Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking

Case / Petition Number:
Civil Appeal No. 2903 of 2023

Case Synopsis & Summary

This Supreme Court Civil Appeal arises from a Bombay High Court Division Bench order under Section 37 of the Arbitration and Conciliation Act, 1996, challenging the Arbitral Tribunal’s award that rejected the contractor’s 3 disputes (Disputes III and IV, in addition to Dispute I). The contract pertained to the construction of a bridge on the Katra Laole section of the Udhampur-Srinagar-Baramulla rail link, executed on 24.11.2004. The respondent claimed reimbursement for Entry Tax and Toll Tax arising during execution; the Arbitral Tribunal rejected these, interpreting contractual clauses 5.1.2, 7.1.1, 7.1.2 and 11.7, and holding that price variation mechanisms governed any tax-related reimbursements, not per-item claims. The Single Judge of the High Court affirmed the Arbitral Tribunal’s view under Section 34. The Division Bench partially allowed the appeal by reinterpreting the contract to include indirect taxes like Entry Tax and Toll Tax under Clause 5.1.2, effectively rewriting the contract. The Supreme Court held that Section 37 review is limited and cannot substitute the Arbitral Tribunal’s interpretation with a view that renders clauses otiose, and found the Tribunal’s reading plausible and harmonious. It restored the Single Judge’s award and set aside the Division Bench’s judgment, with no order as to costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Dhananjaya Y. Chandrachud
  • Pamidighantam Sri Narasimha
  • J. B. Pardiwala
Judgment Date
2023-08-17
Court Decision / Holding
Civil Appeal allowed; judgment of the Division Bench set aside; Single Judge’s order in Arbitration Petition No. 546 of 2015 dated 17.01.2019 restored; No order as to costs.
Final Disposition
Appeal allowed; Division Bench judgment set aside; Award of the Arbitral Tribunal and Single Judge’s order restored; No order as to costs for the appeal

Parties to the Case

Appellants / Petitioners

  • Konkan Railway Corporation Limited

Respondents

  • Chenab Bridge Project Undertaking

Legal Representation & Advocates

Counsels for Petitioners

  • • Shyam Divan
  • • Amlaan Kumar
  • • Musharaf Shaikh
  • • Rukhmini Bobde
  • • Soumya Priyadarshinee
  • • Ankit Ambasta
  • • Amit Kumar Shrivastava
  • • Vishal Prasad (AOR)

Counsels for Respondents

  • • Darius Khambata
  • • Aveak Ganguly
  • • Manu Seshadri
  • • Pallavi Anand
  • • Abhijit Lal
  • • Soumya
  • • Mithu Jain (AOR)

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 (Sections 34, 37)Section 5 (Extent of judicial intervention)

Legal Doctrines & Maxims

  • ejusdem generis
  • harmonious construction / interpretation giving effect to all clauses
  • perversity test for arbitral awards
  • Public Policy of India under Section 34(2) of the Arbitration Act

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contend that the Division Bench exceeded its jurisdiction under Section 37 by re-writing the contract and substituting its own view for the Arbitral Tribunal’s. They submit that Clause 5.1.2 covers taxes chargeable on the contractor’s bills and that 11.7 makes clear that BoQ rates include all taxes; price variation clauses 7.1.1 and 7.1.2 do not permit per-item tax reimbursements and only allow variation as per the price variation formula. They argue that Entry Tax and Toll Tax are not reimbursable under Clause 5.1.2 and that the Arbitral Tribunal rightly held so, with Section 34 guidance. They rely on standard arbitration-jurisdiction authorities (e.g., UHL Power, Dyna Technologies) to show limited review. Respondents":"The respondents submit that Clauses 5.1.2 and 11.7 operate in tandem to enable reimbursement for taxes that are chargeable and increase during execution, and that Division Bench correctly considered the contract’s text to ensure harmonious construction. They argue that price variation provisions do not cover per-item tax increases absent Clause 5.1.2, and that the High Court’s view aligns with contract interpretation principles and precedents (Radha Sundar Dutta, South East Asia Marine Engg., Patel Engineering). They contend the Arbitral Tribunal rewrote the contract and that Section 37 permits such correction in appropriate circumstances."},

