Kirloskar Construction and Engineers Ltd v. Nadeera Sulaiman and Others
Case Synopsis & Summary
This Civil Revision Petition concerns Kirloskar Construction and Engineers Ltd., the defendant, challenging an order that permitted the plaintiffs to sue as indigent persons and entertained a suit for recovery of money on contract work performed by late Sulaiman and a sub-contractor arrangement. The plaintiffs, legal heirs of late Sulaiman, claimed Rs 47,20,000. The court below had previously entertained the indigency petition and dismissed the objection that the disputes should be referred to arbitration under the arbitration clause in the contract. The central issue is whether Clause 17 of the subcontract/contract—stating that “All matters of disputes or differences, if any, shall be referred to the Managing Director of the contractor and his decision on the disputes and difference shall be final and binding on the sub contractors”—constitutes a valid arbitration clause. The defendant contends that naming the Managing Director as arbitrator renders the clause invalid and that the civil court has jurisdiction independent of arbitration. The plaintiffs contend the clause is a valid arbitration agreement, and the arbitrator need not be an independent third party provided the agreement is in writing. The High Court reviews authorities including P. Anand Gajapathi Raju, Hindustan Petroleum v. Pinkcity Midway Petroleums, Konkan Railway v. Rani Construction, and Bihar State Mineral Development Corporation v. Encon Builders, concluding that arbitration clauses may be valid even if the arbitrator is not a disinterested party and that objections are to be raised before the arbitral tribunal. The court sets aside the impugned order and directs referral to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996, allowing the revision.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- S.S. Satheesachandran
- Judgment Date
- 2009-10-19
- Court Decision / Holding
- Revision allowed; impugned order set aside; court directs the parties to refer their disputes to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996.
- Final Disposition
- Revision allowed; lower order set aside; arbitration to be conducted under Section 8, Arbitration and Conciliation Act, 1996.
Parties to the Case
Appellants / Petitioners
- Kirloskar Construction and Engineers Ltd
Respondents
- Nadeera Sulaiman
- Najeena Sheref
- Raheena Sulaiman
- Mahin Abubacker (minor) rep by mother and guardian Nadeera Sulaiman)
Legal Representation & Advocates
Counsels for Petitioners
- • Mr. K. L. Varghese
- • Smt. S. Varghese
Counsels for Respondents
- • Mr. N. P. Samuel
Provisions of Law Cited
Legal Doctrines & Maxims
- Arbitration clause elements (present/future difference, intention to settle by private tribunal, written agreement, ad idem) as per Bihar State Mineral Development Corporation v. Encon Builders (I) (P) Ltd.
- Ouster of civil court jurisdiction in arbitration agreements
Submissions & Arguments
Contentions of Appellants / Petitioners
The defendant contends that Clause 17 naming the Managing Director as arbitrator creates a valid arbitration agreement; even if the arbitrator is not neutral, arbitration is still permissible; disputes, if any, should be referred to arbitration under Section 8. The objection that the court has no jurisdiction due to arbitration clause should be decided by the arbitral tribunal; there is no need for civil adjudication of the underlying claim.
Contentions of Respondents
The plaintiffs contend that the arbitration clause is invalid because the arbitrator is the Managing Director—an officer of the contractor—thus not independent; nonetheless, the court below held there is no valid arbitration agreement. The dispute is not merely about the existence of an arbitration clause but about whether the clause is valid and whether arbitration should proceed.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (4)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Bihar State Mineral Development Corporation v. Encon Builders (I) (P) Ltd. | (2003) 7 SCC 418 | Positive | Used to distill the essential elements of a valid arbitration agreement (present/future differences, intention to submit to a private tribunal, written agreement, ad idem). |
| P. Anand Gajapathi Raju v. P.V.G.Raju and others | (2000) 4 SCC 539 | Positive | Quoted to support that when an arbitration clause exists, courts should refer parties to arbitration and further proceedings relate to the arbitral tribunal. |
| Hindustan Petroleum Corporation Ltd. v. Pinkcity Midway Petroleums | (2003) 6 SCC 503 | Positive | Cited for principle that disputes not covered by the arbitration clause can be examined by the civil court, and that the arbitral tribunal can address issues regarding the existence/validity of the arbitration agreement. |
| Konkan Railway Corporation Ltd. v. Rani Construction (P) Ltd. | (2002) 2 SCC 388 | Positive | Cited for the proposition that objections to the applicability of the arbitration clause must be raised before the arbitral tribunal. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Kirloskar Construction and Engineers Ltd v. Nadeera Sulaiman and Others
Related Decisions & Precedents from High Court of Kerala (2009)
Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality
This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.
Abdul Majeed Kalathil v. District Collector, Malappuram & Others
This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.
WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)
This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."
M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others
The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.