Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Division BenchAppeal partly allowed; cross-objections dismiss...

KERALA STATE ELECTRICITY BOARD v. PAUL P. EAPEN AND OTHERS

Case / Petition Number:
LAA No. 1491/05 & C.O. 27/06

Case Synopsis & Summary

This High Court judgment concerns a land acquisition appeal by the Kerala State Electricity Board (KSEB) against a reference court’s award in a case involving the requisition of 92.20 acres in Manakunnam Village for a 110 kV substation at Kandanad. The board challenges the reference court’s enhancement of land value, reliance on Exts. A11 and A12 (purchase offers) and the Board’s settlement at Rs. 11,900 per cent, contending there is no evidence of a higher value due to time lag; it argues that Ext. A11/A12 did not mature into a binding contract and that the increased value granted by the reference court, including Rs. 50,000 for injurious affection and Rs. 2,00,000 for loss of road frontage, is unwarranted or duplicative. The respondents/claimants defend the enhanced compensation, with advocacy emphasizing injurious affection due to transformer noise, road frontage loss, and the need for proper valuation using cited documents and relevant principles. The court re-evaluates, accepting Exts. A11 and A12 as reflecting market value of Rs. 11,900 per cent on the relevant date, but limits time-based escalation to 30% (4 years’ lag), fixing the land value at Rs. 16,660 per cent. It holds injurious affection and road frontage compensation at Rs. 2 lakhs in total, rejects further awards under section 23(1-A) except for a defined period, and dismisses the claimants’ cross-objections. The appeal is partly allowed; costs follow the result.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Pius C. Kuriakose
  • C.K. Abdul Rehim
Judgment Date
2009-03-06
Court Decision / Holding
Appeal partly allowed. The market value of the acquired land is re-fixed at Rs. 16,660 per cent (not Rs. 11,900 per cent), given the time lag between Ext. A11 and the section 4(1) notification. The separate awards for injurious affection (Rs. 50,000) and loss of road frontage (Rs. 2,00,000) are consolidated into a total of Rs. 2,00,000 for injurious affection to the remainder land and building. The claimants are entitled to additional amount under section 23(1-A) at 12% only for the period from 23-04-1999 to 19-05-2000. The cross-objections filed by the claimants are dismissed. Costs are directed to be borne by the parties throughout. The judgment of the reference court is thus modified to reflect the above adjustments; the appeal is allowed to the above extent and the matter remitted for the necessary formalities consistent with this opinion.
Final Disposition
Appeal partly allowed; cross-objections dismissed; market value and injurious affection adjustments as stated in court decision.

Parties to the Case

Appellants / Petitioners

  • KERALA STATE ELECTRICITY BOARD, represented by its Secretary, Trivandrum
  • THE EXECUTIVE ENGINEER, TRANSMISSION DIVISION, KERALA STATE ELECTRICITY BOARD, KALAMASSERY

Respondents

  • PAUL P. EAPEN
  • MARY MATHEW
  • MEENA MATHEW
  • MAJU MATHEW
  • STATE OF KERALA
  • THE SPECIAL DEPUTY COLLECTOR (LA)

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri.C.K.KARUNAKARAN, SC for KSEB

Counsels for Respondents

  • • Dr. George Abraham for R2 & R4
  • • Sri.Vargheese J.Punnachalil for R1
  • • Sri.Basant Balaji, Sr. Govt. Pleader for R5 & R6

Provisions of Law Cited

Section 4(1) of the Land Acquisition ActSection 23(1-A) of the Land Acquisition Act

Legal Doctrines & Maxims

  • Estoppel

Submissions & Arguments

Contentions of Appellants / Petitioners

The Kerala State Electricity Board contends that the reference court erred in relying on Exts. A11 and A12 for determining market value; Ext.A2 and related negotiations did not mature into a binding contract. It argues there is no credible evidence of an increase in land values due to the time elapsed, particularly since Kandanad was rural; the elevated Rs. 17,255 per cent is unwarranted. The Board challenges the Rs. 50,000 injurious affection and Rs. 2,00,000 for loss of road frontage as unsupported and potentially duplicative with other compensation under section 23(1-A). Citing G.M. Oil & Natural Gas Corporation Ltd. v. R. Jivanbhai Patel, it asserts that escalation for time lag must be moderated by the rural context. It maintains Ext. A11 (Rs. 11,900 per cent) reflects the true market value at the relevant date and argues that higher values should not be imposed without proof of increased value.