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
UHL Power Company Ltd v. State of Himachal Pradesh2022 SCC (Civ) 401PositiveCited by the appellants and relied upon to discuss the scope of Section 37 jurisdiction being akin to Section 34.
South East Asia Marine Engineering and Constructions Limited v Oil India Limited(2020) 5 SCC 164PositiveCited for context on when an award can be interfered with under 37; Division Bench relied on it for justification in similar circumstances.
Radha Sundar Dutta v Mohd Jahadur Rahim & OrsAIR 1959 SC 24Partly Overruled / LimitedCited regarding the principle of preferring an interpretation that gives voice to all clauses; the Court limited applicability in the present Section 37 context.
Dyna Technologies Pvt Ltd v Crompton Greaves Limited(2019) 20 SCC 1PositiveCited to illustrate the constraints on Section 34 review and the standard of perversity.
Ssangyong Engineering & Construction Company Ltd v National Highways Authority of India(2019) 15 SCC 131PositiveCited to discuss perverse or non-perverse interpretations and the need for a contract-wide view.
Parsa Kente Collieries Ltd v Rajasthan Rajya Vidyut Utpadan Nigam Ltd(2019) 7 SCC 236PositiveCited for principles affecting contractual interpretation in arbitration.”},{
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,764 words•~27 min read

