Supreme Court of IndiaSupreme Court · 2002Division BenchAppeals allowed; writ petitions dismissed.

KANHAIYA LAL AGRAWAL v UNION OF INDIA

Case / Petition Number:
43594361 of 2002

Case Synopsis & Summary

This Supreme Court decision concerns tendering for supply, delivery and stacking of ballast for Indian Railways. The first respondent invited tenders for five items, including use of 75,000 cubic metres of machine-crushed ballast, with a 24-month supply period. Tender conditions required bids in words and figures, forbade alterations, and mandated that offers be kept open for a minimum of 90 days; breach could lead to forfeiture of security. Five tenders were received. The appellant submitted a tender on 27 February 2001 that, with a covering letter, promised rebates if the bid was accepted within 45, 60, or 75 days, and to use the machinery quickly. Respondent No.5 also offered post-tender rebates. The contract was awarded to the appellant at rates including the rebate, and Respondent No.5 challenged this, claiming his had the lowest rates. The High Court and Division Bench had held that providing rebates as part of the tender or after opening was either impermissible or ineffective, and directed fresh offers. The Supreme Court, while normally reluctant to intervene in government-contract matters, held that a concession offered at the time of tendering to expedite finalization does not violate tender terms, provided it does not contravene the conditions. The Court stressed that the 90-day open period must be observed and that the commercial aspects of offers must be assessed. Accordingly, the appeals were allowed and writ petitions dismissed, with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • S. Rajendra Babu
  • P. Venkatramana Reddi
Judgment Date
2002-07-29
Court Decision / Holding
Appeals allowed; the High Court and Division Bench orders set aside. The tender offers with rebates, whether made at the time of submitting the tender or in advance of finalization, are permissible so long as they do not contravene tender terms; the writ petitions are dismissed with no costs.
Final Disposition
Appeals allowed; writ petitions dismissed.

Parties to the Case

Appellants / Petitioners

  • Kanhaiya Lal Agrawal

Respondents

  • Union of India

Legal Representation & Advocates

Counsels for Petitioners

  • • Prakash Shrivastava

Counsels for Respondents

  • • Anoop Chaudhary
  • • Ranjit Kumar
  • • Shiv Sagar Tiwari
  • • Bishesha Nand Jha
  • • Manish Singhvi
  • • Anil Katiyar

Legal Doctrines & Maxims

  • Essential condition of tender
  • Collateral vs essential terms in tender contracts
  • Commercial prudence

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the rebate offered with the tender was part of the bid itself and not a post-bid modification. The offer was explicit and within the tender’s open timeframe (minimum 90 days). There was nothing illegal or arbitrary in accepting a concession intended to expedite finalization, and such concessions are part of commercial prudence rather than collusive alteration of the tender. The essential term—the open period and the terms of acceptance—was not violated, and the rebate did not defeat the competitive process; it reflected the commercial realities of speedy procurement.

Contentions of Respondents

Respondents argued that rebates or concessions offered after opening the tender amount to attachments to the tender document, effectively altering the tender terms and undermining equality of treatment among bidders. The tender notice did not contemplate such post-tender amendments and the offer to rebate after opening should be disregarded. They urged adherence to the unconditional tender principle and to recall or re-open the bidding process to ensure fairness and non-arbitrariness.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
G.J. Fernandez v. State of Karnataka and Ors.[1990] 2 SCC 488PositiveCited to support the proposition that essential vs collateral conditions in tendering must be distinguished; non-compliance with essential tender terms allows rejection, and concessions tied to the tender can be permissible if they do not alter essential terms.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,829 words•~9 min read

