Larsen and Toubro Ltd. v. Maharashtra State Electricity Board and Ors.

Case / Petition Number:
Civil Appeal No. 8254 of 1995
Neutral Citation:1995 SCR (Supp) 3

Case Synopsis & Summary

This is a Supreme Court dispute arising from a contract for the construction and commissioning of a Coal Handling Plant for the Maharashtra State Electricity Board (MSEB). Larsen & Toubro Ltd. (L&T) furnished multiple bank guarantees as security for advances, performance, retention money, and liquidated damages. After delays and disputes over trial operation and taking over, the plant was eventually taken over on 10 June 1994 and arbitration proceedings followed. L&T sought injunctive relief restraining invocation of certain bank guarantees, arguing that some invocations were fraudulent, dishonest, and/or made after expiry, and that in the circumstances of completed trial operations and take-over, encashment would cause irreparable injustice. The Bombay High Court refused broad relief, holding that injunctive interference with bank guarantees is warranted only in cases of fraud or irretrievable injustice; it did not grant blanket relief but permitted damages claims via arbitration. The Supreme Court examined the established jurisprudence on bank guarantees, citing Svenska Handelsbanken and other precedents. It modified the injunction on a limited basis: restraining Citi Bank N.A. from invoking the guarantee related to retention money (Item No. 3) on the ground that the plant had been taken over and trial operations completed, which rendered the guarantee non-encashable on its terms. The appeal was allowed in part, with costs not awarded. The decision clarifies the narrow circumstances under which bank guarantees may be restrained from encashment while arbitration proceeds.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • J.S. Verma
  • K.S. Paripoornan
Judgment Date
1995-09-13
Court Decision / Holding
Appeal allowed in part. The Court restrained Citi Bank N.A. from invoking the bank guarantee dated 10.5.1989 (Item No. 3) to permit completion of trial operations and take-over, while affirming the lower court’s order on other guarantees. The interim order was made permanent with modification; no costs awarded.
Final Disposition
Appeal allowed in part (injunction against Citi Bank N.A. limited to item 3; other findings upheld)

Parties to the Case

Appellants / Petitioners

  • Larsen and Toubro Ltd.

Respondents

  • Maharashtra State Electricity Board
  • Standard Chartered Bank
  • ANZ Grindlays Bank PLC
  • Citi Bank, N.A.
  • Bank of Baroda

Legal Representation & Advocates

Counsels for Petitioners

  • • B.M. Naik
  • • V. B. Trivedi
  • • Bharat Sangal

Counsels for Respondents

  • • Harish N. Salve
  • • A.S. Bhasme

Provisions of Law Cited

Civil Procedure Code, 1908, Order 39, Rules 1 and 2Arbitration Act, Section 41

Legal Doctrines & Maxims

  • Confirmed bank guarantees/irrevocable letters of credit cannot be interfered with unless there is fraud and irretrievable injustice involved in the case.
  • There should be a prima facie case of fraud and special equities in the form of preventing irretrievable injustice.
  • Mere irretrievable injustice without prima facie case of established fraud is of no consequence in restraining encashment of bank guarantees.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that bank guarantees were fraudulently and dishonestly invoked, some after expiry, and that in the circumstances of completion of trial operation and take-over, invocation caused irretrievable injustice. It contended that the advance guarantee was encashed improperly and that retention money guarantees (Item Nos. 3 and 5) should be rendered unenforceable or subject to damages to be determined by arbitration. It urged that a broader injunctive relief was warranted to prevent encashment before the arbitrator could assess damages and that the Citi Bank guarantee (Item No. 3) should be restrained from invocation given the plant’s take-over and complete trial operation.

