Tenetowl LogoTenetowl
Landmark CasesDivision BenchAppeal disposed of; High Court order set aside;...

LAND AND BUIILDING DEPARTMENT THROUGH SECRETARY & ANR. v. ATTRO DEVI & ORS.

Case / Petition Number:
Civil Appeal No.2749/2023

Case Synopsis & Summary

This Civil Appeal challenges a Delhi High Court order that held the land in question under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 to have lapsed for non-payment of compensation and non-taking of possession. The underlying land was acquired by the Delhi Development Authority for planned development of Delhi, pursuant to notifications under Section 4 (1989) and Section 6 (1990) of the Land Acquisition Act, 1894, followed by an award in 1992. The respondents sought protection under Section 24(2) of the 2013 Act on the ground that possession was never taken or compensation paid; the High Court relied on Pune Municipal Corporation v. Misrimal Solanki and held lapse. The appellants argued that the Constitution Bench in Indore Development Authority v. Manoharlal overruled Pune and held that compliance with either possession or payment suffices to prevent lapse. The record shows possession was taken on 06.12.2012 and handed over to the DDA; the land is needed for the Delhi-Saharanpur-Dehradun Highway in Bharatmala Pariyojana Phase I, a project of national importance. The Supreme Court agrees with the Indore doctrine; the High Court order is set aside, and compensation must be paid to landowners in accordance with the 2013 Act.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Abhay S. Oka
  • Rajesh Bindal
Judgment Date
2023-04-11
Court Decision / Holding
The appeal is allowed; the High Court’s order set aside. The acquisition is saved under the Indore doctrine, since possession was taken (06.12.2012) and the land has been handed over to DDA. Respondents are entitled to compensation as per their entitlement under the 2013 Act, and the Land Acquisition Officer shall pay the compensation.
Final Disposition
Appeal disposed of; High Court order set aside; compensation to be paid to landowners; LAC to disburse under the 2013 Act.

Parties to the Case

Appellants / Petitioners

  • LAND AND BUIILDING DEPARTMENT THROUGH SECRETARY & ANR.

Respondents

  • ATTRO DEVI & ORS.

Provisions of Law Cited

Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 4 of the Land Acquisition Act, 1894Section 6 of the Land Acquisition Act, 1894Section 16 of the Land Acquisition Act, 1894Section 9 of the Land Acquisition Act, 1894Section 11 of the Land Acquisition Act, 1894Section 17(1) of the Land Acquisition Act, 1894Section 24(1)(a) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 24(1)(b) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 31 of the Land Acquisition Act, 1894Section 34 of the Land Acquisition Act, 1894Section 31(1) of the Land Acquisition Act, 1894

Legal Doctrines & Maxims

  • Possession vests in the State free from encumbrances after award (vesting doctrine).
  • Taking possession under the 2013 Act amounts to taking physical possession; once possession is taken, there is no lapse under Section 24(2).
  • A person retaining possession after vesting is a trespasser; the land vests in the State free from all encumbrances.
  • The proviso to Section 24(2) should be treated as part of Section 24(2).
  • Non-deposit of compensation in court does not by itself cause lapse unless the majority holdings have not been paid; compensation under the 2013 Act must be paid to landowners as on the date of notification.
  • Possession or payment suffices to prevent lapse; if one is completed, lapse does not occur.
  • The five-year period for deemed lapse excludes time during interim orders; the proviso to Section 24(2) interacts with the five-year window.

Submissions & Arguments

Contentions of Appellants / Petitioners

Appellants submit that the Constitution Bench in Indore Development Authority v. Manoharlal overruled Pune Municipal Corporation and held that compliance with either taking possession or payment of compensation suffices to prevent lapse under Section 24(2) of the 2013 Act. In the present case, possession of the land was taken on 06.12.2012 and handed over to DDA; compensation not paid to landowners does not per se render the acquisition liable to lapse since possession satisfies the requisite condition. The land is required for a national infrastructure project (Delhi-Saharanpur-Dehradun Highway) under Bharatmala Pariyojana Phase I, giving national importance to the acquisition. Therefore, the High Court’s lapse finding cannot be sustained; compensation should be determined and paid to the rightful owners, with the Land Acquisition Officer implementing disbursement following the 2013 Act framework.

