Kaushik Narsinhbhai Patel & Ors. v. M/s S.J.R. Prime Corporation Private Limited
Case Synopsis & Summary
Kaushik Narsinhbhai Patel & Ors. approached the NCDRC alleging deficiency in service by the builder in a delayed completion and possession of flats under a construction agreement dated 31.03.2012, with a promised possession by March 2014 and a six-month grace. Possession was handed over only in 2017, after years of delay and various invoices, prompting reliefs including delayed compensation, refund of charges, and the construction of promised amenities. The NCDRC partially allowed the complaint on 15.09.2022, directing payment of interest at 6% p.a. on deposits from due dates, and ordered Green Jogging Track and a Convenience Store, among other reliefs. The order, however, arose after an order dated 27.01.2021 directing the opposite party to file a written statement or face its closure of right, followed by Annexure P-18 (11.08.2021) declaring forfeiture of the right to file a written statement but allowing participation in proceedings. The appellants argued that the forfeiture prevented the opposite party from introducing pleadings via written submissions (Annexure P-21) and that the opposite party improperly relied on new pleadings. The Supreme Court held that, under the Consumer Protection Act, 2019, forfeiture does not entitle a party to file pleadings; it can participate, cross-examine, and argue on legal questions, but pleadings cannot be introduced through submissions. The appeal was partly allowed, modifying the compensation formula and fixing the due date for possession as per Clause 6.1, while affirming 6% interest, and directing NCDRC to compute per flat.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- C.T. Ravikumar
- Sanjay Kumar
- Judgment Date
- 2024-07-22
- Court Decision / Holding
- Appeal Partly allowed. The Supreme Court modified the NCDRC’s formula for computing delayed compensation by fixing the due date for possession in line with Clause 6.1 and permitted compensation to accrue at 6% per annum from the due date of possession, i.e., September 2014, until possession is offered to each complainant. The NCDRC is directed to verify dates of possession for each flat and implement the adjusted liability accordingly; pending applications, if any, stand disposed of.
- Final Disposition
- Appeal Partly allowed.
Parties to the Case
Appellants / Petitioners
- Kaushik Narsinhbhai Patel
- Ors.
Respondents
- M/s S.J.R. Prime Corporation Private Limited
Legal Representation & Advocates
Counsels for Petitioners
- • Mr. Ajit Kumar Sinha, Senior Counsel; Govind Jee; Kartikeya Khanna; Omanakuttan K K; Ayush Mishra; Mrs. Parul Dhurve (Advs.)
Counsels for Respondents
- • Balaji Srinivasan; Devamshu Behl (Advs.)
Provisions of Law Cited
Legal Doctrines & Maxims
- What cannot be done directly, cannot be done indirectly.
- Pleading means the plaint or written statement.
- The rigour of the rule of pleadings; no new ground of claim except by amendment (Order VI, Rule 7).
- A party cannot base its case on evidence not pleaded (Nalini Sunder v. GV Sunder)
- Forfeiture of the right to file a written statement does not disentitle a party from participating in proceedings (Nanda Dulal Pradhan & Anr. v. Dibakar Pradhan & Anr.; Sangram Singh referenced)
Submissions & Arguments
Contentions of Appellants / Petitioners
Appellants contend that Annexure P-18 forfeiture order barred the opposite party from introducing pleadings via written submissions; the NCDRC’s reliance on Annexure P-21 to resist claims was improper; the due date for possession should follow Clause 6.1 of the Construction Agreement; non‑compliance with date-wise payment schedules cannot justify deviation from the Prasannakumaar formula; forfeiture should not convert into automatic entitlement for a favorable order to the complainant; the appellant asks for adherence to established precedents and for proper computation of compensation as per the Construction Agreement and the Prasannakumaar formula.
Contentions of Respondents
Respondents argue that forfeiture of the right to file a written statement does not deprive them of participating in proceedings, cross‑examining witnesses, or arguing legal points; permitting written submissions was permissible to contest allegations; the NCDRC’s decision to consider Clause 6.1 and related terms is valid; the delay caused by the builder warrants compensation; the court should follow established precedents (R.V. Prasannakumaar) while noting any exceptional circumstances; the Respondent asserts that the proceedings should be construed to ensure a fair adjudication under the Consumer Protection Act.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (4)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Nanda Dulal Pradhan & Anr. v. Dibakar Pradhan & Anr. | [2022] 7 SCR 483 : 2022 SCC OnLine SC 822 | Positive | Held that forfeiture of the right to file a written statement does not disentitle a party from participating in proceedings and cross-examining witnesses; supports the Respondent’s right to participate despite forfeiture. |
| Nalini Sunder v. GV Sunder | AIR 2003 Kar 86 | Mentioned Only | Cited for the proposition that a party cannot base its case on evidence not pleaded; used as a guiding principle rather than as binding precedent in the present decision. |
| R.V. Prasannakumaar & others. v. Mantri Castles Private Limited & Another | [2019] 5 SCR 821 : (2020) 14 SCC 769 | Positive | Cited to justify the fixation of the due date for possession and the compensation framework; the Court endorses approach consistent with this precedent. |
| Sangram Singh | Not provided | Mentioned Only | Cited in context of general principle about restoration of rights and pleadings; used as a historical reference rather than a direct ruling in the current matter. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Kaushik Narsinhbhai Patel & Ors. v. M/s S.J.R. Prime Corporation Private Limited
Related Decisions & Precedents from Supreme Court of India (2024)
Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors
This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.
Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others
Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.
Union of India v. M/s Indian Oil Corporation Ltd.
This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.
Gene Campaign & Anr. v. Union of India & Ors.
This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.