High Court of KeralaSingle JudgePetition dismissed

Madhu v. State of Kerala

Case / Petition Number:WP(C).No.7472/2020

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • N. Nagareesh
Judgment Date
2021-04-26
Court Decision / Holding
Writ petition dismissed. The court held that 30% of the remaining cost of the terminated works is recoverable at the agreed rates under Clause 2116.2.1 of the PWD Manual, and that realisation through revenue recovery is permissible. The judgments cited (Raman Iron Foundry; Abraham Sebastian) did not address Clause 2116.2.1 and are not dispositive on this issue.
Final Disposition
Petition dismissed

Parties to the Case

Appellants / Petitioners

  • Madhu, S/O.KITTUNNY, AGED 58 YEARS, CHALAKKALAM, THATHAMANGALAM, PALAKKADU DISTRICT

Respondents

  • The State of Kerala, represented by the Secretary to Government, Water Resource Department, Thiruvananthapuram - 605 036
  • The Chief Engineer, Project I, Irrigation Department, Kozhikode - 673 001
  • The Superintending Engineer, Siruvani Project Circle, Palakkad - 678 002
  • The Executive Engineer, Irrigation Division, Chittoor, Palakkad - 678 002
  • The Deputy Tahasildar, Chittoor Taluk, Palakkad District - 678 002

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri.C.S.MANILAL
  • • Sri S.NIDHEESH

Counsels for Respondents

  • • Smt.DEEPA NARAYANAN

Case Synopsis & Summary

This writ petition (WP(C).No.7472/2020) before the Kerala High Court seeks to quash Exts.P1 and P2 to P6 and challenge revenue recovery proceedings alleged to be illegitimate for non-quantified or non-adjudicated tentative liabilities arising from a government contract for widening the Veliavallampathy Canal. Madhu, a government contractor, was selected for the contract, with an initial estimate of ₹13,31,163, later revised to₹18,89,475, and the work was handed over in December 2004 with a completion deadline in 2005, subsequently extended. The contractor claims substantial work was completed but only part payment of ₹8,41,837.60 was made, leaving ₹3,55,947.20 unpaid. A quick verification by the Enquiry Commissioner and Special Judge (Vigilance) led to a finding that the total value of work performed was ₹11,97,784, and the contract was terminated at the department’s risk and cost. Despite this, the department issued a Revenue Recovery notice for ₹2,99,999 under Section 7 of the Revenue Recovery Act, before liability was quantified. The petitioner argues, citing Union of India v. Raman Iron Foundry and Abraham Sebastian v. State of Kerala, that liquidated damages cannot be recovered until adjudication and that 30% of the remaining cost should be realized only from specific sources under the PWD Manual. The court ultimately upholds the department’s position, holding that Clause 2116.2.1 of the PWD Manual permits recovery of 30% of the remaining works at agreed rates and allows realisation through revenue recovery, dismissing the petition for lack of merit.

Provisions of Law Cited

Section 7 of the Revenue Recovery ActClause 2116.2.1 of the PWD Manual

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner argued that a claim for liquidated damages does not create a debt until liability is adjudicated by a court or adjudicating authority. Relying on Union of India v. Raman Iron Foundry and Abraham Sebastian v. State of Kerala, it was urged that revenue recovery cannot be invoked for the liquidated damages until there is adjudication and that 30% realisation under the PWD Manual should be recovered only from sources enumerated (EMD/security, bill/retention, dues from the department, bank or performance guarantees, or by civil suit).