In The Court Record

Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking

**REPORTABLE** 2023INSC742 **==> picture [71 x 72] intentionally omitted <==** ## IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 2903 OF 2023 (Arising out of S.L.P. (C) No. 5640 of 2023) KONKAN RAILWAY CORPORATION LIMITED ...APPELLANT(S) VERSUS CHENAB BRIDGE PROJECT UNDERTAKING …RESPONDENT(S) ## **J U D G M E N T** ## **PAMIDIGHANTAM SRI NARASIMHA, J.** 1. This appeal arises out of the decision of the Division Bench of the High Court of Bombay under Section 37 of the Arbitration and Conciliation Act 1996,[1] by which the concurrent findings of the Arbitral Tribunal and that of the Single Judge of the High Court under Section 34 of the Act rejecting all claims were set aside and certain claims were allowed. This appeal by Konkan Railway Corporation Limited challenges the legality of the order passed by the Division Bench of the High Court while exercising jurisdiction under Section 37 of the > Signature Not Verified Act. Digitally signed by Deepak Singh Date: 2023.08.18 17:18:29 IST Reason: > 1 Hereinafter ‘the Act’. 1 2. The short facts relevant for the purpose of this appeal are as follows: The Respondent’s tender for construction of a bridge at KM 50/800, on the KatraLaole section of Udhampur-Srinagar-Baramulla rail link, said to be the highest railway bridge in the world, was accepted by the Appellant, leading to the execution of the contract on 24.11.2004. 3. While the contract was in execution, disputes arose between the parties and through an agreement dated 28.02.2012, a Standing Arbitral Tribunal was constituted for resolution of disputes. The respondent raised 35 claims which were clubbed and classified as twelve disputes. The present proceedings arise out of the decision of the Arbitral Tribunal deciding three disputes, being Dispute I (relating to Claim 9), Dispute III (relating to Claims 12, 22 and 28), and Dispute IV (relating to Claims 13, 23 and 29). 4. The Arbitral Tribunal by its award dated 15.11.2014 considered the three disputes and rejected all the claims. The Respondent challenged the award under Section 34 of the Act. The Single Judge of the High Court confirmed the Award and proceeded to dismiss the challenge under Section 34 of the Act. The decision of the Single Judge of the High Court was appealed by the Respondent under Section 37 of the Act, and the Division Bench of the High Court, by the order impugned herein, partly allowed the appeal in the following manner. The Division Bench, while dismissing the appeal with respect to Dispute I, allowed the appeal with respect to the remaining two disputes (Disputes III and IV), and 2 thereby set aside the concurrent findings as regards these disputes. As there is no controversy with respect to Dispute I, we are called upon to examine the legality of the order with respect to Disputes III and IV. 5. The facts relevant for Dispute III are as follows: The contract in favour of the Respondent was entered into on 24.11.2004. At that time the Notification of the Government of Jammu and Kashmir dated 19.12.2003 exempted _Entry Tax_ on earth-moving instruments. However, during the execution of the contract, on 25.01.2008, the Government of Jammu and Kashmir withdrew the exemption notification. Consequently, the Respondent raised claims for reimbursement of Rs. 1,32,29,771/- incurred on account of payment of Entry Tax. 6. In so far as Dispute IV is concerned, it relates to reimbursement of _Toll Tax_ on machinery and materials. As per the extant policy in Jammu and Kashmir, the _Toll Tax_ as applicable on the date of the submission of tender, that is 31.05.2004, was Rs. 400/- per MT. However, through four subsequent notifications issued under Jammu and Kashmir Levy of Toll Tax Act, 1998, the taxes were progressively increased to Rs. 650/- per MT. Consequently, the Respondent raised a claim of Rs. 5,23,279/-, incurred on account of increase in toll tax during the subsistence of the contract. 7. Claims under Dispute III as well as Dispute IV were to be considered in terms of the relevant clauses of the contract, which are Clauses 5.1.2, 7.1.1, 7.1.2, and 11.7. These clauses are extracted hereinbelow for ready reference. Relevant 3 part of Clause 5 of Chapter 5, titled ‘Sales Tax, Turn Over Tax/Local Tax, Duties etc’, is as under: ## _**“Clause 5.1 Sales Tax/Turn Over Tax/Local Tax, Duties Etc.**_ _..._ _**Clause 5.1.2** Sales Tax including turn over tax on works contract, octroi, royalty, toll tax, Duties/Levies as well as services and any other tax levied by central govt., state govt. or local bodies, as applicable 15 days prior to the date of opening of tender shall be considered to be included in the percentage rates quoted by tenderer/s in the Schedule of Items, Rates & Quantities. In case of any increase/decrease in the taxes during the period from 15 days prior to the date of opening of tender to the completion of the work, the net increase/decrease for the balance portion of the work shall be borne/recovered by the Corporation._ _The prevailing rate of Works Contract Tax (WCT) in J & K states to be deducted at source is 4.2% for the registered firms with state taxation department from firms not having the registration, the rate is 8.2%._ _**Clause 5.1.3** Corporation shall deduct the sales tax/Turn Over Tax or any other tax from the Contractor’s bill at the rate as applicable as per rules framed by concerned Govt./Local bodies from time to time and remit it to concerned department and shall issue a certificate regarding Tax/levies so deducted on demand by the contractor.”