Laxmikant & Ors. v. State of Maharashtra & Ors.

Case / Petition Number:
Civil Appeal No. 1965 of 2022 (Arising out of SLP (Civil) No. 16033 of 2021)

Case Synopsis & Summary

This Civil Appeal challenges a Bombay High Court order (Aurangabad Bench) dated 6 August 2021, which held that the reservation of land in the Development Plan stands lapsed for the appellants’ land in Latur because no declaration under Section 126 of the Maharashtra Regional and Town Planning Act, 1966 had been published. The High Court also granted the Planning Authority an additional year to acquire the land, relying on this Court’s decision in Municipal Corporation of Greater Mumbai & Ors. v. Hiraman Sitaram Deorukhar & Ors. The appellants purchased land (Plot Nos. 1, 2, 9 & 10, Survey No. 73, admeasuring 1394.05 sq m) on 21.11.2002 within the Development Plan area, including Site No. 217 for a playground. Although the Development Plan was finalized, it was never implemented, and no acquisition under the Land Acquisition Act, 1894 occurred. After ten years, the appellants served a notice under Section 127 on 16.8.2016 to purchase the reserved land within one year. The Municipal Corporation contested, while the Municipal Corporation of Greater Mumbai in earlier cases discussed the duty to act as cestui que trust and the need to acquire land within a defined period. The Supreme Court held that the ten-year period under Section 126 is sacrosanct and there is no statutory provision for extending it; the 2015 amendment’s extra year is not a new, binding extension. Consequently, the High Court’s direction to acquire within one year was set aside and the appeal allowed; the reservation stands lapsed to the extent of the appellants’ land.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Hemant Gupta
  • V. Ramasesubramanian
Judgment Date
2022-03-23
Court Decision / Holding
Appeal allowed; direction to acquire within one year set aside; the reservation of the land stands lapsed, making the land available for the appellants’ residential use to the extent of their ownership.
Final Disposition
Appeal Allowed

Parties to the Case

Appellants / Petitioners

  • Laxmikant & Ors.

Respondents

  • State of Maharashtra
  • Other Respondents

Provisions of Law Cited

Section 126 of the Maharashtra Regional and Town Planning Act, 1966Section 127 of the Maharashtra Regional and Town Planning Act, 1966Section 31(6) of the Maharashtra Regional and Town Planning Act, 1966Maharashtra Act No. 42 of 2015Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Land Acquisition Act, 1894Article 142 of the Constitution of India

Legal Doctrines & Maxims

  • cestui que trust
  • eminent domain

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contend that once land is reserved in a Development Plan for a public purpose such as a playground, the embargo on its use lasts for ten years under Section 126 of the Act. The subsequent amendment (Act No. 42 of 2015) allowing an additional year to serve a notice for acquisition did not create a perpetual or general extension beyond the statutory timeline. Having purchased the land in 2002 and served notice in 2016, the appellants argue for release of the land from the Development Plan to permit residential use, as the reserved land has not been acquired, and to prevent indefinite restraint on property. The High Court’s reliance on a non-binding period for acquisition is contrary to the statute; the Court should compel strict adherence to ten years plus any statutory maximum, without broad extensions, and declare the reservation lapsed to that extent.

Contentions of Respondents

The respondents emphasize the public nature of land reserved in a Development Plan and the State’s duty, as cestui que trust, to act promptly for acquisition if required for public purposes. They urge that the reservation be protected and that acquisition proceed under the Land Acquisition Act within a meaningful timeframe to ensure development. They rely on the principle that public land should not be diverted for other purposes, consistent with the Bangalore Medical Trust precedent, and caution against reading extra statutory extensions into the plan, despite delays in implementation.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Bangalore Medical Trust v. B.S. Muddappa & Ors.(1991) 4 SCC 54PositiveCited to illustrate that land reserved for public parks/public purposes cannot be diverted to other purposes; reinforces strict adherence to time-bound restrictions on land use.
Municipal Corporation of Greater Mumbai v. Hiraman Sitaram Deorukhar & Ors.(2019) 14 SCC 411Mentioned OnlyRecognized for its discussion on the duty to act as cestui que trust and a six-month period; emphasized that such directions are not binding precedent and may be persuasive rather than controlling.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,215 words•~6 min read

In The Court Record

Laxmikant & Ors. v. State of Maharashtra & Ors.