Contentions of Respondents

Dr. George Abraham contends injurious affection is grossly inadequate, urging at least Rs. 1 lakh more for injurious affection and challenging the separation of injurious affection and road frontage compensation as duplicative. He relies on Exts. C1, C2 and C1(a) to justify loss of frontage and noise impact from transformer operation, arguing the remainder land’s diminished value. He also argues that the reference court erred in applying 23(1-A) benefits beyond the appropriate period. The respondents emphasize urbanization factors and request larger compensation under the principles established by Supreme Court precedents, urging a revaluation that reflects actual downstream effects on remaining property and road access.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
G.M.Oil & Natural Gas Corporation Ltd. v. R. Jivanbhai Patel & another2008 SAR (Civil) 894PositiveCited for principles on time-based escalation of land value; applied as persuasive authority to calibrate permissible increase.
State of Kerala v. Jose Simon2009 (1) KLT 760DistinguishedUsed to discuss escalation rates (urban vs rural); court distinguishes rural context and limits escalation accordingly.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,374 words•~11 min read

In The Court Record

KERALA STATE ELECTRICITY BOARD v. PAUL P. EAPEN AND OTHERS

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE PIUS C.KURIAKOSE & THE HONOURABLE MR. JUSTICE C.K.ABDUL REHIM FRIDAY, THE 6TH MARCH 2009 / 15TH PHALGUNA 1930 LA.App..No. 1491 of 2005 & C.O.27/06 -------------------------LAR.197/2000 of III ADDL.SUB COURT, ERNAKULAM .................... APPELLANT(S): RESPONDENTS 3 AND 4. ---------------------------------- 1. KERALA STATE ELECTRICITY BOARD, REPRESENTED BY ITS SECRETARY, TRIVANDRUM. 2. THE EXECUTIVE ENGINEER, TRANSMISSION DIVISION, KERALA STATE ELECTRICITY BOARD, KALAMASSERY. BY ADV. SRI.C.K.KARUNAKARAN, SC FOR KSEB SRI.C.K.KARUNAKARAN, SC FOR KSEB RESPONDENT(S): CLAIMANTS. ------------------------- 1. PAUL.P.EAPEN, PULLIYATTU TUGALAN, KANDANAD P.O. ERNAKULAM DISTRICT. 2. MARY MATHEW, W/O.PAUL.P.MATHEW, DO. DO. 3. MEENA MATHEW, D/O.PAUL P.MATHEW, DO. DO. 4. MAJU MATHEW, REPRESENTED BY THE DISTRICT COLLECTOR, ERNAKULAM. 5. STATE OF KERALA, REPRESENTED BY THE DISTRICT COLLECTOR, ERNAKULAM. 6. THE SPECIAL DEPUTY COLLECTOR (LA), ERNAKULAM. ADV. DR.GEORGE ABRAHAM FOR R2 TOR4 - SRI.VARGHESE.J.PUNNACHALIL FOR R1 SR. GOVERNMENT PLEADER FOR R5 & R6 SRI.BASANT BALAJI THIS LAND ACQUISITION APPEAL HAVING BEEN FINALLY HEARD ON 06/03/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **PIUS C. KURIAKOSE & C.K.ABDUL REHIM, JJ.** ----------------------------------------------LAA. No. 1491 OF 2005 & C.O. No. 27/06 ----------------------------------------------Dated this the 6th day of March, 2009 ## **J U D G M E N T** ## **Pius C.Kuriakose, J.** Kerala State Electricity Board, the requisitioning authority is in appeal against the judgment of the reference court in a case pertaining to acquisition of 92.20 Ares in Manakunnam Village for the establishment of a 110 K.V. Substation at Kandanad. As against claim for land value at the rate of Rs.50,000/- per cent the land acquisition officer awarded land value at the rate of Rs.5679/- per cent corresponding to Rs.14,032/- per Are. Under the impugned judgment the reference court would re-fix land value at the rate of Rs.17,255/- per cent. Apart from granting enhanced land value for the acquired property on the above basis the reference court has granted an amount of Rs.50,000/- as compensation towards injurious affection and a further amount of Rs.2 lakhs towards compensation for loss of road frontage. In this appeal, the appellant requisitioning LAA. N0. 1491/05 -2- authority contends that the reference court was not justified in not placing reliance on Ext.A2 basis document. The appellant also contends that the court below ought not have placed reliance on Exts.A11 and A12 under which the proposal submitted by the claimants to convey the acquired lands for a sum of Rs.11,900/- was accepted by the Kerala State Electricity Board. It is urged that the acceptance by the Kerala State Electricity Board was subject to a condition that possession of land should be immediately handed over and the proposal failed due to failure on the part of the claimants to surrender lands on time. It is urged that the reference court has granted considerable increase over even the land value proposed and conditionally accepted under Ext. A11 and A12 on the ground of passage of time. But there was no evidence adduced by the claimants to show that land value in the locality has increased during the time which had passed. The award of compensation towards LAA. N0. 1491/05 -3- injurious affection and further amount of Rs.2 lakhs towards compensation for loss of road frontage was not supported by any evidence and it is urged that in any event there is duplication in the matter of award of compensation under those counts by the reference court. Lastly it is urged in the appeal that more than what is due has been awarded towards the amounts eligible to the claimant under section 23(1-A) of the Act. 2. We have heard the submissions of Sri.C.K.Karunakaran, learned standing counsel for the Electricity Board and also those of Dr.George Abraham, learned counsel for claimant respondents 2 to 4. We have heard Sri.Basant Balaji, senior Govt. Pleader for R5 and R6 and we have heard Sri.Varghese J.Punnachal, learned counsel for the first respondent claimant also. Sri.C.K.Karunakaran, standing counsel would assail the judgment of the reference court on the basis of the grounds LAA. N0. 