Contentions of Respondents

The respondents pressed that there was no fraud or irretrievable injustice in the invocation of guarantees. They argued that the advance and liquidated damages guarantees could be invoked as per contract and extended where applicable, and that the retention money guarantees related to partial releases were contested on terms of the contract and the stage of completion. They maintained that the arbitration could adjudicate disputed amounts and that injunction should not disrupt contractual obligations or ongoing arbitral proceedings.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Savenska Handelsbanken v. Indian Charge Chrome and Others[1994] 1 SCC 502PositiveUsed to articulate the governing rule that confirmed bank guarantees/irrevocable LCs cannot be interfered with except on established fraud and irretrievable injustice.
United Commercial Bank v. Bank of India and Others[1981] 2 SCC 766Mentioned OnlyCited as part of the jurisprudential background in forming the bank-guarantee injunction principle.
UP Cooperative Federation Ltd. v. Singh Consultants & Engineers (P) Ltd.[1988] 1 SCC 174Mentioned OnlyCited as part of the lineage of bank-guarantee jurisprudence without being directly applied to the present holding.
General Electric Technical Services Company Inc. v. Punj Sons (P) Ltd. and Anr.[1991] 4 SCC 230Mentioned OnlyCited as part of the acknowledged precedents on injunctive relief against bank guarantees.
Elian and Rabbath v. Matsas and Matsas[1966] 2 Lloyd's Rep. 495Mentioned OnlyCited as comparative English authority in the context of bank-guarantee injunctions.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,005 words•~19 min read

In The Court Record

Larsen and Toubro Ltd. v. Maharashtra State Electricity Board and Ors.

