Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. (and Others)
Case Synopsis & Summary
These Civil Appeals arise from an arbitration dispute between Larsen and Toubro Limited (L&T) and Puri Construction Private Limited (PCL), involving a Development Agreement dated 10 March 1998 for a Gurgaon project, its Supplementary Agreement of 30 December 1999, and a Tripartite Agreement with Lord Krishna Bank. The Arbitral Tribunal held that L&T breached the Development Agreement, found the Supplementary Agreement tainted by coercion and economic duress, and awarded damages including Rs. 35 crore for breach, Rs. 75 crore for loss regarding 15 acres of land, and Rs. 5 crore for non-return of licences, along with a permanent injunction and cost orders, while also granting indemnification for ITCREF’s claims. The learned Single Judge under Section 34 of the Arbitration Act set aside the Arbitral Award. The Division Bench of the Delhi High Court partly allowed the appeals, upholding some findings about coercion and non-novation but modifying monetary relief and indemnification. The Supreme Court, in a binding interpretation of Section 34 jurisprudence, held that the power is limited to setting aside or remanding and cannot modify the award on merits. It reaffirmed the Tribunal’s findings on fundamental breach and non-novation, set aside the monetary quantification and indemnity aspects, maintained the injunction, and disposed of the appeals with a directions to pursue appropriate remedies, including release of title deeds to PCL. The Court ultimately dismissed the appeals.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Abhay S. Oka
- Pankaj Mithal
- Judgment Date
- 2025-04-21
- Court Decision / Holding
- Appeals dismissed. The Supreme Court upheld the Division Bench’s conclusions on merits, confirmed that the Supplementary Agreement was not operative due to economic duress and did not novate the Development Agreement, and sustained the finding of fundamental breach by L&T. It held that Section 34 allows only setting aside or remand, not modification of the award, and accordingly struck down the monetary damages and indemnity provisions quantified by the Tribunal (Rs. 35 crore, Rs. 75 crore, Rs. 5 crore, and the indemnity to ITCREF). The permanent injunction in favor of PCL was upheld, title deeds deposited with the court were directed to be released to PCL, and the matter was left open to pursue appropriate remedies under law. The costs of arbitration awarded to PCL were upheld. The appeals were dismissed.
- Final Disposition
- Appeals dismissed; merits upheld; monetary damages and indemnities reduced or set aside; injunction sustained; title deeds to be released; costs upheld.
Parties to the Case
Appellants / Petitioners
- Larsen and Toubro Limited
Respondents
- Puri Construction Private Limited
Legal Representation & Advocates
Counsels for Petitioners
- •
Counsels for Respondents
- •
Provisions of Law Cited
Legal Doctrines & Maxims
- Patent illegality (as a ground for setting aside awards)
- Limited remedy under Section 34 (set aside or remand)
- plausibility/pplausible view (court defers to arbitral reasoning if plausible)
- Economic duress/undue influence (Section 16(3) of the Contract Act)
- Dominant will doctrine (Section 16(3) of the Contract Act)
- Uncitral Model Law framework (limited interference)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contends that a court exercising supervisory jurisdiction under Section 34 of the Arbitration Act cannot modify or rewrite an arbitral award. It argues that the Division Bench exceeded its scope by partially upholding and modifying disparate parts of the award, including damages and indemnity, which amounts to “rewriting” the award rather than merely setting it aside or remanding. L&T maintains that the Supplementary Agreement was not operative because its conditions precedent were not satisfied, and that the Tribunal’s reliance on economic coercion/duress to invalidate it was not supported by pleadings or evidence. It further asserts that the Bank’s claims and ITCREF’s indemnity were not properly before the Tribunal and that the award’s monetised damages were improperly quantified, relying on L&T’s own loss calculations. L&T emphasizes market-condition considerations and contends that the contract’s clauses (e.g., Clauses 26, 34) and the Tripartite Agreement should have governed remedies, with EDC payments being recoverable, and argues against treating the award as capable of partial perverse modification without remand.
Contentions of Respondents
PCL contends that the Division Bench correctly held that the Supplementary Agreement was tainted by coercion and economic duress and that the Arbitral Tribunal failed to give effect to the true terms of the Development Agreement. It argues that the Supplementary Agreement was designed to secure payments and guarantees amid financial distress and that L&T’s conduct—non-payment of EDC, failure to commence development, and non-return of title deeds—justified termination and damages. It notes that the Bank and ITCREF claims were integral to the disputes, with the Tripartite Agreement linking obligations for EDC and loan repayments. It asserts the Arbitral Tribunal’s reasoning was grounded in substantial evidence and pleaded material, and that the court should not substitute its own evaluation for the Tribunal’s findings. It defends the preservation of injunctive relief and the order to hand over title deeds, while arguing for the vindication of the indemnity claim to ITCREF as concluded by the Tribunal.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (8)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Project Director, National Highways No. 45 E and 220, National Highways Authority of India v. M. Hakeem and Another | (2021) 9 SCC 1 | Positive | Cited as binding authority establishing that Section 34 cannot modify the award; the Court followed this precedent. |
| McDermott International Inc. v. Burn Standard Co. Ltd. & Ors. | (2006) 11 SCC 181 | Positive | Cited for the same principle limiting the court’s power under Section 34 to setting aside/remand rather than modification. |
| Kinnari Mullick v. Ghanshyam Das Damani | (2018) 11 SCC 328 | Positive | Cited for the ‘plausible view’ doctrine and limited remedy under Section 34. |
| Navigant Technologies (P) Ltd. v. Dakshin Haryana Bijli Vitran Nigam Ltd. | (2021) 7 SCC 657 | Positive | Cited in the context of limited judicial interference in Section 34 proceedings. |
| Associate Builders v. Delhi Development Authority | (2015) 3 SCC 49 | Positive | Cited regarding openness to reasonable or plausible findings and limits of judicial scrutiny. |
| Dyna Technologies Private Limited v. Crompton Greaves Limited | (2019) 20 SCC 1 | Positive | Cited to emphasize that courts should not re-express the arbitral tribunal’s precise reasoning; reasons can be implied. |
| S.V. Samudram v. State of Karnataka and Another | (2024) 3 SCC 623 | Positive | Cited to illustrate standards for evaluating plausibility of arbitral awards in supervisory review. |
| Dakshin Haryana Bijli Vitran Nigam Ltd. v. Navigant Technologies (P) Ltd. | (2021) 7 SCC 657 | Positive | Reiterated the limited scope of interference under Section 34. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Larsen and Toubro Limited v. Puri Construction Pvt. Ltd. (and Others)
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.