Contentions of Respondents

Respondents contend that the writ petition was decided based on law as it existed at the time of the High Court decision, and cannot be revisited by a subsequent Constitution Bench ruling. They rely on Pune Municipal Corporation v. Misrimal Solanki (2014) 3 SCC 183 to argue that non-payment of compensation yields lapse under Section 24(2) of the 2013 Act, and that the five-year window and deposit provisions are to be construed in that light. They maintain that the High Court correctly held lapse, and that the decision should stand unless and until the earlier legal regime is expressly overruled by the Court.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Pune Municipal Corporation & Anr. v. Misrimal Solanki & Ors.2014) 3 SCC 183OverruledConstitution Bench in Indore Development Authority v. Manoharlal overruled Pune Municipal's approach to Section 24(2) and held compliance with possession or payment can save the acquisition from lapse.
Indore Development Authority v. Manoharlal and Others2020) 8 SCC 129PositiveConstitution Bench decision establishing that satisfying either possession or payment suffices to prevent lapse and guiding interpretation of vesting/possession under the 1894 Act and 2013 Act; followed by this judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,697 words•~13 min read

In The Court Record

LAND AND BUIILDING DEPARTMENT THROUGH SECRETARY & ANR. v. ATTRO DEVI & ORS.

**D.No.23608/2021** # **REPORTABLE** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** # **Civil Appeal No.2749/2023** **(arising out of S.L.P.(Civil) No.7510/2023** **(arising out of S.L.P.(Civil) D.No.23608/2021)** # **LAND AND BUIILDING DEPARTMENT THROUGH SECRETARY & ANR.** **…APPELLANT(S)** ## **VS.** ## **ATTRO DEVI & ORS.** **…RESPONDENT(S)** ## **J U D G M E N T** ## **Rajesh Bindal, J.** 1. Delay condoned. 2. Leave granted. 3. The appellants have challenged the order dated 20.12.2017 passed by the High Court of Delhi. Vide aforesaid order, writ petition filed by the respondents was allowed holding Signature Not Verified Digitally signed byAnita Malhotra that in view of Section 24(2) of the Right to Fair Compensation Date: 2023.04.11 17:43:58 IST Reason: and Transparency in Land Acquisition, Rehabilitation and Page 1 of 14 **D.No.23608/2021** Resettlement Act, 2013 (for short “ **the 2013 Act** ”), the acquisition in respect to the land in dispute, has lapsed. 4. From the facts of the case as are available on record, it is evident that vide notification dated 23.06.1989 issued under Section 4 of the Land Acquisition Act, 1894 large chunk of the land including the land of petitioner comprised in Khasra No.1 Etc/57/1 and Khasra No.1 Etc/58/1, situated in revenue estate of village Ghonda, Chauhan Khadar, New Delhi was sought to be acquired for planned development of Delhi. It was followed by the notification issued under Section 6 dated 20.06.1990. The Award was announced on 19.06.1992. 5. A writ petition was filed in the High Court invoking Section 24(2) of the 2013 Act claiming that the acquisition in question has lapsed as neither possession has been taken nor the compensation therefor has been paid. The appellant’s stand before the High Court was that the possession of the land was taken on 06.12.2012 and handed over to the DDA on the spot. The compensation could not be paid to the recorded land owners as they never came forward to claim the same. Page 2 of 14 **D.No.23608/2021** 6. The High Court relying upon the judgment of this Court in _**Pune Municipal Corporation & Anr. v. Misirimal Solanki & Ors.** (2014) 3 SCC 183_ held that since the compensation was not paid to the landowners, i.e., the respondents herein, the acquisition in question has lapsed. 7. The arguments raised by learned counsel appearing for the appellants are that in view of the Constitution Bench judgment of this Court in _**Indore Development Authority v. Manoharlal and Others**_ (2020) 8 SCC 129 whereby earlier judgment of this Court in _**Pune Municipal Corporation & Anr.’s**_ case (supra) was overruled, the order passed by the High Court is liable to be set aside. It was opined by the Constitution Bench that compliance of either of the two conditions _i.e._ taking over of possession of the land or payment of compensation, is good enough to sustain the acquisition. From the undisputed facts available on record it is evident that in the present case, the possession of land in dispute was taken after the acquisition was complete. Page 3 of 14 **D.No.23608/2021** 8. Additionally, an important fact brought to our attention is that the subject land is required by NHAI for construction of the Delhi­Saharanpur­Dehradun Highway starting from Akshardham Junction to Delhi/UP Border, in the State of Delhi in Phase­I of Bharatmala Pariyojana. Even the contractors have been appointed to execute the project, which may be delayed due to pendency of the present appeal. The subject land is therefore a part of the project which is of national importance. 