## LARSEN AND TOUBRO LTD. _v._ MAHARASHTRA STATE ELECTRICITY BOARD AND ORS. ## SEPTEMBER 13,1995 [J.S. VERMA AND K.S. PARIPOORNAN, JJ.] _Civil Procedure Code, 1908, Order-39, Rules I and 2-Bank Guarantees-Fumished under the contract Injunction against invocation of-A confi1med bank guarantee can not be inte1f ered with, unless there is an established fraud and iJTetrievable injustice involved in the case._ c A contract was executed between the parties upon furnishing Bank Guarantees by appellants viz. security against advance, performance, two guarantees for partial release of retention money and security against liquidated damages. D As per contract clauses, after taking trial and performance test, the Plant was taken over by the respondent Electricity Board and a taken over certificate was issued in favour of appellant. For the settlement of its claim, appellant invoked the arbitration clause as per contract. Meeting of arbitrators took place and certain directions were passed by them for filing E the respective claims of the parties to contract. prior to filing its claim, respondent no.I invoked all the Bank Guarantees except performance guarantee. Appellant filed arbitration petition contending that Bank Guarantees have been fraudulently and dishonestly invoked and that also after the date of expiry of said guarantees. Petition was dismissed by the High Court holding only in the event of fraud or irretrievable injustice, the F court would be entitled to interfere in a transaction involving a Bank Guarantee and under no other circumstances; No fraud or irretrievable injustice have been made out; Relief regarding the amount wrongly recovered from the appellant can be claimed before arbitrator by way of damages; and that Communication by the respondent to the appellant and G Bank concerned requesting for extension of expiry date serves the purpose of notices for invocation of Bank Guarantee, so it can not be said that invocation was after the date of expiry of the said guarantees. Against the Order of High Court Appellant preferred an appeal by way of special leave, contending that Bank Guarantees have been H 615 616 SUPREME COURT REPORTS (1995] SUPP. 3 S.C.R. - A fraudulently and dishonestly invoked, and that as far as Bank Guarantee towards advance was concerned, no amount remained balance towards advance, rather they have to recover some amount from respondent no. l. Contention with regard to two bank guarantees towards retention money was that respondent no. 1 was bound to return the retention money as per clause of contract when plan was taken over by them after taking trial r..:ad - B performance test. Regarding Guarantee towards liquidated damages it was contended that damages should be proved and be quantified before invocation of Bank Guarantees. Allowing the appeal in part, this Court - c HELD : 1. Invocation of advance Bank Guarantee was in proper time. [624-B] 2. No fraud of irretrievable injustice have been made out by invocation of Bank Guarantees regarding partial retention money and security D against liquidated damages. [624-H] 3. Guarantee dealing with partial release of retention money furnished by Citi Bank, N.A. was a conditional guarantee, and will ensure only till successful completion of the trial operation and plant is taken over by first respondent. Since stipulation as per clauses of agreement have been E successfully, fulfilled and plant was admittedly taken over by the first respondent that event having ensured, the invocation of Bank Guarantee is not encashable on its terms. [624-E] 4. The appellant is entitled to an order of injunction, to a limited extent, against respondent nos. 1and4 (Citi Bank, N.A.), restraining them F from invoking the Bank Guarantee given by the 4th respondent-citi Bank, N.A. dated 10.5.1989. [626-B] _Savenska Handelsbaken_ v. _Indian Charge Chrome_ a~id _Others,_ [1994] 1 SCC 502; _United Commercial Bank_ v. _Bank of India and Others,_ [1981] 2 G SCC 766; _UP. Cooperative Federation Ltd._ v. _Singh Consultants & Engineers (P) Ltd., [1988] 1 SCC 174; General Electlic Technical Services Company Inco._ v. _Pwzj Sons (P) Ltd. and Anr.,_ [1991] 4 SCC 230 and _Elian and Rabbath_ v. _Matsas and Mat.ms,_ [1966] 2 Lloyd's Report 495, referred to. CIVIL APPELLATE JURISDICTION : Civil Appeal No. 8254.of H 1995. L.T. LTD. _v._ MAHARASHTRA STATE ELECTRICITY BD. (PARIPOORNAN, J.) 617 From the Judgment and Order dated 20.10.94 of the Bombay High Court in Arbitration Petition Lodg. No. 240 of 1994. B.M. Naik, V. B. Trivedi and Bharat Sangal, for the Appellant. Harish N. Salve, and A.S. Bhasme, for the Respondents. The Judgment of the Court was delivered by ## **PARIPOORNAN, J.** Leave granted. > The appellant, petitioner in arbitration petition Lodg. No. 240/94 in C the High Court of Judicature at Bombay, initiated under Section 41 of the Arbitration Act, has filed this appeal by special leave against the order passed by N.D. Vyas, **.T.