determined by the Central Transmission Utility or the State Transmission Utility, it cannot be said that for captive generation plant, the State Commission’s permission is required. Right to open access to transmit/ carry electricity to the captive user is granted by the Act, and is not subject to and does not require the Sate Commission’s permission. The - G right is conditioned by availability of transmission facility, which aspect can be determined by the Central or State transmission utility. Only in case of dispute, the State Commission may adjudicate. 10. In light of the above observations and findings, the issue whether such captive users are subject to levy of additional surcharge H leviable under sub-section (4) of Section 42 is required to be considered. MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. 413 LTD. v. M/S. JSW STEEL LIMITED [M. R. SHAH, J.] 11. Sub-section (4) of Section 42 shall be applicable only in a case where the State Commission permits a consumer or class of consumers to receive supply of electricity from a person other than the distribution licensee of his area of supply and only such consumer shall be liable to pay additional surcharge on the charges of wheeling, as may be specified by the State Commission. Captive user requires no such permission, as he has statutory right. At this stage, it is required to be noted that as per the Scheme of the Act, there can be two classes of consumers, (i) the ordinary consumer or class of consumers who is supplied with electricity for his own use by a distribution licensee / licensee and; (ii) captive consumers, who are permitted to generate for their own use as per Section 9 of the Act, 2003. A B C 12. The term “consumer” is defined in Section 2(15), which reads as under :- “(15) “consumer” means any person who is supplied with electricity for his own use by a licensee or the Government or by any other person engaged in the business of supplying electricity to the public under this Act or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity with the works of a licensee, the Government or such other person, as the case may be;” 13. Ordinarily, a consumer or class of consumers has to receive supply of electricity from the distribution licensee of his area of supply. However, with the permission of the State Commission such a consumer or class of consumers may receive supply of electricity from the person other than the distribution licensee of his area of supply, however, subject to payment of additional surcharge on the charges of wheeling as may be specified by the State Commission to meet the fixed cost of such distribution licensee arising out of his obligation to supply. There is a logic behind the levy of additional surcharge on the charges of wheeling in such a situation and/or eventuality, because the distribution licensee has already incurred the expenditure, entered into purchase agreements and has invested the money for supply of electricity to the consumers or class of consumers of the area of his supply for which the distribution license is issued. Therefore, if a consumer or class of consumers want to receive the supply of electricity from a person other than the distribution licensee of his area of supply, he has to compensate for the fixed cost D E F G H 414 SUPREME COURT REPORTS [2021] 9 S.C.R. - A and expenses of such distribution licensee arising out of his obligation to supply. Therefore, the levy of additional surcharge under sub-section (4) of Section 42 can be said to be justified and can be imposed and also can be said to be compensatory in nature. However, as observed hereinabove, sub-section (4) of Section 42 shall be applicable only in a case where the State Commission permits a consumer or class of consumers to receive - B supply of electricity from a person other than the person – distribution licensee of his area of supply. So far as captive consumers/captive users are concerned, no such permission of the State Commission is required and by operation of law namely Section 9 captive generation and distribution to captive users is permitted. Therefore, so far as the captive - C consumers / captive users are concerned, they are not liable to pay the additional surcharge under Section 42(4) of the Act, 2003. In the case of the captive consumers/captive users, they have also to incur the expenditure and/or invest the money for constructing, maintaining or operating a captive generating plant and dedicated transmission lines. Therefore, as such the Appellate Tribunal has rightly held that so far as - D the captive consumers/captive users are concerned, the additional surcharge under sub-section (4) of Section 42 of the Act, 2003 shall not be leviable. 14. Even otherwise, it is required to be noted that the consumers defined under Section 2(15) and the captive consumers are different E and distinct and they form a separate class by themselves. So far as captive consumers are concerned, they incur a huge expenditure/invest a huge amount for the purpose of construction, maintenance or operation of a captive generating plant and dedicated transmission lines. However, so far as the consumers defined under Section 2(15) are concerned, - F they as such are not to incur any expenditure and/or invest any amount at all. Therefore, if the appellant is held to be right in submitting that even the captive consumers, who are a separate class by themselves are subjected to levy of additional surcharge under Section 42(4), in that case, it will be discriminatory and it can be said that unequals are treated equally. Therefore, it is to be held that such captive consumers/captive - G users, who form a separate class other than the consumers defined under Section 2(15) of the Act, 2003, shall not be subjected to and/or liable to pay additional surcharge leviable under Section 42(4) of the Act, 2003. 15. In view of the above and for the reasons stated above, the present appeals fail and deserve to be dismissed and are accordingly H MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. 415 LTD. v. M/S. JSW STEEL LIMITED [M. R. SHAH, J.] dismissed. However, in the facts and circumstances of the case there A shall be no order as to costs. 16. It is reported that pursuant to the interim order passed by this Court dated 01.07.2019, staying the operation and implementation of the impugned order passed by the Appellate Tribunal, the appellant – distribution licensee has recovered the additional surcharge. Therefore, as such once it is held that the captive consumers/captive users are not liable to pay the additional surcharge leviable under Section 42(4) of the Act, 2003, the appellant – distribution licensee has to refund the same. However, considering the fact that there shall be huge liability on the appellant – distribution license if they have to now refund the amount of additional surcharge recovered at a stretch, we direct that the additional surcharge already recovered from the captive consumers/captive users shall be adjusted in the future wheeling charges bills. B C 17. Present appeals are accordingly dismissed with the above observations. D Divya Pandey Appeals dismissed. E F G H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.