MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.

Case / Petition Number:
Civil Appeal No. 9732 of 2016
Neutral Citation:[2016] 7 S.C.R. 127

Case Synopsis & Summary

This appeal arises from a contractual dispute between Mahanadi Coalfields Ltd. (MCL) and Dhansar Engineering Co. Pvt. Ltd. (the respondents) over a 2003 contract (NIT-276) for the extraction and transfer of coal using surface miners at Lakhanpur OCP. Clause 5 of the agreement permits a variation of +/- 30% in tendered quantity while the contract is subsisting; the contract period was originally through 15 April 2004 and was extended to 15 July 2004 at the respondents’ request. In June 2004, MCL approved an increase of 30% in quantity at the existing rate, before the extended expiry, raising questions about the permissibility of late variation and the corresponding extension of time. The respondents later sought to close the contract due to financial hardship, while MCL refused, insisting the contract be completed and the unfinished portion re-tendered to a rival at a higher rate. The respondents withdrew from operations; MCL imposed penalties and claimed damages for the unfinished work performed through a third party. The High Court quashed the penalty and directed release of dues. The Supreme Court held that Clause 5 must be read with the contract as a whole, accepted that the employer could extend time for the enhanced quantity under other clauses, but found the respondents liable for breach in not completing the 130% quantity within the contract term or extended term. The Court partly allowed the appeal, set aside the High Court order, and left open the quantum of penalties, with liberty for representation. The decision contemplates recovery of financial loss while permitting consideration of penalty waivers under the contract’s terms.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • T. S. Thakur
  • A. M. Khanwilkar
Judgment Date
2016-09-27
Court Decision / Holding
Partly allowing the appeal. The Supreme Court held that Clause 5 cannot be read in isolation and must be read with the contract as a whole. It held that the employer could extend the contract period and allot extra work up to 30% during subsistence with proper invocation of other clauses. However, the respondents breached by not completing the balance work within the extended period, making them liable for the unfinished work’s financial loss and the related penalties to the extent permitted. The judgment set aside the High Court’s order and disposed of the writ petition reliefs in terms, while leaving the quantum of penalty open and permitting the respondents to make representations to the appellants for waiving the penalty in light of the contract’s terms. The appeal is partly allowed with no costs.
Final Disposition
Partly allowed

Parties to the Case

Appellants / Petitioners

  • MAHANADI COALFIELDS LTD. & ORS.

Respondents

  • M/S. Dhansar Engineering Co. Pvt. Ltd.
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Gourab Banerji, Sr. Adv.
  • • K. N. Madhusoodhanan
  • • T. G. Narayanan Nair
  • • S. A. Haseeb
  • • Sahil Tagotra, Adv.

Counsels for Respondents

  • • Rakesh Dwivedi, Sr. Adv.
  • • Arunabh Chowdhury
  • • Anupam Lal Das
  • • Vaibhav Tomar
  • • Ms. Shruti Choudhry
  • • Karma Dorjee
  • • Anirudh Singh
  • • Ms. Barnii Chowdhury, Advs. for the Respondent

Provisions of Law Cited

Clause 2Clause 5Clause 11.0 (Variation in Scheduled Quantity, Extent and Rate)Clause 13 (Time for Completion of Contract)Clause 14.0 (Extension of Date of Completion)Clause 30.0 (Default and Penalty)Clause 30.1 (Loss or Damage)Clause 30.2 (Shortfall Penalty in Mechanical Excavation and Loading)Clause 30.3 (Waiver of Penalty)Clause 31.0 (Settlement of Disputes)Clause 16 (Forfeiture of Earnest Money)NIT 276/ LOI (as context)Article 226 of the Constitution of India

Legal Doctrines & Maxims

  • Read the contract as a whole, not in isolation
  • A clause permitting variation does not exempt performance of the contract, including extensions when warranted by other clauses
  • If a penalty is claimed under a contract, the claimant must prove the loss or damage incurred (Mau Ia Bux v. Union of India)
  • The availability of an alternative remedy under contract does not automatically bar extraordinary/writ relief under Article 226 in appropriate cases
  • Not every contention requiring the setting aside of a contractual order can be sustained merely because there is a remedy under the contract; courts can exercise supervisory jurisdiction in appropriate circumstances

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that Clause 5 of the contract permits a 30% variation in quantity to be exercised even during subsistence of the contract and that time extensions under other clauses (e.g., Clause 14.0) could accommodate the completion of the enhanced quantity. They maintained that an extension was granted in response to the respondents’ requests and that the respondents were bound to complete the enhanced quantity, failing which they would be liable for compensation and penalties for the unfinished work, including losses arising from hiring a third party. They further argued that the High Court should not entertain a purely contractual dispute under Article 226 when an internal dispute-resolution mechanism (Clause 31) existed and that the Board’s penalties were justified under the contract.

Contentions of Respondents

The respondents argued that the 30% extra quantity could not be allotted at the fag end of the extended contract period without 45 days’ clear notice as required by Clause 5 and thus violated the contract. They contended the penalty measures were unjustified, especially since there was no proven loss of production, and the contract had been re-tendered with a higher rate. They argued that the High Court correctly quashed the penalty and that the Board’s actions lacked transparency and proper justification. They urged that the writ petition was maintainable under Article 226 and that the remedy in Clause 31 should suffice. They asserted financial hardship compelled withdrawal and sought relief including waiver of penalties.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (8)

Case NameCitationTreatmentExplanation
Mau Ia Bux v. Union of India1969 2 SCC 554PositiveUsed to establish the principle that penalties under a contract require proof of loss; a sum named as penalty without showing actual loss is not automatically enforceable.
Gorkha Security Services v. Government (NCT of Delhi) & Ors.2014 9 SCC 105Mentioned OnlyCited among authorities; not relied upon decisively in the judgement.
Kumari Shrilekha Vidyarthi & Ors v. State of U.P.1991 1 SCC 212Mentioned OnlyReferenced in the footnotes; not pivotal to the decision.
Popcorn Entertainment v. City Development Corporation2007 9 SCC 593Mentioned OnlyCited to discuss alternative remedies vs. writ petitions; not a controlling authority in this case.
Harbanslal Sahnia & Anr. v. Indian Oil Corporation Ltd. & Ors.2013 2 SCC 107Mentioned OnlyListed among the cited precedents without being determinative of the core ruling.
Union of India & Ors. v. Tantia Construction Pvt. Ltd.2011 5 SCC 697Mentioned OnlyCited as authority in context; not foundational to the main holding.
MP State Agro Industries Development Corpn. & Anr. v. Jahan Khan2007 10 SCC 88Mentioned OnlyCited as authority; not central to the decision.
Whirlpool Corporation v. Registrar of Trade Marks, Mumbai1998 8 SCC 1Mentioned OnlyListed among authorities without driving the outcome.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•9,668 words•~44 min read

In The Court Record

MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.

