Supreme Court of IndiaSupreme Court · 2019Division BenchAppeal dismissed; impugned judgment upheld.

MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD.

Case / Petition Number:
Civil Appeal No.1766 of 2019
Neutral Citation:[2019] 4 S.C.R. 885

Case Synopsis & Summary

This Civil Appeal arises from a dispute under the Telecom Regulatory Authority of India Act, 1997, where Mahanagar Telephone Nigam Ltd. (MTNL) sought to recover Rs 1,10,57,268 plus interest from Tata Communications Ltd. for last‑mile connectivity services under Purchase Order dated 01.10.2008. The Purchase Order constrains liquidated damages to a maximum of 12% for delays. MTNL argued for relief under quantum meruit (Section 70) on the basis that the contract governs the relationship but a portion of the work was performed, and the respondent benefited. The Telecom Disputes Settlement and Appellate Tribunal (TDSAT) found that the full billed amount could not be recovered beyond the 12% cap, deducting Rs.25,83,181 and calculating the balance as payable to MTNL as Rs.84,74,087 with 9% interest from the due date. The Supreme Court analyzed whether quantum meruit under Section 70 is permissible in a contract context and whether damages should be governed by Section 74. It traced authorities on 70 and 74, emphasizing that Section 74 governs contractual breaches and that liquidated damages cannot exceed the contractually fixed amount. The Court upheld the TDSAT order, dismissing MTNL’s appeal and reaffirming that the 12% cap is final; MTNL is entitled to Rs.84,74,087 with 9% interest.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • R. F. Nariman
  • Vineet Saran
Judgment Date
2019-02-27
Court Decision / Holding
Appeal dismissed. The impugned judgment of the TDSAT is upheld. The appellant can claim only Rs.84,74,087 as principal (Rs.1,10,57,268 minus Rs.25,83,181) with interest at 9% from the due date to the date of judgment. The 12% liquidated damages cap under the contract is the final measure of damages, and higher amounts beyond this cap cannot be awarded. The Court thus declines to apply quantum meruit in place of the contract- provided remedy and affirms the Tribunal’s order.
Final Disposition
Appeal dismissed; impugned judgment upheld.

Parties to the Case

Appellants / Petitioners

  • Mahanagar Telephone Nigam Ltd.

Respondents

  • Tata Communications Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • Sumit Chander
  • • Shagufa Salim
  • • Ms. Garima Prashad

Counsels for Respondents

  • • Ms. Dharitry Phookan

Provisions of Law Cited

Section 70 of the Indian Contract Act, 1872Section 74 of the Indian Contract Act, 1872Sections 68, 69, 71, 72 of the Indian Contract Act, 1872Section 73 of the Indian Contract Act, 1872Section 16.2, 16.3, 16.4 of the Purchase Order/Contract

Legal Doctrines & Maxims

  • Quantum meruit
  • Quasi‑contract / restitution
  • Unjust enrichment
  • Liquidated damages vs penalty
  • Genuine pre‑estimate of damages
  • Reasonable compensation

Submissions & Arguments

Contentions of Appellants / Petitioners

MTNL contended that compensation for non‑gratuitous acts can arise under Section 70 even in a contract context, i.e., quantum meruit where the contract does not fix a remedy for the specific situation and where the other party has benefitted. They argued that the unilateral imposition of rentals for dark fibre and the lack of reliable data on actual costs prevented a higher deduction; they urged the Court to consider quantum meruit or a more precise calculation within the bounds of Section 70 and the contract’s liquidated damages clause, arguing that the 12% cap is the ceiling, not an entitlement to additional damages beyond that cap, and that the contract terms should not enable unjust enrichment.