1491/05 -4- raised in the memorandum of appeal. He would draw our attention to judgment of the Supreme Court in G.M.Oil & Natural Gas Corporation Ltd. v. R.Jivanbhai Patel & another, (2008 SAR (Civil) 894) and submit that Kandanad in Manakunnam Village where the acquired property is situated is a rural area and therefore there is no justification for granting an increase of 15% per cent every year over the value reflected in A11 and A12 for passage of time. Mr.Karunakaran submitted that the proposals evident from Exts.A11 and A12 had never matured into a contract and the negotiations were broken due to the default of the claimants. He submitted further that there is no legal evidence to support the award of Rs.50,000/- towards compensation for injurious affection. The claim is based on the noise occasionally created by the transformers and other heavy machineries installed on the Sub-station constructed on the acquired property and the Advocate Commissioner's LAA. N0. 1491/05 -5- report is of no value in assessing the eligible compensation on the count of injurious affection. The learned counsel would strongly assail the award of a further amount of Rs.2 lakhs as compensation for loss of road frontage. The standing counsel would read over to us the commissioner's reports Exts. C1, C2 and sketch C1(a) and submit that there is nothing in those reports which will justify the award of Rs.2 lakhs on the above count. The amount has been awarded purely on guess work. 3. Dr.George Abraham who addressed most of the arguments on behalf of the claimants would draw our attention to the memorandum of cross objections filed by his parties and submit that the compensation awarded towards injurious affection is grossly inadequate. Learned counsel submitted that the total extent of the remainder property retained by the claimants after acquisition of a portion from their extensive holdings is 8.36 acres and LAA. N0. 1491/05 -6- therefore a further amount of at least Rs.1 lakh ought to be granted towards injurious affection. 4. We have anxiously considered the rival submissions addressed at the Bar. We have made a re-appraisal of the evidence which is available in this case. We are of the view that the learned Subordinate Judge was perfectly justified in placing reliance on Exts.A11 and A12 in preference to all the other items of evidence available in the case for determining the market value of the land which was acquired. Exts.A11 and A12 will show that in response to an offer by the claimants to sell their land extending to 2.15 acres for installation of the proposed 110 K.V. Sub-station at the rate of Rs.12,000/- per cent, the Kerala State Electricity Board requested the claimants to sell the property to them at a slightly lesser amount, i.e., Rs.11,900/- per cent and that the Board has accorded sanction for acquisition of the claimants' land at the rate of Rs.11,900/- per cent. It is LAA. N0. 1491/05 -7- clear from the evidence that both sides had agreed that the sum of Rs.11,900/- per cent was the market value of the land at the relevant time, i.e., 1-7-1995. Having agreed to purchase the land from the claimants at the rate of Rs.11,900/- per cent and issued Ext.A11 order the appellant Board cannot contend before the reference court that the market value of the land as on the date of A11 was lesser than Rs.11,900/- per cent. We feel that principles of estoppel have been correctly applied by the reference court in this case against the Electricity Board and the reference court acted correctly in proceeding on the basis that as on the date of Ext.A11 the correct market value of the land was Rs.11,900/-. Interestingly, the value which emerges on a cumulative reading of the other documents produced from the side of the claimants in support of their claim for enhancement of land value will also show that the correct market value of the acquired property at that time was LAA. N0. 1491/05 -8- more or less equal to the above sum of Rs.11,900/- per cent. 5. While we are endorsing the reference court's view that as on the date of Ext.A11 the prevailing market value was Rs.11,900/- per cent we are unable to approve the decision of that court in granting an increase of 45% over that amount taking into account the time that has passed between Ext.A11 and the publication of the relevant section 4(1) notification. It appears to us that the learned Subordinate Judge proceeded as if the time gap between the date of Ext.A11 and the date of section 4(1) notification is only 3 years and that is why total increase of 45% is given calculating increase at the rate of 15% every year. Supreme Court has in G.M.Oil and Natural Gas Corporation v. R.Jivanbhai Patel & another, (2008 SAR (Civil) 894) spoken about the percentage of escalation to be granted based on time lag between date of document relied on and LAA. N0. 