# [2016] 7 S.C.R. 127 # MAHANADI COALFIELDS LTD. & ORS. A v. MIS. DHANSAR ENGINEERING CO. PVT. LTD. & ANR. (Civil Appeal No. 9732of2016) SEPTEMBER 27, 2016 [T. S. THAKUR, CJI AND A. M. KHANWILKAR, J.] _Contract_ - _Work contract_ - _For extraction and transfer of Coal/Coal Measure Strata by deploying surface 111iners_ - _As per the terms and conditions of the tender docu111ent as well as the agreement, the tender quantity could be reduced or increased by 30% on the sa111e ter111s and conditions_ - _Ti111e for co111pletion of contract work was extended at the request of the contractor_ - _During the subsistence of the contract period appellant-company passed order for increase of 30% extra quantity_ - _The contractor requested the company for closure of contract and informed its intention to withdraw fro111 operation after full contract period due to financial hardship_ - _The. company therefore gave lhe re111aining work to a third party at higher rate_ - _Co111pany i111posed penalty on the contractor for non-execution of lhe remaining work_ - _The penalty was inclusive of the financial loss incurred by the company due to allocation of that work at higher rate_ - _Contractor filed writ petition_ - _Petition allowed by High Court_ - _On appeal, held: Clause 5 of the agreement empoil'ered lhe company to increase or reduce the quantify_ - _of work by 30%, whilst the contract was subsisting Therefore, obligation of contractor to complete the extra work in ter111s of the contract within the contract period or extended period was imperative_ - _Contractor co111mitted breach of contractual obligation in not completing the balance work_ - _The contractor is liable to compensate for the financial loss suffered by the company in_ - _assigning the remaining work at higher rate However, liberty is granted to the contractor to make representation to the co111pany requesting to waive the penally in terms of the contract._ Partly allowing the appeal, the Court HELD: 1. Clause 5 of the Contract cannot be read in isolation. The other terms and conditions of the contract must be read as a whole. Clause 5 of the agreement dated 26[1] h May 2003 posits authority in the appellants to reduce or increase the tendered quantity by +/- 30%, whilst the contract is subsisting. 127 B c D E F G H 128 [2016) 7 S.C.R. SUPREME COURT REPORTS - A Indisputably, the original contract period was upto IS•h April, 2004. At the instance of the respondents, the same stood extended till ts•h July 2004. The extra 30% work was allotted to the respondents on 11 •h June 2004, before expiry of the extended contract period i.e. 15[1] h July 2004. As the contract period was extended and that decision was allowed to attain finality, it - B inevitably obliged the respondents to fulfill all the contractual stipulations under the original agreement including to complete the assigned quantity of work - be it original quantity or extra quantity - before tS•h July 2004. The fact that they had to suffer financial loss due to low contract rate could not be cited as an - c excuse to extricate from that contractual qbligation. [Para 18] J148-F-H; 149-AJ 2. Failure to comply with the contractual obligation of executing the original quantity of work or the extra work, as the case may be, must visit the respondents with liability to D compensate the appellants in terms of other express clauses of the contract to the extent of unfinished work and in particular the financial loss suffered by the appellants for getting the same work executed through a third agency at a higher rate. The fact that the respondents executed 108.47% of work before lS'h July 2004, could be no justification to relieve them of their obligation E to compensate the appellants with suitable amount for the unfinished contract work (out of 130%). [Para 19) (149-B-C] 3. It is not correct to say that the extra quantity of work could not have been allotted to them, absent 45 clear days notice that too at the fag end of the contract period. It is one thing to say F that the contractor should be given suffieient time to complete the extra work commensurate with the extra quantity required to be executed by him. However, in law, it is not open to contend that even though the contract period is still subsisting, the principal (appellants) could not have exercised its option to increase the quantity of work to the extent permissible under G that clause, to be executed by the contractor within the contract period. The principal (appellants) could be asked to exercise their option to extend the contract period beyond ts•h July, 2004, to enable the respondents to complete the unfinished extra work. If such request were to be made by the respondents, there would H have been corresponding obligation on the appellants to extend MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR 129 ENGINEERING CO. PVT. LTD. & ANR. the contact period commensurate with the increased quantity of work in terms of clause 5 of the agreement. The respondents, instead, opted to walk out of the contract for the sole reason that the contract rate agreed by them was very low and was causing financial loss to them. That can be no just reason to not fulfill their contractual obligation. [Para 20] (149-D-G] 4. Tile stipulation in clause 5 providing for 45 clear days notice was not an impediment for the appellants to allot extra quantity of work upto 30%, whilst the contract period was subsisting.The said stipulation would come into play only if the respondents were also called upon to increase the machine capacity by upto 30% extra "daily" quantity. In the present case, the appellants merely allotted extra 30% quantity without requiring the respondents to increase the daily quantity. There is markl'd difference between increasing the extra quantity during the contract period and that of increasing the extra "daily" quantity. [Para 21] [149-H; 150-A-B] 5. The respondents are not right in contending that the appellants-Company had no authority to grant extension of time to complete the enhanced quantity. This is evidenct from the other contractual terms such as Clause 11.0 - providing for variation in the scheduled quantity, extent and rate; Clause 13 - time for completion of contract and more particularly Clause 14.0 - for extension of date of completion. Clause 14.0 (e) was available and ought to have been invoked by the respondents in this situation. [Para 22] [150-F-G] 6. The respor.tlents committed breach of their contractual obligation, in not completing the balance work out of 130% of work (i.e. 130 - 108.47%). To that extent the respondents became liable to compensate the appellants including by way of penalty and in particular towards the financial loss caused to the appellants due to assigning the unfinished work to a third agency (contractor) at a higher rate. [Para 23] (151-B-C] A B c D E F G > 7. It is indisputable that financial loss was suffered by the appellants on account of assigning the unfinished work to a third agency (contractor) at a higher rate. The fact that no loss of production was suffered by the appellants, cannot relieve the respondents of that liability. It is a different matter that the H [2016] 7 S.C.R. 130 SUPREME COURT REPORTS - A respondents were not put to notice before the final decision was taken by the appellants to recover the financial loss along with penalty. The respondents could have approached the appellants for reconsideration of their demand towards penalty, in terms of Clause 30.3 of the contract; and persuade the appellants to waive the penalty amount to be recovered from them. Even if this appeal - B succeeds, the respondents can be granted an opportunity to make a representation to the Appellants - company, who in turn can deal with the same in accordance with law. [Para 24] (151-F-H; 152-A-C] - _Mau/a Bux v. Union_ ~f _India_ (1969) 2 SCC 554 : 1970 - c (1) SCR 928; _Gorkha Security Sen1ices_ " _Government (NCT of Delhi)_ & _Ors._ (2014) 9 SCC 105; _Kumari Shrilekha Vidyarthi_ & _Ors v. State of U.P._ (1991) 1 SCC 212 : 1990 (1) Suppl. SCR 625 - referred to. 8. However, that would not absolve the respondents from D the financial liability arising due to difference of rate of contract and the actual cost incurred by the appellants to complete the unfinished work out of 130% of the contract quantity, through a third agency at a higher rate. That can be recovered by the appellants from the respondents along with interest accrued thereon at such rate, as may be permissible in law, even if the E representation made by the respondents for recall or modification of the penalty amount is pending consideration. [Para 24] [152D-E] - _Popcorn Enterainment vs. City Development Corporation,_ (2007) 9 SCC 593; _Harbanslal Sahnia_ - F & _Anr. vs. Indian Oil Corporation Ltd._ & _Ors._ (20fl3) 2 SCC 107; _Union of India_ & _Ors. vs. Tantia Construction Pvt. Ltd._ (2011) 5 SCC 697; _M P. State Agro Industries Development Corpn._ & _Anr. vs. Jahan Khan_ (2007) 10 SCC 88; _Whirlpool Corporation vs. Registrar of Trade Marks, Mumbai_ (1998) 8 SCC 1 - referred to. - G Case Law Reference ||1970 (1) SCR 928|referred to|Para24| |---|---|---|---| ||(2014) 9sec105|referred to|Para24| ||1990 (1) Suppl. SCR 625|referred to|Para24| ||2007 (3) SCR 17|referred to|Para25| |H|(2003) 2sec_101_|referred to|Para25| MAHANADI COALFIELDS LTD. & ORS. v. _MIS._ DHANSAR 131 ENGINEERING CO. PVT. LTD. 2011 (5) SCR 397 referred to Para 25 A 2007 (9) SCR 715 referred to Para 25 1998 (2) Suppl. SCR 359 referred to Para 25 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 9732 of2016. From the Judgment and Order dated 07.11.2012 of the High Court B of Orissa, Cuttack in W. P. (C) No. I 093 of 2006. Gourab Banerji, Sr. Adv., K. N. Madhusoodhanan KN., T. G. Narayanan Nair, S. A. Haseeb, Sahil Tagotra, Advs. for the Appellants. Rakesh Dwivedi, Sr. Adv., Arunabh Chowdhury, Anupam Lal Das, Vaibhav Tomar, Ms. Shruti Choudhry, Karma Dorjee, Anirudh Singh, Ms. Barna) i Chowdhury, Ad vs. for the Respondent. c The Judgment of the Court was delivered by > A. M. KHANWILKAR, J. I. Leave granted. 