High CourtDivision BenchAppeal Allowed

MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE

Case / Petition Number:Civil Appeal No. 4914 of 2022
Neutral Citation:SUPREME COURT REPORTS [2022] 7 S.C.R. 522

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Dr. Dhananjaya Y. Chandrachud
  • A S Bopanna
Judgment Date
2022-07-25
Court Decision / Holding
Appeal Allowed. The High Court’s order appointing a sole arbitrator is set aside; there was no arbitration agreement between the parties under Sections 2(b) and 7 of the 1996 Act, so no reference to arbitration could be made. The respondent may pursue remedies in law. Pending applications, if any, are disposed of.
Final Disposition
Appeal Allowed

Parties to the Case

Appellants / Petitioners

  • MAHANADI COALFIELDS LTD
  • ANR

Respondents

  • M/s IVRCL AMR JOINT VENTURE

Legal Representation & Advocates

Counsels for Petitioners

  • • K. K. Venugopal, AG
  • • Soumyajit Pani
  • • Siddharth Jain

Counsels for Respondents

  • • S. Niranjan Reddy, Sr. Adv.
  • • Polanki Gowtham
  • • Amitabh Sinha
  • • Sanjay Mishra
  • • Ajit Yadav
  • • Ms. Divya Roy

Case Synopsis & Summary

The dispute concerns clause 15 of the Contract Agreement dated 30 January 2012 between Mahanadi Coalfields Ltd (a subsidiary of Coal India Limited) and IVRCL AMR Joint Venture. Clause 15 is titled Settlement of Disputes/Arbitration, but its substantive text directs disputes to be settled at the company level first, with a written request to the Engineer-in-Charge within 30 days, and ultimately directs redressal through government guidelines or civil courts, rather than a formal arbitration. The High Court of Orissa had treated this clause as an arbitration agreement permitting reference under Section 11(6). The Supreme Court, however, reexamined the clause using the Jagdish Chander v. Ramesh Chander framework, noting that an arbitration agreement must reveal an intention to submit disputes to a private tribunal, be in writing, and bind the parties to an arbitrator or Arbitral Tribunal. It also considered a 7 April 2017 policy letter by CIL, which merely expressed a desire to settle disputes through arbitration and required a further agreement, not a binding arbitration clause. Relying on Mayavati Trading and Valley Transport, the Court held that Clause 15 does not meet the essential attributes of an arbitration agreement, so there was no valid arbitration agreement. Consequently, invocation under 11(6) was improper, and the appeal is allowed with the respondent free to pursue legal remedies. The decision reinforces a nuanced test for arbitration agreements, distinguishing company-level dispute resolution from true arbitration.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 2(b)Arbitration and Conciliation Act, 1996 - Section 7Arbitration and Conciliation Act, 1996 - Section 11(6)

Legal Doctrines & Maxims

  • Arbitration agreement must show clear intention to refer disputes to arbitration (Jagdish Chander v. Ramesh Chander, 2007)
  • Arbitration clause may be valid only if it contains essential attributes of an arbitration agreement (Jagdish Chander, para. 8)
  • Mayavati Trading Private Ltd. v. Pradyut Deb Burman (2019) 8 SCC 714 – look into arbitration clause, not mere possibility
  • IB Valley Transport, Vijay Laxmi (P) Ltd. v. Mahanadi Coalfields Ltd. (2014) 10 SCC 630 – company-level dispute resolution mechanism can’t substitute for arbitration

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that clause 15, titled 'Settlement of Disputes/Arbitration', does not constitute an arbitration agreement. It fungibly provides a company-level dispute resolution mechanism and does not reveal an intention to refer present or future disputes to arbitration. It requires only that disputes be resolved through internal mechanisms or a court of law, not a private arbitral tribunal. The 7 April 2017 policy letter cannot convert clause 15 into an arbitration clause and does not bind the parties to arbitrate; invocation under Section 11(6) was invalid for lack of a valid arbitration agreement. They urged that the respondent should pursue civil remedies as provided by law.