_ 7.1. Clauses 7.1.1 and 7.1.2 from Chapter 7, titled ‘Price Variation’, are as under: _“_ _**Clause 7.1.1** The rates quoted by tenderer and accepted by the Corporation shall hold good till the completion of the work and no additional, individual claim shall be admissible on account of fluctuation in market rates, increase in taxes/any other levies/tolls etc. except the payment/recovery for overall market situation shall be made as per price variation clause given below._ 4 _**Clause 7.1.2** No cognizance shall be given for any sort of fluctuations in taxes and other market conditions etc. for any individual item for the purpose of making adjustments in payments. The contract shall, however, be governed by the general price variation clause as under.”_ ## 7.2. Clause 11.7, in Chapter 11, titled ‘Schedule of Items, Rates & Quantities - Bill of Quantities’, is as follows: _“_ _**Clause 11.7** The rates and prices tendered in the priced Bill of Quantities, shall except in so far as it is otherwise provided under the contract, include all construction plant, labour, supervision, materials, all temporary works, false works, all leads and lifts, erection, specified finishes, maintenance, establishment and overhead charges, insurance, profits, foreign taxation and levies, taxes, royalties and duties together with all general risks, liabilities and obligations set out or implied in the contract and including remedy of any defects during the Defects Liability Period.”_ 8. _The Decision of the Arbitral Tribunal_ : The Arbitral Tribunal interpreted the contract and construed Clause 5.1.2 of the contract as limited to taxes that could be raised by the Respondent-Contractor directly on the Appellant, as opposed to taxes that formed part of the materials quoted in the ‘Schedule of Items of Rates - Bill of Quantities’. For this, the Arbitral Tribunal also relied on Clause 11.7 of the Contract. The Arbitral Tribunal was of the view that Entry Taxes on earth-moving equipment formed part of the cost of the works quoted in the Bill of Quantities. For this reason, the Arbitral Tribunal came to the conclusion that the increased liability on account of imposition of Entry Tax could not be reimbursed under Clause 5.1.2, as recoupment for the same could 5 only be governed by the Price Variation clauses (clause 7.1.1 and 7.1.2 in Chapter 7). 8.1 Interpreting the Price Variation clauses, the Arbitral Tribunal noted that the contract only provided for generic price variation based on a standardised formula. It also found that Clause 7.1.2 specifically barred cognizance of “ _any_ _sort of fluctuations in taxes and other market conditions for any individual item for the purpose of making adjustments in payments_ ”. Accordingly, the Arbitral Tribunal held that the claim for recouping increased tax liability for individual or specific items, in this case, the imposition of entry tax, could not be reimbursed under Clauses 7.1.1 and 7.1.2. 8.2 The Tribunal reasoned that the contractor was aware of these conditions at the time when the prices were quoted, and therefore, the claim could not succeed under Price Variation clauses. 8.3 As regards the claim for Toll Tax which formed part of Dispute IV, the Tribunal adopted the same interpretation of the contractual clauses and rejected the claim. 9. _Decision of the High Court under Section 34 of the Act_ : The Respondent’s challenge to the Arbitral Award under Section 34 of the Act was considered and dismissed by the Single Judge of the High Court by its order dated 17.01.2019. The High Court concluded that there were two possible views with respect to the construction of relevant clauses of the contract. However, as the Arbitral Tribunal 6 adopted one interpretation and since it was a reasonable interpretation, the Single Judge of the High Court held that there was no justification for exercising jurisdiction under Section 34 of the Act to interfere with the findings of the Arbitral Tribunal. 10. _Decision of the Division Bench under Section 37 of the Act_ : The Division Bench of the High Court, while considering the appeal under Section 37 of the Act, proceeded to reinterpret the contractual clauses and arrived at a distinct conclusion. The Division Bench rejected the Arbitral Tribunal’s and the Single Judge’s interpretation of Clause 5.1.2 of the contract and came to the conclusion that the said clause will also include indirect taxes such as service tax, GST, Works Contract Tax, etc. While doing so, the Division Bench applied the principle of _ejusdem generis_ to include even Entry Tax in Clause 5.1.2. The Division Bench of the High Court reversed the conclusion of the Arbitral Tribunal and the Single Judge of the High Court on the ground that they had simply assumed that the tax liability of items forming part of the Bill of Quantities was ‘inbuilt’ in the quoted costs and that no evidence was supplied to substantiate the same. The Division Bench also noted that reimbursement on account of increase in ‘toll taxes’ was specifically provided for in Clause 5.1.2 of the contract, and hence, claim for the same could not be rejected. In view of its conclusion, the Division Bench did not find it necessary to refer to Clauses 7.1.1 and 7.1.2 relating to price variation clauses, as the claims were justified under Clause 5.1.2 7 itself. Finally, relying