Contentions of Respondents

The respondents argued that the Government is entitled to recover 30% of the cost of remaining works under Clause 2116.2.1 of the PWD Manual and that the 30% can be realised through revenue recovery as it is a sum due to the Government; Clause 2116.2.1 is an active provision that permits realization beyond the purely enumerated sources.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Union of India v. Raman Iron FoundryAIR 1974 SC 1265Mentioned OnlyCited to discuss liquidated damages but not dealing with Clause 2116.2.1; thus not controlling for the present issue.
Abraham Sebastian v. State of Kerala2002 (3) KLT 839Mentioned OnlyCited as not dealing with Clause 2116.2.1; thus not controlling on the present question.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Madhu v. State of Kerala and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT** ## **THE HONOURABLE MR.JUSTICE N.NAGARESH** **MONDAY, THE 26TH DAY OF APRIL 2021/6TH VAISAKHA, 1943** ## **WP(C).No.7472 OF 2020(H)** ## **PETITIONER:** **MADHU, S/O.KITTUNNY, AGED 58 YEARS, CHALAKKALAM, THATHAMANGALAM, PALAKKADU DISTRICT.** **BY ADVS. SRI.C.S.MANILAL SRI.S.NIDHEESH** ## **RESPONDENTS:** |**1**|**THE STATE OF KERALA, REPRESENTED BY**| |---|---| ||**THE SECRETARY TO GOVERNMENT,**| ||**WATER RESOURCE DEPARTMENT,**| ||**THIRUVANANTHAPURAM - 605 036.**| |**2**|**THE CHIEF ENGINEER, PROJECT I,**| ||**IRRIGATION DEPARTMENT,**| ||**KOZHIKODE - 673 001.**| |**3**|**SUPERINTENDING ENGINEER,**| ||**SIRUVANI PROJECT CIRCLE,**| ||**PALAKKADU - 678 002.**| |**4**|**THE EXECUTIVE ENGINEER,**| ||**IRRIGATION DIVISION, CHITTOOR,**| ||**PALAKKADU - 678 002.**| |**5**|**THE DEPUTY TAHASILDAR,**| ||**CHITTOOR TALUK,**| ||**PALAKKAD DISTRICT - 678 002.**| ||**BY SR.GOVERNMENT PLEADER SMT.DEEPA NARAYANAN**| **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 08.02.2021 AND THE COURT ON 26-04-2021 DELIVERED THE FOLLOWING:** WP(C) No.7472/2020 : 2 : ## **J U D G M E N T** ~ ~ ~ ~ ~ ~ ~ ~ ~ _**Dated this the 26[th] day of April, 2021**_ The petitioner, who is a Government Contractor, has approached this Court seeking to quash Exts.P1 and P2 to P6 and to declare that revenue recovery proceedings cannot be invoked in respect of tentative liability and inabilities which are not quantified or adjudicated by the Civil Court or other Adjudicating Authority and hence the recovery proceedings are illegal and non-est. 2. The petitioner was selected for award of the work “Widening the existing Veliavallampathy Canal from Ch: 8930m to 9210m”. The probable amount of contract was ₹13,31,163/-. An agreement was executed on 18.05.2004. The site was handed over to the petitioner on 31.12.2004. The work had to be completed before 30.06.2005. The WP(C) No.7472/2020 : 3 : respondents later extended the period up to 31.12.2005. 3. The petitioner states that the estimate was revised at the instance of the Department to ₹18,89,475/- on 22.04.2005. According to the petitioner, the work could not be completed due to non-supply of Departmental materials and on account of denial of part bills. The petitioner completed substantial work and raised a part bill for ₹12,50,075/-. However, only ₹8,41,837/- was paid. An amount of ₹3,55,947/- is yet to be paid. 4. While so, one Mayilswami filed a complaint before the Enquiry Commissioner and Special Judge, Thrissur. The Enquiry Commissioner ordered a quick verification. In the quick verification, the Vigilance found that the total volume of the work done by the petitioner is ₹11,97,784/- and after deducting the first part bill of ₹8,41,837.60, the balance amount due is ₹3,55,947.20. The Vigilance recommended termination of the contract at the risk and cost of the petitioner. Thereupon, without issuing any notice, the contract was cancelled as per Ext.P1 proceedings. WP(C) No.7472/2020 : 4 : 5. The petitioner states that the security amount of ₹1,00,000/- which was directed to be adjusted against another work of the petitioner was later released on 28.04.2007. Retention amount due to the petitioner was also released on 31.03.2006. The petitioner also remitted ₹26,665/- being the amount quantified as the cost of cement. 