Contentions of Respondents

Tata Communications contended that the contract fixed liquidated damages up to 12% and that Section 70’s quantum meruit remedy does not override express contract terms. They argued that clause 16.2 to 16.4 of the Purchase Order governs damages and that the liquidated damages cap (12%) is final and non‑challengeable. They asserted there was no basis to award damages beyond the stipulated sum and that the claimant’s unilateral imposition of dark‑fibre rents was unauthorized. The respondents urged upholding the Tribunal’s approach and the contract’s terms, and maintaining that quantum meruit is inapplicable where a contract exists and specifies damages.”},

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Moselle Solomon v. Martin & Co.ILR (1935) 62 Cal 612Mentioned OnlyHistorical discussion on Section 70; the judgment notes a split verdict in Moselle, illustrating early debates on Section 70’s reach when contracts exist.
Kanhayalal Bisandayal Bhiwapurkar (Dr.) v. Indarchandji Hamirmalji SisodiaAIR 1947 Nag 84Mentioned OnlyUsed to illustrate the interaction of Section 70 with contract; serves as background rather than a controlling authority in the present case.
Alopi Parshad and Sons Ltd. v. Union of India[1960] 2 SCR 793PositiveApplied to show that quantum meruit cannot displace express contractual terms governing remuneration for work under contract.
Mulamchand v. State of M.P[1968] 3 SCR 214PositiveFoundational discussion on Section 70, quasi‑contract, and the limits of remedy when a contract governs relations.
Orissa Industrial Infrastructure Development Corpn. v. Mesco Kalinga Steel Ltd.(2017) 5 SCC 86PositiveNoted as a later authority that follows the established approach to Section 70/74 in contract matters.
Kailash Nath Associates v. DDA(2015) 4 SCC 136, [2015] 1 SCR 627PositiveCited for the framework of Section 74: genuine pre‑estimate vs penalty; cap on liquidated damages and the principle that compensation must be within statutory limits.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,926 words•~23 min read

In The Court Record

MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD.

