Case Synopsis & Summary
This appeal concerns a pre-emption dispute where the decree holder deposited funds as directed but with a small deficit due to an inadvertent miscalculation. The trial court directed deposit of ₹7,600 against a decree amount of ₹9,214 minus 1/5 already deposited; the deposited amount on 19.09.1988 was short by ₹14. Subsequently, multiple applications sought permission to deposit the deficit and condonation of delay, leading to a sequence of orders: dismissal threats, revision, and a High Court review. The core issue is whether a court may extend the time for deposit under Section 148 CPC in a pre-emption suit when the shortfall arises from a bona fide error and is relatively minor. The appellants argued illiteracy and bona fide error, relying on Johri Singh v. Sukh Pal Singh and Others and Jang Singh v. Brij Lal and Others to justify extension after expiry of the prescribed period. The respondents contended that non-compliance with the decree warrants no relief. The Supreme Court held that courts do have the jurisdiction under Section 148 CPC to extend time for deposit in such circumstances, provided the mistake is bona fide and not due to negligence. The impugned High Court/Trial Court orders were set aside; the appellants were permitted to deposit ₹14 by 20.05.2024, with costs of ₹1,00,000 payable to the respondents for the prolonged litigation.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Rajesh Bindal
- Prasanna Bhalachandra Varale
- Judgment Date
- 2024-05-03
- Court Decision / Holding
- Appeal allowed. The impugned order of the High Court (recalling the revision) and the lower court orders are set aside. The appellants are permitted to deposit ₹14 in the court below on or before 20.05.2024. The respondents shall be entitled to withdraw the entire amount deposited, if not already done. In recognition of the prolonged litigation caused by the appellants’ error, the Court directs the appellants to pay costs of ₹1,00,000 to the respondents, to be deposited in the Trial Court within the same time frame, with liberty to the respondents to withdraw the same.
- Final Disposition
- Appeal allowed
Parties to the Case
Appellants / Petitioners
- Kanihya @ Kanhi (Dead) Through LRS.
Respondents
- Sukhi Ram and others
Legal Representation & Advocates
Counsels for Petitioners
- • J. B. Mudgal
- • Vanshika Mudgil
- • R. C. Kaushik
Counsels for Respondents
- • S.P. Laller
- • Anil Hooda
- • Priyank
- • Rameshwar Prasad Goyal
Provisions of Law Cited
Legal Doctrines & Maxims
- actus curiae neminem gravabit
- certum est quod certum reddi potest
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants argued that the shortfall of ₹14 arose from a bona fide clerical/calculation error and not from neglect or inaction. They contended that Section 148 CPC authorizes the court to extend the time for deposit in pre-emption matters when a minor defect occurs, citing Johri Singh v. Sukh Pal Singh and Others and Jang Singh v. Brij Lal and Others to justify extension even after expiry. The appellants emphasized illiteracy and lack of procedural sophistication as factors; they urged the Court to set aside the High Court's recall of the revision order and permit payment of the deficit by a fixed date, with costs to compensate the respondents for prolonged litigation.
Contentions of Respondents
The respondents argued strict compliance with the decree in the pre-emption suit and that no relief should be granted for non-deposit. They pointed out that the amount deposited was calculated by others and that any shortfall should have been addressed earlier; they highlighted that a belated deposit and condonation petitions should not override the decree. They urged that extension of time in such matters is unwarranted and that the High Court correctly recalled earlier orders; they sought to preserve the procedural course and cost allocations in the interest of finality.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (4)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Johri Singh v. Sukh Pal Singh and Others | [1989] Supp. 1 SCR 17 | Positive | Followed; held that non-deposit of a small fraction due to inadvertent mistake can be remedied by extending time under Section 148 CPC when the mistake is bona fide. |
| Jang Singh v. Brij Lal and Others | [1964] 2 SCR 145 | Positive | Followed; supports discretionary extension under Section 148 CPC in similar contexts. |
| Jogdhayan | [(1983) 1 SCC 26 : (1983) 1 SCR 844] | Mentioned Only | Cited to discuss the principle of actus curiae neminem gravabit and inadvertent error but not treated as controlling authority. |
| AIR 1966 SC 1631 | AIR 1966 SC 1631 | Mentioned Only | Referenced alongside Jang Singh to illustrate related precedent cited in context of actus curiae. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Kanihya @ Kanhi (Dead) Through LRS. v. Sukhi Ram & Ors.
Related Decisions & Precedents from Supreme Court of India (2024)
Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors
This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.
Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others
Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.
Union of India v. M/s Indian Oil Corporation Ltd.
This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.
Gene Campaign & Anr. v. Union of India & Ors.
This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.