This Supreme Court Civil Appeal challenges a Punjab and Haryana High Court order dismissing a writ petition seeking release of land acquired under the Land Acquisition Act, 1894 for development in Sultanpur, Sonipat. Kishore Chhabra claims possession of land measuring 386 sq. yards and 3078 sq. yards, bought in 1986, with a running factory since 1970. The State issued Section 4 (1992) and Section 6 (1993) notifications, with possession deemed transferred following an Award in 1995. The High Court dismissed earlier writ petitions; the present petition challenges the 17.08.2010 order denying release of land. The appellant contends discriminatory treatment because other lands in the same notification were released, and relies on Government policies dated 26.10.2007 and earlier 1991 to argue that pre-existing factories should be released and that his case falls within these parameters. He asserts that he has operated a factory since 1970, and that a Change of Land Use (CLU) or other prerequisites should not bar release. The State counters that the land falls in a green belt, substantial development has occurred, and the appellant did not obtain CLU nor object under Section 5-A, making release impermissible, with delay and laches also argued. The Court ultimately rejects discrimination, but, under Article 142, directs compensation to be calculated under the 2013 Act as of its commencement date, clarifying the decision is not a precedential ruling. The appeal is disposed of with no costs."

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • B. R. Gavai
  • Prashant Kumar Mishra
  • K. V. Viswanathan
Judgment Date
2025-04-01
Court Decision / Holding
The Court rejected the discrimination claim, but invoked Article 142 to direct that compensation be calculated under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 as of its commencement date. The order clarifies that it is based on peculiar facts and should not be treated as a precedent. The appeal is disposed of with no order as to costs.
Final Disposition
Appeal disposed of. The Court directs that compensation be calculated under the 2013 Act as on its commencement date, and clarifies that this is a peculiar-facts order not to be treated as a precedent. No costs awarded.

Parties to the Case

Appellants / Petitioners

  • Kishore Chhabra

Respondents

  • The State of Haryana & Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Nidhesh Gupta, Senior Counsel

Counsels for Respondents

  • • Mr. K.M. Nataraj, Additional Solicitor General

Provisions of Law Cited

Land Acquisition Act, 1894 - Section 4Land Acquisition Act, 1894 - Section 5-ALand Acquisition Act, 1894 - Section 6Land Acquisition Act, 1894 - Section 9Land Acquisition Act, 1894 - Section 48(1)Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Punjab Scheduled Roads & Controlled Areas Restrictions of Unregulated Development Act, 1963

Legal Doctrines & Maxims

  • Article 142 of the Constitution of India
  • Principles of res judicata
  • Discrimination (equal protection) doctrine

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that release of land released in respect of other lands in the same notification demonstrates discriminatory treatment and that his factory existed since 1970, predating the Section 4 notification. He relied on Government policies (26.06.1991; 26.10.2007; 24.01.2011) that contemplate release of pre-existing factories and development-friendly releases, and he asserted that the absence of a Change of Land Use (CLU) certificate should not bar release, particularly where the land is used for industrial purposes. He contended that the State’s 17.08.2010 rejection was unjustified and lacked reasoned assignment of facts, and that the matter should be resolved in his favor under the relevant policy framework and constitutional principles. He also argued that the petition should not be barred by delay or res judicata given the evolving representations and prior orders.

Contentions of Respondents

The State argued delay and laches, and that release is impermissible since possession had already been taken and a CLU certificate was not obtained. It pointed to the green belt designation and substantial public expenditure already incurred on sector development, which would be undermined by release. It maintained that the appellant did not pray for release in earlier petitions and did not fall within the policy frameworks for release under Section 48(1) of the Act or the 2007/1991 policies. It asserted that the petition was not maintainable on merits and that a directive under Article 142 to compute compensation under the 2013 Act would improperly override established acquisition. It stressed non-applicability of post-award releases to the present case and distinguished the released lands from the appellant’s land.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (10)