885 [2019] 4 S.C.R. 885 MAHANAGAR TELEPHONE NIGAM LTD. A v. ## TATA COMMUNICATIONS LTD. (Civil Appeal No.1766 of 2019) FEBRUARY 27, 2019 B ## **[R. F. NARIMAN AND VINEET SARAN, JJ.]** _Contract Act, 1872 – ss. 74 and 70 – Compensation for breach of contract where penalty stipulated for – Claim in_ quantum meruit _u/s. 70 when parties governed by contract – Permissibility of – Purchase Order wherein respondent was to provide last mile connectivity at two places of the appellant and levy of liquidated damages were to be limited to a maximum of 12% – Bills raised by the respondent for the services rendered amounting to Rs. 2,15,25,512/- – On account of limitation of 12%, the appellants could not have levied and deducted an amount more than Rs. 25,83,181/-, however, the appellant proceeded to unilaterally impose rentals at their own rate of dark fibre – Appellant adjusted the amount from dues payable to the respondent by deduction from the bill raised by the respondent – Respondent filed petition before the tribunal against the appellant for recovery of Rs.1,10,57,268/plus interest thereon – Tribunal held that the principal amount to be paid back to the respondent by the appellant would be Rs.84,74,087/- with 9% interest thereon after deducting Rs.25,83,181/- (12% liquidated damages) from Rs. 1,10,57,268/- – On appeal, held: Instant case is covered by s. 74 – Tribunal rightly held that a maximum of 12% can be levied as liquidated damages under the contract, which would amount to Rs. 25 lakh – Since this clause governs the relations between the parties, contractually speaking a higher figure, cannot be awarded as liquidated damages, which is to be considered as final – Appellant can claim only this sum – Thus, the order of the tribunal upheld – Telecom Regulatory Authority of India Act, 1997._ C D E F G ## **Dismissing the appeal, the Court** **HELD: 1.1 Section 70 occurs in Chapter V of the Contract Act, which chapter is headed, “of certain relations resembling** H 885 886 SUPREME COURT REPORTS [2019] 4 S.C.R. - A **those created by contract”. There are five sections that are contained in this Chapter. Each of them is posited on the fact that there is, in fact, no contractual relationship between the parties claiming under this Chapter. For example, under Section 68, if a person incapable of entering into a contract is supplied necessaries by another person, then the person who has furnished** - B **such supplies becomes entitled to be reimbursed from the property of the person so incapable of entering into the contract. Section 69 also deals with a case where a person has no contractual relationship with the other person mentioned therein, but who is interested in the payment of money which the other person is** - C **bound by law to pay, and who, therefore, pays it on behalf of such person. Such person is entitled to be reimbursed by the other person. Under Section 71, again, the finder of goods spoken of is a person who is fastened with the responsibility of a bailee as there is no contractual relationship between the finder of goods and the goods which belong to another person. Equally, under** - D **Section 72, a person to whom money has been paid or anything delivered by mistake or coercion must repay or return it, or else, such person would be unjustly enriched. Here again, there is no contractual relationship between the parties. It is in this setting that Section 70 occurs. [Para 2] [890-F-H; 891-A-B]** - E **1.2 The instant case is really covered by Section 74 of the** - **Contract Act, which occurs in Chapter VI, which is headed, “of the consequences of breach of contract”. [Para 10] [895-B]** - **1.3 The impugned judgment of TDSAT rightly held that a** - **maximum of 12% can be levied as liquidated damages under the** - F **contract, which sum would amount to a sum of INR 25 lakh. Since this clause governs the relations between the parties, obviously, a higher figure, contractually speaking, cannot be awarded as liquidated damages, which are to be considered as final and not challengeable by the supplier. This being the case, the appellant** - G **can claim only this sum. Anything claimed above this sum would have to be refunded to the respondent. The impugned judgment of the TDSAT is upheld. [Paras 13, 14] [897-G-H; 898-A-B]** H 887 MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD. _Moselle Solomon v. Martin & Co._ **ILR (1935) 62 Cal 612;** _Kanhayalal Bisandayal Bhiwapurkar (Dr.) v. Indarchandji Hamirmalji Sisodia_ **AIR 1947 Nag 84;** _Alopi Parshad and Sons Ltd. v. Union of India_ **[1960] 2 SCR 793;** _Mulamchand v. State of M.P_ **. [1968] 3 SCR 214;** _Orissa Industrial Infrastructure Development Corpn. v. Mesco Kalinga Steel Ltd._ **(2017) 5 SCC 86;** _Kailash Nath Associates v. DDA_ **(2015) 4 SCC 136 : [2015] 1 SCR 627** _**–**_ **referred to** A B ## **Case Law Reference** |**Case**|**Law Reference**||| |---|---|---|---| |**(1935) 62 Cal 612**|**referred to**|**Para 3**|C| |**AIR 1947 Nag 84**|**referred to**|**Para 4**|| |**[1960] 2 SCR 793**|**referred to**|**Para 5**|| |**[1968] 3 SCR 214**|**referred to**|**Para 6**|| |**(2017) 5 SCC 86**|**referred to**|**Para 7**|D| |**[2015] 1 SCR 627**|**referred to**|**Para 11**|| CIVIL APPELLATE JURISDICTION: Civil Appeal No.1766 of 2019. From the Judgment and Order dated 25.06.2018 of the Telecom Disputes Settlement and Appellate Tribunal, New Delhi in TP No.465 of 2012. E Sumit Chander, Shagufa Salim, Ms. Garima Prashad, Advs. for the Appellant. Ms. Dharitry Phookan, Adv. for the Respondent. F The Judgment of the Court was delivered by **R. F. NARIMAN, J.