Supreme Court of IndiaSupreme Court · 2019Division BenchAppeal disposed of

KOLKATA WEST INTERNATIONAL CITY PVT LTD v. DEVASIS RUDRA

Case / Petition Number:
Civil Appeal No. 3182 of 2019
Neutral Citation:[2019] 2 S.C.R. 1070

Case Synopsis & Summary

This appeal arises from a consumer dispute regarding a Buyer’s Agreement dated 2 July 2007 for a D Row House, where possession was to be handed over by 31 December 2008 with a six-month grace period. The respondent, an allottee, paid Rs 39,29,280 in 2006. The West Bengal State Consumer Disputes Redressal Commission (SCDRC) allowed the complaint and directed refund with 12% simple interest and Rs 5 lakhs as compensation; the National Consumer Disputes Redressal Commission (NCDRC) reduced the compensation to Rs 2 lakhs. The appellant contends that the primary relief sought was delivery of possession and that possession was offered; it argues the Buyer’s Agreement is one-sided, with buyer-dominated interest if default occurs by the buyer (18% interest) but SBI savings-bank rate for delays by the developer. It stresses the seven-year delay (completion certificate dated 29 March 2016, notice of possession in 2016) is unreasonable and unfair to the buyer who was ready to accept possession in 2011. The Court notes the clause would not preclude reasonable compensation and interest, finds the seven-year delay unconscionable, affirms refunds, and modifies interest to 9% per annum. The appeal is disposed of with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Dr. Dhananjaya Y. Chandrachud
  • Hemant Gupta
Judgment Date
2019-03-25
Court Decision / Holding
The appeal is disposed of. The Court notes that the Buyer’s Agreement was one-sided and did not preclude the buyer’s right to reasonable interest or compensation. It held that seven years’ delay in possession was unreasonable and unfair, affirming the refund orders of the SCDRC/NCDRC. However, the Court modified the NCDRC’s interest rate, directing that interest be paid at 9% per annum (instead of 12%). The outstanding amount is to be released from funds deposited by the appellant, with any balance refunded. There shall be no order as to costs. Pending applications, if any, shall stand disposed of.
Final Disposition
Appeal disposed of

Parties to the Case

Appellants / Petitioners

  • Kolkata West International City Pvt Ltd

Respondents

  • Devasis Rudra

Legal Representation & Advocates

Counsels for Petitioners

  • • A Ravinder Narain
  • • Siddharth Banthia
  • • Rajat Gava
  • • Rajan Narain

Counsels for Respondents

  • • Supriya Bose
  • • Debajyoti Deb
  • • Subhasish Bhowmick
  • • Goldy Goyel

Provisions of Law Cited

Consumer Protection Act, 1986

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the Buyer’s Agreement provided for possession by 31 December 2008 with a six-month grace period, failing which the developer would pay the prevailing SBI savings-bank rate as interest for delay. The agreement is argued to be unilaterally biased in favor of the developer: it imposes 18% interest on the buyer for default, while default by the developer would attract only SBI savings-bank rate, and even then, the buyer should not be deprived of a reasonable remedy such as possession or refund. The buyer indicated readiness to accept possession as of 2011 and emphasized that seven years’ delay (completion certificate received 29 March 2016) is unreasonable; it urged refund of amounts with reasonable interest and possibly compensation. It emphasized that the remedy of refund was available and that the contract should not compel indefinite waiting.

Contentions of Respondents

The respondent/posture argued readiness to accept possession in 2011; discussions of a settlement in related matters; the official offer of possession appears to have been conditional or not formal. It relied on the contractual clause that delay beyond 30 June 2009 would attract SBI savings-bank interest for the developer, and that the buyer’s prayer for refund was plausible given the prolonged delay and hardship. The respondent contended the NCDRC’s 12% interest reflected economic loss and that the developer’s substantial investment warranted protection; it maintained the orders directing refund were justified.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,170 words•~10 min read