## **REPORTABLE** ## **IN THE SUPREME COURT OF INDIA** ## **CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. 1965 OF 2022 (ARISING OUT OF SLP (CIVIL) NO. 16033 OF 2021)** LAXMIKANT & ORS. .....APPELLANT(S) VERSUS STATE OF MAHARASHTRA & ORS. .....RESPONDENT(S) ## **J U D G M E N T** ## **HEMANT GUPTA, J.** 1. The challenge in the present appeal is to an order dated 6.8.2021 passed by the High Court of Judicature at Bombay, Bench at Aurangabad, holding that the reservation of land in the Development Plan stands lapsed as no declaration under Section 126 of the Maharashtra Regional and Town Planning Act, 1966[1] was published. However, the Planning Authority was given one year time to acquire the land once reserved relying upon the judgment of this Court reported as **Municipal Corporation of Greater Mumbai & Ors.** v. **Hiraman Sitaram Deorukhar & Ors.[2]** . Signature Not Verified Digitally signed byJayant Kumar Arora 2. A final Development Plan was published under Section 31(6) of the Act Date: 2022.03.23 16:53:27 IST Reason: - 1 For short, the ‘Act’ 2 (2019) 14 SCC 411 1 on 2.1.2002 which came into force on 18.2.2002 in respect of land including the land owned by the appellants such as Latur Reservation Site bearing No. 217 for playground. The appellants purchased the land bearing Plot Nos. 1, 2, 9 & 10 admeasuring 1394.05 square meters out of Survey No. 73, admeasuring 6500 square meters on 21.11.2002. Though the Development Plan was finalized, but the same was never implemented nor any action was taken for acquisition of the land under the Land Acquisition Act, 1894. After expiry of ten years, the appellants issued notice on 16.8.2016 under Section 127 of the Act so as to purchase the reserved land within one year of the date of the notice. Such notice was acknowledged by the respondent Municipal Corporation on 20/22.8.2016 to submit measuring plan showing reservation thereon including the area owned by the appellants. 3. It was thereafter that the appellants filed a writ petition before the High Court for a writ of mandamus directing the respondents to treat the land of the appellants bearing Survey No. 73 as released from the Development Plan of Latur Municipal Corporation and that reservation of Site No. 217 for playground be declared to have lapsed to the extent of the land owned by the appellants and that the land is available for the residential use of the appellants. In the counter affidavit filed by the Municipal Corporation, it was inter alia submitted that the proposal was submitted to respondent No. 2 i.e., the Collector, Latur to take effective steps for acquiring the land bearing Survey No. 73 as the land 2 was reserved for playground. The proposal was returned by the Competent Authority but no effective decision has been taken over the said proposal. 4. Thus, it was beyond dispute that the land once included in the Development Plan under Section 31(6) of the Act was not acquired within the period of ten years and within additional period of one year after purchase notice was submitted by the appellants on 16.8.2016 and, in fact, not till the writ petition was decided by the High Court. The Municipal Corporation is not aggrieved against the declaration granted by the High Court of the fact that the reservation of the land stands lapsed. It is only the land owner who has come in appeal before this Court against the restriction of one year put by the High Court giving additional time to respondents to acquire the land. 5. This Court in **Municipal Corporation of Greater Mumbai** was examining the reservation of land for a garden in a Development Plan in the year 1966 but the same was not acquired even after purchase notice was served by the land owner. However, relying upon the judgment of this Court reported as **Bangalore Medical Trust** v. **B.S. Muddappa & Ors.[3]** and some other judgments, it was held that the land reserved for public park cannot be permitted to be converted for other public purposes. 6. We have heard learned counsel for the parties and find that the liberty given by the High Court to acquire the land within an additional period - 3 (1991) 4 SCC 54 3 of one year is not contemplated by the statute. This Court in **Bangalore Medical Trust,** a Public Interest Litigation, interfered with the decision of the Bangalore Development Authority to convert the land reserved for public parks for the purposes of construction of a hospital. It was in these circumstances that this Court intervened, indicting the land reserved for public parks to be used for other purposes. 7. This Court in **Municipal Corporation of Greater Mumbai** held that the authorities have been given a duty to act as a cestui que trust (beneficiary of the trust) with respect to public park and had thus directed to acquire land under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 within a period of six months. Such direction was given under Article 142 of the Constitution of India keeping in view the facts of the case. Such direction and period for acquisition of land is not a law declared by this Court which is to be treated as binding precedent for this Court and the subordinate courts subordinate in terms of Article 141 read with Article 144 of the Constitution. Therefore, once the Act does not contemplate any further period for acquisition, the Court cannot grant additional period for acquisition of land. The land was reserved for a public purpose way back in 2002. By such reservation, the land owner could not use the land for any other purpose for ten years. After the expiry of ten years, the land owner had served a 4 notice calling upon the respondents to acquire the land but still the land was not acquired. The land owner cannot be deprived of the use of the land for years together. Once an embargo has been put on a land owner not to use the land in a particular manner, the said restriction cannot be kept open-ended for indefinite period. The Statute has provided a period of ten years to acquire the land under Section 126 of the Act. Additional one year is granted to the land owner to serve a notice for acquisition prior to the amendment by Maharashtra Act No. 42 of 2015. Such time line is sacrosanct and has to be adhered to by the State or by the Authorities under the State. 8. The State or its functionaries cannot be directed to acquire the land as the acquisition is on its satisfaction that the land is required for a public purpose. If the State was inactive for long number of years, the Courts would not issue direction for acquisition of land, which is exercise of power of the State to invoke its rights of eminent domain. 9. In view thereof, the direction to acquire land within a period of one year is in fact contravening the time line fixed under the Statute. Consequently, the direction to acquire the land within one year is set aside. The appeal is allowed. **.............................................J. (HEMANT GUPTA) .............................................J.** ## **(V. RAMASUBRAMANIAN)** **NEW DELHI; MARCH 23, 2022.** 5
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.