High CourtDivision BenchAppeal allowed

Lakshmichand v. State of Andhra Pradesh

Case / Petition Number:Civil Appeal No. 1083 H of 1986
Neutral Citation:1987 SCR 112

Case Details & Bench

Court
High Court
Hon'ble Judges
  • R.S. Pathak
  • G.L. Oza
Judgment Date
1986-11-05
Court Decision / Holding
Appeal allowed. The High Court’s judgment is modified: the adjustment based on the final bill relating to the contract covered by the award is maintained, while the adjustment claimed under the other contract is set aside. The decretal amount is to be adjusted as per the first claim, and the second claim cannot be set off against the decretal amount at this stage. Costs to the parties.
Final Disposition
Appeal allowed

Parties to the Case

Appellants / Petitioners

  • Lakshmichand

Respondents

  • State of Andhra Pradesh

Legal Representation & Advocates

Counsels for Petitioners

  • • Dr. Y.S. Chitale
  • • G.N. Narayan
  • • N. Nittar

Counsels for Respondents

  • • T.S. Krishnamurthy Iyer
  • • T.V.S.N. Chari
  • • Ms. V. Grover

Case Synopsis & Summary

Lakshmichand, a contractor, entered into two contracts for road works on the Hyderabad–Vijayawada National Highway with the Government of Andhra Pradesh. While work progressed, he claimed losses due to delays, escalation in rates, and other heads; the Arbitrator awarded Rs 99,00,000 under five heads. The Civil Court did not decree the award, but the Andhra Pradesh High Court later allowed it to the extent of Rs 16,00,000 plus interest. For realization, the contractor filed Execution Petition No. 48 of 1982. The State Government claimed an adjustment (set-off) of Rs 22,91,332 against the decretal amount, consisting of (a) Rs 10,21,800 claimed on the final bill preparation under the first contract, and (b) Rs 12,69,532 claimed under a separate contract for alleged breach. The Executing Court and later the High Court held the first adjustment valid under clause 68 and the second under clause 71, albeit with the latter to await arbitration. The appellant contended that Order 21 Rule 18 CPC does not permit such set-off in execution proceedings. The Supreme Court held that, in some circumstances, set-off can be allowed beyond strictly the terms of Order 21 Rule 18; the first adjustment was valid as a provisional payment subject to the final bill, while the second did not meet the equitable-set-off criteria and could not be invoked against the decretal amount. The appeal was allowed in part and the High Court’s order modified accordingly, with costs.

Provisions of Law Cited

Order 21 Rule 18, CPC 1908Clause 68 of the contractClause 71 of the contract

Legal Doctrines & Maxims

  • Equitable set-off (doctrine)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the State Government is not entitled to a set-off in execution proceedings and that the amount sought to be adjusted comprises (a) a sum claimed by the State on final bill preparation under the first contract and (b) a sum claimed under a separate contract for breach. He argues that Order 21 Rule 18 CPC does not apply to this case; the second claim is not an ascertainable sum and there is no cross-transaction basis to justify equitable set-off. Relying on contractual clauses, he asserts that payment of the decretal amount should not be subordinated to disputed adjustments when the contract remains in progress and final settlement is pending.

Contentions of Respondents

The respondents submit that the court has power to grant an equitable set-off in appropriate cases even if not strictly within Order 21 Rule 18. They contend that clause 68 permits adjustment against the final bill for work under the award, and clause 71 permits retention or deduction from amounts due under another contract. They argue that the first adjustment is justified since it arises from work performed while the contract was ongoing and is subject to final settlement, while the second adjustment is contingent on arbitration and cannot be set off against the decretal amount.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Bhoganadham Seshaiah v. Budhi Veerabhadrayya (died) & Ors.AIR 1972 Andhra Pradesh 134PositiveApproved by the Supreme Court as authority on the power to grant equitable set-off in appropriate circumstances.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Lakshmichand v. State of Andhra Pradesh and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