** dated 20.10.1994. The appellant's prayer for injunction against the first respondent (Maharashtra State Electricity Board) from invoking or claiming or demanding or releasing any amount **D** whatsoever, under certain bank guarantees given by respondent Nos. 2 to 5 was dismissed by the aforesaid order by the learned Judge. Respondent Nos. 1to5 in the arbitration petition Lodg. No 240/94 as also in this appeal are- (1) Maharashtra State Electricity Board, Bombay, (2) Standard Chartered Bank, Branch Bombay, (30 Grindlays Bank P.1.C., Branch Bombay, (4) Citi Bank, N.A., branch Bombay and (5) Bank of Baroda, branch E Bombay. The first respondent invited tenders for supply and commission of Coal Handling Plant. The appellant's tender,which was accepted, culminated in a contract, executed between the parties, dated 9.3.1989. The value of the contract was Rs. 61,11,07,200. The appellant furnished the following five Bank Guarantees : F |followingfiveBank Guarantees :|followingfiveBank Guarantees :|Bank Guarantees :|||| |---|---|---|---|---|---| |Sl.<br>Name of the<br>No.<br>Bank||No.of the<br>Bank<br>Guarantee|Nature of<br>the Bank<br>Guarantee|Amount of<br>the Bank<br>extended<br>Guarantee<br>inRs.|Last<br>extended<br>date.| |1.|Standard<br>Chartered<br>Bank/Res po-<br>ndent No.2|529/88/153|Security<br>against<br>advance<br>payment|5,50,30,000|31.5.94| |2.|ANZ<br>Grindlays<br>Bank, PLC<br>Respondent<br>No.3|1101/88/384/G|1101/88/384/GPerformance|6,17,28,000|31.3.95| |---|---|---|---|---|---| |3.|Citi Bank,<br>N.A.<br>Respondent<br>No.4|26247|Partial<br>release of<br>retention<br>money|2,72,39,850|19.11.94| |4.|Bankof<br>Baroda,<br>Respondent<br>No._5_|73/309|Security<br>against<br>liquidated<br>damage|6.,13,40,978|26.9.94| |_5._|Standard<br>Chartered<br>Bank,<br>Respondent<br>No.2|529/92/380|Partial<br>release of<br>retention<br>money|1,12,00,000|31.12.94| (Vol. II page 4 of Paper Book) E The completion of the Plant seems to have been delayed. The parties are blaming each other for the delay. After taking the trial and performance test, the Plant was taken over by the first respondent on 10.6.1994. On the same day a take-over certificate was also issued. It is seen that earlier on 29.3.1994, the appellant lodged its claim. The first respondent denied the F claims so made. they did not make any counter-claim then. On 4.6.1994, the appellant invoked the arbitration clause as per the contract. A meeting of the Arbitrators took place on 14.9.1994. The Arbitrators gave certain directions. In pursuance thereto the appellant filed its claim on 30.9.1994. The Arbitrators gave time to the first respondent to file their counter claim on or before 30.11.1994. In the mean-while on 1.10.1994 the first responG dent invoked all the Bank Guarantees except Guarantee No. 2 mentioned herein-above (Performance Guarantee). The Court passed an order directing the status quo to be mentioned on 17.10.1994. Appellant filed arbitration petition Lodg. No. 240/94 and contended that the Bank Guarantees have been fraudulently and dishonestly invoked. Regarding Guarantees in H respect of advance and liquidated damages, it was further alleged that they L.T. LTD. _v._ MAHARASHTRASIATEELECIRICITYBD. (PARIPOORNAN,J.] 619 were invoked after the date of expiry of the said guarantees. V?'as, J. A rejected the above pleas and declined to grant the interim relief as p~ayed for the appellant. As agreed to by counsel on both sides, the interim order was made the order in the main petition itself. Arbitration petition Lodg. No. 240/94 was dismissed. Hence this appeal by special leave. We heard appellant's counsel Mr. B.M. Naik, senior Advocate, and Mr. Barish N. Salve, senior Advocate, who appeared for the respondents. At the outset we should make it clear that the Bank guarantee relating to performance, item No. 2 mentioned in the preceding paragraph, was not invoked and is not covered by the subject matter of this proceeding. B c Before we adjudicate the rival pleas urged before us by counsel for the parties, it will be useful to bear in mind the salient principles to be borne in mind by the Court in the matter of grant of injunction against the enforcement of a Bank . Guarantee/irrevocable Letter of Credit. After survey of the earlier decisions of this Court in _United Commercial Bank_ v. _Bank of India and Ors.,_ [1981] 2 SCC 766, _U.P. Cooperative Federation Ltd._ D v. _Singh Consultants & Engineers (P) Ltd.,_ [1988] 1 SCC 174, _General Electlic Technical Service Company Inc._ v. _Punj Sons (P) Ltd. and Anr.,_ [1991] 4 SCC 230 and the decisions of the Court of appeal in England in _Elian and Rabbath_ v. _Matsas and Matsas,_ [1966] 2 Lloyd's Report 495 and a few American decisions, this Court in _Svenska Handelsbanken_ v. _Mis._ E _Indian Charge Chrome and Others,_ [1994] 1 SCC 502, laid down the law thus: E " ......... in case of confirmed bank guarantees/irrevocable letters of credit, it cannot be interfered with unless