on _Radha Sundar Dutta_ v. _Mohd Jahadur Rahim & Ors_ ,[2] the High Court came to the conclusion that it is a “ _well-settled principle that if there are two constructions possible of a contract, then the one that gives effect and voice to all clauses will be preferred over the other that renders one of them otiose or nugatory_ ”. Adopting this approach, the Division Bench of the High Court proceeded to hold that the Arbitral Tribunal failed to interpret the contractual clauses _harmoniously and holistically_ . It finally concluded that the approach adopted by the Arbitral Tribunal would amount to perversity, and therefore, found it necessary to set aside the Award, and allow claims covered under Disputes III and IV. 11. This judgment of the Division Bench of the Hight Court led to the present civil appeal before us. 12. _Submissions on behalf of the Appellant_ : Mr Shyam Divan, Senior Advocate, along with Mr Amlaan Kumar, Mr Musharaf Shaikh, Ms Rukhmini Bobde, Ms Soumya Priyadarshinee, Mr Ankit Ambasta, Mr Amit Kumar Shrivastava, Advocates, and Mr Vishal Prasad, AOR appeared on behalf of the Appellants. They submitted that the Division Bench of the High Court exceeded its limited jurisdiction under Section 37 of the Act by reinterpreting the contract and substituting its view for the Arbitral Tribunal’s, assuming the role of a court of appeal. They relied on _UHL Power Company Limited_ v. _State of Himachal_ > 2 AIR 1959 SC 24. 8 _Pradesh_[3] and _South East Asia Marine Engineering and Constructions Limited Oil India Limited_[4] for this purpose. 12.1 Next, they submitted that the parties agreed to a lump-sum contract price payable to the Respondent-Contractor. The Contractor split the agreed prices into several components and indicated the division in the ‘Schedule of Items and Rates - Bill of Quantities’, which inhered the cost and effort involved in execution of the items mentioned therein. There is no indication that the amount incurred in the execution of the entries therein would be separately reimbursed. They added that Clause 11.7 of the contract expressly indicates that the prices mentioned in the Bill of Quantities are inclusive of all costs that are liable to be incurred in the execution of the contract. 12.2 Further, they also submitted that the Arbitral Tribunal holistically interpreted Clauses 5.1.2, 7.1.1 and 7.1.2 of the contract to opine that individual tax claims would not be reimbursed by the Appellant-Corporation. The Arbitral Tribunal held that Clause 5.1.2 operates in a separate field, i.e., it operates in the field of taxes directly payable by the Corporation to the Contractor. They further added that the mention of toll tax and _octroi_ in Clause 5.1.2 is only incidental, and does not render the recovery of taxes by the Contractor implicit. On the other hand, the fluctuations in price of entries in the Bill of Quantities (or for mobilisation of construction material and machinery) was recoverable only as per > 3 (2022) 4 SCC 116. > 4 (2020) 5 SCC 164. 9 the scheme of Price Variation in Clauses 7.1.1 and 7.1.2, which expressly exclude cognizance of fluctuations in price of individual items. 13. _Submissions on behalf of the Respondents_ : Mr Darius Khambata, Senior Advocate, along with Mr Aveak Ganguly, Mr Manu Seshadri, Ms Pallavi Anand, Mr Abhijit Lal, Ms Soumya, Advocates and Mr Mithu Jain, AOR appeared on behalf of the Contractor-Respondent. They submitted that the High Court rightly interfered with the findings of the Arbitral Tribunal as it had rewritten the contract. They submitted that every canon of contractual interpretation provides for harmonious construction of _seemingly_ contradictory clauses, and constructing contracts such that no clause is rendered otiose. 13.1 They submitted that undoubtedly, Clauses 5.1.2 and 7.1.1 operate in separate fields, i.e., Clause 5.1.2 of the Special Conditions of Contract is a special clause that deals with taxes and provides for reimbursement on account of increase of taxes by the Corporation. Clauses 7.1.1 and 7.1.2, on the other hand, prohibit additional and individual claims for price variation, apart from the ones already mentioned in Clause 5.1.2. By limiting Clause 5.1.2 to the taxes that can be billed by the Contractor on the Corporation, the Arbitral Tribunal impermissibly rewrote the terms of the contract. Instead of harmonising the provisions of the contract, it inserted new terms and contradictions to it. 13.2 The respondents submitted that the Division Bench of the High Court was well within its jurisdiction under Section 37 of the Act to partially set aside the 10 Award. To substantiate their submissions, they relied on _Adani Power (Mudra) Limited_ v. _Gujarat Electricity Regulatory Commission and Ors.,_[5] _Radha Sundar Dutta_ v. _Mohd Jahadur Rahim & Ors_ . (supra), _Satyanarayana Construction Company_ v. _Union of India and Ors._ ,[6] and _Delhi Development Authority_ v. _R.S. Sharma and Company, New Delhi_ .[7] 14. _Analysis:_ At the outset, we may state that the jurisdiction of the Court under Section 37 of the Act, as clarified by this Court in _MMTC Ltd._ v. _Vedanta Ltd._ , is akin to the jurisdiction of the court under Section 34 of the Act.[8] Scope of interference by a court in an appeal under Section 37 of the Act, in examining an order, setting aside or refusing to set aside an award, is restricted and subject to the same grounds as the challenge under Section 34 of the Act. 15. Therefore, the scope of jurisdiction under Section 34 and Section 37 of the Act is not akin to normal appellate jurisdiction.