Contentions of Respondents

The respondents contended that clause 15, read with the policy letter, leads to arbitration or at least to an agreement to arbitrate; thus, the High Court correctly invoked Section 11(6) and referred the dispute to arbitration. They argued that the clause’s structure and the related policy reflect consent to arbitration, and the matter falls within an arbitration framework established by the parties.

Cited Precedents (7)

Case NameCitationTreatmentExplanation
Jagdish Chander v. Ramesh Chander(2007) 5 SCC 719; [2007] 5 SCR 720PositiveFormulated the core test for what constitutes an arbitration agreement and the essential attributes required; used to interpret Clause 15.
Mayavati Trading Private Limited v. Pradyut Deb Burman(2019) 8 SCC 714PositiveEmphasized looking into the arbitration clause itself; not merely relying on generic assurances.
Valley Transport, Vijay Laxmi (P) Ltd. v. Mahanadi Coalfields Ltd.(2014) 10 SCC 630Positive Used to illustrate company-level dispute resolution mechanisms before resorting to legal remedies.
K. K. Modi v. K. N. Modi(1998) 3 SCC 573; [1998] 1 SCR 601Mentioned OnlyCited as background authority in the development of the arbitration agreement doctrine.
Bharat Bhushan Bansal v. U.P. Small Industries Development Corp. Ltd.(1999) 2 SCC 166; [1999] 1 SCR 181Mentioned OnlyCited as background; not a controlling factor in the present decision.
Bihar State Mineral Development Corpn v Encon Builders (I) (P) Ltd.(2003) 7 SCC 418; [2003] 2 Suppl. SCR 812Mentioned OnlyCited as background authorities in arbitration law.
State of Orissa v. Damodar Das(1996) 2 SCC 216; [1995] 6 Suppl. SCR 800Mentioned OnlyCited as background authority in the arbitration doctrine.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