Case NameCitationTreatmentExplanation
Sube Singh vs. State of Haryana2 (2001) 7 SCC 545Mentioned OnlyCited in submissions but not discussed or applied in the decision.
Hari Ram Vs. State of Haryana3 (2010) 3 SCC 621Mentioned OnlyCited in submissions but not analyzed in the judgment.
Sham Lal vs State of Punjab4 (2013) 14 SCC 393Mentioned OnlyCited in submissions without a clear analytical application in the decision.
Haryana State Industrial Development Corporation vs. Shakuntla5 (2010) 12 SCC 448Mentioned OnlyCited by parties but not elaborated or followed in the ruling.
Raghbir Singh Sehrawat vs. State of Haryana6 (2012) 1 SCC 792Mentioned OnlyCited without discussion or application to the facts.
Patasi Devi vs. State of Haryana7 (2012) 9 SCC 503Mentioned OnlyCited but not treated as a binding precedent in the decision.
Usha Stud & Agricultural Farms (P) Ltd. vs. State of Haryana8 (2013) 4 SCC 210Mentioned OnlyCited in the arguments; the judgment does not rely on its principles.
Women's Education Trust vs. State of Haryana9 (2013) 8 SCC 99Mentioned OnlyReferenced but not distinguished or applied in the adjudication.
Siemens Engg. & Mfg. Co. of India Ltd. vs. Union of India10 (1976) 2 SCC 981Mentioned OnlyCited as a general precedent; not explicitly relied upon for the ruling.
State of Punjab vs. Bandeep Singh11 (2016) 1 SCC 724Mentioned OnlyCited in the context of discussions but not used to decide the case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,310 words•~11 min read

In The Court Record

Kishore Chhabra vs The State of Haryana & Ors.