In The Court Record

KANHAIYA LAL AGRAWAL v UNION OF INDIA

A ## KANHAIY A LAL AGRA WAL _v._ ## UNION OF INDIA JULY 29, 2002 B [S. RAJENDRA BABU AND P. VENKATARAMA REDDI, JJ.) _Government Contracts-Supply of material-Invitation of tenders-One of the tenderers offering tender with rebate-Acceptance of such tenderWhether illegal or arbitrary-Held, since such an offer was made at the time_ C _of submission of tender and such an offer was given as an additional inducement to accept the offer expeditiously the acceptance thereof is not illegal or arbitrary._ In these appeals, the question that arose for consideration was D whether the tender offered by the appellant-tenderer with the rebate could have been accepted and whether such acceptance would affect the interests of any other party. ## Allowing the appeals, the Court E E HELD: 1.1. Bureaucratic delay is a notorious fact and delay in finalising tenders will cause hardship to the tenderer. In such circumstances, if a hardened businessman makes an attractive offer of concessional rates if tender is finalized within a shorter period, it cannot be said that the rates offered are offered subject to conditions. The rates offered are clear and. the time within which they are to be accepted is also F clear. As long as such offer does not militate against the terms and conditions of inviting tender it cannot be said that such offer is not within its scope. All that is required is that offer made is to be kept open for a minimum period of 90 days. Offer in compliance of that term has been made by the appellant. The concession or rebate given is an additional G inducement to accept the offer expeditiously to have a proper return on the investment made by the tenderer in the e~uipment and not keeping the labour idle for long periods which is part of commercial prudence. The com~rcial aspect of each one of the offers made by the parties will have to be ascertained and, thereafter a decision taken to accept or reject a tender. [287-E-G) H 284 285 KANHAlYA LAL v. U.O.l. [S. RAJENDRA BABU, J.] 1.2. Appellant made his offer of concessional rates along with the tender while respondent No.5 made such offer after opening of the tenders. It is difficult to conceive that respondent No.5 who is a prudent **businessman would not be aware of commercial practice of giving rebate** or concession in the event of quick finalization of a transaction. What the appellant offered was part of the tender itself while respondent No.5 made such offer separately and much later. There was nothing illegal or arbitrary on the part of Railway Administration in accepting the offer of the appellant, which was made at the time of submitting the tender itself. (288-B-C] _G.J Fernandez_ v. _State of Karnataka and Ors .._ [1990) 2 SCC 488, referred to. CIVIL APPELLATE JURISDICTION Civil Appeal Nos. 43594361 of 2002. From the Judgment and Order dated 27.2.2002 of the Madhya Pradesh High Court in LPA No. 173, 198, 211 of 2001at Jabalpur. D Prakash Shrivastava for the Appellant. Anoop Chaudhary and Ranjit Kumar, Shiv Sagar Tiwari, Bishesha Nand Jha, Manish Singh vi and Anil Katiyar for' the Respondents. The Judgment of the Court was delivered by E ## RAJENDRA BABU, J. Leave granted. The first respondent invited tenders for execution of five items of work including supply, delivery and stacking of75,000 cubic metre Machine crushed track ballast as per specifications at its depot in Naurozabad and loading it F into railway wagons. The supply period was for 24 months. The conditions in the tender notice required that the rates at which supply was to be made had to be stated in words as well as in figures against each item of work as per Schedule attached thereto; that the tenders submitted with any omissions or alteration of the tender document were liable to be rejected; however, G permissible corrections could be attached with due signature of tenderers; that the tenderer should hold the offer open till such date as may be specified in the tender which was for a minimum period of 90 days from the date of opening of the tender; that contravention of the conditions would automatically result in forfeiture of security deposit; that the tender was liable to be rejected for non-compliance of any of the conditions in the tender form. H 286 SUPREME COURT REPORTS [2002] SUPP. I S.C.R. A Five tenders were received. The appellant made his tender on 27.02.2001 with a cove.ring letter that if his offer is accepted within the stipulated time rebate would be offered by him t0 the effect that in case the contract was given to him within 45 days, 60 days and 75 days, he would extend rebate of 5%, 3% and 2% respectively on the rates tendered by him. Respondent No. 5 had made a similar offer but after five days of the opening of the B tender, while the appellant had made such offer of rebate even at the time of making the tender in the letter accompanying the tender documents. However, respondent No. 5 offered to reduce rates by 1.25% if accepted in 30 days and l % if accepted in 45 days. The l st respondent accepted the tender offered by the appellant on the rates subject to rebate. Agreement was entered into by C him on 19.04.2001. Respondent No.5 filed a writ petition claiming that his tender should have been accepted, as the rates offered by him are the lowest. The learned Single Judge, before whom acceptance of the tender offered by the appellant was challenged, took the view that the tender notice did not admit of an offer being made in the form of rebate as offered by the appellant D and it was also clear that an offer made by respondent No. 5 after the opening of the tender is of no consequence and gave the direction of taking fresh offers from the appellant and Respondent No. 5. The matter was carried in appeal to the Division Bench. The Division Bench, after adverting to several decisions on the question of award of contracts, stated that the tender notice E did not contemplate any attachment of conditions by giving rebate which would amount to alteration of the tender document which is impermissible; that the tender should be unconditional and relaxation, if any, should have been notified to all the tenderers to enable them to change their rates; that all the tenderers should have been treated equally and fairly, and on that basis, took the view that the tender of Respondent No.5 is at a lower rate and hence, F acceptable and set aside the order of the learned Single Judge directing fresh negotiations with the parties. The Division Bench directed that supply of material by the appellant be stopped forthwith and balance material be taken from Respondent No.5 at the rate furnished by him. Hence, these appeals against the order of the High Court. G This Court is normally reluctant to intervene in matters of entering into contracts by the Government, but if the same is found to be unreasonable, arbitrary, _malafide_ or is in disregard of mandatory procedures it will not hesitate to nullify or rectify such actions. H lt is settled law that when an essential condition of tender is not complied . KANHAIYA LAL _v._ U.0.L [S. RAJENDRA BABU. J.] 287 with, it is open to the person inviting tender to reject the same. Whether a A condition is essential or collateral could be ascertained by reference to consequence of non-compliance thereto. If non-fulfilment of the requirement results in rejection of the tender, then it would be essential part of the tender otherwise it is only a collateral term. This legal position has been well explained in _G.J. Fernandez_ v. _State of Karnataka and Ors.,_ [ 1990] 2 SCC 488. B In the present case, the short question that falls for consideration is whether the tender offered by the appellant with the rebate could have been accepted and whether such acceptance would affect the interests of any other party. The letter dated 27.2.2001 accompanying the tender made by the C appellant after setting out rate offered by him also set out certain circumstances with a note in the following terms :- - "Note :- I would like to offer if the tender is finalised in my favour: - (a) 5% reduction in rate within 45 days; D - (b) 3% reduction in rate within 60 days; - (c) 2% reduction in rate within 75 days; - (d) to make use of the machinery at the quickest possible time." Bureaucratic delay is a notorious fact and delay in finalising tenders will cause hardship to the tenderer. In such circumstances, if a hardened businessman makes an attractive offer of concessional rates iftender is finalized within a shorter period, it cannot be said that the rates offered are subject to conditions. The rates offered ·are clear and the time within which they are to be accepted is also clear. As long as such offer does not militate against the F terms and conditions of inviting tender it cannot be said that such offer is not within its scope. All that is required is that offer made is to be kept open for a minimum period of 90 days. Offer in compliance of that term has been made by the appellant. The concession or rebate given is an additional inducement to accept the offer expeditiously to have a proper return on the investment made by the tenderer in the equipment and not keeping the labour G idle for long periods which is part of commercial prudence. The commercial aspect of each one of the offers made by the parties will have to be ascertained and, thereafter a decision taken to accept or reject a tender. > The Division Bench of the High Court proceeded on the basis that the H 288 SUPREME COURT REPORTS [2002] SUPP. I S.C.R. A offer of concession is contrary to the terms of tender but we have demonstrated to the contrary. Now the appellant made his offer of concessional rates along with the tender while Respondent No.5 made such offer after opening of the tenders. It is difficult to conceive that the Respondent No.5 who is a prudent B businessman would not be aware of commercial practice of giving rebate or concession in the event of quick finalization of a transaction. What the appellant offered was part of the tender itself while the Respondent No. 5 made such offer separately and much later. There was nothing illegal or arbitrary on the part of Railway Administration in accepting the offer of the C appellant, which was made at the time of submitting the tender itself. In the result, we allow these appeals by setting aside the orders made by the High Court both by the Division Bench and the learned Single Judge and dismiss the writ petition. No costs. D N.J. Appeals allowed.
End of Judgment Record
Browse All Supreme Court of India (2002) Decisions
2002-12-17