** 1. The present appeal arises out of a dispute under the Telecom Regulatory Authority of India Act, 1997. The relief sought through a petition before the Telecom Disputes Settlement and Appellate Tribunal, New Delhi [“ **TDSAT** ”] by the respondent, Tata Communication Ltd. against the appellant, Mahanagar Telephone Nigam Ltd., is for a recovery of a sum of INR 1,10,57,268/- plus interest thereon. The question that arose between the parties is whether the appellant G H 888 SUPREME COURT REPORTS [2019] 4 S.C.R. - A was justified in adjusting this amount from the dues payable to the respondent by deduction from the bills raised by the respondent. Since the Purchase Order dated 01.10.2008 forms the basis for the claim, it is important to set out clauses 4 and 8 of the said Purchase Order as under: - B “ **4.SCOPE OF ORDER** xxx xxx xxx - C iv. Termination of the bandwidth on STM-1 would be done at the MTNL sites/locations in Delhi (Kidwai Bhawan and Nehru Place) and Mumbai (Fountain Head & Prabha Devi) respectively as per the requirement with redundancy in last mile connectivity. For this bandwidth termination purpose, optical/electrical converter, cable and any other hardware/software etc. required, if any, would be arranged by the bidder free of cost.” xxx xxx xxx D ## “ **8. DELIVERY SCHEDULE** (i) The physical connectivity for bandwidth should be completed within two months from the date of place of Purchase Order.” The TDSAT, on considering this Purchase Order, held: E F G “ **25.** At this stage, it falls for consideration as to what relief the petitioner is entitled to on the basis of strength of its own case. For this purpose, it is useful to note at the outset that the petitioner was required to provide the last mile connectivity as per paragraph 4(iv) of the P.O. within two months. It is also not in dispute that petitioner did not provide the required connectivity not only by December 2008 but even by time when it chose to terminate the contract on 11.01.2011. The defence pleaded and argued on behalf of petitioner is that it was neither given access to the buildings/ premises of the respondents nor the permission for affecting the last mile connectivity. This stand was sought to be justified by placing reliance on Emails written by the petitioner on 01.06.2010 which is more than a year after grant of permission by Delhi and Mumbai units around March and April 2009. On going through the communication dated 01.06.2010, it is evident that the plea that respondents did not allow entry to the petitioner into their H 889 MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.] premises in Mumbai has been raised quite belatedly and does not appear to be correct and convincing. Hence, we find petitioner’s case to be weak and unacceptable in so far as it puts the blame totally upon the respondent for its inability or failure to provide the last mile connectivity. No doubt there was some delay by the respondents at the initial stage but that alone cannot justify or absolve petitioner’s total failure. **26.** If we had reliable materials to find out the exact cost of providing the last mile connectivity at each of the two premises in Mumbai and Delhi, we would have reduced that much amount from the claim of the petitioner and allowed the rest. That would have served the interest of justice and prevented unjust enrichment of the petitioner. However, in absence of such reliable materials as to actual costs which the petitioner has saved by non-compliance with the requirements of paragraph 4(iv) of the P.O., we have looked closely at the case of both the parties and we find that at best the respondents could have invoked clause 16 and more particularly, clause 16.2 which provide for liquidated damages in certain eventualities like failure to deliver the stores/services or to install and commission the project in whole or in part. The admitted default on the part of the petitioner can safely be treated as failure or delay affecting the installation/commissioning of a part of the project requiring last mile connectivity. In such a case, as per clause 16.2(b) of the Agreement (P.O.), liquidated damages can be levied on the affected part of the project. As per clause 16.2(c), the liquidated damages must be limited to a maximum of 12%. In the present case the full amount billed and receivable by the petitioner for services rendered is disclosed as Rs.2,15,25,512/-, hence, on account of limitation of 12%, the respondents could not have levied and deducted an amount more than Rs.25,83,181/-. Instead of adopting this lawful course, the respondents proceeded to unilaterally impose rentals at their own rate of dark fibre. Such action of the respondents amounts to adjudicating a claim in its own favour without any authority for such unilateral act either under Section 70 of the Contract Act or under any of the provisions of the Contract(P.O.). A B C D E F G xxx xxx xxx H 890 SUPREME COURT REPORTS [2019] 4 S.C.R. A **28.