[9] It is well-settled that courts ought not to interfere with the arbitral award in a casual and cavalier manner. The mere possibility of an alternative view on facts or interpretation of the contract does not entitle courts to reverse the findings of the Arbitral Tribunal.[10] In _Dyna_ > 5 (2019) 19 SCC 9. 6 (2011) 15 SCC 101. 7 (2008) 13 SCC 80. > 8 (2019) 4 SCC 163: “para 14. As far as interference with an order made under Section 34, as per Section 37, is concerned, it cannot be disputed that such interference under Section 37 cannot travel beyond the restrictions laid down under Section 34. In other words, the court cannot undertake an independent assessment of the merits of the award, and must only ascertain that the exercise of power by the court under Section 34 has not exceeded the scope of the provision.” > 9 UHL Power Company Ltd. v. State of Himachal Pradesh (2022) 2 SCC (Civ) 401, para 15. _See also_ : Dyna Technologies Pvt Ltd v. Crompton Greaves Limited (2019) 20 SCC 1, para 24, 25. > 10 ibid; _Ssangyong Engineering. & Construction Company Ltd_ . _v. National Highways Authority of India_ ( _NHAI)_ (2019) 15 SCC 131; _Parsa Kente Collieries Ltd._ v. _Rajasthan Rajya Vidyut Utpadan Nigam Ltd_ ., (2019) 7 SCC 236, para 11.1. 11 _Technologies Private Limited_ v. _Crompton Greaves Limited_ (2019) 20 SCC 1, ## this Court held: _“24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated._ _25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act.”_ 16. In the present case, the Arbitral Tribunal interpreted the contractual clauses and rejected the Respondent’s claims pertaining to Disputes I, III and IV. The findings were affirmed by the Single Judge of the High Court in a challenge under Section 34 of the Act, who concluded that the interpretation of the Arbitral 12 Tribunal was clearly a possible view, that was reasonable and fair-minded in approach. 17. It is important to extract the relevant portion of the Award, where the Tribunal considered and interpreted the contractual clauses pertaining to Disputes III and IV: _“40. A careful reading of the relevant provisions of the contract shows that claimant will not be entitled to reimbursement of Entry Tax paid by it. Clause 5.1.2 of Special Conditions provides that sales tax or turnover tax on works contract or other tax on the amount billed to respondent, levied or increased during the execution of the work; shall be borne by the respondent. For example, if the price of goods sold is Rs. 2000/- and at the time of contract, the goods were not subject to Sales Tax, but subsequently during the execution of the work, the State subjected such sale of goods to Sales Tax, at the rate of 5%, the contractor will be entitled to receive under clause 5.1.2, the Sales Tax at 5% on the price of Rs. 2000/-. Similarly, if Works Contract Tax is increased from the rate of 4.2% prevailing at the time of making the contract, the contractor will be entitled to the higher rate, by claiming the difference. Therefore, what clause 5.1.2 deals with is taxes “chargeable” by the contractor on the bills raised on the respondent. It does not deal with or provide for reimbursement of increase in taxes which may indirectly be a component of the price or rate quoted and which is be governed only by the price variation clause. This is obviously because when a contractor quotes a rate for an item of work, such rate will have various components like material cost, labour cost, fuel cost, overheads and profits. The contractor does not indicate the break-up of the various components that make up the quoted price. Obviously the rates so quoted, if it involves use of a material, will include the cost of the material plus any tax paid thereon; and if it involves use of some machinery/equipment, it will include the hire charges in respect of the_ 13 _machinery/equipment and any taxes thereon. It is clear from the contract that in regard to such components of a rate, claimant is not entitled to seek reimbursement of any increase in price or taxes and all that it will be entitled to, will be an increase that is permitted in accordance with the formula in the price variation clause. The price variation clause only provides for price variation in a general manner in accordance with a standardized price variation formula, and not reimbursement of the actual increases. That is why clause 11.7 of BoQ provides that the rates/prices shall include all taxes and clauses 7.1.1 and 7.1.2 clearly provide that rates quoted by the tenderer and accepted by the KRCL, shall hold good till the completion of the work and no additional individual claim shall be admissible on account of increases in tax or other levies except for the provision made by way of price variation clause._ _..._ _43. ... As noticed above, the contract does not contemplate reimbursement of indirect cost, taxes incurred by the claimant for executing the work. The contract contemplates the contractor quoting a price for executing a work by taking all circumstances into account and all increase that may take place. The contractor knew when it quoted, that it is entitled to only the price quoted and only variation in price as permitted by the price variation clause. The contract does not provide for payment or reimbursement of each and every increase in the price of material or tax thereon, which may go into the execution of a work.”