there is fraud and irretrievable injustice involved in the case and fraud has to be an established fraud ...... " (p.523) F " .......... irretrievable injustice which was made the basis for grant of injunction really was on the ground that the guarantee was not encashable on its terms ........... " (p.524) G "... ....... there should be prima. facie case of fraud and special equities in the form of preventing irretrievable injustice between the parties. Mere irretrievable injustice without prima facie case of established fraud is of no consequence _in restraining_ the encashment of bank guarantee." (pp. 526-527) H 620 SUPREME COURT REPORTS [1995] SUPP. 3 S.C.R. E A In the order appealed against the learned Judge has referred to the decisions aforesaid and has held thus : B 11 •••••••• Only in the event of fraud or irretrievable injustice, the Court would be entitled to interfere in a transaction involving a bank guarantee and under no other circumstances. The petitioners have failed on both these counts." (Paper Book - Vol.-I p. 7) Appellant's Counsel contended that the Bank Guarantees have been fraudulently and dishonestly invoked by the first respondent. It was subc mitted that so far as the Bank Guarantee towards advance was concerned, no amount remains as balance towards advance and in fact a sum of Rs. 27,000 is recoverable from the first respondent. With regard to the two Bank Guarantees, dealing with retention money (Item Nos. 3 and 5) it was contended that the trial was taken by the first respondent after which D performance test was also done and thereafter the take-over was completed and so, on the basis of the contract, the first respondent was bound to return the Retention Guarantees. Regarding liquidated damages (Item No. 4) it was contended that the first respondent should prove that they suffered damages and quantify the same before invoking the Guarantee. It was also contended that the invocation of the Guarantee relating to adE vance and liquidated damages was after the expiry of the period. The learned Judge found that no fraud or irretrievable injustice has been made out. The Court also held that the appellant will be able to claim relief before the Arbitrators by way of damages, for amounts wrongly recovered, and so no irretrievable injustice can be said to exist. The learned Judge F also held that the first respondent by separate letters dated 14.9.1994 and 10.5.1994 addressed to the Bank of Baroda and Standard Chartered Bank respectively, while requesting to extend the Bank Guarantee, specifically stated that, if it was not so done, the communication should be treated as notice for encashment of the Bank Guarantee and these communications G addressed to the respective banks prior to the Guarantees would serve the purpose of notice to the banks and so it cannot be held that the invocation was after the date of expiry of the said Guarantees. c F Having heard Counsel and on perusing the relevant records, we are of the view that the order of the Court below regarding Item No. 3 - Partial H relase of retention money in the sum of Rs. 2,72,39,850, Guarantee given ## LT.LTD. _v._ MAHARASIITRASTATEELECTRICTIYBD. [PARIPOOR.~AN,J.) 621 by the Citi Bank alone requires modification. We will deal with the various A items in seriatim : ITEM NO. l: _Security against advance payment (Advance Bank Guarantee)._ The Guarantee given on this count by the Standard Chartered Bank B for a sum of Rs. 5,50,30,000 is contained in paper book Volume II at pages 109 to 113. It was agreed at the bar that the Bank Guarantee has not been invoked for the entire sum of Rs. 5.50_ crores but is limited to a sum of Rs. 8 lakhs only. We find that dispute exists with regard to the said subject matters, as is evident from the relevant papers - (Volume II Pages 312 and C 316). It is seen from the communication dated 10.5.1994 addressed by the first respondent to the appellant, with an endorsement to the Standard Chartered Bank, that a request was made to extend the validity of the Bank Guarantee for a further period of 6 months, i.e., 30.11.1994 and in case the extension is not received before that date, the communication be treated as notice for encashment (Vol. II pages 33 to 34 of the Paper book). We D are of the view that the invocation of the Guarantee is in time. We hold that in the light of the dispute pending before the Arbitrator, the Court below was justified in declining to grant an injunction against the invocation of the Bank Guarantee on this count. E _Item Nos. 3,_ & 5 _: Partial release of retention money :_ Items 3 and 5, though come under the same category, are not similar in content and scope. Item 3, relates to Bank Guarantee furnished by the Citi Bank, N.A. in the sum of Rs. 2.72 cores. It is a conditional Guarantee. Copy of the document is available in paper book Volume II at pages 122 F to 126. The relevant portions in the Guarantee in volume II at pages 124 and 125 of the