1 2025 INSC 419 **REPORTABLE** **==> picture [72 x 72] intentionally omitted <==** IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION # **CIVIL APPEAL NO. 8968 OF 2013** ## **KISHORE CHHABRA …. APPELLANT** ## **VERSUS** **THE STATE OF HARYANA & ORS. .... RESPONDENTS** ## **J U D G M E N T** ## **PRASHANT KUMAR MISHRA, J.** **1.** Challenge in this appeal is to the order passed by the High Court of Punjab and Haryana whereby the writ petition of the appellant, calling in question the order dated 17.08.2010 passed by the respondent/State rejecting his representation for release of his Signature Not Verified Digitally signed by SAPNA BISHT Date: 2025.04.01 17:29:45 ISTReason: land from acquisition, has been dismissed. 2 **2.** Briefly stated, the facts of the matter are that the appellant is the owner in possession of the land and constructed area measuring 386 sq. yards and 3078 sq. yards at Sultanpur, Sonipat, Haryana having purchased the same from the owner of M/s. Haryana Kamoplast Industries, Sonipat vide sale deed dated 04.08.1986. **2.1** On 09.11.1992, the State of Haryana issued notification under Section 4 of the Land Acquisition Act, 1894[1] for acquisition of land for the development and utilization of land for residential and commercial area along with sector road at Sonipat. Amongst other villages, the land situated in appellant's village-Sultanpur was also the subject matter of acquisition. The total area being 329.70 acres as per Section 6 Notification issued on 06.11.1993, the appellant's land was also included in the Notification so issued. The appellant claims to have submitted objections under Section 5-A of the Act. The Land Acquisition Collector passed an Award No. 10 on 05.11.1995 mentioning that the possession of the land acquired had already been taken vide Rapat Rozanamcha No. 229 dated 05.11.1995 and the same vests with the Government. 1 “the Act’ 3 **2.2.** The appellant's 1[st] writ petition challenging the land acquisition proceedings was dismissed by the High Court and his 2[nd] writ petition filed in the year 2008 was dismissed as withdrawn as his representation was pending. The present is the third writ petition filed by the appellant seeking release of the land as also seeking quashing of the order dated 17.08.2010 whereby his request for release of the land was rejected by the State Government. **2.3.** The High Court dismissed the writ petition mainly on the ground that the possession is deemed to have been taken and continuing with physical possession would not confer any right whatsoever upon the appellant. ## _**SUBMISSIONS BY THE APPELLANT**_ **3.** Mr. Nidhesh Gupta, learned senior counsel appearing on behalf of the appellant strenuously urged that in respect of the same Notification of the same village the State has released the land, and on the other hand, land of the appellant has not been released although the same is similarly situated, as such, the appellant has been singled out in a discriminatory manner. Learned senior counsel would refer to and rely upon various orders passed by the State Government directing release of the land both at the pre-award and post-award stage. It is further submitted that there 4 is a running factory on the subject land since 1970 i.e. even before the issuance of Notification under Section 4 of the Act, therefore, his case for release of the land squarely falls within the parameters set forth in the State Government's policy dated 26.10.2007. Learned senior counsel would also urge that the order dated 17.08.2010 rejecting appellant's representation is unsustainable as the same has been passed without assigning any reason. Learned senior counsel has placed reliance on **"Sube Singh vs. State of Haryana"[2] , "Hari Ram Vs. State of Haryana"[3] , "Sham Lal vs State of Punjab"[4] , "Haryana State Industrial Development Corporation vs. Shakuntla"[5] , "Raghbir Singh Sehrawat vs. State of Haryana"[6] , "Patasi Devi vs. State of Haryana"[7] , " Usha Stud & Agricultural Farms (P) Ltd. vs. State of Haryana"[8] , "Women's Education Trust vs. State of Haryana"[9] , "Siemens Engg. & Mfg. Co. of India Ltd. vs. Union of India[10] & "State of Punjab vs. Bandeep Singh".[11]** ## _**SUBMISSIONS BY STATE OF HARYANA**_ > 2 (2001) 7 SCC 545 3 (2010) 3 SCC 621 > 4 (2013) 14 SCC 393 > 5 (2010) 12 SCC 448 > 6 (2012) 1 SCC 792 > 7 (2012) 9 SCC 503 > 8 (2013) 4 SCC 210 9 (2013) 8 SCC 99 > 10 (1976) 2 SCC 981 > 11 (2016) 1 SCC 724 5 **4.** Mr. K.M. Nataraj, learned Additional Solicitor General appearing on behalf of the State of Haryana has argued that the writ petition suffers from huge delay and laches; possession of the land having already been taken, its release is not legally permissible and that even if any other land has been wrongly released, the same would not confer any legal right upon the appellant for release of his land as his case is not covered under the policy. It is also argued that in response to notice under Section 9 of the Act, the appellant submitted his claim for grant of compensation @ of Rs. 5,000/- per sq. yard without praying for release of the land. It is also submitted that in the first writ petition the appellant did not make any prayer for release of the land and the second writ petition was dismissed as withdrawn. Therefore, the present writ petition was not maintainable being barred under the principles of _res judicata_ . Countering the appellant's submission of discrimination, Mr. Nataraj has distinguished the release orders made in favour of other landowners. ## _**STATE POLICIES FOR RELEASE OF LAND FROM ACQUISITION:**_ ## _**5. (i) Policy dated 26.06.1991**_ Para 4 of this policy which was prevalent at the relevant time provided that the existing factories should not be acquired and 6 should be released from the acquisition proceedings and constructed area of 'A' and 'B' Grade should be left out of acquisition. Para 6 provided that the area which is liable to be left out or acquired should be decided at the time of the decision on the report under Section 5-A of the Act. ## _**(ii) Policy dated 26.10.2007**_ This policy provided that any factory or commercial establishment which existed prior to Section 4 Notification will be considered for release with further stipulation that the Government may also consider release of land in the interest of integrated and planned development where the owners have approached the Hon'ble Court with further proviso that the Government may release land on the grounds other than stated above under Section 48(1) of the Act under exceptionally justifiable circumstances for the reasons to be recorded in writing. In the opening part of this policy, it is mentioned that no request will be considered after one year of the award and only those requests will be considered by the Government where objections under Section 5-A were filed. ## **(iii)** _**Policy dated 24.01.2011**_ This policy contained similar provisions like the earlier policy dated 26.10.2007. However, this policy was issued after passing of 7 the order dated 17.08.2010, therefore, the appellant’s case would not fall under this policy. **6.