_ (emphasis supplied) 18. The Single Judge of the High Court affirmed the findings of the Arbitral Tribunal. The reason for upholding the decision of the Tribunal is not that the Single Judge exercising jurisdiction under Section 34 of the Act is in complete agreement with the interpretation of the contractual clauses by the Arbitral Tribunal. The Learned Judge exercising jurisdiction under Section 34 of the Act 14 kept in mind the scope of challenge to an Arbitral Award as elucidated by a number of decisions of this Court. Section 34 jurisdiction will not be exercised merely because an alternative view on facts and interpretation of contract exists. In its own words, the conclusion of the Single Judge Bench of the High Court is as follows: _“10. … The ambiguity does not come from clause 5.1.1, but from the fact that there are other clauses in the contract, such as clauses 7.1.1 and 7.1.2. One way to look at the co-existence of these clauses is to treat clauses 7.1.1 and 7.1.2 merely as an exclusion for working out price variation, since it is specifically provided for in clause 5.1.2. Equally, there is another way of looking at these three clauses, and that is : clauses 7.1.1 and 7.1.2 make it clear that no increase in tax in the case of any component forming part of BoQ rates, which was considered by the contractor for quoting his rates for any particular item, should be allowed to the contractor; it is only when particular taxes were actually to be paid on the deliveries of the contractor, these would be included for reimbursement by the employer under clause 5.1.2. The arbitrator adopted the latter view. It cannot be said either that it is an unreasonable view or a view which is either impossible or which no fair and judiciously minded person would have taken. The award on this dispute, thus, does not merit any interference under Section 34 of the Act, having regard to the law stated by the Supreme Court in the case of Associate Builders (supra).”_ 19. In appeal under Section 37 of the Act, the Division Bench of the High Court took a different position. It opined that the construction of the clauses by the Arbitral Tribunal was not even a possible view, and observed as follows: _“30. ... What is more appropriate is the well-settled principle that if there are two constructions possible of a_ 15 _contract, then the one that gives effect and voice to all clauses will be preferred over the other that renders one of them otiose or nugatory [Radha Sundar Dutta v Mohd Jahadur Rahim & Ors, AIR 1959 SC 24]. There is some law to suggest that if an Award does not construe the contract as a whole then it is not a possible view and it is perverse [South East Asia Marine Engineering and Constructions Ltd v Oil India Ltd, (2020) 5 SCC 164; Patel Engineering Ltd v North Eastern Electric Power Corporation Ltd, (2020) 7 SCC 167]. As regards the dispute for reimbursement on account of toll tax effected by the Government of Jammu and Kashmir through various Notifications, Chenab Bridge’s case stands on an even stronger footing. This is because toll tax is specifically mentioned in Clause 5.1.2 and the arbitral view amounts to an entire deletion of those two words. This is clearly impermissible.”_ 20. The principle of interpretation of contracts adopted by the Division Bench of the High Court that when _two constructions are possible, then courts must prefer the one which gives effect and voice to all clauses,_ does not have absolute application. The said interpretation is subject to the jurisdiction which a court is called upon to exercise. While exercising jurisdiction under Section 37 of the Act, the Court is concerned about the jurisdiction that the Section 34 Court exercised while considering the challenge to the Arbitral Award. The jurisdiction under Section 34 of the Act is exercised only to see if the Arbitral Tribunal’s view is perverse or manifestly arbitrary. Accordingly, the question of reinterpreting the contract on an alternative view does not arise. If this is the principle applicable to exercise of jurisdiction under Section 34 of the Act, a Division Bench exercising jurisdiction under Section 37 of the Act cannot reverse an Award, much less the 16 decision of a Single Judge, on the ground that they have not _given effect and voice to all clauses_ of the contract. This is where the Division Bench of the High Court committed an error, in re-interpreting a contractual clause while exercising jurisdiction under Section 37 of the Act. In any event, the decision in _Radha Sundar Dutta_ (supra), relied on by the High Court was decided in 1959, and it pertains to proceedings arising under the Village Chaukidari Act, 1870 and Bengal Patni Taluks Regulation of 1819. Reliance on this judgment particularly for interfering with the concurrent interpretations of the contractual clause by the Arbitral Tribunal and Single Judge under Section 34 of the Act is not justified. 21. As far as the decisions in _South East Asia Marine Engineering and Constructions Limited_ (supra) and _Patel Engineering Limited_ v. _North Eastern Electric Power Corporation Limited_[11] are concerned, in both the cases, this Court affirmed the interference by a court exercising jurisdiction under Section 37 of the Act, with the concurrent findings of the Arbitral Tribunal as well as the court under Section 34 of the Act, for good and valid reasons. In _South East Asia Marine Engineering and Constructions Limited_ (supra), the Section 37 Court interfered with the Award as the Arbitral Tribunal allowed the claim for price escalation for High-Speed Diesel under the ‘Change in Law’ clause, by construing the circular increasing the HSD price as having “force of law”. The ‘Change in Law’ clause therein provided for reimbursement of any additional > 11 (2020) 7 SCC 167. 