2. This appeal challenges the judgment of the Division Bench of the High Court of Orissa at Cuttack dated 7[1] h November 2012 in Writ Petition (Civil) No. I 093/2006. D 3. Briefly stated, on 2"d December 2002 the appellants issued notice inviting tenders for the work of extraction and transfer of Coal/Coal Measure Strata (CMS) by deploying "Surface Miners" on hiring basis at various Open Cast Projects, inter-alia, at Lakhanpur. > The respondents were declared the lowest bidder having quoted Rs.17/- per cubic meter for the stated.contract. A letter of intent was issued in favour of the respondents on 4•h April,2003 which was accepted by the respondents on 14[1] h April, 2003. Work order was issued in favour of the respondents on 23'd April, 2003 and a formal agreement was executed between the parties on 26'h May 2003. The relevant clauses of the agreement are clauses 2 to 5 which read as under: _"2) Time shall be considered as one of the essence of the contract and the time for the completion e-f the contract shall be counted from 16.04.2003 of from the date of issue of L.O.L to which terms the contractor agreed at the time when his tender was accepted and the contract shall be completed by 15. 04.2004 provided, sufficient face is provided by the management._ E F 'G H 132 [2016] 7 S.C.R. SUPREME COURT REPORTS A _3) The ll'ork order has already been issued for a period of one year for a quantity of 49,50, 000 Cum. At the rate of Rs. 17. 00/Cum. for an amount of Rs. 8,41, 5 0. 000. 00._ _4) The contractor shall re-deploy the Swface Miner in other OCPs as per direction of the Company._ B c D _5) The tendered quantity may be reduced or increased by_ +/- _30%. No claim shall lie on the company for such variation in guantitv whether increase or decrease. The tenderer must be in a position to increase the machine capacity upon 30% extra daily quantity within 45 days notice."_ _(emphasis supplied)_ 4. As the agreement refers to the terms and conditions of the tender document, we may usefully refer to the relevant clauses therein. _"11.0 VARIATION IN SCHEDULED QUANTITY EXTENT AND RATE_ _The quantity given in the "Schedule of Quantity s provisional and is meant to indicate the extent of the ll'ork and to provide a uniform basis for tendering and any variation either by addition or omission shall not vitiate the contract._ E · _The tendered quantitv may be reduced or increased by 30%. No claim shall be on the company for such variation in quantity whether increase or decrease. Tenderer must be in a position to increase the machine capacily ll'ilhin 45 davs notice to achieve the extra increased quantity._ F _If the additional altered or substituted ll'ork includes any item of work for which no "rate is specified in the contract, "rate" for such item shall be determined by the Company Headquarters in the following manner:-_ _The rate shall be derived from the rate for similar or near_ G _similar item of work awarded in the Company, or_ _The rate shall be derived from contractors rate claimed for such item of work supported by analysis of the rate claimed by the contractor. The rate to be determined by the Company Headquarters as may be considered reasonable taking into_ H _account percentage of profit and overhead not exceeding ten_ MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR 133 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] _percent or on the basis of market rate. if any prevailing at the_ A _time when work was done._ _However, the Engineer-in-charge shall be at liberty to cancel the instruction by giving notice in writing and to arrange to carry out the work in such manner as he considers advisable under the circumstances. The contractor shall under no_ B _circumstances suspend the work in the plea of non-settlement of rates._ _The time ofco111pletion of the originally contracted work shall be extended/reduced by the Company in lhe proportion that the additional/reduced work (in value) hears to the original contracted work (in value). as 111ay be assessed and certified by the Engineer-in-charge._ > _The company through its Engineer-in-charge or his representative, on behalf of the company, shall have power to 0111it any part of the work for any other reason and the contractor shall be bound to cany oul the work in accordance with the instruction given to Engineer-in-change. No clai111 for extra chargeslda111ages shall be 111ade by the contractor on these grounds._ _/11 the event of any deviation being ordered which in the opinion of the contractor changes radically the original scope and nature of the contract, the contractor shall under no circu111stances smpend the work, either original or altered or substituted and the dispute/disagreement as to the nature of deviation or the rate to be paid therefore shall be resolved separately with the company._ c D E F ## _13. TIME FOR COMPLETION OF CONTRACT_ _Time is the essence of the contract._ _The contractual period of work shall be as specified in NIT/LOI Agreement. The work shall be deemed to have commenced within 60 days of the issue of Letter of Intent at all the places and should be able to execute I 00% of the daily awarded quantity fro111 6/th day fro111 the date of issue of LOI._ _Agreement should be executed before the release of/", on Ale. bill._ G H 134 (2016] 7 S.C.R. SUPREME COURT REPORTS A _For fai/z;re to reach the desired quantity from 61'" day of issue of LOI, contractor shall be liable for penalty_ @ _20% of amount for shortfall quantity i.e. (shortfall quantity x awarded rate x 20%)._ _The contractor must be prepared to work continuously_ B _for three shifts a day and all the working days in a yem:_ _If the contractor, without valid reason, commits default in commencing the execution of the work within 60 days from the date of issue of LOI or fails to altain within specified date of issue of Letter of Intent, the required quantity to give the_ C _ultimate output as per the schedule of quantity, the company shall without prejudice to any other right or remedy, be at liberty, by giving I 5 days notice in writing to the contractor, to forfeit the Earnest Money deposited by him and to terminate the contract._ D .................... .. · _14.0 EXTENSION OF DATE OF COMPLETION_ > _On happening of any event causing delay as stated hereunder, the contractor shall apply for time extension to the CGMIGM of the Area._ E _a) Abnormally bad weather_ - _b) Serous loss or damage by fire_ - _c) Civil Commotion, strike or lockout affecting execution of work_ F _d) Non-availability of working force or site which is the responsibility of the company to supply._ - _e) Any other cause which. at the sole discretion of the company. is beyond the control of the contractor._ G _The contractor may request the company in writing for extension of time within I 4 days of happening of such event ceasing delay stating the period for which extension is desired. the company may. considering the eligibility of the request. give a fair and reasonable exte11sion of time of completion of the work. Such extension shall be commu11icated_ H MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR 135 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] _to the contractor, in writing, by the company through the_ A _Engineer-in-charge within 1 month of the date of receipt of such request._ ## _30.0 DEFAULT AND PENALTY 30.1 LOSS OR DAMAGE_ _Any loss or anv expenditure for damages incurred by company will be recoverable from the contractor whether fitlly or partly if such expenditure for damages have been caused either directly or indirectly due to any negligence or failure on the part of the contractor._ B c ## _30.2. SHORTFALL PENALTY IN MECHANICAL EXCAVATION AND LOADING_ _The average daily quantity of the quarter shall be worked out by dividing the mutually agreed quarterly al/oiled quantity by the working days of the quarter, ending on 30'" June, 30'" September, 31" December & 31" March Average daily quantity of a quarter must conform to average daily quantity of the year contractual period._ _In the event of the Contractors failure to comply with the rate of rate of progress as per the agreed progress chart the contractor shall be liable to pay a penalty on the quantity by which the contractor has fallen short from the allotted quarterly quantity at the rate of 20% of the awarded rate._ _For failure of produce size coal as per NIT (-JOO 111111 size), the contactor shall also be liable for penalty at the rate of 20% of the awarded rate for such over size quantity._ _The shortfall penalty will be recovered concurrently from the running bill which will be adjusted annually suh}ect to that the total penalty is limited to 20% of (Annual Shortfall Quantity x Rate)._ D E F G ## _30.3 WA/VAL OF PENALTY_ _The company may at its sole discretion waive the pqyment of penalty in full or in part in request received from the contractor