522 SUPREME COURT REPORTS[2022] 7 S.C.R. 522 [2022] 7 S.C.R. A ## MAHANADI COALFIELDS LTD & ANR v. ## M/s IVRCL AMR JOINT VENTURE (Civil Appeal No. 4914 of 2022) B JULY 25, 2022 ## **[DR. DHANANJAYA Y CHANDRACHUD AND A S BOPANNA, JJ.]** _Arbitration and Conciliation Act, 1996 – ss. 2(b), 7 and 11(6) – Arbitration agreement – Attributes – Contract Agreement entered_ C _between appellant (a subsidiary of CIL) and respondent on 30 January 2012 – Dispute between the parties – Invocation of jurisdiction u/s.11(6) by respondent before the High Court for appointment of arbitrator – Challenged, on ground that there was no arbitration agreement between the parties within meaning of_ D _ss.2(b) and 7 – Held: It was wrong on the part of the High Court to construe Clause 15 of the Contract Agreement dated 30 January 2012 as an arbitration agreement – Clause 15 of the Contract Agreement was titled “Settlement of Disputes/Arbitration”, however, substantive part of the provision makes it abundantly clear that there was no arbitration agreement between the parties agreeing to_ E _refer either present or future disputes to arbitration – Clause 15 of the Contract Agreement was a dispute resolution mechanism at the company level, rather than an arbitration agreement and did not comport with the essential attributes of an arbitration agreement in terms of s.7 as well as the principles laid down under_ Jagdish Chander F _case – Policy document / communication dated 7 April 2017 issued by CIL also cannot be construed as an arbitration agreement between appellants and respondent in terms of s.7 of the Act so as to compel the appellants to appoint an arbitrator, since it merely indicates a desire on behalf of CIL to have disputes related to work contracts settled by arbitration and requires both the parties to_ G _arrive at a further agreement to proceed to arbitration when the dispute arises – Invocation of jurisdiction of the High Court u/ s.11(6) of the Act was accordingly not valid and there being no arbitration agreement between the appellants and the respondent, no reference to arbitration could have been made – Respondent,_ H 522 523 MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE _however, at liberty to seek recourse to remedy available in law to_ A _pursue redressal of its grievances._ ## **Allowing the appeal, the Court** **HELD:1. Section 2(b) of the Arbitration and Conciliation Act, 1996 defines an arbitration agreement to mean an agreement as referred to in Section 7. In terms of Section 7, an arbitration agreement is an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not. Sub-section (2) of Section 7 stipulates that an arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement. In terms of sub-section (3) of Section 7, the arbitration agreement has to be in writing. [Para 8][527-G-H; 528-A]** **2. In the present case, clause 15 of the Contract Agreement is titled “Settlement of Disputes/Arbitration”. However, the substantive part of the provision makes it abundantly clear that there is no arbitration agreement between the parties agreeing to refer either present or future disputes to arbitration. Clause 15 of the Contract Agreement is a dispute resolution mechanism at the company level, rather than an arbitration agreement. Consequently, in case of a dispute, the respondent was supposed to write to the Engineer-in-charge for resolving the dispute. Clause 15 does not comport with the essential attributes of an arbitration agreement in terms of section 7 of the 1996 Act as well as the principles laid down under** _**Jagdish Chander**_ **case. A plain reading of the clause leaves no manner of doubt about its import. There is no written agreement to refer either present or future disputes to arbitration. Neither does the substantive part of the clause refer to arbitration as the mode of settlement, nor does it provide for a reference of disputes between the parties to arbitration. It does not disclose any intention of either party to make the Engineer-in-Charge, or any other person for that matter, an arbitrator in respect of disputes that may arise between the parties. Further, the said clause does not make the decision of the Engineer-in-Charge, or any other arbitrator, final or binding on the parties. Therefore, it was wrong on the part of the High** B C D E F G H 524 SUPREME COURT REPORTS [2022] 7 S.C.R. - A **Court to construe clause 15 of the Contract Agreement as an arbitration agreement. [Paras 10, 13][530-E; 531-D-G]** _Jagdish Chander v. Ramesh Chander_ **(2007) 5 SCC 719 : [2007] 5 SCR 720 – relied on** **3. On 7[th] April, 2017, CIL issued a policy document to its** B **General Managers for the settlement of disputes or differences arising out of works and services contracts through arbitration. The communication dated 7 April 2017 however merely indicates a desire on behalf of CIL to have disputes related to work contracts settled by arbitration. It requires both the parties to arrive at a** C **further agreement to proceed to arbitration when the dispute arises. Therefore, in view of the principles laid down in** _**Jagdish Chander**_ **case, following a line of precedent, clause 5 in the aforesaid communication cannot be construed as an arbitration agreement between