In The Court Record

KOLKATA WEST INTERNATIONAL CITY PVT LTD v. DEVASIS RUDRA

1070 SUPREME COURT REPORTS [2019] 2 S.C.R.[2019] 2 S.C.R. 1070 A KOLKATA WEST INTERNATIONAL CITY PVT LTD v. ## DEVASIS RUDRA (Civil Appeal No. 3182 of 2019) B MARCH 25, 2019 ## **[DR. DHANANJAYA Y CHANDRACHUD AND HEMANT GUPTA, JJ.]** _Consumer Protection Act, 1986:_ - _Housing – Failure to deliver possession – Buyer having_ - C _claimed compensation from the developer, entitled to seek refund amount or estopped from doing so – On facts, in terms of the buyer’s agreement, developer was to handover possession to the buyer by the stipulated date with a grace period of further six months – However, failure of developer to deliver the possession of houses –_ - D _Complaint by the buyer seeking possession of houses and in alternate for refund of the amount paid to developer with 12% interest p.a. and compensation of Rs.20 lakhs – Order by the State Commission directing the developer to refund the amount with 12% interest p.a. and compensation of Rs 5 lakhs – However, compensation amount reduced to Rs. 2 lakhs by the National_ - E _Commission – On appeal, held: In the buyer’s agreement, for default on the part of the buyer, the buyer liable to pay interest at the rate of 18% p.a., however, for default on the part of the developer, the developer liable to pay interest only at the savings bank rate prescribed by the SBI – Agreement being one sided, would not_ - F _preclude the right and remedy available to the buyer to claim reasonable interest or compensation – Buyer can be expected to wait for possession for a reasonable period – It would be unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession – Completion certificate was received nearly seven years after the extended date_ - G _for the handing over of possession which was not at all reasonable – Thus, the orders passed by the forum below for refund justified – Rate of interest payable by the developer to the buyer modified to 9% p.a. instead of 12% p.a. – Interest._ H 1070 1071 KOLKATA WEST INTERNATIONAL CITY PVT LTD v. DEVASIS RUDRA ## **Disposing of the appeal, the Court** **HELD: 1.1 Under the Agreement clause, any delay beyond 30 June 2009 would result in the developer being required to pay interest at the prevailing savings bank interest of the State Bank of India. Interestingly, where the buyer is in default, the agreement stipulates that interest at the rate of 18 per cent from the date of default until the date of payment would be charged for a period of two months, failing which the allotment would be cancelled by deducting 5% of the entire value of the property. The agreement was evidently one sided. The clause will not preclude the right and remedy available to the buyer to claim reasonable interest or, as the case may be, compensation. [Para 10][1074-A-D]** **1.2 In terms of the Buyer’s agreement, the date for handing over possession was 31 December 2008, with a grace period of six months. Even in 2011, when the buyer filed a consumer complaint, he was ready and willing to accept possession. It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. [Para 11][1074-E-G]** **1.3 In the circumstances, the orders passed by the SCDRC and by the NCDRC for refund of moneys were justified. Having regard to all the facts and circumstances of the case, the order of the NCDRC is modified by directing that the appellant would pay interest at the rate of 9% per annum to the respondent instead and in place of 12% as directed by the NCDRC. [Para 12, 13][1075-A]** A B C D E F G CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3182 of 2019. From the Judgment and Order dated 21.11.2016 of the National Consumer Disputes Redressal Commission, New Delhi in First Appeal H No. 958 of 2016. 1072 SUPREME COURT REPORTS [2019] 2 S.C.R. A Ravinder Narain, Siddharth Banthia, Rajat Gava, Rajan Narain, Advs. for the Appellant. Supriya Bose, Sr. Adv., Debajyoti Deb, Subhasish Bhowmick, Ms. Goldy Goyel, Advs. for the Respondent. The Judgment of the Court was delivered by B ## **DR. DHANANJAYA Y CHANDRACHUD, J.** 1. Leave granted. 2. This appeal arises from the judgment dated 21 November 2016 of the National Consumer Disputes Redressal Commission[1] . C 3. A Buyer’s Agreement dated 2 July 2007 was entered into between the appellant and the respondent. The respondent paid an amount of Rs 39,29,280 in 2006 in terms of a letter of allotment dated 20 September 2006. The agreement between the parties envisaged that the appellant would hand over possession of a D Row House to the respondent by 31 December 2008 with a grace period of a further six months ending on 30 June 2009. 4. The respondent filed a consumer complaint before the West Bengal State Consumer Disputes Redressal Commission[2] in 2011 praying for possession of the Row House and in the alternative for the refund of E the amount paid to the developer together with interest at 12% per annum. Compensation of Rs 20 lakhs was also claimed. 5. The SCDRC allowed the complaint by directing the appellant to refund the moneys paid by the respondent together with interest at 12% per annum and compensation of Rs 5 lakhs. The NCDRC has F modified this order by reducing the compensation from Rs 5 lakhs to Rs 2 lakhs. 