depending the merit o[lhe case if the entire work is completed within the date as specified in the contract or within extended_ H 136 [2016] 7 S.C.R. SUPREME COURT REPORTS A _period approved without imposing penalty._ ## _31.0. SETTLEMENT OF DISPUTE_ _Except where otherwise provided for in the contract, all questions and disputes relating to meaning of the scope, specification and instructions herein before mentioned and as to any other question, claim right matter or thing whatsoever in any way arising out of or relating to the contract, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute_ . _the same whether arising during the progress of the work or after the completion or abandonment thereof, shall be referred to the Chairman-Cum-Managing Director of the Company or any other person authorized by him._ B c _It is also a terms of the Contract if the contractor (s) do/does not make any demand for any claim(s) in writing 90 days of receiving the intimation from the company that the bill is ready for payment or of the date of receiving payment whichever is earlier, the claim of the Contractor(s) will be deemed to have been waived and absolutely barred and the Company shall be released and discharged of all liabilities under the contract in respect of these claims._ " D E _(emphasis supplied)_ 5. The respondents commenced the work of surface miners at Lakhanpur and completed around 70% of the awarded quantity by the end ofFebruary 2004. Due to financial problems faced by the respondents vi de letter dated l 3m February 2004, they requested the appellants to F allow them to close the contract by invoking power to reduce the quantity by 30% of awarded quantity, under clause 11 of the general terms and conditions of the NIT; and to issue fresh tender for the remaining work. The appellants did not accede to the said request and informed the respondents vide letter dated l 6'h February 2004, stating that the G agreement is for performing the contract upto 100% of awarded value and provision of executing extra 30% quantity on the same terms and conditions. The respondents requested the appellants vide letter dated 9'h May 2004 to extend the time frame for completion of the remaining contract 1:1pto l 5'h July 2004 as the contract period was only till I 5'h April, 2004. The said letter reads thus: H MAHANADI COALFIELDS LTD. & ORS. v. _MIS._ DHANSAR 137 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] ANNEXURE-P8 A _**DHANSAR ENGINEERING CO. PVT. LTD.,**_ _SITE_ _P.O. Dhansar P. 0. Jorabaga Dhanbad_ - _828106 (Jharkhand) Via Be/pahar Ph: 0326_ - _3071611707 4. Dist. :Jhars11guda(Orissa) Fax: 0326 303294 Ph.: 066./5 -233222 E-mail- decopl'ci dte. vsnl.net. in_ **B** _Ref No. DECO/NIT 27612004_ _Date: 09. 05.2004_ c _To_ _The chief General Manager Lakhanpur Area Mahanadi Coalfields Ltd.,_ (Throu~h _proper channel)_ D _Sub: WORK OF EXTRACTION AND TRANSFER OF COAL/ COAL MEASURE STRATA BY DEPLOYING SURFACE MINER ON HIRING AT LAKHANPUR OCP OF LAKHANPUR AREA_ - _(NIT 276) VIDE WORK ORDER NO. MCLICGM/LKPAI SO(M)/SUR. MINER/2003-041001 DATED 23.04.2003._ E _Dear Sir,_ _Management is fully aware that tender rate of Rs. 171per Cum for the work is all ti111e low and wholly zmworkable. We are working at this rate at a colossal loss._ F _We started the work almost at the approach of monsoon on 16. 04.2003 and we could not also speed up progress because of transportation restriction between 11.00 A.M & 4. 00 P.M against heat wave alert and thereafter on-set of_ G _heavy rains consequenting upon bad, water-logged & slippery road followed by short supply of rakes. With all these operational hazards beyond our control, we could acco111plish 34. 74 Lakhs Cum upto 31.03.2004._ **H** [20 ! 6] 7 S.C.R. 138 SUPREME COURT REPORTS A _As our financial loss was soaring day by day, we had requested for foreclosure of the work after we have completed 70% of the work but this was not agreed to by GM(TC) vide his letter No. 1251 dated 26.03.2004._ _Therefore, being under contractual obligation we had, no_ B _other alternative but to apply for extension of time upto 15.07.2004 and would request you to kindly treat the contract as closed with the completion of the above mvarded quantity as we are ill-afford to bear further loss._ ## c ## _Thanking You,_ _Yours faithft1lly, Sdl-_ _For Dhansar Engineering Co. Pvt. Ltd."_ 6. This request of the respondents was considered by the appellants in its 68[1] h Meeting of the Board. Extension of three months time was D granted while reserving the right to impose penalty. The respondents were informed accordingly vide letter dated S[1] h June 2004. As a result of this decision, the contract period was extended until IS[1] h July 2004 on the same terms and conditions agreed upon. As the contract period was subsisting till J Sth July2004, the appellants issued an approval order dated E 11th June 2004 to increase of 30% extra quantity i.e. 14.8 Lakh cubic meter at the existing rate of next tender rate or .whichever is lower, amounting to Rs. 252.42 Lakh. The respondents by letter dated J Jth June 2004, however, reiterated that the contract be treated as closed - as they were on the verge of completing the quantity specified in the contract by I S[1] h June 2004. The said letter reads thus: F _"ANNEXURE-P9_ _DHANSAR ENGINEERING CO. PVT. LTD.,_ _SITE_ _P. 0. Dhansar_ _P. 0. Jorabaga_ _Dhanbad_ - _828106 (Jharkhand) Via Belpahar_ G _Ph: 0326_ - _30716117074. Dist.: Jharsuguda (Orissa) Fax: 0326 303294 Ph.: 06645 -233222 E-mail_ - _decopl0 dte. vsnl. net. in_ _Ref No. DECO/NIT 27612004_ _Dale: 11.06.2004_ H 139 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] _To_ • _The chief General Manager Lakhanpur Area Mahanadi Coalfields Ltd.,_ A _Sub: NIT NO. 276-EXTRACT/ON AND TRANSFER OF COAL/COAL MEASURE STRATA BY DEPLOYING SURFACE MINER ON HR/NG BASIS AT LAKHANPUR OCP OF MCL_ B _Dear Sir,_ _We would like to inform you that the order quantity of 49.50 lakh Cum is in the verge of completion, and is expected that this quantity will be fully completed by 15.06.2004._ C _In this connection kindly refer to our letter No. DECO/NIT -2761 2004 dated 09. 05.2004 under which we had requested your good-self to treat the contract as closed with the completion of the quantity of 49.50 lakh Cum. In reiterating our request we would inform you that we may be forced to stop the machine as it is giving trouble and we are not able to repair the machine for dire scarcity ofjimd_ D _Thanking You,_ _Yours faithfully, Sd/For Dhansar Engineering Co. Pvt. Ltd._ E _Copy to: I) The Director (Technical) MCL, Bur/a, 2) The General Manager, Lakhanpur Area._ 7. The respondents by another letter dated 6[1] h July 2004 seeking closure of contract due to financial hardship, stated that they were withdrawing their operations. The appellants, however, by letter dated 7•h July 2004 called upon the respondents to continue with the remaining work assigned under the contract which was still subsisting; and also noted that the respondents had by then completed only I 05% of the contract work out of 130%. The said communication reads thus: F G _"ANNEXURE -P12_ _"UNDER JURISDICTION OF SAMBALPUR COURT ONLY"_ ## _MAHANADI COALFIELDS LIMITED_ _(A SUBSDIARY OF COAL INDIA LIMITED)_ H 140 SUPREME COURT REPORTS [2016) 7 S.C.R. A _Corporate Office Office o.fthe Chief General Manager_ _M.C.l. Complex LAKHANPVRAREA Jagriti Vihar P. 0. bandhabahal_ - _Via: Belpahar Bur/a_ - _768018 Dist.: Jharsuguda, Pin 768217 Dist: Sambalpur (Orissa) phone: 33202, STD CODE: 06645_ 8 ## _Ref No. MCLICGMILKPAISO(M)/932_ _Dale: 07.07.2004_ _To_ _Mis Dhansar Engineering Co. pvt. ltd._ - C _Site Office: P. 0. Jorabaga, Via_ - _Belpahar. Dist: Jharsuguda (Orissa) Pin: 768217._ - _Ref {I) Work order No. MCLICGMLILKPAISOM{M)!Sur Miner/2003041001 dated 23. 04.2003 for Exlraction am/Trans.fer of Coal/Coal_ - D _measure strata by deploying_ 'Su~(ace _Miners" on hiring basis at lakhanpur OCP (NIT-276)._ - _Sub: Contract of Swface Miner work at lakhnapur OCP (under NIT No. 276)_ - E _Dear Sir._ - _Kindly re.fer to your letter No. DECO/NJT-27612004 dated 6.07.2004 on the above subject._ _This is to bring to your notice that as per clause No.2 of the work_ F _order forming part of the agreemenl the tendered quantity can be increased by 30% and no claim shall lie on the company for such variation till date only 105% (approx.) of the awarded quantity has been executed by you. There is no communication fro111 MCLHQ for ftnali:rntion of new contract for the above work till date._ _Jn such condition you are requested to continue your operation of_ G _surface 111iner at lakhanpur OCP till co111pletion of 30% extra quantity. Withdrawal of operations of Swface Miner at this stage will seriously affect dispatch of coal to our Pit head customer {OPGC) and other linkage customers earning a bad name to the company._ - H - _Thanking You,_ MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR 141 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] _Yours faithfully,_ A _SD/GENERAL MANAGER LAKHANPUR AREA_ _Copy to: The Chairman-cum-Managing Directo1; MCL Buria The Director (T), MCL, Bur/a The General Manager (TC), MCL HQ, Bur/a The Slaff Officer (Mining) LKPA"_ B 8. The respondents, however, renewed their request to the c appcll.1;11' to allow them to close the contract vide letters dated Slh July 2004 amt 12[1] " July 2004. The respondents finally wrote to the appellants on 15[1] " July 2004 which reads thus: "ANNEXURE-Pl5 DHANSAR ENGINEERING