** As a result of aforesaid discussion, the claim of the petitioner is allowed but in part only. The principal amount which the respondent must refund or pay back to the petitioner would be Rs.1,10,57,268 – Rs.25,83,181= Rs.84,74,087/-. Petitioner has also claimed an amount of Rs.66,33,414/- by way of interest from the date the amounts became due and upto 15.07.2012. It has B calculated this amount by applying a rate of 18%. The calculations are in Annexure P-14 which discloses the dates when the short payments were made after deductions. We are not persuaded to allow interest @ 18% in absence of any such stipulation in the Agreement (P.O.). Hence, while allowing the principal amount of C Rs.84,74,087/- in favour of the petitioner, we direct payment of interest at the rate of 9% from the date the amounts became due upto the date of this judgment/order.” A 2. Having heard the learned counsel for both sides, one neat question arises before this Court, which is, whether, when parties are D governed by contract, a claim in _quantum meruit_ under Section 70 of the Indian Contract Act, 1872[“ **Contract Act** ”] would be permissible. Section 70 of the Contract Act reads as under: “ **70. Obligation of person enjoying benefit of non-gratuitous act.—** Where a person lawfully does anything for another person, E or delivers anything to him, not intending to do so gratuitously, and such other person enjoys the benefit thereof, the latter is bound to make compensation to the former in respect of, or to restore, the thing so done or delivered.” This Section occurs in Chapter V of the Contract Act, which F chapter is headed, “of certain relations resembling those created by contract”. There are five sections that are contained in this Chapter. Each of them is posited on the fact that there is, in fact, no contractual relationship between the parties claiming under this Chapter. For example, under Section 68, if a person incapable of entering into a contract is supplied necessaries by another person, then the person who has furnished G such supplies becomes entitled to be reimbursed from the property of the person so incapable of entering into the contract. Section 69 also deals with a case where a person has no contractual relationship with the other person mentioned therein, but who is interested in the payment of money which the other person is bound by law to pay, and who, H 891 MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.] therefore, pays it on behalf of such person. Such person is entitled to be A reimbursed by the other person. Under Section 71, again, the finder of goods spoken of is a person who is fastened with the responsibility of a bailee as there is no contractual relationship between the finder of goods and the goods which belong to another person. Equally, under Section 72, a person to whom money has been paid or anything delivered by B mistake or coercion must repay or return it, or else, such person would be unjustly enriched. Here again, there is no contractual relationship between the parties. It is in this setting that Section 70 occurs. 3. An early judgment reported as **Moselle Solomon v. Martin & Co.** , ILR (1935) 62 Cal 612 resulted in a split verdict between the two judges on the point of whether Section 70 of the Contract Act can apply when there is, in fact, a contract between the parties. Lort-Williams, J. held: “There remains to be decided the question whether the second defendant is liable under section 70 of the Indian Contract Act and to what extent. The remedy provided by this section is not dependent upon the law relating to the liabilities of principal and agent. It is an independent remedy, which is based upon a different cause of action, namely, upon whether a person has lawfully done anything for another or has delivered anything to him not intending to do so gratuitously, and such other person has enjoyed the benefit thereof. If so, he must either make compensation in respect of, or restore the thing so done or delivered.” C D E (at page 619) On the other hand, Jack, J. held: F “As regards the appeal, it is clear that the second defendant cannot be held liable under section 70 of the Contract Act, in as much as this is a case of contract and, where there is an express contract, section 70 has no application, as shown by the heading of Chapter V of the Act, in which the section finds a place. It is headed “Of Certain Relations Resembling Those Created by Contract”, G evidently excluding relations actually created by contract, as in this case. The Contract Act is, however, not exhaustive.” (at page 623) H 892 SUPREME COURT REPORTS [2019] 4 S.C.R. A 4.In **Kanhayalal Bisandayal Bhiwapurkar (Dr.) v. Indarchandji Hamirmalji Sisodia** , AIR 1947 Nag 84,a learned Single Judge of the High Court was dealing with an application by an eyespecialist of repute who wished to recover an amount of INR 188/- as the price of professional work, i.e., getting a cataract removed in accordance with an agreement with one Mt. Laxmibai and her son-inB law, Mohan Lal, by which agreement, the said operation was to be performed. An appeal to Sections 68 and 70 of the Contract Act was turned down in the following terms: “ **10.