6. The petitioner states that though the Department attempted to re-tender the balance work twice, the work was not carried out. As the work could not be carried out, the actual risk and cost cannot be quantified in order to fix any liability on the petitioner. Without quantifying the liability, the Department issued a requisition to the revenue authority for recovery and amount of ₹2,99,999/- from the petitioner. Accordingly, Ext.P6 demand notice was issued under Section 7 of the Revenue Recovery Act. The petitioner challenges Exts.P1 and P6. 7. The learned counsel for the petitioner, relying on the judgment of the Apex Court in _**Union of India v. Raman Iron Foundry** [AIR 1974 SC 1265],_ argued that a claim for WP(C) No.7472/2020 : 5 : liquidated damages does not give rise to a debt until the liability is adjudicated and damages assessed by a decree or order of a court or other Adjudicating Authority. Relying on the judgment of this Court in _**Abraham Sebastian v. State of Kerala** [2002 (3) KLT839]_ , the learned counsel argued that actual loss which the Government had to suffer in a terminated contract can be assessed only after the completion of the work and till then, no revenue recovery proceedings can be initiated against the appellant. 8. As regards realisation of 30% of the cost provided under the PWD Manual, the learned counsel for the petitioner argued that the said 30% amount can be realised only from EMD/security, bill amount/retention amount, any dues from the Department to the contractor or bank guarantee/ performance guarantee or by filing a civil suit. Revenue recovery proceedings cannot be resorted to for recovering the said 30% of the cost. 9. The 4[th] respondent–Executive Engineer contested the case filing counter affidavit. According to the 4[th] WP(C) No.7472/2020 : 6 : respondent, the Government is entitled to recover 30% of the cost through revenue recovery proceedings. In the additional counter affidavit filed by the respondents, it has been stated that as per the PWD Manual, an amount equal to 30% of the cost of the remaining works at the agreed rates of terminated contract has to be paid by the petitioner. In the petitioner's case, 30% of the cost of remaining works was calculated by the Department as per law based on original agreement and the work schedule. In view of the provisions contained in the PWD Manual, there is no need to wait till the work is arranged alternatively through another contractor, for realising the said 30% amount. 10. Heard learned counsel for the petitioner and learned Government Pleader representing the respondents. 11. The petitioner is challenging revenue recovery proceedings initiated by the respondents for recovery of 30% of the cost of the remaining work at agreed rates, on two grounds. Firstly, the amount towards liquidated damages can be recovered from the petitioner only after adjudication of the WP(C) No.7472/2020 : 7 : amount by a civil court or any other competent authority. 12. Secondly, even under the PWD Manual, recovery of 30% of the cost of the remaining work can be realised only from EMD/security, bill amount/retention money, any dues from Department to the contractor, bank guarantee/ performance guarantee or by filing civil suit against the contractor. Revenue recovery proceedings for recovery of the 30% of the cost of the remaining work is not contemplated under the PWD Manual. 13. It is true that a claim for liquidated damages does not give rise to a debt until the liability is adjudicated and damages assessed by a decree or order of a civil court or any other Adjudicating Authority. When there is a breach of contract, the party who commits the breach does not _co instanti_ incur any pecuniary obligation, nor does the party complaining of the breach become entitled to a debt due from the other party. However, when there is an agreement or contract enabling one of the parties to recover a pre-decided sum, such party would be entitled to realise the amount in WP(C) No.7472/2020 : 8 : accordance with the law without resorting to any proceedings for adjudication of the said amount. 