CO. PVT. **LTD.,** D ## SITE P.O. Dhansar P.O. Jorabaga Dhanbad- 828106 (Jharkhand) Via Belpahar Ph: 0326-307161/7074. Dist.: Jharsuguda (Orissa) E Fax: 0326 303294 Ph.: 06645 -233222 E-mail-decopl@dte.vsnl.net.in Ref: No. DECO/NIT 276/2004 Date: 15.07.2004 To F The General Manager, Lakhanpur Area, MCL, Sub: Closing Down of work of Surface Miner at lakhanpur OCP under NITNo.276 Dear Sir, A copy ofour letter No. DECO/NIT/2004 dated 12.07.2004 addressed to CMD MCL Burla with copies to D(T) and GM(TC), MCL HQ is enclosed herewith for your information. H 142 [2016] 7 S.C.R. SUPREME COURT REPORTS A B As notified this is to inform you that we are stopping the work and withdrawing from operations at Lakhanpur OCP with effect from 16.07.2004 (FN). It is not out of place to mention that we had been expressing out intention to abandon execution after completing I 00% of the work on account ofour un-economical plight out has been continuing wit the execution to cooperate with the management to arrange next recourse, so as to ensure that the production schedule of Lakhanpur OCP does not suffer any set back. · We could not however elicit any communication to our letters or any sympathetic decision from the·management. In the meanwhile the contract period also expired by 15.07 .2004. c In view of the above situation we have no other alternative but to withdraw from operation after working the full period of the contract. You are therefore requested to kindly take up final measurement as on 15.07.2004 and finalise the contract. Thanking you and assuring you of our best cooperation to all time come. D ## Yours faithfully, Sci/- For Dhansar Engineering Co. Pvt. Ltd. E Copy to: I. The CMD, MCL, Burla Fax No. 0663 -2432066/2542366 2. The D(T), MCL, Burla, Fax No. 0663-2542509 3. TheGM (TC),MCL, Burla, Fax No. 0663-2542629." F 9. As the respondents had already informed the appellants of their intention to withdraw from operation after the full contract period, a fresh tender process was commenced by the appellants which culminated with a letterofintent in favourofthird party (Sainik Mining and Allied Services) but at a higher rate ofRs.31.50 per cubic meter. G I 0. The bills submitted by the respondents for the work executed under the contract dated 26'h May 2003 were considered by the Board of the appellants in its 72"d meeting. The decision taken in the said meeting was communicated to the .respondents by letter dated 8[1] h December 2014 which reads thus: H MAHANADI COALFIELDS LTD. & ORS. v. _MIS._ DHANSAR 143 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] "ANNEXURE R/9 A MAHANADI COALFIELDS LIMITED (A subsidiary of Coal India Limited) P.O. -Jagruti Vihar, Burla, Distt. Sambalpur-768020 (Orissa) Gram: SAMBCOAL,: Fax: (0663)2542770 Phone: PBX:- (0663) 2542461 to 2542469 B Ref.1\o. MCUSBP/GM(TC)/200411047 Dt. 08.12.2004 To, General Manager, Lakhanpur Area c Dear Sir, Enclosed herewith please find a copy of Extract from the Draft Minutes of the 72"• meeting of the Board of Directors of MCL held on 27[1] h November, 2004 at Kolkata in respect of imposing penalty by way of forfeiture of Earnest Money Deposit of Rs. 20.00 lakhs to _Mis._ Dhansar D Engineering (P) Ltd., for non-performance of 130% of the total contracted quantity under NIT - 276. The relevant extract is appended below:- " The Board deliberated on the subject in detail and in consideration of the facts and circumstances highlighted in the agenda note and in recognition of the clarification offered during deliberation, decided that penalty as proposed in the agenda note in terms of the E pr_ovisions of the contract be imposed on _Mis_ Dhansar Engineering pvt. Ltd. For non-performance of 130% of the total contracted quantity under NIT-276. Proposed in the Agenda Note Clause No. 16- (Forfeiture of Earnest Money) The contractor is liable for forfeiture Money Deposit under F Clause No. l6(a) and l 6(d) which reads as under:- [ 6(2) withdraws his offer during the validity period of offer. I 6(a) fails to execute the order as per terms and conditions thereof. In the present case the EMD is Rs. 20.00 lakhs. Clause No. 30.2 (Shortfall penalty in Mechanical excavation and loading) 130% of Contract Quantity-63,70,000.00 Cu.m. G Final quantity executed-53,49,437.55 Cu.m. Balance quantity to be executed- 10,20,562.45 Cu.m. Working rate -Rs. 17.00 perCu.m. 20% of working rate Rs. 3.40 per Cu.m. Payable penalty for not executing Upto 130% quantity Rs.34,69,91 l.OO H 144 [2016] 7 S.C.R. SUPREME COURT REPORTS A These penalties may be imposed individually or collectively depending on the decision taken by the Management. The imposition of penalty may be decided on the background that the contractor working at a very low rate has executed I 08.4 7% in spite of incurring heavy losses and withdrew only when the new contract was finished ensuring that there is no loss of production. B Yours faithfully Sd/- lllegible General Manager (TC) Encl : As above" c 11. The Board of the appellants in its 78[111 ] Meeting decided to impose penalty for non-execution of the balance contract work by the respondents and including the financial loss incurred by the appellants due to allocation of that work to third party at higher rate. Jn terms of that decision, an approval order for recovery of penalty was issued by D the appellants on J'd November 2005 which reads thus: _"ANNEXURE -19_ ## _MAHANADI COALFIELDS LIMITED_ E _(A subsidiwy of Coal India limited) P._ 0. - _Jagriti Vihar Bur/a_ - _768018_ _Distt: Sambalpur-768020 (Orissa) Gram: SAMBCOAL,: Fax: (0663) 2542770 Phone: PBX:- 2542461to2542470_ F _Ref No. MCLISBPIGM(TC)/200511100 Date: 03.11.2005_ ## _APPROVAL ORDER_ G _Sub: Imposition of penalty to Mis Dhansar Engineering Company Pvt. Ltd., under NIT-276 (DI; 01.12.2002) for the work of "Extraction and Transfer of Coal/Coal Measure Strata by deploying "Surface Miners" on hiring basis at lakhanpur OCP, Lakhanpur Area._ H _On recommendation of the commil/ee to examine the issue on imposition of penalty under NIT -276 dated 02.12.2002 to Mis Dhansar Engineering Company Pvt. ltd .. for the work of "Extraction and Transfer of Coal/Coal Measure Strata by deploying "Swface Miners" on hiring basis at Lakhanpur OCP, lakhanpur Area, the same has_ 145 MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] A _been pgreed by D(T) !D(F)ID(P)/CMDIMCl. The MCl Board in its_ A _78'• meeting held on 27. 10.2005 under item No. 78.C/20 has been pleased to approve the proposal of imposition of penalty in terms of provision of the contract to Mis. Dhansar Engineering Company Pvt. ltd. '73y non performance of 130% of total contacted under NIT-276 (dt: 02. 12.2002) for an amount of Rs. 1,57,40,655.22 (Rupees One Crore Fifty-seven lakh Forty Thousand Six Hundred Fifty-five and_ B _paisa Twenty-two only) under the Clause_ - _30. 1 (loss or damage) of the agreement._ _Sd/- General Manager (TC)_ _Distribution:_ _1. GM lakhanpur Area_ _2. CGM(F) MCl, HQ_ c _3. TS to CMD, MCl_ _4. TS to D(T), MCl_ _5. Secy. To D(F), MCl_ _6. Sanction Order file"_ D 12.Aggrieved, the respondents filed Writ Petition under Article 226 of the Constitution oflndia and prayed as follows: _"PRAYER_ _In the circumstances, it is therefore prayed that Your lordships be graciously pleased to issue a Rule NISI in the nature of certiorari calling upon the Opposite Parties, to show cause as why the impugned letter dated 08.12.2004 vide Annexure-22 issued by the General Manager (TC), Mahanadi Coal Fields limited, Opposite party No.2 imposing penalty shall not be quashed and if the Opposite Parties fail to show cause or show insufficient cause make the said Rule absolute. AND_ _Issue a Writ in the nature of mandamus directing the Opposite parties to pay a sum of Rs. 79,01,434.60 to the Petitioner No.I Company, which has been illegally withholding by the Opposite parties._ E F _AND_ _Issue a Writ in the· nature of Mandamus directing the Opposite Parties to pay interest@ 18% per annum as the Opposite Parties have illegally withhold the outstanding dues of Rs. 79,01,434.60 of Petitioner No. I Company since 15. 07.2004._ G ## _A/VD_ _fssue such other Writ/Writs, Order/Orders, Direction/Directions as this Hon 'ble Court may deem it fit and proper._ _And/or this act of Kindness the Petitioner shall as_in duty bound ever pray._ " H 146 [2016] 7 S.C.R . . SUPREME COURT REPORTS A l 3. The Writ Petition was opposed by the appellants by filing reply affidavit. The appellants raised preliminary objection about the maintainability of the Writ Petition. On merits, the appellants asserted that the demand raised against the respondents was in accord with the terms and conditions of the contract and ifthe respondents were aggrieved by the same they were free to resort to the procedure for settlement B under clause 31 of the agreement. The Division Bench of the High Court, however, allowed the Writ Petition preferred by the respondents on the finding that it was not permissible for the appellants to allot extra work to the respondents at the fag end of the contract period in terms of clause 5 of the contract which envisaged giving 45 clear days notice for c variation of the quantity under the contract. That notice was given to the respondents only on J J <h June 2004 even though the extended contract period was to expire on J S<h July 2004. The Court held that, surprisingly after extending the contract period on S<h June 2004, within six days on 11th June 2004 the appellants decided to enhance the contract quantity by 30%. That was not a bonafide act and was unacceptable. The Court D also held that the appellants had not offered any explanation as to in what circumstances decision to impose penalty was taken by the Board of Directors. The Court further noted that the respondents had executed the contract upto I 08.4 7% at a very low rate, and incurred heavy losses in that regard. Further, a new contract for Lakhanpur OCP was already E awarded and there was no loss of production caused to the appellants. On these basis, the Division Bench allowed the Writ Petition in the following terms: A B c D _"16. Accordingly, the letter dated 8.12.2004 of the General Manager (T.C) Mahanadi Coalfields Limited under Annexure-_ F _22 proposing to levy shortfall penalty as well_ a~. _its Approval Order dated 03.11.2005 under Annexure-A to the counter affidavit are hereby quashed ._ . _The outstanding dues payable to the petitioner be released in its favour within the period of thirty days along with simple interest_ @ _8% per annum to be computed from the date of conclusion of contract, i.e. from_ G _16. 