** In the course of the argument, an appeal was made to the principles underlying Ss. 68 and 70, Contract Act, for making the C husband liable. Indeed S. 68, deals with the supply of necessaries but that is in respect of a person incapable of entering into a contract or “any one whom he is legally bound to support”, i.e. the dependent of a person incompetent to contract. Indarchandji was not incompetent to contract and this section is inapplicable to D him. As to S. 70, it must be observed that this section cannot be availed of by a person who relies on an express contract as the plaintiff alleged to have entered into with Mt. Laxmibai in this case. The husband never entered into the picture when the plaintiff settled the terms with her. Nor is there anything to show how the husband received any benefit. It is only actual benefit which will E famish a ground of action. If the wife had been cured of her ailment completely, perhaps that circumstance might be material; but there is no evidence on the point.” 5. In **Alopi Parshad and Sons Ltd. v. Union of India** , (1960) 2 F SCR 793, this Court dealt with an arbitration award which, _inter alia_ , awarded certain amount on the basis of _quantum meruit_ . In setting aside the Award on the ground of error apparent on the face of the record, this Court held: “…… _Ghee_ having been supplied by the Agents under the terms of the contract, the right of the Agents was to receive remuneration G under the terms of that contract. It is difficult to appreciate the argument advanced by Mr. Chatterjee that the Agents were entitled to claim remuneration at rates substantially different from the terms stipulated, on the basis of _quantum meruit_ . Compensation _quantum meruit_ is awarded for work done or services rendered, H 893 MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.] when the price thereof is not fixed by a contract. For work done A or services rendered pursuant to the terms of a contract, compensation _quantum meruit_ cannot be awarded where the contract provides for the consideration payable in that behalf. _Quantum meruit is_ but reasonable compensation awarded on implication of a contract to remunerate, and an express stipulation B governing the relations between the parties under a contract, cannot be displaced by assuming that the stipulation is not reasonable……” (at page 809) 6. In **Mulamchand v. State of M.P.** ,(1968) 3 SCR 214, this Court held that the provisions of Section 175(3) of the Government of India Act are mandatory in character and based on public policy. Therefore, the formalities that are stipulated when contracts are entered into on behalf of the Government cannot be waived or dispensed with. In dealing with a claim made under Section 70 of the Contract Act, this Court then went on to hold: “…… In other words, if the conditions imposed by Section 70 of the Indian Contract Act are satisfied then the provisions of that section can be invoked by the aggrieved party to the void contract. The first condition is that a person should lawfully do something for another person or deliver something to him; the second condition is that doing the said thing or delivering the said thing he must not intend to act gratuitously; and the third condition is that the other person for whom something is done or to whom something is delivered must enjoy the benefit thereof. If these conditions are satisfied, Section 70 imposes upon the latter person the liability to make compensation to the former in respect of, or to restore, the thing so done or delivered. The important point to notice is that in a case falling under Section 70 the person doing something for another or delivering something to another cannot sue for the specific performance of the contract, nor ask for damages for the breach of the contract, for the simple reason that there is no contract between him and the other person for whom he does something or to whom he delivers something. So where a claim for compensation is made by one person against another under Section 70, it is not on the basis of any subsisting contract between C D E F G H 894 SUPREME COURT REPORTS [2019] 4 S.C.R. A the parties but on a different kind of obligation. The juristic basis of the obligation in such a case is not founded upon any contract or tort but upon a third category of law, namely, quasi-contract or restitution……” (at pp. 221-222) B 7. This judgment has been recently referred to and followed in **Orissa Industrial Infrastructure Development Corpn. v. Mesco Kalinga Steel Ltd.** , (2017) 5 SCC 86 at paragraph 21. 8. Indeed, the aforesaid position in law is made clearer by Section 73 of the Contract Act. Section 73 reads as follows: C D “ **73. Compensation for loss or damage caused by breach of contract.—** When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach. E F **Compensation for failure to discharge obligation resembling those created by contract.—** When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract. _Explanation_ .—In estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account.” G 9. This Section makes it clear that damages arising out of a breach of contract is treated separately from damages resulting from obligations resembling those created by contract. When a contract has been broken, damages are recoverable under paragraph 1 of Section 73.When, H 895 MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.] however, a claim for damages arises from obligations resembling those A created by contract, this would be covered by paragraph 3 of Section 73. 