14. In the case of the petitioner, the petitioner has executed contract accepting the provisions contained in the PWD Manual. Clause 2116.2.1 of the PWD Manual reads as follows: ## “ **2116.2.1 Realisation of loss on account termination** An amount equal to 30% of the cost of the remaining works at agreed rates of the terminated contract shall be recovered from the defaulted contractor towards the risk and cost. The contractor shall be directed to remit the risk and cost amount within three months. There is no need to wait till the work is arranged alternatively through another contractor and the total loss sustainable due to the default of the original contractor is assessed. Such loss, if any, shall be realised after completion of the work. If he falls to remit the amount within this periods following steps can be adopted for realisation of loss. The amount can be realised from the following: 2. EMD/Security 3. Bill amount/retention if any due to the contract. 4. Any dues from department to the contract. 5. Bank Guarantee/Performance Guarantee or By filing civil suit against the contractor.” ## 15. As there is a specific agreement between the petitioner and the respondents in this regard, the respondents will be entitled to recover 30% of the cost of the remaining WP(C) No.7472/2020 : 9 : works at the agreed rates from the petitioner. The judgment of the Apex Court in _**Raman Iron Foundry**_ (supra) or the judgment of this Court in _**Abraham Sebastian**_ (supra) did not deal with Clause 2116.2.1 of the PWD Manual and therefore those judgments would not be of any help to the petitioner. 16. The further argument of the petitioner is that the said 30% of the cost of the remaining works can be realised by the respondents only from EMD/security, Bill amount/ retention amount, any dues from the department to the petitioner, bank guarantee/performance guarantee or by filing civil suit. The argument is that as the said Clause of the PWD Manual does not specify revenue recovery under the Revenue Recovery Act as one of the mode of realising the amount, the respondents cannot resort to revenue recovery. 17. Clause 2116.2.1 of the PWD Manual states that “an amount equal to 30% of the cost of the remaining works at agreed rates of the terminated contract shall be recovered from the defaulted contractor towards the risk and cost“. Therefore, as per the PWD Manual and the contract entered WP(C) No.7472/2020 : 10 : into by the petitioner with the respondents, the respondents can legally claim 30% amount on termination of petitioner’s contract. The provisions for realising the amount from EMD/security etc. mentioned in Clause 2116.2.1 of the PWD Manual can be treated only as explanatory, and not exhaustive. The Government can very well resort to revenue recovery as the 30% of the cost of the remaining works at agreed rates of a terminated contract, is a sum due to the Government. For the above said reasons, this Court finds no merit in the claim made by the petitioner in the writ petition. The writ petition lacks merit and it is accordingly dismissed. Sd/- **N. NAGARESH, JUDGE** aks/16.04.2021 WP(C) No.7472/2020 : 11 : ## **APPENDIX** ## **PETITIONER'S EXHIBITS:** **EXHIBIT P1 TRUE COPY OF THE PROCEEDINGS OF THE 4TH RESPONDENT DATED 30/5/2014.** **EXHIBIT P2 TRUE COPY OF THE LETTER DATED 20/12/2016 SENT BY THE 4TH RESPONDENT TO THE ADDITIONAL GOVERNMENT PLEADER PALAKKADU.** **EXHIBIT P3 TRUE COPY OF THE RE-TENDER DATED 23/11/2017 ISSUED BY 3RD RESPONDENT.** **EXHIBIT P4 TRUE COPY OF THE RE-TENDER DATED 12/12/2017 ISSUED BY 3RD RESPONDENT.** **EXHIBIT P5 TRUE COPY OF THE SELECTION NOTICE DATED 16/5/2017 ISSUED TO M.M.JOHN.** **EXHIBIT P6 TRUE COPY OF THE REVENUE RECOVERY NOTICE DATED 10/1/2020 ISSUED BY 5TH RESPONDENT.** ## **RESPONDENTS' EXHIBITS:** **ANNEXURE R1(a) TRUE COPY OF THE LETTER DATED 04.12.2015 ISSUED BY THE EECUTIVE ENGINEER, IRRIGATION DIVISION, CHITTOOR TO THE PETITIONER** **ANNEXURE R1(b) TRUE COPY REPORT OF THE ASSISTANT EXECUTIVE ENGINEER, KOZHINJAMPARA RBC SUB DIVISION DATED 05.12.2015 ASSESSING THE LIABILITY OF THE BALANCE WORK. ANNEXURE R1(c) TRUE COPY OF THE RELEVANT PORTION OF PWD MANUAL.** ## **ncd**