7.2004. The bank guarantee furnished by the petitioners, pursuant to the direction of this Court dated 28. 7.2009 are hereby directed to be cancelled and consequently, directed that the same be returned to the petitioners forthwith._ _The writ petition is allowed with the aforesaid terms. No_ H _Costs."_ MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR 147 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] 14.Aggrieved, the appellants have filed the present appeal. This Court passed an interim order on I 2[1] h April, 2013, directirig to maintain status quo as it existed on that date until further orders. 15. According to the appellants the High Court has committed manifest error in entertaining the Writ Petition. Firstly, in respect of a purely contractual matter and moreso when efficacious remedy under clause 31 of the contract was available to the respondents for redressal of their grievance. Secondly, on merits the High Court has misconstrued and misapplied the contractual terms and in particular clause 5 ofthe contract. However, ifthe terms and conditions of the contract are read as a whole, it leaves no manner of doubt that the appellants had the discretion to extend the original contract period; and having done so at the request of the respondents, the respondents were bound by the terms of the contract till 15[1] h July 2004. Further, before that date at any point of time, :: was open to the appellants to reduce or increase the contract quantity upto 30%. The sole plea of the respondents for their inability to perform the contract was founded on financial difficulty and sufferance offurther loss due to low contract rate. That can be no consideration for walking out of the contract. Moreso, after the extra quantity was allocated the respondents could have asked for further time for completing the extra work, if they were not in a position to complete the same within the contract period. That request could have been considered by the appellants appropriately. The respondents did not do so. Instead, they insisted to withdraw from operation merely because the rate of contract was not affordable to them. Resultantly, the appellants had to allot the extra quantity of unfinished work by the respondents, to third party at a higher rate. The fact that the appellants did not suffer any loss of production, it does not follow that no financial loss was suffered by the appellants due to higher rate paid for the unfinished extra work. The appellants were, therefore, justified in recovering the difference of rate in respect of unfinished extra work and penalty therefor. That was a legitimate demand under the terms and conditions of the contract between the parties. A B c D E F G 16. The respondents, on the other hand, contend that it was unfair on the part of the appellants not to allow the respondents to close the contract as per the original contract and within the extended contract period i.e. upto I 5[1] h July 2004. Further, the respondents cannot be made liable for the unfinished extra quantity of work as that was allotted only H 148 [2016] 7 S.C.R. SUPREME COURT REPORTS - A on 11th June 2004, leaving very I ittle time for the respondents to complete the same for which the appellants should blame themseh .... ,. According to the respondents, the High Court was right in concluding that clause 5 of the agreement did not permit the appella1its to allot an extra quantity of work to the extent of 30% at the fag end of the extended contract period, absent 45 clear days notice mandated therein. Further, the High - B Court has passed an equitable order also keeping in mind that the respondents had already executed 108.4 7% of the contract work by suffering heavy losses, which fact is substantiated from the execution of new contract at the rate of Rs.31.50 per cubic meter as against the rate of Rs.17 /- per cubic meter payable to the respondents. It is also - c contended thatthe demand for penalty amount is unilateral and without any just cause. The same is illegal. Hence, contends the learned counsel, the appeal be dismissed. 17. Having heard the learned counsel for the parties at some length, we find force in the plea of the appellants. The challenge in the Writ D Petition filed by the respondents was limited to the letter dated 8th December 2004, issued by the General Manager of the appellants. The respondents had not challenged the extension Of contract period till 15th July 2004 vide letter dated 5th June 2004, the decision of the appellants to allot an extra quantity of30% work and much less the decision of the Board to impose penalty taken on 27th October, 2005 and communicated E to the respondents vide Approval Order dated 3rd November 2005. The High Court, however, has not only set aside the letter dated 8th December 2004 but also the Approval Order dated 3rd November 2005. 18. For doing so, the High Court has taken support from clause 5 of the Contract. That clause cannot be read in isolation. The other terms F and conditions of the contract must be read as a whole. Clause 5 of the agreement dated 26th May 2003 posits authority in the appellants to reduce or increase the t.endered quantity by +/- 30%, whilst the contract is subsisting. Indisputably, the original contract period was upto J 5th April, 2004. At the instance of these respondents, the same stood extended till G J 5th July 2004. The extra 30% work was allotted to the respondents on 11th June 2004, before expiry of the extended contract period i.e. 15th July 2004. As the contract period was extended and that decision was allowed to attain finality, it inevitably obliged the respondents to fulfill all the contractual stipulations under the original agreement including to complete the assigned quantity of work- be it original quantity or extra H MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR 149 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] quantity- before l 5'h July 2004. The fact that they had to suffer financial loss due to low contract rate could not be cited as an excuse to extricate from that contractual obligation. 19. Failure to comply with the contractual obligation of executing the original quantity of work or the extra work, as the case may be, must visit the respondents with liability to compensate the appellants in terms of other express clauses of the contract to the extent of unfinished work and in particular the financial loss suffered by the appellants for getting the same work executed through a third agency at a higher rate. The fact that the respondents executed I 08.4 7% of work before l 5'h July 2004, could be no justification to relieve them of their obligation to compensate the appellants with suitable amount for the unfinished contract work (out of 130%). 20. Presumably to get over this position, the respondents relying on clause 5 of the agreement would contend that the extra quantity of work could not be allotted to them, absent 45 clear days notice that too at the fag end of the contract period. This argument, in our opinion, is a complete misreading of the said clause. It is one thing to say that the contractor should be given sufficient time to complete the extra work commensurate with the extra quantity required to•be executed by him. However, in law, it is not open to contend that even though the contract period is still subsisting, the principal (appellants) could not have exercised its option to increase the quantity of work to the extent permissible under that clause, to be executed by the contractor within the contract period. The principal (appellants) could be asked to exercise their option to extend the contract period beyond J 5•h July, 2004, to enable the respondents to complete the unfinished extra work. If such request were to be made by the respondents, there would have been corresponding obligation oi~ the appellants to extend the contact period commensurate with the increased quantity of work in terms of clause 5 of the agreement. The respondents, instead, opted to walk out of the contract for the sole reason that the contract rate agreed by them was very low and was causing financial loss to them. That can be no just reason to not fulfill their contractual obligation. 