High CourtDivision BenchAppeals dismissed; directions issued for paymen...

Lafarge Aggregates & Concrete India P. Ltd v. Sukarsh Azad

Case / Petition Number:Cr. A. No. 1941 of 2013; Cr. A. No. 1942 of 2013
Neutral Citation:[2013] 11 S.C.R 74

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Gyan Sudha Misra
  • Pinaki Chandrasekhar Ghose
Judgment Date
2013-09-10
Court Decision / Holding
Appeals dismissed. The Court dismissed the appeal challenging the recall of the ex parte order on merit, and dismissed the other appeal on delay as well as on merits, but directed the respondents to make a lump-sum payment of Rs. 5 lakhs (including interest and compensation) to the appellant towards the cheque for which stop payment instructions were issued. If the appellant did not accept the offer, they would still be barred from pursuing the complaint. The decision reflects a balance between upholding the NI Act’s objective of ensuring payment and tolerating some flexibility in equity and justice.
Final Disposition
Appeals dismissed; directions issued for payment of Rs. 5 lakhs towards the stopped-payment cheque; one appeal dismissed on merit and the other on delay and merits subject to payment directive.

Parties to the Case

Appellants / Petitioners

  • Lafarge Aggregates & Concrete India P. Ltd

Respondents

  • Sukarsh Azad
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Ajay Bhargava
  • • Vanita Bhargava
  • • Nitin Mishra
  • • Abhijeet Swaroop
  • • Khaitan & Co.

Counsels for Respondents

  • • Sudhir Walia
  • • Abhishek Atrey

Case Synopsis & Summary

This case concerns a criminal appeal under Section 138 of the Negotiable Instruments Act, 1881 arising from a complaint for dishonour of a cheque. Lafarge Aggregates & Concrete India Pvt. Ltd. (the appellant) challenged a Punjab & Haryana High Court order that quashed the criminal complaint and all consequential proceedings against Sukarsh Azad and another, directors of M/s. Ria Constructions Ltd., after the makers issued a cheque of Rs. 2,50,000 that was dishonoured due to a stop-payment instruction. The appellant sought recall of the ex parte order quashing the complaint and the consequent proceedings under CrPC 482. The High Court had allowed the petition, but the recall application was dismissed for non-appearance, and the appellant pursued Special Leave Petitions (SLPs) in this Court. The Supreme Court held that the appeal challenging the recall of the ex parte order lacked merit due to failure to show sufficient cause for non-appearance, yet, in the interests of equity, fairness, and justice, directed the respondents to pay the appellant Rs. 5 lakhs (to be treated as a lump-sum amount including interest and compensation) towards the stopped-payment cheque. The Court also noted the object of the NI Act is to preserve the credibility of negotiable instruments and to compel honouring of the instrument, while acknowledging the consequences of stop-payment and the role of the Director in the given context.

Provisions of Law Cited

Negotiable Instruments Act, 1881 s. 138Criminal Procedure Code, 1973 s. 482Civil Procedure Code, 1908 Order IX Rule 13Sections 138 to 142 of the Negotiable Instruments Act

Legal Doctrines & Maxims

  • Equity, justice and fair play in dispensing justice
  • Primary object of the Negotiable Instruments Act is not merely penal but to maintain the efficacy and value of negotiable instruments by compelling honour of the instrument
  • Object of Sections 138 to 142 NI Act is to inculcate faith in the efficacy of banking operations and credibility in transacting business of negotiable instruments
  • Statutory presumption of dishonest intention upon dishonour of cheque (where stop payment is involved) and the consequent liability of the drawer

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that the recall of the ex parte quashing order should be entertained since the High Court's order was ex parte and the applicant was not afforded a fair opportunity. It was contended that the recalled order should be restored and the appellant should be able to pursue the complaint; reliance was placed on the test laid down in NK Wahi v. Shekhar Singh to determine sufficiency of cause for non-appearance. It was argued that payment offered later by the respondents did not automatically discharge the grievance, and that the primary purpose of the NI Act is to ensure the instrument is honoured and to maintain faith in banking transactions. The appellant asserted a legitimate right to pursue the complaint and sought to recover the cheque amount along with interest or compensation.