the appellants and the respondent in terms of section 7 of the 1996 Act so as to compel the appellants to** D **appoint an arbitrator. [Paras 14 and 17][531-H; 532-A; 533-B-C]** **4. The invocation of the jurisdiction of the High Court under** **Section 11(6) of the 1996 Act was not valid and there being no arbitration agreement between the appellants and the respondent, no reference to arbitration could have been made. The respondent** E **would, however, be at liberty to seek recourse to the remedy available in law to pursue the redressal of its grievances. [Para 19][533-E-F]** - _K. K. Modi v. K. N. Modi_ **(1998) 3 SCC 573 : [1998] 1 SCR 601;** _Bharat Bhushan Bansal v. U.P. Small_ - F _Industries Corpn. Ltd._ **(1999) 2 SCC 166 : [1999] 1 SCR 181;** _Bihar State Mineral Development Corpn v. Encon Builders (I) (P) Ltd._ **(2003) 7 SCC 418 : [2003] 2 Suppl. SCR 812;** _State of Orissa v. Damodar Das_ **(1996) 2 SCC 216 : [1995] 6 Suppl. SCR 800 and** _IB_ - G _Valley Transport, Vijay Laxmi (P) Ltd. v. Mahanadi Coalfields Ltd._ **(2014) 10 SCC 630 – referred to.** ## **Case Law Reference** **[2007] 5 SCR 720 relied on Para 9** H MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE 525 |**[1998]**|**1 SCR 601**|**referred to**|**Para 9**|A| |---|---|---|---|---| |**[1999]**|**1 SCR 181**|**referred to**|**Para 9**|| |**[2003]**|**2 Suppl. SCR 812**|**referred to**|**Para 9**|| |**[1995]**|**6 Suppl. SCR 800**|**referred to**|**Para 9**|| |**(2014)**|**10 SCC 630**|**referred to**|**Para 12**|B| CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4914 of 2022. From the Judgment and Order dated 29.11.2019 of the High Court of Orissa at Cuttack in ARBP No. 44 of 2018. C K. K. Venugopal, AG, Soumyajit Pani, Siddharth Jain, Advs. for the Appellants. S. Niranjan Reddy, Sr. Adv., Polanki Gowtham, Amitabh Sinha, Sanjay Mishra, Ajit Yadav, Ms. Divya Roy, Advs. for the Respondent. The Judgment of the Court was delivered by D ## **DR DHANANJAYA Y CHANDRACHUD, J.** ## 1. Leave granted. 2. The appellant, Mahanadi Coalfields Ltd., is a subsidiary of Coal India Limited[1] . The respondent, IVRCL AMR Joint Venture, is a joint venture of engineering contractors engaged in the business of infrastructure development. On 11 October 2010, the appellant floated an e-tender for the work of strengthening and widening of a coal transportation road at the Talcher Coalfields in the State of Orissa. The respondent was the successful bidder and was awarded a work order on 14 December 2011. A ‘Contract Agreement’ was entered into between the parties on 30 January 2012, in terms of which the work order was to be executed between 16 January 2012 and 14 January 2015. 3. In a meeting held on 28 June 2012, the appellant advised the respondent to expedite the mobilization of resources to start the work immediately. Later, the appellant sent a series of letters to the respondent requesting it to expedite the work as per the work schedule. In 2013 and 2014, the appellant served several notices to the respondent when the E F G H 1 “CIL’’ 526 SUPREME COURT REPORTS [2022] 7 S.C.R. - A latter failed to adhere to the work schedule. Ultimately, the appellant terminated the work order on 15 May 2014 allegedly on account of delay in completing the work and the inability of the respondent to meet the work schedule. 4. Thereafter, on 12 October 2017 the respondent raised a claim B of Rs. 128,65,12,688 enumerating the latches and delays on the part of the appellant. The claim was rejected by the appellant on 18 December 2017. Subsequently, the respondent issued a notice of arbitration to the appellant by a letter dated 9 April 2018 in terms of clause 15 of the Contract Agreement. Through the said arbitration notice, the respondent called upon the appellant to give its consent to the appointment of Justice C Asok Kumar Ganguly as the sole arbitrator. Having received no response from the appellant to the arbitration notice within 15 days, the respondent filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996[2] before the High Court of Orissa. 5. On 29 November 2019, a Single Judge of the High Court of D Orissa allowed the application under Section 11 of the 1996 Act by appointing a sole arbitrator. The relevant extracts of the High Court’s decision read as follows: - “3. Learned counsel for both the sides do not dispute the fact that Clause 15 of the contract agreement provides for “Settlement of - E dispute/Arbitration” in case there is any dispute or difference between the parties. 4. Mr. R Sharma, learned counsel for the opposite party has taken different contentions on merit. He has also brought to the notice of this Court clause 19 of the letter dated 14.12.2011 (Annexure- F 3), which reads as under: - _“19. That matters relating to any dispute or difference arising out of the tender, work order and subsequent contract agreement entered into, based on this tender and work order shall be subject to the jurisdiction of District Court, Angul_ - G _only.”_ 5. However, in view of the decisions of the Hon’ble Supreme Court in the case of Mayavati Trading Private Limited vs. Pradyuat Deb Burman, reported in (2019) 8 SCC 714, the Court has to look H 2 “1996 Act’’ MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.] 