21. Relying on the third sentence (last sentence) in clause 5, it was contended that the employer could not have increased the tendered quantity in absence of 45 clear days notice. We agree with the appellants that the said stipulation would come into play only if the respondents A B c D E F G H 150 [2016) 7 S.C.R. SUPREME COURT REPORTS - A were also called upon to increase the machine capacity by upto 30% extra "daily" quantity. In the present case, the appellants merely allotted extra 30% quantity without requiring the respondents to increase the daily quantity. There is marked difference between increasing the extra quantity during the contract period and that of increasing the extra "daily" quantity. In the case of latter, the contractor would be required to step - B up the machine capacity for which giving of 45 clear days notice to him is necessary. Suffice it to observe that the stipulation in the third sentence of clause 5 providing for 45 clear days notice was not an impediment for the appellants to allot extra quantity of work upto 3 0%, whi 1st the contract period was subsisting. B c 22. The respondents had then relied on the notings of the Project Officer dated 26'h January 2005 to contend that assigning of extra work to the respondents at the fag end of the contract period was doubted even by the said officer. The observations of the Project Officer cannot be the basis to construe the scope of Clause 5 of the contract. Besides, it was only an inter-depa11mental communication which was duly considered at different level in the office of the appellants, but finally it is the decision of the Board of Directors of the appellants that must prevail. As a matter of fact, Clause 5 of the agreement empowers the appellants to increase or reduce the quantity of work upto permissible limit whilst the contract was subsisting. That power having been exercised, the obligation of the contractor to complete the extra.work in terms of the subject contract within the contract period or extended contract period was imperative. The respondents are not right in contending that the appellants-Company had no authority to grant extension of time to complete the enhanced quantity. This contention deserves to be stated to be rejected, keeping in mind the other contractual terms such as Clause 11.0 - providing for variation in the scheduled quantity, extent and rate; Clause 13 - time for completion of contract and more particularly Clause 14.0- for extension of date of completion. Clause 14.0 (e) was available and ought to have been invoked by the respondents in this situation. It postulates that for any other cause not specifically provided in sub-clauses (a) to (d) of the same Clause, at the so.le discretion of the appellants, the date ofcompletion could be extended, ifit was found to be necessary because of situation beyond the control of the contractor. That clause could be invoked for the situation in which the respondents were placed due to extra work allocated to them at the fag end of the coritract (extended) period. D E F G H MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR 151 ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] 23. ln our opinion, clause 5 did not prohibitthe principal (appellants) to allot upto extra 30% quantity of work, for want of 45 clear days of subsisting contract period. Whereas, that option could be exercised by the appellants at any time until the contract period was subsisting, which in this case was until J 5•h July 2004. In the present case, such notice regarding increase of work upto 30% permissible under clause 5 of the agreement, was given on 11 •h June 2004. On this finding, it must follow that the respondents committed breach of their contractual obligation, in not completing the balance work out of 130% of work (i.e. 130 - I 08.4 7%). To that extent the respondents became liable to compensate the appellants including by way of penalty and in particular towards the financial loss caused to the appellants due to assigning the unfinished work to a third agency (contractor) at a higher rate. The amount demanded by the appellants includes the difference of contractual rate and the actual loss suffered by the appellants for completing the unfinished work through a third agency (contractor) at a higher rate, as is noticed from the communication dated 8'11 December 2004 sent to the respondents. 24. The respondents, would then contend that, the appellants without giving any opportunity to the respondents unilaterally imposed penalty and despite the noting of the General Managerthat there was no loss of production to the appellants. Similarly, a doubt was expressed by the Project Officer regarding giving extra work to the respondents at the fag end of the contract period. The respondents have relied on the decision of this Court in _Mau/a Bux vs. U11io11 of lntlia[1] ,_ in which it has been held that "where a sum is named in the contract in the nature of a penalty, where loss in terms of money can be determined. th1.: party claiming compensation must prove the loss suffered by it." It is, however, indisputable that financial loss was suffered by the appellants on account ofassigning the unfinished work to a third agency (contractor) at a higher rate. In that, the contract rate for the same work to be done by the respondents would have been at Rs. 17/- per cubic meter, which the appellants were required to get it executed at the rate of Rs. 31.50 per cubic meter through a third agency. The fact that no loss of production was suffered by the appellants cannot relieve the respondents of that liability. It is a different matter that the respondents were not put to notice before the final decision was taken by the appellants to recover the financial loss along with penalty. The respondents could have > 1 (1969) 2 sec 554 A B c D E F G H [2016] 7 S.C.R. 152 SUPREME COURT REPORTS - A approached the appellants for reconsideration of their demand towards penalty, in terms of Clause 30.3 of the contract; and persuade the appellants to waive the penalty amount to be recovered from them. The respondents, however, chose to straightway approach the High Court by way of Writ Petition. Notably, the High Court has not set aside the penalty amount as such, butthe entire demand being impermissible. Since - B we have reversed the findings and conclusion of the High Court and even if this appeal succeeds, the respondents can be granted an opportunity to make a representation to the Appel I ants - company, who in turn can deal with the same in accordance with law. If the appellants accept the claim of the respondents about the unjustness of penalty or - c quantum thereof, they would be free to withdraw or modify their claim for recovery of penalty amount, if so advised. In the event, the appellants reject the representation, they will be free to recover the amount as demanded towards penalty along with interest accrued thereon, as may be permissible in law. However, that would not absolve the respondents from the financial liability arising due to difference of rate of contract - D and the actual cost incurred by the appellants to complete the unfinished work out of 130% of the contract quantity, through a third agency at a higher rate. That can be recovered by the appellants from the respondents along with interest accrued thereon at such rate, as may be permissible in law, even ifthe representation made by the respondents for recall or - E modification of the penalty amount is pending consideration. Considering the above, it is not necessary for us to burden this judgment with the contention of the respondents that the penalty imposed without any notice or hearing to the respondents is vitiated; as also the decisions relied in support of that contention in the case of _Gorklta Security Services vs. Govemment (NCT of Del/ii)_ & _Ors.[1 ] and Kunwri Slirileklia Vidyartlli_ - F & _Ors vs. State of U.P._[3 ] 25. Similarly, it is not necessary for us to burden this judgment with the decisions relied on by the respondents, to contend that existence of alternative remedy is no bar to entertain a Writ Petition under Article 226 of the Constitution of India, as held in the cases of _Popcorn_ G _Enterainment vs. City Development Corporation[4] , Harbanslal Sallnia_ & _Anr. vs. Indian Oil Corporation Ltd._ & _Ors.-', Union of_ - 2 (2014) 9 sec 105 - 3 (1991) I SCC212 H ' (2007) 9 sec 593 ' (2003) 2 sec _101_ MAHANADI COALFIELDS LTD. & ORS. v. M/S. DHANSAR ENGINEERING CO. PVT. LTD. [A. M. KHANWILKAR, J.] 153 _India_ & _Ors. vs. Tantia Construction Pvt. Ltd.•, M.P. State Agro_ A _Industries Developmen_t Corpn._ & _Anr. Vs. Jalwn Kllan[7 ] and Whirlpool Corporation vs. Registrar of Trade Marks, M umbai[8] •_ For, we have already examined the merits of the controversy and more so granted liberty to the respondents to make representation to the appellants on the question of justness of the demand towards penalty or the quantum B thereof. It will be open to the respondents to pursue remedy in that behalf, as may be permissible in law. We are not expressing any opinion one way or the other on the issue of penalty amount. All questions in that behalf are left open. B 26. Accordingly, we partly allow this appeal. The judgment of the Division Bench dated 7'h November 2012 is set aside. The reliefs claimed by the respondents in the Writ Petition are disposed of in the above terms. c 27. The appeal is partly allowed in the above terms with no order as to costs. D Kalpana K. Tripathy Appeal partly allowed. ' (2011)5 sec 697 ' (2007) 1 o sec 88 • (1998) 8 sec 1
End of Judgment Record
Browse All Supreme Court of India (2016) Decisions
2016-03-16