LAKSHMICHAND & BALCHAND A _v._ -,,-STATE OF ANDHRA PRADESH NOVEMBER 5, 1986 B [R.S. PATHAK AND G.L. OZA, JJ.] _Civil Procedure_ _Code,_ _1908-0rder 21,_ _Rule_ _18-Power of the_ _y_ _Court to_ _allow set off-When is_ _a claim founded on doctrine_ _of equit-_ _able set off._ I ##### c The appellant...:ontractor entered into two agreements with the -~ ### respondent State for carrying out certain road repairing works. Clause " _,,.. 68 of the agreement provided for preparation or the final bill of the contractor after taking into account amounts received by him earlier, while clause 71 permitted the State to retain or deduct money due under the contract from an amount due to the contractor under any other D contract. While the work was in progress the contractor made certain claims in respect of loss suffered on account of delay, escalation of rates and other heads. The arbitrato1· held the contractor entitled to Rs.99 lacs. The civil court refused _to_ pass a decree in terms of the award. The High Court on appeal allowed the claim to the extent of Rs.16 lacs together with interest. The co111tractor claimed recovery of decretal E amount with interest in terms of the award and cost of execution proceedings. The respondent State contested the claim contending that a sum of Rs.22 lacs was recoverable from the appellant and claimed adjustment against the amount due under the decree. The Executing Court held the respondent State entitled to set off. ##### .... F In the revision petition before the High Court it was contended for the appellant that the respondent State was not entitled to set off in execution proceedings, and that the sum of which adjustment was sought ~. consisted of (a) an amount claimed by respondent State as due to it upon preparation of the final bill in respect of the contracts covered by the ..\ award, and (b) an amount claimed by the respondent State under a G separate contract on the ground that the appellant bad committed a breach of that contract. The High Court having regard to cl. 68 of the agreement found the respondent State entitled to set off so far as the first claim was concerned. It justified the second claim also by reference to cl. 71 of the contract hut held that adjustment claimed could not be ..,.. made against the decretal amount hut must await determination upon H the arbitration. 108 LAKSHMICHAND _v._ STATE OF ANDHRA PRADESH 109 -,· In this appeal by special leave it was contended that Order 21, A 1 Rule 18 of the Code of Civil Procedure, under which a set off can he claimed, does not apply in terms to the present case. Allowing the appeal in part, the Court, HELD: I. The Court has the power to allow a set off in certain B I circumstances even in cases which do not strictly fall within the terms of Order 21, Rule IS of the Code of Civil Procedure. [Il2B] ### . . I... . _Bhoganadham Seshaiah_ v. _Budhi Veerabhadrayya (died)_ _&_ _Ors.,_ _r'"_ -AIR 1972 Andhra Pradesh 134, approved. 2. The respondent State's claim to adjustment of the amount due to it upon the preparation of the final bill is covered by cl. 68 of the contract. What was awarded to the contractor under the decree was an amount relating to a part only of the work entrusted to him. The con· tract was still in the process of execution. Any amount claimed by him for such work was subject to a final settlement of account on the preparation of the final bill. The right to payment depended on the terms of the contract. Any payment made while the contract was still being workecl ont was in the natnre of a provisional payment. It was always sobject to adjnstment against amount,s found doe on preparation of the final bill. Such adjustinent was implied in the very terms or the COD· tract. The High Court was, therefore, right in holding that the amount claimed by the State Government on this count was entitled to be set off against the decretal amount claimed by the contractor. [1!2C El ### c D E 3.1 The claim to adjustment of the amount claimed on breach of ·, another contract is founded in the doctrine of equitable set off but ##### ['- there is no e>idence on record to bring the case within the operation of the doctrine. It is not a case where cross demands rise out of the same _,..)._ transaction, or the demands are so connected in their natnre and circumstances that they can be looked upon as part of one transaction. [I l 2F GI 3.2 The benefit of cl. 71 of the contract can be claimed only if the amount sought to. he retained is an ascertained sum, an amount which G · can be readily adjusted against the amount payable under the other contract. In the instant case, the amount sought to be adjusted had yet to be determined. as a liability against the contractor. The decision of the High CIHlrt eannot, therefore, be sustained. [1!2GH, l !3A) CIVIL APPELLATE JURISDICTION: Civil Appeal No. ~083 H of 1986 110 SUPREME COURT REPORTS (1987] I S.C.R. A From the judgment and order dated 13.4.1984 of the Andhra Pradesh High Court in C.R.P. No. 3072 of 1983. Dr. Y.S. Chitale, G.N. Narayan and N. Nittarfor the Appellant. T.S. Krishnamurthy Iyer, T.V.S.N. Chari and Ms. V. Grover for B the Respondent. _y_ The Order of the Court was delivered by **PATHAK,** **J.** This appeal is directed against the judgment and order of the High Court of Andhra Pradesh disposing of a revision,,... ###### ~#### c [petition filed ][by ][the Appellant ][in ][execution prbceedings. ] The Appellant is a contractor, who entered info two agreements _:... with the Government of the State of Andhra Pradesh for providing B. T. Macadam wearing coat and seal coat along two stretches of the Hyderabad-Vijayawada Na.tional Highway. While the work was in D progress, the contractor made certain claims in respect of the loss suffered on account of delay, escalation of rates and other heads. The claims were referred to arbitration. On September 4, 1979 the Arbitrator held the contractor entitled to a sum of Rs.99,00,000 under five heads of claim. The contractor applied to the Civil Court for making the award a rule of the Court while the State Government E prayed for setting aside the entire award. The Civil Court set aside the award and refused to pass a decree in terms of the award. 