Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1996Division BenchAppeals dismissed.

KM. PREETA SINGH ETC. v. HARYANA URBAN DEVELOPMENT AUTHORITY AND ORS.

Case / Petition Number:
Civil Appeal No. 7759 of 1996

Case Synopsis & Summary

This Supreme Court appeal concerns the legality of demanding an additional price from allottees under the Punjab Urban Estates (Sale of Sites) Rules, 1965, in the Haryana urban development housing program. The appellants challenge a directive requiring payment of a substantial additional amount (approximately Rs. 1 lakh) beyond the original price, arguing that the respondents lacked power to impose such a demand after the initial payment. The Court examines Rule 2(aa), which defines “additional price” as the sum determined by the State Government for sale of a site, keeping in view enhancements in compensation under Section 18 of the Land Acquisition Act, 1894, and the costs incurred by the State Government in related proceedings. It also notes Rule 4(1) and the explanatory clauses, establishing that the sale price includes the additional price and the cost of improvement, and that the entire expenditure for land acquisition and development is to be borne by the allottees when sites or buildings are sold. The appellants insist they had already paid the original amount and seek relief from further charges. The High Court declined to interfere with the respondents’ action. The Supreme Court, after granting leave, upheld the High Court’s decision, holding no illegality in the demand and dismissing the appeals with no costs. The decision clarifies the statutory structure of price realization under the rules and the financial responsibilities placed on allottees.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • G.B. Pattanaik
Judgment Date
1996-04-22
Court Decision / Holding
Appeals dismissed.
Final Disposition
Appeals dismissed.

Parties to the Case

Appellants / Petitioners

  • KM. PREETA SINGH
  • ETC.

Respondents

  • Haryana Urban Development Authority
  • ORS

Legal Representation & Advocates

Counsels for Petitioners

  • • Subodh Markandeya
  • • Mrs. Chitra Markandeya

Counsels for Respondents

  • • Indu Malhotra
  • • D.B. Vohra

Provisions of Law Cited

Punjab Urban Estates (Sale of Sites) Rules, 1965 – Rule 2(aa)Punjab Urban Estates (Sale of Sites) Rules, 1965 – Rule 4(1)Section 2(aa) – Punjab Urban Estates (Sale of Sites) Rules, 1965Land Acquisition Act, 1894 – Section 18Land Acquisition Act, 1894 – Section 3 (Clauses (d) of Section 3)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the respondents had no authority to demand the additional amount after the original payment had been made, arguing lack of statutory power to levy the “additional price” under the 1965 rules.

Contentions of Respondents

The respondents argued that the sale price necessarily includes the additional price and costs of development and improvement, as defined by Rule 2(aa) and other related provisions, and that the appellants were liable under these rules; the authority acted within its statutory powers.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•740 words•~4 min read

In The Court Record

KM. PREETA SINGH ETC. v. HARYANA URBAN DEVELOPMENT AUTHORITY AND ORS.