6. Mr. Ravinder Narain, learned counsel appearing on behalf of the appellant submits that the primary relief which was sought in the consumer complaint was for delivery of possession. According to G the appellant, the completion certificate was received on 29 March 2016, which was intimated to the respondent on 11 April 2016. Moreover, before the SCDRC, in its written submissions, the appellant had offered possession of the Row House to the respondent. It has also been stated that in a complaint which was filed by an association representing H 1”NCDRC” - 2”SCDRC” 1073 KOLKATA WEST INTERNATIONAL CITY PVT LTD v. DEVASIS RUDRA [DR. DHANANJAYA Y CHANDRACHUD, J.] the allottees of 161 Row houses, a settlement was arrived on 11 September 2018 before the NCDRC specifying the date on which possession would be handed over together with interest at 6% per annum instead of 4% as mentioned in the Buyers’ Agreement. It was urged that the developer having made a substantial investment in terms of the agreement, a direction for refund is not warranted. It has also been urged that the SCDRC in the course of its decision erroneously observed that the developer was unable to fulfill its obligation to complete the construction within the agreed period and it was not certain when the Row house would be handed over. It was urged that this observation by the SCDRC is contrary to the record since before it, a specific offer of possession was made. 7. It has been urged on behalf of the respondent by Mr. Supriya Bose, learned senior counsel that a consumer complaint was filed in the year 2011. At that stage, the respondent was bonafide ready and willing to accept possession. However, nearly seven years have elapsed after the extended date for the delivery of possession which expired on 30 June 2009. In spite of this, no offer of possession was forthcoming. Learned senior counsel submitted that the letter dated 22 March 2016 of the developer was conditional and despite the subsequent letter dated 11 April 2016, no formal offer of possession was ever made by the appellant. Moreover, it was urged that the interest awarded by the NCDRC at the rate of 12% is just having regard to the economic loss and hardship suffered by the respondent. 8. While considering the rival submissions, we must at the outset advert to the following clause which was contained in the Buyer’s Agreement: “Unless prevented by circumstances beyond the control of the company and subject to Force Majeure, KWIC shall ensure to complete the said unit in all respect within 31[st] December 2008 only for the Cluster D. Further there will be a grace period of 6 months (up to 30[th] June, 2009) from the date of completion. In case the possession is not transferred after expiry of the said grace period, KWIC will be liable to pay prevailing saving Bank interest of the State Bank of India for each month of delay on the money given by the allottee as compensation but no compensation will be paid on account of force majeure reasons.” A B C D E F G H ## 1074 SUPREME COURT REPORTS [2019] 2 S.C.R. A 9. It is the above clause which is pressed in aid by the developer. Under the aforesaid clause, any delay beyond 30 June 2009 would result in the developer being required to pay interest at the prevailing savings bank interest of the State Bank of India. Interestingly, where the buyer is in default, the agreement stipulates that interest at the rate of 18 per cent from the date of default until the date of payment would be charged B for a period of two months, failing which the allotment would be cancelled by deducting 5% of the entire value of the property. The agreement was evidently one sided. For a default on the part of the buyer, interest at the rate of 18% was liable to be charged. However, a default on the part of the developer in handing over possession would C make him liable to pay interest only at the savings bank rate prescribed by the SBI. There is merit in the submission which has been urged by the buyer that the agreement was one sided. The clause which has been extracted in the earlier part of this order will not preclude the right and remedy available to the buyer to claim reasonable interest or, as the case may be, compensation. - D 10. The essential aspect of the case which is required to be analysed is whether the buyer was entitled to seek a refund or was estopped from doing so, having claimed compensation as the primary relief in the consumer complaint. The Buyer’s Agreement is dated 2 July 2007. In terms of the agreement, the date for handing over possession was 31 E December 2008, with a grace period of six months. Even in 2011, when the buyer filed a consumer complaint, he was ready and willing to accept possession. It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date - F of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non- - G suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. 11. In the circumstances, we are of the view that the orders passed by the SCDRC and by the NCDRC for refund of moneys were justified. H KOLKATA WEST INTERNATIONAL CITY PVT LTD v. DEVASIS RUDRA [DR. DHANANJAYA Y CHANDRACHUD, J.] 1075 12. Having regard to all the facts and circumstances of the case, A we modify the order of the NCDRC by directing that the appellant shall pay interest at the rate of 9% per annum to the respondent instead and in place of 12% as directed by the NCDRC. Save and except for the above modification, we affirm the directions of the NCDRC. 13. The amount outstanding in terms of the directions of this B Court shall be released out of the moneys which have been deposited by the appellant. The balance, if any, that remains shall be refunded to the appellant. 14. The appeal is, accordingly, disposed of. There shall be no order as to costs. C 15. Pending application(s), if any, shall stand disposed of. Nidhi Jain Appeal disposed of. D E F G H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.