527 into the arbitration clause. In that view of the matter, the matter is required to be referred to the arbitrator.” A 6. Mr K K Venugopal, learned Attorney General for India, appears on behalf of the appellants, while Mr S Niranjan Reddy, learned Senior Counsel, appears on behalf of the respondent. 7. The submission which has been urged on behalf of the appellants by the learned Attorney General is that clause 15 of the Contract Agreement dated 30 January 2012 does not constitute an arbitration agreement. Hence, it has been urged that in the absence of an arbitration agreement within the meaning of Sections 2(b) and 7 of the 1996 Act, the very invocation of the jurisdiction under Section 11(6) was not valid. In order to appreciate the submission, it would be necessary to extract clause 15 of the Contract Agreement. The provision reads as follows: B C - “15. Settlement of Disputes/Arbitration: - 15.1 It is incumbent upon the contractor to avoid litigation and disputes during the course of execution. However, if such disputes take place between the contractor and the department, effort shall be made first to settle the disputes at the company level. The contractor should make request in writing to the Engineer-in-Charge for settlement of such disputes/claims within 30 (thirty) days of arising of the case of dispute/claim failing which no disputes/claims of the contractor shall be entertained by the company. - 15.2 If differences still persist, the settlement of the dispute with Govt. Agencies shall be dealt with as per the Guidelines issued by the Ministry of Finance, Govt. of India in this regard. In case of parties other than Govt. Agencies, the redressal of the disputes may be sought in the Court of Law.” 8. Section 2(b) of the 1996 Act defines an arbitration agreement to mean an agreement as referred to in Section 7. In terms of Section 7, an arbitration agreement is an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not. Sub-section (2) of Section 7 stipulates that an arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement. In terms of sub-section (3) of Section D E F G H 528 SUPREME COURT REPORTS [2022] 7 S.C.R. - A 7, the arbitration agreement has to be in writing. Sub-section (4) of Section 7 then stipulates that: - “(4) An arbitration agreement is in writing if it is contained in- - (a) a document signed by the parties; B C - (b) an exchange of letters, telex, telegrams or other means of telecommunication including communication through electronic means which provide a record of the agreement; or - (c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.” 9. In **Jagdish Chander** v. **Ramesh Chander** ,[3] a two-judge bench of this Court, while relying upon the earlier decisions in **K. K. Modi** v. **K. N. Modi** ,[4] **Bharat Bhushan Bansal** v. **U.P. Small Industries** D **Corpn. Ltd** ,[5] **Bihar State Mineral Development Corpn** v. **Encon Builders (I) (P) Ltd** .,[6] and **State of Orissa** v. **Damodar Das** ,[7] enumerated the principles governing what constitutes an arbitration agreement. Justice R V Raveendran, speaking on behalf of the bench, held that the words used in an arbitration agreement should disclose a determination and obligation on behalf of parties to refer disputes to E arbitration. This court held: “8 (i) The intention of the parties to enter into an arbitration agreement shall have to be gathered from the terms of the agreement. If the terms of the agreement clearly indicate an intention on the part of the parties to the agreement to refer their F disputes to a private tribunal for adjudication and a willingness to be bound by the decision of such tribunal on such disputes, it is arbitration agreement. **While there is no specific form of an arbitration agreement, the words used should disclose a determination and obligation to go to arbitration and not merely contemplate the possibility of going for arbitration.** G **Where there is merely a possibility of the parties agreeing** G 3 (2007) 5 SCC 719 4 (1998) 3 SCC 573 5 (1999) 2 SCC 166 6 (2003) 7 SCC 418 H 7 (1996) 2 SCC 216 MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.] ## **to arbitration in future, as contrasted from an obligation to refer disputes to arbitration, there is no valid and binding arbitration agreement.** (ii) Even if the words “arbitration” and “Arbitral Tribunal (or arbitrator)” are not used with reference to the process of settlement or with reference to the private tribunal which has to adjudicate upon the disputes, in a clause relating to settlement of disputes, it does not detract from the clause being an arbitration agreement if it has the attributes or elements of an arbitration agreement. They are: (a) The agreement should be in writing. (b) The parties should have agreed to refer any disputes (present or future) between them to the decision of a private tribunal. (c) The private tribunal should be empowered to adjudicate upon the disputes in an impartial manner, giving due opportunity to the parties to put forth their case before it. (d) The parties should have agreed that the decision of the private tribunal in respect of the disputes will be binding on them. (iii) Where the clause provides that in the event of disputes arising between the