** The respondent/State is resisting the appellant’s case for release of land on the ground that the appellant having not preferred any objection under Section 5-A of the Act and his request being delayed, he is not entitled for release of land. Objection to release appellant’s land is also on the ground that the appellant does not have a valid Change of Land Use[12] certificate which is a fundamental prerequisite for the release of land. Further objection is on the ground that the land falls within a designated green belt and substantial government expenditure has already been incurred on development. ## _**– ANALYSIS WHETHER THE APPELLANT POSSESSES A VALID**_ ## _**CLU.**_ **7.** We shall first deal with the core issue as to whether the appellant possesses a valid CLU for running the factory which he claims to be running since 1970. The Department of Town & Country Planning, Government of Haryana declared, vide Notification no. 2366-2TCP-64/24048 dated 23.09.1964, area around Municipal Town Sonipat as controlled area under Section 4(1) (a) of the Punjab Scheduled Roads & Controlled Areas Restrictions of 12 ‘CLU’ 8 Unregulated Development Act, 1963. By virtue of the said provisions and Notification any land falling in the area is required to obtain CLU for development. The appellant’s land falls within this controlled area, yet the appellant did not obtain any CLU. In the material papers available on record, including the pleadings, the appellant has not submitted any CLU granted in his favour or in favour of his predecessor. For establishing a factory or any other commercial development being valid, a CLU is a prerequisite , in the absence of which, running a factory on the said land cannot be validated so as to include his case within the sweep of the policy dated 26.06.1991 or 26.10.2007 **8.** It is the specific stand of the respondent/State in its counter affidavit that the appellant has not obtained a CLU to which the appellant has not submitted any rejoinder. It is thus manifest that the requirement for CLU being a statutory mandate, release of land, in the absence of CLU is not permissible. ## _**PLEA OF DISCRIMINATION**_ **9.** The appellant’s claim release of land on the plea of discrimination upon submission that the lands belonging to Devraj Dewan, Northern India Carbonates Pvt. Ltd., Gatta Factory, Ashok Kumar Sawing Machine and Deewan Palace have been released from 9 acquisitions. However, the appellant has been singled out for unfavourable treatment though his case is similarly situated. **10.** Material on record reveals that the award was passed on 05.11.1995 and Rapat Roznamcha No. 229 dated 15.11.1995 was prepared much later than the order of release dated 08.04.1994 in favour of Devraj Dewan. The said Devraj Dewan submitted his application for CLU and the State Government took a decision on 31.05.1992 to process the matter for grant of CLU and was eventually granted before Section 4 Notification, the appellant cannot claim discrimination vis-à-vis Devraj Dewan. Similar is the case with Northern India Carbonates Pvt. Ltd and moreover such land held by Northern India Carbonates Pvt. Ltd which was part of road/green belt was not released. In respect of other released lands it is mentioned by the respondent/State in its counter affidavit/written submissions that the same are not part of the same Notification. It is, thus, apparent that the appellant’s case stands on a different footing inasmuch as the appellant has not obtained a valid CLU. Thus, the appellant’s plea of discrimination is liable to be rejected. _**EXPENDITURE ALREADY INCURRED BY THE STATE GOVERNMENT IN DEVELOPMENT OF THE ACQUIRED AREA**_ 10 **11.** In its additional affidavit, the respondent/State of Haryana has categorically stated that the concerned department of the State Government has already incurred huge amount on account of development of the Sectors falling under the Notification and total expenditure of Rs. 2661.88 lakhs have been incurred towards the construction of sector roads, water supply networks, sewerage and stormwater drainage systems. Sector-3, which is part of the Notification, is commercial sector and the land has been earmarked for public utilities i.e. Fire Station, Petrol Pump, Police Station, Telephone Exchange, Auto Market etc. and even 21 commercial plots of large scale have also been allotted to multiplex developments and are being developed, and one Leisure Vally Park has already been planned. Thus, release of the subject land will affect the entire planning of the land acquired under the Notification. It is also clear from the record that the land in question is abutting the institutional Plot No. 2, 18-meter-wide road and 30meter green belt, hence, release of the land would affect the green belt/road. ## _**ISSUE OF DELAY, LACHES AND RES JUDICATA**_ **12.** On the issue of delay and laches, suffice it would be to mention that the State has been considering the request for release 11 of land and change of land use as late as in the year 2020-21 whereas the appellant has been pursuing his case for release at least from the year 2007-08 onwards. Thus, the appellant's request does not suffer from delay and laches. Insofar as plea of applicability of principles of _res judicata_ is concerned, the first writ petition was not for release of land. The second writ petition was withdrawn because the appellant's representation was pending, and the present writ petition has been preferred, after his representation was rejected, impugning the rejection order dated 17.08.2010. Thus, the appellant's request for release of land has never been considered on merits by the High Court in any of the writ petitions. Thus, the appellant’s prayer for release of land cannot be thrown out on principles of _res judicata_ , however it is not acceptable on merits. **13.** For the above stated reasons, we are not inclined to accept the appellant’s prayer for release of land on the ground of discrimination. However, since the appellant claims to be in continuous physical possession of the land wherein a factory is in operation and the department has not satisfactorily controverted this aspect of the matter, on the special facts of this case, in exercise of our power under Article 142, we deem it appropriate to direct that the compensation payable to the appellant should be calculated under the Right to Fair Compensation and Transparency 12 in Land Acquisition, Rehabilitation and Resettlement Act, 2013 as on the date of commencement of the said Act. This order is made on the peculiar facts of the case and is not to be treated as a precedent to be relied upon in other cases. It is ordered accordingly. Resultantly, the appeal is disposed of in the above stated terms. No order as to costs. **…………………………………………..J. (B.R. GAVAI)** **…………………………………………..J. (PRASHANT KUMAR MISHRA)** **…………………………………………..J. (K.V. VISWANATHAN)** **NEW DELHI; APRIL 01, 2025**
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.