Contentions of Respondents

The respondents contended that the recall application should be rejected as the recall of an ex parte order was not justified; the averments did not meet the test in NK Wahi and the High Court’s discretionary order was proper. They argued that the mere offer to pay the cheque amount later could not automatically nullify the complaint, and the statutory framework intends to punish dishonour due to stop-payment and ensure the drawer’s liability. They urged that the case be disposed of in a manner that preserves the integrity of the NI Act while addressing the equity concerns.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
N.K. Wahi v. Shekhar Singh and C. Others(2007) 9 SCC 481PositiveThe Court refers to the test laid down in NK Wahi to determine whether there was sufficient cause for recall of an ex parte order and applies it to assess the recall application, ultimately finding that the recall was not justified due to lack of sufficient cause.
Rajneesh Aggarwal v. Amit J. Bhalla(2001) 1 SCC 631DistinguishedAppellant’s reliance on this decision was not accepted; the Court did not follow the reasoning of Rajneesh Aggarwal in the present context, distinguishing it from the facts or holding.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Lafarge Aggregates & Concrete India P. Ltd v. Sukarsh Azad and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## [2013] 11 S.C.R 74 A LAFARGE AGGREGATES & CONCRETE INDIA P. LTD _v._ SUKARSH AZAD & ANR (Criminal Appeal No. 1941 of 2013) B SEPTEMBER 10, 2013 ## [GYAN SUDHA MISRA AND PINAKI CHANDRA GHOSE, JJ.] - - _Negotiable Instruments Act, 1881 s. 138 Code of_ - C _Civil Procedure, 1908- Order IX r.13 Dishonour of cheque_ - _of amount Rs.2,50,0001- On the ground of 'stop payment'_ - _instruction Complaint uls. 138 of Negotiable Instruments Act_ - - _Petition u/s. 482 High Court quashed the complaint and_ - _the consequential proceedings, by ex-parte order_ D _Application for recall of the ex-parte order dismissed_ - _Present appeals against the order dismissing the application for recalling the ex-parte order and also against the ex-parte_ - _order Held: Appeal against the order in application for recalling the ex-parte order is devoid of merit as the applicant_ E _failed to offer sufficient cause for his non-appearance on the_ - _date when the complaint was quashed The appeal against the ex-parte order is liable to be dismissed on the ground of delay as well as on merit_ - _However, in the interest of equity, justice and fair play, direction to make payment to the_ F _complainant for_ a _sum of Rs.5 lakhs, which would be treated as an overall amount including interest and compensation towards the cheque for which 'stop payment 'instruction was issued._ CRIMINAL APPELLATE JURISDICTION: Criminal Appeal G No.1941 of 2013. From the Judgment & Order dated 09.11.2010 of the High Court of Punjab & Haryana at Chandigarh in CRM No. 55019 of 2010 in Crl. Misc. No. 20203 of 2010. H 74 # LAFARGE AGGREGATES & CONCRETE INDIA P. LTD _v._ SUKARSH AZAD 75 ## WITH A Crl. A. No. 1942 of 2013. Ajay Bhargava, Vanita Bhargava, Nitin Mishra, Abhijeet Swaroop, Khaitan & Co. for the Appellant. B Sudhir Walia, Abhishek Atrey for the Respondents. The following Order of the Court was delivered by ## **ORDER** c 1. Leave granted. 2. The appellant herein has challenged the order passed by the High Court whereby it t.ias allowed the petition filed by the respondents herein, who are the Directors in a company D known as M/s. Ria Constructions Ltd. and was pleased to quash the complaint lodged by the appellant as also all consequential proceedings pending before the Magistrate in regard to the complaint lodged by the appellant for an offence under Section 138 of the Negotiable Instruments Act, 1881. E 3. Admittedly, the accused no. 2 in the complaint had issued the cheque in favour of the appellant for a sum of Rs.2,50,000/-, which was dishonoured as there was instruction of 'stop payment' by the Managing Director. This led to the lodgment of a complaint at the instance of the petitioner in which proceedings started. F 4. At this stage, the respondents herein filed a petition under Section 482 of the Code of Criminal Procedure, 1973 {"Cr.P.C." for short) praying for quashing of the complaint and all consequential proceeding wherein the respondents had offered to tender the cheque amount of Rs.2,50,000/- to the appellant who had lodged the complaint alleging that the stop payment instructions by the respondents was illegal which made the offence triable in a summary procedure before the Magistrate. As already stated, the respondents offered to pay G H ## 76 SUPREME COURT REPORTS [2013] 11 S.C.R. A the cheque amount of Rs.2,50,000/- which had been dishonoured due to instructions of stop payment. 5. The High Court allowed the petition filed by the respondents herein for quashing of the proceeding but the said 8[order was passed ex-parte. The appellant, therefore, filed ][an ] application for recall of the said order but the High Court dismissed the application for recall on the ground. that the averments in the complaint did not meet the test laid .down by this Court in the matter of _N.K. Wahi_ Vs. _Shekhar Singh and_ C _others,_ 2007 (9) SCC 481. It is this order which' is under challenge in this special leave petition at the instance of the appellant-complainant. 6. We have heard counsel for the appellant as also the respondents and taking an overall view of the matter, we are D · of the opinion that this appeal is not fit to be entertained against rejection of the application for recall of the order by which the proceedings against the respondents herein had been quashed by the High Court. Nevertheless, we are conscious of the fact that the appellant should not be deprived of the amount for which E the respondents had stopped payment which led to the lodgment of the complaint. We; therefore, suggested to the respondents that they should honour the cheque which had been issued by them by making the payment along with the interest, which would be in the nature of compensation for stop F payment instructions at their instance and that amount by way of lump sum amount including interest and compensation would be around Rs.5 lakhs. 