parties, the disputes shall be referred to arbitration, it is an arbitration agreement. Where there is a specific and direct expression of intent to have the disputes settled by arbitration, it is not necessary to set out the attributes of an arbitration agreement to make it an arbitration agreement. **But where the clause relating to settlement of disputes, contains words which specifically exclude any of the attributes of an arbitration agreement or contains anything that detracts from an arbitration agreement, it will not be arbitration agreement. For example, where an agreement requires or permits an authority to decide a claim or dispute without hearing, or requires the authority to act in the interests of only one of the parties, or provides that the decision of the authority will not be final and binding on the parties, or that if either party is not satisfied with the decision of the authority, he may file a civil suit seeking relief, it cannot be termed as an arbitration agreement** . (iv) **But mere use of the word “arbitration” or “arbitrator” in a clause will not make it an arbitration agreement, if it requires or contemplates a further or fresh consent of the** 529 A B C D E F G H 530 SUPREME COURT REPORTS [2022] 7 S.C.R. A **parties for reference to arbitration.** For example, use of words such as “parties can, if they so desire, refer their disputes to arbitration” or “in the event of any dispute, the parties may also agree to refer the same to arbitration” or “if any disputes arise between the parties, they should consider settlement by arbitration” in a clause relating to settlement of disputes, indicate that the B clause is not intended to be an arbitration agreement. Similarly, a clause which states that “if the parties so decide, the disputes shall be referred to arbitration” or “any disputes between parties, if they so agree, shall be referred to arbitration” is not an arbitration agreement. **Such clauses merely indicate a desire or hope to** C **have the disputes settled by arbitration, or a tentative arrangement to explore arbitration as a mode of settlement if and when a dispute arises. Such clauses require the parties to arrive at a further agreement to go to arbitration, as and when the disputes arise. Any agreement or clause in an agreement requiring or contemplating a further** D **consent or consensus before a reference to arbitration, is not an arbitration agreement, but an agreement to enter into an arbitration agreement in future** .” (emphasis supplied) E 10. In the present case, clause 15 of the Contract Agreement is titled “Settlement of Disputes/Arbitration”. However, the substantive part of the provision makes it abundantly clear that there is no arbitration agreement between the parties agreeing to refer either present or future disputes to arbitration. F 11. Clause 15.1 contains a reference to the steps to be taken for settlement of disputes between the parties. Clause 15.2 stipulates that if differences still persist, the settlement of the disputes with government agencies shall be dealt with in accordance with the guidelines of the Ministry of Finance. In the case of parties other than government agencies, the redressal of disputes has to be sought in a court of law. G 12. A clause similar to clause 15 of the Contract Agreement in the present case was considered by a bench of this Court in **IB Valley Transport, Vijay Laxmi (P) Ltd** . v. **Mahanadi Coalfields Ltd** consisting of J Chelameswar and A. K. Sikri, JJ.[8] In the said case, the H 8 (2014) 10 SCC 630. MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.] 531 clause was interpreted as an alternative remedy at the company level to A be exhausted before taking recourse to other suitable legal remedies. It was observed: “10. From the aforesaid narration of facts, **it becomes clear that Clause 12 of the general terms and conditions provides for a mechanism of dispute resolution before resorting to the legal remedies** . This clause specifically states that it is incumbent upon the contractor to avoid litigation and disputes during the course of execution. **If any dispute takes place between the contractor and the department, effort shall be made first to settle the disputes at the company level. Further, this clause states that the contractors should make request in writing to the Engineer Incharge for settlement of such dispute/ claim within 30 days of arising of cause of dispute/claim.** ” B C (emphasis supplied) 13. The above extract makes it abundantly clear that clause 15 of the Contract Agreement is a dispute resolution mechanism at the company level, rather than an arbitration agreement. Consequently, in case of a dispute, the respondent was supposed to write to the Engineer-in-charge for resolving the dispute. Clause 15 does not comport with the essential attributes of an arbitration agreement in terms of section 7 of the 1996 Act as well as the principles laid down under **Jagdish Chander** (supra). A plain reading of the above clause leaves no manner of doubt about its import. There is no written agreement to refer either present or future disputes to arbitration. Neither does the substantive part of the clause refer to arbitration as the mode of settlement, nor does