10. Indeed, the present case is really covered by Section 74 of the Contract Act, which occurs in Chapter VI, which is headed, “of the consequences of breach of contract”. Section 74 states: B “ **74. Compensation for breach of contract where penalty stipulated for.** — When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether C or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for. _Explanation_ .—A stipulation for increased interest from the date of default may be a stipulation by way of penalty. _Exception_ .—When any person enters into any bail-bond, recognizance or other instrument of the same nature, or, under the provisions of any law, or under the orders of the Central Government or of any State Government, gives any bond for the performance of any public duty or act in which the public are interested, he shall be liable, upon breach of any condition of any such instrument, to pay the whole sum mentioned therein. _Explanation_ .—A person who enters into a contract with Government does not necessarily thereby undertake any public duty, or promise to do an act in which the public are interested.” D E F 11. In **Kailash Nath Associates v. DDA** , (2015) 4 SCC 136, after considering the case law on Section 74, this Court held: “ **43.** On a conspectus of the above authorities, the law on compensation for breach of contract under Section 74 can be G stated to be as follows: **43.1.** Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach H 896 SUPREME COURT REPORTS [2019] 4 S.C.R. A can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the B amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the court cannot grant reasonable compensation. C D **43.2.** Reasonable compensation will be fixed on well-known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act. **43.3.** Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a sine qua non for the applicability of the section. **43.4.** The section applies whether a person is a plaintiff or a defendant in a suit. **43.5.** The sum spoken of may already be paid or be payable in future. E **43.6.** The expression “whether or not actual damage or loss is proved to have been caused thereby” means that where it is possible to prove actual damage or loss, such proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the F contract, if a genuine pre-estimate of damage or loss, can be awarded.” 12. In the present case, clauses 16.2 to 16.4 are relevant, and are set out as under: ## “ **16.2 (a)FOR DELIVERY OF STORES:** G Should the supplier fail to deliver the store/services or any consignment thereof within the period prescribed for delivery, the purchaser shall be entitled to recover 0.5% of the value of the delayed supply for each week of delay or part thereof for H 897 MAHANAGAR TELEPHONE NIGAM LTD. v. TATA COMMUNICATIONS LTD. [R.F. NARIMAN, J.] a period up to 10 (TEN) weeks and thereafter at the rate of A 0.7% of the value of the delayed supply for each week of delay or part thereof for another TEN weeks of delay. In the case of package supply where the delayed portion of the supply materially hampers installation and commissioning of the systems, L/D charges shall be levied as above on the total B value of the concerned package of the Purchase Order. However, when supply is made within 21 days of QA clearance in the extended delivery period, the consignee may accept the stores and in such cases the LD shall be levied upto the date of QA clearance. ## **16.2 (b)FOR INSTALLATION & COMMISSIONING** Should the supplier fail to install and commission the project within the stipulated time the purchaser shall be entitled to recover 0.5% of the value of the purchase order for each week of delay or part thereof for a period upto 10 (TEN) weeks and thereafter @ 0.7% of the value of purchase order for each week of delay or part thereof for another 10 (TEN) weeks of delay. In cases, where the delay affects installation/ commissioning of part of the project and part of the equipment is already in commercial use, then in such cases, LD shall be levied on the affected part of the project. C D E **16.2 (c).** The Liquidated Damages, as per Clause 16.2(a) and 16.2(b) above shall be limited to a maximum of 12%, even in case the DP extension is given beyond 20 weeks. **16.3.** Provisions contained in Clause 16.2(a) shall not be applicable for durations (periods) which attract L.D. against clause 16.2(b) above. F **16.4.** Quantum of liquidated damages assessed and levied by the purchaser shall be final and not challengeable by the supplier.” 13. As has been correctly held by the impugned judgment, a maximum of 12% can be levied as liquidated damages under the contract, which sum would amount to a sum of INR 25 lakh. Since this clause governs the relations between the parties, obviously, a higher figure, contractually speaking, cannot be awarded as liquidated damages, which G H 898 SUPREME COURT REPORTS [2019] 4 S.C.R. - A are to be considered as final and not challengeable by the supplier. This being the case, the appellant can claim only this sum. Anything claimed above this sum would have to be refunded to the respondent. 14. In this view of the matter, we uphold the impugned judgment of the TDSAT and dismiss the present appeal. B Nidhi Jain Appeal dismissed. C D E F G H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.