'The contractor appealed to the High Court, and on April 19, 1982 the High Court allowed the appeal to the extent of one of the claims only, the ###### .... claim being for loss of profit in the sum of Rs. 16,00,000 together with ## F claim. interest. The appeal was dismissed in respect of the other heads of /" I # For the realisation of the amount due under the decree the con- l. tractor filed Execution Petition No.48 of 1982 before the V Additional Judge, City Civil Court, Hyderabad claiming recovery of Rs.16,00,000 towards the decretal amount, Rs.7,80,000 towards interest in terms of G the award up to the date of the execution petition and Rs.8,691 to wards costs of the Execution Petition. The State Government filed objections, contending inter alia that a sum of Rs.22,91,332 was recoverable by it from the contractor and claimed adjustment against the amount due to the contractor under the said decree. It urged that after H [adjusting the amount due to the State Government the balance pay-] able to the contractor would stand reduced to Rs.76,667. This sum J. LAKSHMICHAND _v._ STATE OF ANDHRA PRADESH [PATHAK, J.Jl l l together with the other deposits of the contractor with the Government and refundable to him, viz. Rs.3,92,236 was deposited in the Executing Court. The contractor withdrew the amount without prejudice to his rights to contest the adjustment. The Executing Court held that the State Government was entitled to set_ off-the amounts claimed by it, and accordingly adjourned· the Execution Petition for further proceedings. The contractor filed a revision petition before the High Court and contended that the State Government was not entitled to claim I.. _adjustment in execution proceedings. It was pointed out that the sum ##### r of Rs.22,91,332 of which adjustment was sought by the State Govern ment against the amount for which the contractor had taken out execution, consisted of (a) an amount of Rs.10,21,800 claimed by the State _--f-_ Government as due to it upon the preparation of the final bill in respect of the contracts covered by the award and (b) an amount of Rs. 12,69,532 claimed by the State Government under a separate contract on the ground that the contractor had committed a breach of that contract. The contractor disputed both claims. He contended that the final bill in respect of the earlier contract had been prepared in his · absence and that he challenged the inclusion of several items in that bill. In regard to the latter amount he urged that he was not guilty of· any breach of contract. A B #### c D E F G H The High Court has found that so far as the first claim to adjustment was concerned the State Government was justified in making·it because the arbitr_ation was effected while the work was still in progress and the contract was in the process of execution by the contractor, and having regard to clause 68 of the agreement final payment had to be made to the contractor after taking into account the amount which had been received by him earlier. The seConct claim to adjustment was made by the State Government under another contract, and the High Court justified that claim hy reference to clause 71 of that contract, which permitted the Government to retain or deduct money due under the contract from an amount due to the contractor under any other contract. However, it held that the adjustments claimed by the State Government could not be made against tl>e decretal amount but must . await determination upon due arbitration. Learned counsel. for the Appellant contends before us that the State Government is not entitled to a set off at all because, he says, a set off can be claimed only under Order 21 Rule 18 of the Code of Civil Procedure and that provision does not apply in terms to . the present 112 SUPREME COURT REPORTS [1987] l S.C.R. A case. Learned counsel for the respondent urges, on the other hand, that the power of the Court extends to granting an equitable set off in appropriate cases, and the High Court was therefore justified in making the order which it did. We have no doubt that in certain cases the Court has the power to B allow a set off even in cases which do not strictly fall within the terms of Order 21 Rule 18 of the Code. A Full Bench of the Andhra Pradesh High Court has discussed the matter in _Bhoganadham Seshaiah_ v. _Budhi Veerabhadrayya (died) and Others,_ AIR [!972) Andhra Pradesh !34 and has examined at some length the circumstances in which such I ##### set off may be granted. The facts before us, however, call for a some- - .A, C what different consideration. So far as the first claim to adjustment is concerned, the matter is covered by clause 68 of the contract. What was awarded to the contractor under the decree was an amount relating to a part only of the work entrusted to him. The contract was still in the process of execution. Any amount claimed by him for such work was subject to a final settlement of account on the preparation of the _D_ final bill. The right to payment depended on the terms of the contract. E Any payment made while the contract was still being worked out was in the nature of a provisional payment. It was always subject to adjustment against amounts found due against the contractor on preparation of the final bill. Such adjustment was implied in the very terms of the contract. Therefore, in regard to the adjustment claimed by the State Government on the first count the High Court is right, in our opinion •. in holding that the amount claimed by the State Government, as determined on arbitration, was entitled to a set off against the decretal amount claimed by the contractor, and that payment of the decretal amount was to be subject to such adjustment. F In regard to the claim to adjustment on the second count the __,~ position is more controversial. The claim is founded in the doLtrine of equitable set off, but we do not find evidence before us to bring the case within the operation of the doctrine. It is not a case where cross demands rise out of the same transaction or the demands are so connected in their nature and circumstances that they can be looked upon G as part of one transaction. Nor can assistance be derived from clause 71. The benefit of that provision can be claimed only if the amount sought to be retained is an ascertained sum, an amount which can be readily adjusted against the amount payable under the other contract. Here, the amount sought to be adjusted has yet to be determined as a liability against the contractor. It has been disputed by the appellant. H Accordingly, clause 71 cannot be invoked. In the result, the decision LAKSHMICHAND _v._ STATE OF ANDHRA PRADESH (PATHAK. J.( l l3 of ine High Court in respect of the adjustment of Rs.12,69;532 cannot A be sustained. In the circumstances, the appeal is allowed in part, the judgment and order of the High Couc:t is modified in so far that while the adjustment claimed by the State Government on the basis of the final bill relating to the contract covered by the award is maintained, the direc_·1_ ' tion in respect of the. adjustment of 1he claim made under the other contract is 'set aside. The parties will bear their oWTYcosts . . P.S.S. r~ ### _-(_ Appeal allowed. B ##### c