Union of India v. Mis. Ambica Construction

This judgment addresses whether an arbitrator can award pendente lite interest when a contract expressly bars such interest, within the framework of Indian arbitration law. The Union of India approached this dispute after two arbitrators failed to publish an award and after a long procedural history in the Calcutta High Court and various SLPs. The core issue is whether pendente lite interest can be awarded where the contract contains explicit clauses barring such interest, and how this interacts with the implied terms of arbitration under the Arbitration Act, 1940 and, for post-1996 matters, the Arbitration and Conciliation Act, 1996. The Court traces a lineage of decisions (GC Roy; NC Budharaj; Sayeed Ahmed; Harish Chandra; Balimela; Engineers-De-Space-Age; Tehri Hydro) and clarifies that while arbitrators are generally creatures of the contract, their power to award pendente lite interest is bounded by express contractual bars. It concludes that no pendente lite interest can be awarded if the contract expressly prohibits it. The judgment also recognizes Tehri Hydro’s reasoning and clarifies the status of earlier decisions, holding certain observations as overruled or limited prospectively. The result is that the High Court and the award are to be modified to reflect the absence of pendente lite interest, with a reference answered and no costs awarded.”

2016-08-29

Madhya Pradesh State Road Transport Corporation v. Manoj Kumar & Anr.

This is a civil appeal challenging the voluntary retirement scheme (VRS) introduced by the Madhya Pradesh State Road Transport Corporation (MPSRTC) to downsize its workforce as the company faced losses and declining business. The scheme opened on July 1, 2005 and closed on August 1, 2005, with employees permitted to submit their option for voluntary retirement (VRS) within that window. The scheme included a clause stating that once an employee’s option was submitted it could not ordinarily be withdrawn, yet the scheme was a funded, time-bound arrangement requiring the employer to create a fund and to lay out a process for acceptance and settlement. In October 2006, the Corporation issued an amendment extending the period to October 28, 2006, prompting questions whether this extension created a new scheme or was merely an extension of the original. Several employees who had submitted applications sought withdrawal after August 1, 2005, and in some cases after the extension, while the Corporation accepted their VRS applications and disbursed terminal dues. The High Court of Madhya Pradesh upheld the employees’ right to withdraw within the relevant periods, but the Supreme Court concluded that VRS schemes, being contractual and funded, are invitations to offer governed by the Indian Contract Act, and withdrawals are permissible only within the valid period; the extension does not automatically grant a right to withdraw beyond the original window. The Court accordingly set aside some reinstatement orders and disposed of the appeals in favor of the Corporation in most respects.

2016-07-01

Mahipal Singh Rana, Advocate v. State of Uttar Pradesh

The appeal arises from a High Court of Allahabad judgment (Criminal Contempt Petition No.16 of 2004) finding the appellant, an advocate, guilty of criminal contempt for intimidating and berating a Civil Judge, Etah, on two dates (16 April 2003 and 13 May 2003). The Allahabad High Court sentenced him to two months’ simple imprisonment and imposed a fine, with a direction to Bar Council authorities to consider disciplinary action for professional misconduct. On admission to this Supreme Court, the matter was referred to a larger bench to decide whether a case of criminal contempt by a lawyer could also implicate professional misconduct beyond the contempt regime, and whether the Court could exercise suo motu jurisdiction under the Advocates Act if Bar Councils fail to act. The Court examined the separation of powers between contempt proceedings and Bar Council disciplinary processes, the scope of Article 142/129, and the ability to regulate appearance in courts (including the right to practice vs. the right to appear). It held that contempt conviction was justified and upheld the High Court’s finding, but set aside the imprisonment sentence due to the appellant’s advanced age. It sustained a two-year enrollment suspension under Section 24A of the Advocates Act and directed the Bar Councils to suspend the licence for an additional five years, with further appearance restrictions until the contemnor purges himself of contempt. The judgment emphasizes reform of regulatory mechanisms governing the legal profession and the State Bar Councils’ failings in acting on earlier notices.

2016-03-10

CHARANJIT KAUR v. BIKRAM SINGH & ANR.

Charanjit Kaur, wife of Bikram Singh, faced dowry-related harassment under sections 498A and 406 IPC. The trial court convicted the husband and imposed a one-year RI for each offence, with the sentences to run concurrently and a fine of Rs. 1,000/- with default imprisonment. The wife appealed against the conviction and also sought enhancement of punishment; the husband cross-appealed. The mother-in-law was acquitted; the father-in-law had died. The Sessions Court at Kapurthala modified the sentence by permitting the husband to deposit Rs. 2,50,000 payable to the appellant within one month, so that he could obtain the benefit of probation under Section 4(1) of the Probation of Offenders Act, 1958. The wife’s revision before the High Court of Punjab & Haryana at Chandigarh was dismissed in a summary manner, reportedly influenced by the deposit. The Supreme Court, noting the summary disposal and the deposit-driven rationale, held that the impugned order required setting aside so that the matter could be re-heard on merits. It directed remand to the High Court for a fresh decision strictly in accordance with law, without entering into the merits of rival submissions in this order. The decision was delivered by a Single Judge, Justice Shiva Kirti Singh, on March 10, 2016.