it provide for a reference of disputes between the parties to arbitration. It does not disclose any intention of either party to make the Engineer-in-Charge, or any other person for that matter, an arbitrator in respect of disputes that may arise between the parties. Further, the said clause does not make the decision of the Engineer-in-Charge, or any other arbitrator, final or binding on the parties. Therefore, it was wrong on the part of the High Court to construe clause 15 of the Contract Agreement as an arbitration agreement. D E F G 14. However, it has been urged on behalf of the respondent by Mr S Niranjan Reddy that the first appellant is a subsidiary of CIL. It has been submitted that on 7 April 2017, CIL issued a policy document H 532 SUPREME COURT REPORTS [2022] 7 S.C.R. - A to its General Managers for the settlement of disputes or differences arising out of works and services contracts through arbitration. Clause 5 of the above communication provides as follows: - “Past/existing work order/contract: 5. With regards to dispute/differences cropping up in existing B work order/contract, employer (department) shall adopt procedure for settlement of the same, through arbitration process. As you are aware that neither the CIL Manuals nor contract document at present contains any clause regarding arbitration, therefore, dispute/differences cannot C be referred to arbitration straight away. Hence, before referring the matter to arbitration, consent of the other party (contractor) is necessary for redressal of dispute/ differences through arbitration. Once, the contractor agrees for settlement of dispute/differences arising out of contracts through arbitration, an agreement may be signed between D employer and contractor for referring the dispute/ differences to Sole Arbitration by a person appointed by Competent Authority of CIL/CMD of Subsidiaries (as the case may be). The rest of the procedure shall be as per the Arbitration and Conciliation Act, 1996 as amended by E Amendment Act of 2015 and also as per instruction incorporated in clause “Settlement of Disputes through Arbitration”.” 15. Hence, it is urged that the first appellant being a subsidiary of CIL and being a public sector undertaking may well consider as to whether F the disputes which have arisen between the appellants and the respondent should be referred to arbitration. In this context, the appellants and the respondent placed reliance on an order dated 20 July 2018 of the Chief Justice of the High Court of Orissa in Arbitration Petition No 59 of 2016. 16. We are unable to subscribe to the submission which has been G urged on behalf of the respondent based on the policy letter dated 7 April 2017. The communication which has been issued by CIL refers to the possibility of a consensual resolution of disputes or differences through arbitration as neither the CIL manuals nor the contract document, at the time, contained a clause regarding arbitration. However, it has been submitted that once the contractor has agreed to settle a dispute through H MAHANADI COALFIELDS LTD & ANR v. M/s IVRCL AMR JOINT VENTURE [DR DHANANJAYA Y CHANDRACHUD, J.] arbitration, the agreement may be signed between the employer and the contractor for reference to arbitration, by a person to be appointed by the competent authority of CIL or, as the case may be, the Chairman and Managing Director of the subsidiaries. 17. The communication dated 7 April 2017 merely indicates a desire on behalf of CIL to have disputes related to work contracts settled by arbitration. It requires both the parties to arrive at a further agreement to proceed to arbitration when the dispute arises. Therefore, in view of the principles laid down in **Jagdish Chander** (supra), following a line of precedent, clause 5 in the aforesaid communication cannot be construed as an arbitration agreement between the appellants and the respondent in terms of section 7 of the 1996 Act so as to compel the appellants to appoint an arbitrator. 18. The order of the Chief Justice of the High Court of Orissa dated 20 July 2018 proceeds on an understanding that the learned counsel for both the sides did not dispute the fact that clause 15 of the Contract Agreement and clause 5 of the policy decision 7 April 2017 taken by CIL provide for appointment of an arbitrator in case there is any dispute or difference between the parties. The order has, therefore, proceeded on an understanding of counsel, which in any event cannot be regarded as a binding statement of law on the existence of an arbitration agreement. 19. For the above reasons, we have come to the conclusion that the invocation of the jurisdiction of the High Court under Section 11(6) of the 1996 Act was not valid and there being no arbitration agreement between the appellants and the respondent, no reference to arbitration could have been made. We accordingly allow the appeal and set aside the impugned judgment and order of the High Court dated 29 November 2019. The respondent would, however, be at liberty to seek recourse to the remedy available in law to pursue the redressal of its grievances. 533 A B C D E F 20. Pending application, if any, stands disposed of. G H Bibhuti Bhushan Bose (Assisted by : Rakhi, LCRA) Appeal allowed.