A ## KM. PREETA SINGH ETC. _v._ HARYANA URBAN DEVELOPMENT AUTHORITY AND ORS. APRIL 22, 1996 [K. RAMASWAMY AND G.B. PATTANAIK, .TJ.] B _Punjab Urban Estates (Sale of Sites) Rules, 1965:_ _Rules 2(aa), 4( 1}-Allotment of Site-Demand of additional price-Power of Development authority-Held, Allottee liable to pay sale price including additional price, and cost of improvement-E11tire e:i.penditure i11cu1Ted to be bome by allottees--Development authoiiry-Harya11a Urba11 Housing Scheme._ CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7759 of 1996 Etc. C D From the Judgment and Order dated 28.5.91 of the Punjab & Haryana High Court in C.W.P. No. 16511 of 1990 . • Janis. Subodh Markandaya and Mrs. Chitra Markandeya for the Appel- E Ms. Indu Malhotra (D.B. Vohra) (NP) for the Respondents. The following Order of the Court was delivered : Delay condoned. F Leave granted in the Special Leave Petition. The question that arises for consideration is : whether the respondents have committed any illegality in directing the appellants to pay a sum of Rs. l lakh and odd as additional amount as intimated in their calculation G memo dated August 9, 1990? The claim of the appellants is that the respondents have no power to direct payment of the additional amount when the appellants have already paid as per the original demand. It is true that initially, the provisional amount was calculated at the rate of cost incurred in the scheme known as the Haryana Urban Development HousH 621 SUPREME COl:RT REPORTS 11996] SUPP. l S.C.R. 622 - A ing Scheme in Sector 21, Gurgaon. Thereafter, the appeJlants were called upon to pay the additional amount. The contention is that the respondents have got no power to call upon the appellants to pay the additional amount. B c Section 2(aa) of the Punjab Urban Estates (Sale of Siles) Rules, 1965 defines "additional price" to mean such sum of money as may be determined by the State Government, in respect of the sale of a site by allotment, having regard to the amount of compensation by which the compensation awarded by the Collector for the land acquired by the State Government of which the site sold forms a part, is enhanced by the court on a reference made under Section 18 of the Land Acquisition Act, 1894 and the amount of cost incurred by the State Government in respect of such reference. Explanation cm;sagcs that "for the purposes of this clause and sub-rule (l) of Rule 4, the expression "the court" means the court as defined in Clames ( d) of Section 3 of the Land Acquisition Act, 1894 and D where an appeal is filed, the appellate court." ## 'Sale price' has been absorbed in Rule 4. A conjoint reading of the above rules would clearly indicate that the E allottee is liable to pay a sale price including the additional price and the cost incurred and also the cost of improvement of the sites. It is to be remembered Lhat the respondent-HUDA is only a statutory body for catering to the housing requirement of the persons eligible to claim for allotment. They dCquire the land, develop it and construct buildings and **allot the buildings or the sites, as the case may be. Under these circumstan-** F **ces, the entire expenditure incurred in connection with the acquisition of** the land and develupment thereon is required to be borne by the allottees **\vhcn** th~ **sites or the buildings sold after the development are offered on the date of the sale in a<.:cunJance \Vith thr;** regulation~ **and abo** condition~ **of** ~ale-". **It is s1;en that in the notice dated r'\ugust 9, 1990 1 the total area, G .net .irca, the payable amount for the gross acreage, the acreage left for the** devdupmental purpose, balance recoverable from the plot holders, plottable area have been given for each of the area and recovery rate also has **been mentioned under the said notice. Under these c1rcumstances, there** is no ambiguity left in the calculations. If, at all, the appellants had got any **H** doubt, they would have approached the authority and sought for further PREETASINGHv. H.U.DA 623 information. It is not the case that they had sought the information um! the A same was withheld. Under these circumstances, we do not find any illegality in the action taken by the respondents. The High Court, therefore, was right in refusing to interfere with the order. G.N. The appeals are dismissed. No costs. Appeals dismissed. B
End of Judgment Record
Browse All Supreme Court of India (1996) Decisions
1996-08-16

Pfizer Ltd. v Mazdoor Congress and ors.

Pfizer Ltd. v Mazdoor Congress and ors is a Supreme Court appeal arising from writ petitions under Article 227 challenging the Bombay High Court’s reversal of Labour Court and Industrial Court findings that Pfizer had not committed an unfair labour practice in terminating two security staff, Waman S. Surve and R.B. Sail. The matter centers on the terminations of Surve and Sail after arrests in a theft case involving Pfizer property and the company’s loss of confidence in their suitability as watch and ward personnel. The Labour Court dismissed the complaints under Section 28 of the MRTU & PULP Act, and the Industrial Court upheld that dismissal; the High Court, however, intervened in a petition under Article 227, allowing an unfair labour practice claim under Item 1(1) of Schedule IV on the grounds of undue haste and ordering reinstatement with back wages. The apex court reverses, holding that undue haste is a question of fact to be determined on evidence and that no case under Item 1(1) was pleaded or proven before the lower fora or the High Court. It stresses that new arguments cannot be introduced at the Article 227 stage absent prior pleadings and evidence. The Court restores the Labour Court’s and Industrial Court’s decisions and allows Pfizer’s appeals, clarifying the evidentiary and pleading boundaries for unfair labour practices in industrial relations law.