paperbook, are as follows : "AND WHEREAS at the request of the contractors, we, CITI BANK N.A. (hereinafter referred to as "The Bank" has agreed to G guarantee 2, 72,39,850 (Rupees Two Crores, Seventy Two lakhs, Thirty Nine thousand, Eight hundred fifty only) covering the amount of the said payments _till successful completion of t1ial operations._ " In pursuance of the said agreement and in Consideration of the H SUPREME COURT REPORTS [1995] SUPP. 3 S.C.R. 622 A board making the said payment to the contractors, the Bank hereby agree with the Board as follows : B c 1. The Bank hereby agree unequivocally and uncondition to guarantee the said amount released by the _Board till successful completion of trial operations in due perf onnance of the contract_ and undertakes to at Bombay within _48_ hrs. on demand in writing from MSEB, or any officer authorised by it in this behalf of any amount upto and not exceeding Rs. 2,72,39,850/- (Rupees Two crores, Seventy two lakhs, Thirtynine thousand, Eight hundred fifty only) to the Maharashtra State Electricity Board on behalf of the contractors ......................... . D 2. That the guarantee hereby given shall be continuing guarantee upto 19 May, 1990. The validity of this Bank guarantee will be extended one month prior to its present validity at the request of the Board for suitable period(s) _till successful completion of trial operations."_ ## (emphasis supplied) E > Volume II, pages 46 to 108, contains a copy of the agreement executed between the appellant and the first respondent Board. The following clauses therein at pages paragraphs 70.1, 70.2, 70.3 and 70.4.01, appearing at pages 92 to _95,_ are relevant in the this connections. They are as fellows: "70.1 (i) .......................................... . F ## G (iii) After the precommissioning tests are satisfactorily completed equipment shall be considered ready for initial operation. During initial .operation, the complete equipment shall be operated integral with sub-system and supporting equipment as a complete plant. ## 70.2 TRIAL OPERATION : H' (I) After satisfactory initial operation, the Plant shall then be. put on trial operation. The period of trial L.T.LID. _v._ MAHARASHTRASTATEELEcrRIC11YBD. (PARIPOORNAN,J.) 623 operation shall be 30 days from the date of completion A of initial operation. During the period of trial operation, all the necessary adjustments in the plant/equipments shall be made by the Contractor and make ready the same in all respects for performance and guarantee test. Out of trial operation, the plant shall run for atleast a B period of 100 hours at the rated capacity. Out of these 100 hrs. a minimum of 20 hours of operation at the rated load shall be established for the mode of operation from wagon tippler to the bunker. B ## 70.3 _PERFORMANCE TESTS AT SITES:_ c (i) _The perfomiance test shall be conducted at site by the Contractor, after successful completion of trial operation._ The duration of the performance t~st of the plant at the rated capacity shall be of 2 hours. Performance Guarantee test shall in any case be conducted within D 45 days of successful completion of trial operation or within the extended period as can be mutually agreed. In case the performance test cannot be conducted within a period of 75 days after successful completion of trial operation due to reasons solely attributable to E owner, the time frame and method of conductance of the same shall be discussed mutually and finalised. ## xxx xxx xxx - (v) Any special equipment, tools and tackles required for the successful completion of the performance tests shall be provided by the Contractor free of cost." - "70.4.01 Upon successful completion of all the performance tests at site, the owner shall _issue to the Contractor a "Taking Over Ce1tificate" as a proof of the final accep-_ G _tance of the equipment ........... "_ (emphasis supplied) The first respondent Board intimated the appellant by communication dated 10.6.1994 thus: SUPREME COURT REPORTS [1995] SUPP. 3 S.C.R. 624 A B "After reasonable completion of the Coal Handling Plant works as per the contract 2 M part-A, capacity operation of the various equipments of C.H.P. were planned from 15th January, 1994. Rates as well as design capacity trials also tried Certain Points for stabilisation which were pointed to L&T were attended. _Since these tlials are generally satisfa.ctOJy as per Claus.e no. 70.2_ & _70.3,_ all the commissioned equipments under the contract of 2M Part-A are taken over by MSEB for regular operation and maintenance from _10th June, 1994 as per Clause No. 70.4 of Contract Agreement Vol. I."