9. On the other hand, the arguments raised by learned counsel for the respondents are that the writ petition having been decided on the basis of law as existing on the date of decision by the High Court cannot be set aside on the basis of the subsequent judgment of this Court. The High Court had held that compensation having not been paid, as per the interpretation of Section 24(2) of the 2013 Act by this Court in _**Pune Municipal Corporation’s**_ case (supra), the acquisition proceedings lapsed. It is a matter of fact which has been noticed Page 4 of 14 **D.No.23608/2021** in the order passed by the High Court that the possession of the land had already been taken by the authority concerned. 10. Heard learned counsel appearing for the parties and perused the records. 11. The Constitution Bench of this Court in _**Indore Development Authority's**_ case (supra) had opined that satisfaction of either of the conditions namely either taking possession of the acquired land or payment of compensation to the landowners would be sufficient to save the acquisition from being lapsed in terms of Section 24(2) of the 2013 Act. Various questions posed before the Constitution Bench of this Court were also answered. Relevant para­Nos. 362 and 366 are extracted below: _“362. Resultantly, the decision rendered in Pune Municipal Corporation & Anr. (supra) is hereby overruled and all other decisions in which Pune Municipal Corporation (supra) has been followed, are also overruled. … ..._ _366. In view of the aforesaid discussion, we answer the questions as under:_ _366.1. Under the provisions of Section 24(1)(a) in case the award is not made as on 1­1­2014, the_ Page 5 of 14 **D.No.23608/2021** _date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act._ _366.2. In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed._ _366.3. The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse._ ## _**(emphasis supplied)**_ _366.4. The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence_ Page 6 of 14 **D.No.23608/2021** _of non­ deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non­deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non­ deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act._ _366.5. In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non­payment or non­ deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot_ Page 7 of 14 **D.No.23608/2021** _claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act._ _366.6. The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b)._ _366.7. The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2)._ _366.8. The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1­1­2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years._ _366.9. Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land_ Page 8 of 14 **D.No.23608/2021** _acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1­1­2014. It does not revive stale and time­ barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.”_ 12. The issue as to what is meant by "possession of the land by the State after its acquisition" has also been considered by Constitution Bench of Hon'ble Supreme Court in _**Indore Development Authority’s**_ case (supra). It is opined therein that after the acquisition of land and passing of award, the land vests in the State free from all encumbrances. The vesting of land with the State is with possession. Any person retaining the possession thereafter has to be treated trespasser. When large chunk of land is acquired, the State is not supposed to put some person or police force to retain the possession and start cultivating on the land till it is utilized. The Government is also not supposed to start residing or physically occupying the same once process of the acquisition is complete. If after the process of acquisition is Page 9 of 14 **D.No.23608/2021** complete and land vest in the State free from all encumbrances with possession, any person retaining the land or any re­entry made by any person is nothing else but trespass on the State land. Relevant paragraphs 244, 245 and 256 are extracted below: _**"244** . Section 16 of the Act of 1894 provided that possession of land may be taken by the State Government after passing of an award and thereupon land vest free from all encumbrances in the State Government. Similar are the provisions made in the case of urgency in Section 17(1). The word "possession" has been used in the Act of 1894, whereas in Section 24(2) of Act of 2013, the expression "physical possession" is used. It is submitted that drawing of panchnama for taking over the possession is not enough when the actual physical possession remained with the landowner and Section 24(2) requires actual physical possession to be taken, not the possession in any other form. When