1996-01-09

Union of India v. S.S. Uppal and Anr.

This appeal concerns the fixation of seniority for an officer absorbed into the Indian Administrative Service (IAS) from a state civil service quota. Respondent No.1, S.S. Uppal, a Development Officer in Madhya Pradesh’s Commerce and Industry Department, was considered for IAS absorption under Rule 8(2) of the IAS (Recruitment) Rules, 1954. A panel of four officers was prepared for vacancies arising up to 1 February 1989, with Uppal placed at serial No.4, making him eligible only for the February 1989 vacancy. Although the vacancy arose earlier, he was not appointed until 15 February 1989, and on 3 February 1989 the IAS (Regulation of Seniority) Rules were amended to introduce a weightage-based method for determining Year of Allotment (YOA) for those appointed by selection. Uppal challenged Rule 2 of the 1989 Amendment Rules as ultra vires and argued his seniority should be determined by the rules in force on 1 February 1989. The Central Administrative Tribunal accepted that the vacancy occurred before the amendment, so unamended rules should apply. The Supreme Court held that seniority in the IAS is determined by the rules in force on the date of appointment, not the date of vacancy, and that weightage cannot be retrospective unless provided. It emphasized that mere inclusion in a panel does not guarantee appointment and that the Central Government may amend seniority rules from time to time. The appeal was allowed, and the Tribunal’s order set aside.

1996-03-29

Thimmappa v. Siddaramakka

Thimmappa v. Siddaramakka concerns a deed of reconveyance attached to a sale of land. The reconveyance deed provided that if the respondent vendor repaid Rs. 5,000 within eight years from the sale date (July 20, 1968), the sale deed would be executed and registered in her favor. The respondent contended she offered payment before the eight-year period expired and sought specific performance through reconveyance; the appellant allegedly refused. The trial court accepted the respondent's evidence of offer within the period; the appellate court reversed, holding time was the essence of the contract and thus the suit was barred by limitation. The Karnataka High Court then set aside the appellate decree and restored the trial court’s decree. The Supreme Court held that, unless the deed of agreement of sale fixes a date for performance, time is not necessarily the essence of the contract. It found that Thimmappa had agreed to reconveyance conditioned on repayment within eight years, and that the respondent offered payment before expiry while the appellant refused to reconvey. The cause of action arose on expiry of eight years from July 20, 1973, but the suit was filed on July 20, 1976, within the period from the date of refusal (July 19, 1976). The Court concluded the suit was not barred by limitation, dismissed the appeal, and upheld the High Court’s restoration of the trial court’s decree.

1996-11-19

STATE OF UTTAR PRADESH AND ORS. v. V.K. JAIN

State of Uttar Pradesh and Ors. v. V.K. Jain concerns the regulation of compounded entertainment tax for cinema theatres under the Uttar Pradesh Entertainments and Betting Tax Act, 1979 and related Rules. The respondent cinema proprietor sought to reduce seating capacity from 540 to 450 for the 1995-96 year and to opt for the compounded tax system under Rule 24-A. The District Magistrate rejected both applications; the Allahabad High Court quashed that rejection, holding that the District Magistrate had no power to ignore or alter the seating capacity indicated in the option application. The State appealed to the Supreme Court. The Court held that a proprietor cannot enter into a composite agreement indicating a reduced seating capacity from the maximum stated in the licence, and the District Magistrate cannot adopt any seating capacity other than the maximum in the licence for Rule 24-A purposes. To reduce seating capacity, the proprietor must approach the licensing authority under Rule 14 of the U.P. Cinematograph Rules, 1951 to amend the licence, and only then can the amended capacity be used for Rule 24-A calculations. The decision emphasizes that the maximum seats fixed in the licence, not ad hoc figures, determine the governing base for taxation and that post-composition adjustments require proper licensing amendments. The Government suggests a clarifying recast of sub-rule (4) for the post-composition period to avoid litigation.