1491/05 -9- the date of publication of section 4(1) notification. A Division Bench of this Court in the judgment in State of Kerala v. Jose Simon, (2009 (1) KLT 760) to which one among us (PCK(J) was also party, has followed the principles laid down by the Supreme Court in G.M.Oil and Natural Gas Corporation Ltd.'s case and noticed that increase of market value in urban and semi-urban areas is about 10% to 15% while the corresponding increase in rural areas can only be around half of it, i.e., about 5% to 7.5% per annum. Despite its proximity to the Municipal Town of Tripunithura and the developments which have taken place in and around Kandanad in the recent past we are unable to agree that Kandanad was an urban or even semi-urban area at the time of publication of Section 4(1) notification. The percentage of increase which should have been granted by the reference court for the time lag between date of Ext.A11 and the date of publication of section 4(1) notification, LAA. N0. 1491/05 -10- according to us, would not have been more than 7.5% per annum. But at the same time, the actual time lag is 4 years and not 3 years as the reference court appears to have thought. Therefore the maximum increase which could be granted every year on the sum of Rs,.11,900/- revealed by Ext.A11 is only 30% and according to us the land value which should have been determined for the acquired land is Rs.16,660/- per cent. 6. The fervent and persuasive submissions of Dr.George Abraham notwithstanding, we are unable to agree that the respondents claimants are entitled for a further amount of Rs.1 lakh towards compensation for injurious affection. According to us, the reference court erred seriously in awarding compensation for injurious affection and compensation for loss of road frontage separately. According to us, the award of Rs.50,000/ granted specifically towards injurious affection and the LAA. N0. 1491/05 -11- award of Rs.2 lakhs granted towards compensation for loss of road frontage are both compensations awarded to the remainder property of the claimants and hence will fall within the same count of compensation. We do notice that to a very slight extent the value of the remainder property belonging to the claimant has become reduced. Here again, we feel that the reference court was under the impression that road frontage of the remainder property has been lost by the acquisition. Even earlier the properties of the claimants were not abutting the road. A straight private road had been provided from the public road to the entire holding of the claimants. As a result of the acquisition the said private road had to be shifted a little with the result that the length of the road connecting the public road to the remainder property of the claimants has become slightly longer. The injurious affection to the building quantified by the reference court at Rs.50,000/- is virtually on account of LAA. N0. 1491/05 -12- the noise which may be created by the machineries installed in the Sub-station established on the acquired property. There is no acceptable legal evidence regarding the extent of noise and the impact the same may have on peaceful living in the building. According to us, no portion of the building has been directly affected by the acquisition and the building remains intact in spite of the acquisition. Diminution in value of the building at best can be only because of the situation that the private road which led straight into the building has been shifted as already indicated. According to us, applying the settled principle for computation of compensation for diminution in land value and taking into account the extent of dry land which remains under the possession of the respondents the maximum total compensation which could be awarded to the claimants towards the count of injurious affection is Rs.2 lakhs. The judgment of the reference court will have to be LAA. N0. 1491/05 -13- interfered with in this count also. We notice that a mistake has been committed by the reference court in awarding additional amounts under section 23(1-A). According to us, the above amount will be admissible only during the period from 23-4-1999 till 19-5-2000. 7. The result of the above discussion is that the crossobjection filed by the claimants will stand dismissed. The appeal will stand allowed to the following extent. The determination of market value of the acquired property by the reference court is set aside. The market value of the acquired land is re-fixed at Rs.16,660/- per cent. The total enhanced land value will stand re-fixed accordingly. The award of separate amount of Rs.50,000/and Rs.2 lakhs by the reference court for injurious affection for the building and the remainder land is modified and it is held that the total amount which is to be awarded to the claimants towards injurious affection for both land and LAA. N0. 1491/05 -14- building is Rs.2 lakhs. It is clarified that the claimants are entitled for the additional amount under section 23(1-A) at 12%, only during the period from 23-4-1999 till 19-5-2000. Appeal is allowed to the above extent and the parties are directed to suffer their costs through out. **(PIUS C.KURIAKOSE, JUDGE)** **(C.K. ABDUL REHIM, JUDGE)** **ksv/**
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.