17 costs on account of “change in or enactment of any law or interpretation of existing law”. The High Court, exercising jurisdiction under Section 37 of the Act, and this Court, found that the Arbitral Tribunal incorrectly construed the ‘Change in Law’ clause as akin to a _force majeure_ clause and allowed the claims. This was held to not be a possible interpretation of the contract and hence, the Award was set aside. Similarly, in _Patel Engineering Ltd._ (supra), the Arbitral Award was found to be based on irrelevant facts and the outcome was found to result in unjust enrichment, the latter being in violation of public policy of India under Section 34(2) of the Act. Therefore, in both these cases, this Court was convinced that the view of the Arbitral Tribunal was not even a possible view, and hence, perverse in nature. 22. In the present case, we have examined the appreciation of evidence by the Arbitral Tribunal as well as the Single Judge of the High Court. We are convinced that their appreciation of the facts and interpretation of the contract is reasonable, and comprises a possible view. Keeping in mind the mandate of Section 5 of the Act 1996,[12] we note the observation of this Court in _Vidya Drolia and Ors._ v. _Durga Trading Corporation_[13] : _“Arbitration is a private dispute resolution mechanism whereby two or more parties agree to resolve their current or future disputes by an Arbitral Tribunal, as an alternative to adjudication by the courts or a public_ > 12 Arbitration and Conciliation Act, 1996, section 5: > “ **5. Extent of judicial intervention** .—Notwithstanding anything contained in any other law for the time being in force, in matters governed by this Part, no judicial authority shall intervene except where so provided in this Part.” > 13 (2021) 2 SCC 1, para 18. 18 _forum established by law. Parties by mutual agreement forgo their right in law to have their disputes adjudicated in the courts/public forum. Arbitration agreement gives contractual authority to the Arbitral Tribunal to adjudicate the disputes and bind the parties.”_ 23. The conclusion of the Division Bench of the High Court that the Award is liable to be set aside on the ground of perversity is incorrect, as it overlooks the principle laid down in _Associate Builders_ v. _Delhi Development Authority_ ,[14] where this Court held: _“32. A good working test of perversity is contained in two judgments. In Excise and Taxation Officer-cumAssessing Authority v. Gopi Nath & Sons [1992 Supp (2) SCC 312] , it was held: (SCC p. 317, para 7) “7. … It is, no doubt, true that if a finding of fact is arrived at by ignoring or excluding relevant material or by taking into consideration irrelevant material or if the finding so outrageously defies logic as to suffer from the vice of irrationality incurring the blame of being perverse, then, the finding is rendered infirm in law.”_ _In Kuldeep Singh v. Commr. of Police [(1999) 2 SCC 10 : 1999 SCC (L&S) 429] , it was held: (SCC p. 14, para 10)_ _“10. A broad distinction has, therefore, to be maintained between the decisions which are perverse and those which are not. If a decision is arrived at on no evidence or evidence which is thoroughly unreliable and no reasonable person would act upon it, the order would be perverse. But if there is some evidence on record which is acceptable and which could be relied upon, howsoever compendious it may be, the conclusions would not be treated as perverse and the findings would not be interfered with._ 14 (2015) 3 SCC 49. 19 _33. It must clearly be understood that when a court is applying the “public policy” test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected. A possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award. Thus an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score.”_ ## (emphasis supplied) 24. Having considered the matter in detail, we are of the opinion that the Division Bench of the High Court committed an error in setting aside the concurrent findings of the Arbitral Tribunal and the Single Judge of the High Court. The Award of the Arbitral Tribunal and the decision of the Single Judge of the High Court under Section 34 of the Act cannot be termed as perverse or patently illegal as concluded by the Division Bench of the High Court. The decision of the Arbitral Tribunal is a plausible view, and the Single Judge refrained from interfering with it under Section 34 of the Act. We are of the opinion that the Division Bench should not have interfered with these orders. 25. For the reasons stated above, we allow Civil Appeal No. 2903 of 2023 and set aside the judgment of the Division Bench of the High Court of Judicature at Bombay in Appeal No. 458 of 2019 dated 23.09.2022, and restore the judgment 20 and order of the Single Judge in Arbitration Petition No. 546 of 2015 dated ## 17.01.2019. No order as to costs. ……..……………………………….CJI. [Dr Dhananjaya Y Chandrachud] ……………….………………………….J. [Pamidighantam Sri Narasimha] ……………….………………………….J. [J.B. Pardiwala] **New Delhi; August 17, 2023** 21
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.