the State has acquired the land and award has been passed, land vests in the State Government free from all encumbrances. The act of vesting of the land in the State is with possession, any person retaining the possession, thereafter, has to be treated as trespasser and has_ Page 10 of 14 **D.No.23608/2021** ## _no right to possess the land which vests in the State free from all encumbrances._ _**245** . The question which arises whether there is any difference between taking possession under the Act of 1894 and the expression "physical possession" used in Section 24(2). As a matter of fact, what was contemplated under the Act of 1894, by taking the possession meant only physical possession of the land. Taking over the possession under the Act of 2013 always amounted to taking over physical possession of the land. When the State Government acquires land and drawns up a memorandum of taking possession, that amounts to taking the physical possession of the land. On the large chunk of property or otherwise which is acquired, the Government is not supposed to put some other person or the police force in possession to retain it and start cultivating it till the land is used by it for the purpose for which it has been acquired. The Government is not supposed to start residing or to physically occupy it once possession has been taken by drawing the inquest proceedings for obtaining possession thereof. Thereafter, if any further retaining of land or any re­entry is made on the land or someone starts cultivation on the open land or starts residing in the outhouse, etc., is_ Page 11 of 14 **D.No.23608/2021** _deemed to be the trespasser on land which in possession of the State. The possession of trespasser always inures for the benefit of the real owner that is the State Government in the case._ _xxxx_ _**256** . Thus, it is apparent that vesting is with possession and the statute has provided under Sections 16 and 17 of the Act of 1894 that once possession is taken, absolute vesting occurred. It is an indefeasible right and vesting is with possession thereafter. The vesting specified under Section 16, takes place after various steps, such as, notification under Section 4, declaration under Section 6, notice under Section 9, award under Section 11 and then possession. The statutory provision of vesting of property absolutely free from all encumbrances has to be accorded full effect. Not only the possession vests in the State but all other encumbrances are also removed forthwith. The title of the landholder ceases and the state becomes the absolute owner and in possession of the property. Thereafter there is no control of the landowner over the property. He cannot have any animus to take the property and to control it. Even if he has retained the possession or otherwise trespassed upon it after possession has been taken by the State, he is a trespasser and such_ Page 12 of 14 **D.No.23608/2021** _possession of trespasser enures for his benefit and_ _**"** on behalf of the owner_ _**.**_ ## _**(emphasis supplied)**_ 13. It is also a fact to be noticed and taken care of that large chunk of land is acquired for planned development to take care of immediate need and also keep buffer for future requirements. Such portion of land may be lying vacant also. As has been observed in _**Indore Development Authority’s**_ case (supra) by this Court, the State agencies are not supposed to put police force to protect possession of the land taken after process of acquisition is complete. As far as the case in hand is concerned, the land even if was lying vacant, is required now for a project of national importance for construction of the Delhi­ Saharanpur­Dehradun Highway starting from Akshardham Junction to Delhi/UP Border, in the State of Delhi in Phase­I of Bharatmala Pariyojana. 14. It is the undisputed fact on the record, as has been noticed in the impugned order passed by the High Court, the possession of the land was taken over by the Land Acquisition Collector and handed over to Delhi Development Authority. Page 13 of 14 **D.No.23608/2021** Report of possession proceedings dated 06.12.2012 has also been placed on record. Hence, one of the conditions being satisfied, we need not examine any other argument. 15. Keeping in view the aforesaid fact and the law laid down by the Constitution Bench of this Court in _**Indore Development Authority’s**_ case (supra), in our opinion the order passed by the High Court cannot be legally sustained and the same is accordingly set aside. However, the respondents shall be entitled to receive compensation as per their entitlement. The Land Acquisition Officer should also take steps to pay the same to the rightful owner. 16. The appeal is disposed of accordingly. **……………………J.** **[Abhay S. Oka]** **……….……………J. [Rajesh Bindal]** **New Delhi; 11.04.2023.** Page 14 of 14
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.