_ c ## (emphasis supplied) The appellant wrote to the first respondent on 21.2.1994 that the plant was completed and so all Bank Guarantees have served their contractual requirements. On a perusal of the relevant clauses in the contract, executed D between the appellant and the first respondent, and the communication of the first respondent dated 10.6.1994, it is fairly clear that the stipulations or conditions mentioned as per clauses 70.2, 70.3 and 70.4 have been successfully fulfilled and the Plant was admittedly taken over by the first respondent. The Guarantee given by the Citi Bank, N.a. dated 10th of May, 1989 appearing in Volume II at pages 122 to 126 will ensure only till E successful completion of the trial operations and the plant is taken over. That event having ensued, the invocation of the Guarantee given by the Citi Bank dated 10.5.1985 in the sum of Rs. 2.72 crores is not encashable on its terms and in order to prevent irretrievable injustice, an injunction as prayed for, to respondents 1 and 4 deserves to be issued on that score. The F Court below was in error in not doing so. We hereby restrain respondents 1 and 4 from invoking the Bank Guarantee aforesaid. F But item No. 5 partial release of retention money, for which the second respondent, Standard Chartered Bank has given a Bank Guarantee for Rs. 1,12,00,000 (Rs. 1.12 crores) stands on a different footing. The G relevant Guarantee is contained in paper book Volume II at pages 134 to 138. The first respondent made an ad hoc payment of Rs. 1.11 crores out of the total retention amount for which the Guarantee was furnished by the Standard Chartered Bank. _It is an unequivocal and unconditional Guarantee._ We hold that no fraud or irretrievable injustice has been made H out by the appellant. The court below was justified in declining to issue an LT.LID. _v._ MAHARASHTRASfAIBELECIRICilYBD. (PARIPOORNAN,J.] 625 A ## order of injunction on -this count. The last item is covered by the Guarantee specified as No. 4 hereinabove. It was furnished by the Bank of Baroda as a security against 'liquidated damages'. The Guarantee is contained in paper book Volume II at pages 129-131. The Bank has given Guarantee for Rs. 6.13 crores against the liquidated damages recoverable by the first respondent Board, from the appellant. The relevant clause regarding levy of liquidated damages is contained at pages 99 and 100 of the Paper book, (Clause 75.01), to the following effect: B c "75.01 If the Contractor fails to complete the works as per the clause 72.01 item 1, 2 and 3 within a period of 25 months from the date of letter of intent or within any extension of time granted by the owner then the liquidated damages shall be levied by the Owner on the Contractor at the rate of 1/2% (one half of one per D cent) per week of delay of the contract price for the works limited to 10% (ten percent) of the contract price of the works." • Appellant's Counsel argued that before invoking the Bank Guarantee the first respondent should have levied the liquidated damages and only E for the sum so determined, and intimated to the appellant, the Bank Guarantee can be invoked. It was further argued that the Guarantee was due for expiry on 26.9.1994 and it bas been invoked after the expiry of the said period. There is no force in the above pleas. It is common ground that the arbitration proceeding for resolving the dispute between the parties (appellant and the respondent) is pending before the arbitrator. The F parties are at issue as to whether the Plant was completed in time or was delayed. They are blaming each other for the delay. That is a matter to be adjudicated in the proceedings. It is also brought to our notice that the first respondent has claimed liquidated damages as per clause 75.01 of the contract of more than eight crores - much more than the amount of Rs. 6.13 crores guaranteed. Since the decision in the arbitration proceedings G has an impact on this aspect, we are of the view that no prima facie case of fraud or irretrievable injustice is made out to restrain respondents, 1 and 5 from invoking the Bank Guarantee. Perusal of the communication dated 14.9.1994, sent by the first respondent to· the appellant and also t6 the Bank of Baroda appearing in paper book Volume 1 at pages 35 to 36, H 626 SUPREME COURT REPORTS [1995] SUPP. 3 S.C.R. - A will show that a request to extend the validity of the Bank Guarantee which was to expire on 26.9.1994, was made and if not so done, the communication was to be treated as notice for encashment of the Bank Guarantee. The plea that the invocation was not in proper time is also without substance. B In the result, we hold that the appeal succeeds in part. The appellant is entitled to an order of Injunction, to a limited extent, against respondent Nos. 1 and 4 (Citi Bank N.A.), restraining them from invoking the Bank Guarantee given by the 4th respondent - Citi Bank, N.A. dated 10.5.1989 (item No. 3 stated hereinabove) (Volume II at pages 122 to 126 of the C Paper book). Subject to the above modification, the order passed by the Court below dated 20.10.1994 is affirmed. In the circumstances, their shall be no order as to costs. ## R.A. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (1995) Decisions
1995-02-23