7. The respondents have agreed to pay the said amount but the appellant has refused to accept the payment and G insisted that the appeal against rejection of the recall application should be allowed by this Court. Counsel for the appellant submitted that merely because the accused has offered to make the payment at a later stage, the same cannot compel the complainant-appellant to accept it and the H complainant-appellant would be justified in pursuing the # LAFARGE AGGREGATES & CONCRETE INDIA P. 77 LTD _v._ SUKARSH AZAD complaint which was lodged under the Negotiable Instruments A Act, 1881. In support of his submission, counsel for the . Appellant also relied on a citation of _Rajneesh Aggafllfal Vs._ · _Amit J. Bhalla_ (2001) 1 SCC 631. > 8. However, we do not feel persuaded Jo accept this B submission as the appellant has to apprise himself that the > primary object and reason of the Negotiable Instruments Act, 1881, is not merely penal in nature but is ·to- maintain the efficiency and value of a negotiable instrument-by making the accused honour the negotiable instrument and paying the C amount for which the instrument had been executed. > 9. The object of bringing Sections 138 to 142 of the Negotiable Instruments Act on statute appears to be to inculcate faith in the efficacy of banking operations and > credibility in transacting business of negotiable instruments. D Despite several remedy, Section 138 of the Act i~ intended to prevent dishonesty on the part of the drawer of negotiable instrument to draw a cheque without sufficient funds in his account maintained by him in a bank and induces the payee or holder in due course to act upon it. Therefore, once a cheque E is drawn by a person of an account maintained by him for payment of any amount or discharge of liability or debt or is returned by a bank with endorsement like (I) refer to drawer (ii) exceeds arrangements and (iii) instruction for stop payment and like other usual endorsement, it amounts to dishonour within F > the meaning of Section 138 of the Act. Therefore, even after issuance of notice if the payee or holder does not make the payment within the stipulated period, the statutory presumption would be of dishonest intention exposing ·to criminal liability. 10. But in the instant case, the negotiable instrument which G admittedly is a cheque was issued by respondent no. 2 who is the managing director and the contesting respondents herein against whom the proceedings have been quashed are not the director of the company in a statutory capacity and, therefore, the payments towards cheque in any case could not have been H 78 SUPREME COURT REPORTS [2013) 11 S.C.R. - A made by them and it was respondent no. 2 who was liable to honour the cheque. Nevertheless, the respondents offered to make the payment to the appellant/complainant, yet the appellant refused to accept the payment and pursued the complaint which was quashed by the High Court on which date - B the appellant had failed to appear without sufficient cause. Thereafter, if the High Court refused to recall that order, we do not consider that there were sufficient grounds necessarily to recall the order quashing the complaint. 11. However, in the interest of equity, justice and fairplay, C we deem it appropriate to direct the respondents to make the payment to the appellant by issuing a demand draft in their favour for a sum of Rs.5 lakhs, which would be treated as an overall amount including interest and compensation towards the cheque for which stop payment instructions had been issued. D If the same is not acceptable to the appellant, it is 'their choice but that would not allow them to prosecute the respondents herein in pursuance to the complaint which they have lodged implicating these two respondents. E 12. Besides this, the appellant also ought to take note of the fact that these appeals are not directed against the order by which the complaint had been quashed insofar as these two respondents are concerned but it is directed against the order of the High Court by which it refused to recall the order by which F the complaint had been quashed. The appellant had failed to offer any sufficient cause for their non-appearance on the date when the complaint had been quashed and if we were to be driven to merely taking a technical view of the matter, these appeals could have been rejected even on the.ground of nonG sufficiency of material furnished by the appellant in the High Court against refusal to recall the order in which case the petitioner cannot realise even the amount towards the cheque issued in their favour. But considering the fact that the appellant would be deprived of their due amount of Rs.2,50,000/-, we delved into the factual details and considered just and H LAFARGE AGGREGATES & CONCRETE INDIA P. LTD _v._ SUKARSH AZAD appropriate to direct the respondents to make the payment for A the sake of substantial justice to the complainant-appellant as also in view of the analogous appeal, arising out of SLP{Crl)No. 1145/ 2012 directed against the order dated 10th September, 2010 passed in Crl.Misc.No.20203 of 2010 whereby the High Court had allowed the petition filed by the B respondents herein under Section 482 of the Code of Criminal Procedure, 1973 and was pleased to quash the proceedings against them. It was in this context that we thought it appropriate to direct the respondents to make the payment towards the cheque in which stop payment instructions had been issued. c Besides this, the appeal is time barred by 359 days for which also we see no justification. On the one hand, the appellant has sought to impress upon this Court to take a technical view of the matter by urging that the respondents had not made the payment during the 15 days notice period, even though that had D been offered at a later stage, but ignoring his own conduct he expects this Court to condone the huge delay of 359 days in filing the appeal, which is fit to be rejected outright. 13. Hence, appeal arising out SLP{Crl) No. 1327 of 2011 is dismissed on merit and appeal arising out of SLP{Crl) No. E 1145 of 2012 is dismissed on the ground of delay as also on merits subject to the direction of payment to the appellant by the respondents. K.K.T. Appeals dismissed.