Inder Singh v. State of Punjab

Inder Singh, convicted under Section 302 IPC for the murder of Amar Singh, questions the High Court’s affirmation of his life-term sentence. The prosecution’s version is that Amar Singh, who had gone to see off a tractor driver, did not return home; on the night of 31 March/1 April 1984, the appellant, armed with a barchha, lay in wait behind a heap of manure and suddenly sprang upon Amar Singh, while PW4 (the deceased’s father) and PW5 (the mother) were trying to intervene. Amar Singh died instantaneously from a fatal neck wound, with the post‑mortem revealing injuries that pointed to a lethal strike. The Trial Court convicted the appellant under Section 302 IPC, while acquitting two co‑accused. In the appeal before the Supreme Court, the defence argued that the appellant’s motive was merely to thrash Amar Singh for suspected theft of cauliflowers, and that lying in wait with a weapon did not necessarily prove an intention to kill. The Court rejects this: the manner of the assault, the weapon used, the location and extent of the injuries, and the fact that PW4 was also injured while trying to save Amar Singh indicate a determined intention to cause fatal injury. The Court also notes the prompt FIR, the medical evidence, and the recovery of the weapon as corroboration, sustaining the conviction. The appeal is dismissed.

1995-03-27

SUBORDINATE SERVICES SELECTION BOARD v. BIR SINGH AND ANR./RAM NIWAS AND ORS.

This Supreme Court decision concerns the interpretation of reservation in Ex-Servicemen posts and the eligibility of dependents of ex-servicemen for clerical posts in A-class offices. The case arose from a dispute over whether dependents of ex-servicemen, who possess Matriculation but do not have First Division in Matriculation or Second Division in Intermediate, could be considered for appointment to A-class clerical posts when ex-servicemen are unavailable and vacancies exist in the reserved quota. The government had reserved A-class posts for ex-servicemen and prescribed stratified qualifications for A-class and B-class offices; in 1979, to avoid lapsing of reserved posts, it was decided that dependent sons and daughters of ex-servicemen who fulfilled all prescribed conditions should be considered on merit for posts reserved for ex-servicemen to the extent of non-availability of suitable ex-servicemen. The respondents, dependents of ex-servicemen, argued that the 7.9.1991 advertisement did not distinguish between A- and B-class posts and that their Matriculation alone made them eligible for A-class posts on par with ex-servicemen. The High Court held them eligible, but the Court reversed, holding that such dependents are not entitled unless they meet the prescribed qualifications (Matric with First Division or Intermediate with Second Division) or are ex-servicemen. The appeals were allowed.

1995-11-01

Yadu Nandan Garg v. State of Rajasthan and Ors.

This appeal concerns a preliminary notification under Section 4(1) of the Rajasthan Land Acquisition Act, 1953 for the 'planned development of Jaipur city' and a declaration under Section 6 issued after the improvement scheme had been finalised. The appellant, Yadu Nandan Garg, had purchased part of the land in 1970 and built a residence there, while Anand Nursery nearby obtained an exemption. The challenge focused on: (i) alleged unexplained delay between the preliminary notification and the declaration, (ii) discriminatory treatment in granting exemption to Anand Nursery but not to the appellant, and (iii) misdescriptions of survey numbers in the Section 9 notice, namely 265 vs 265/1. The Rajasthan High Court had dismissed the challenge, and the Supreme Court, in its division bench, upheld the validity of the acquisition. The Court held that a purchaser cannot acquire title against the State by clinging to an encumbrance after the notification and finalisation of the scheme; under Section 16 the State is entitled to possession with absolute title free from encumbrances. It rejected the contention of inordinate delay, noting the usual administrative time involved in finalising the scheme. It also held that wrong exemptions or mis-stated survey numbers do not invalidate the notification under Section 4(1), provided the main survey number is mentioned, and that discrimination claims fail given lack of a universal benefit. Consequently, the appeal was dismissed without costs.

1995-09-19

Controller of Examination, Utkal University and Anr. v. Paurnamasi Das and Anr.

These two Civil Appeals arise from challenges to the awarding of BA honours by Utkal University under its Regulations for pre-degree and final degree examinations, and the operation of the 1990 Hard Case Rule. Regulation 12 prescribes separate classification in pre-degree and final degree exams, to be shown on the diploma, with specific percentage thresholds for Second Class and First Class honours in both stages. Regulation 16(b) makes the final degree honours list depend solely on marks obtained in the final examination, subject to retaining honours in the pre-degree stage. The Hard Case Rule provides grace marks (up to 0.5%) to enable a candidate to retain honours or attain a higher class, but must be applied per part of the examination. The respondents, in two appeals, were short by 4 marks in their final degree honours papers, seeking to add 4 grace marks (0.5% of 800) by aggregating marks across pre-degree and final degree, an approach the High Court accepted but the University challenged. The Court held that the Hard Case Rule applies separately to each examination part, and that only up to 2 grace marks could be added in the final degree examination (not across parts). The High Court’s view was thus incorrect, and the appeals were allowed with writ petitions dismissed."