Devender Pal Singh v. State N.C.T. of Delhi

This judgment deals with three review petitions under Article 137 of the Constitution challenging the death sentence in cases involving murder. The petitions focus on whether death should be imposed when one of the three Judges on the bench records acquittal or advocates a life sentence. The Court clarifies that while the scope of review in criminal proceedings has broadened, a review is not a re-hearing of the original appeal and must be grounded in a miscarriage of justice. Review petitions are normally disposed of by circulation, not as full-blown re-arguments, and are permissible only where there is a grave error, manifest on the face of the order, or a miscarriage of justice. The opinion cites P.N. Eswara Iyer and Suthendraraja to stress that review is not routine and cannot be equated with the original hearing; the finality of judgments is preserved unless compelling reasons exist. The majority holds that a death sentence should not be reconsidered merely because two Judges share a different view than one Judge, nor should acquittal by a lower court automatically negate the Possibility of a death sentence if the circumstances still warrant it. The judgment also discusses the “rarest of rare” standard from Bachan Singh and the scope of reference to a larger Bench. A dissent by Shah, J. proposes that altering the death sentence to life imprisonment would meet justice in some cases, but the majority dismisses the petitions.

2002-04-24

Narpat Singh v Jaipur Development Authority

This Supreme Court decision concerns the long-running dispute over land acquired under the Lal Kothi Scheme in Jaipur. Land belonging to four appellants was acquired for a public purpose and an award awarded monetary compensation along with directions to allot residential plots of 1000 or 2000 square yards. On reference, courts enhanced the monetary compensation while upholding the plot allotments. A tripartite settlement among the claimants, the State Government and the Urban Improvement Trust ( UIT, later Ja ipur Development Authority, JDA) reduced the compensation in exchange for plot allotments, with contestants paying a reduced price to acquire plots. Executions proceeded and plots were delivered. The High Court later set aside the compromise decree, holding that the allotment of land by an award in land acquisition proceedings lacked jurisdiction and was inexecutable, relying on precedents such as Jaipur Development Authority v. Radhey Shyam and Secretary v. Daulat Mal Jain. The Supreme Court, while acknowledging the discretionary nature of Article 136, held that this case does not justify upsetting the compromise. It directed the state to restore appeals for merits and to determine quantum of monetary compensation excluding plots, while also directing allotment of smaller plots (about 250 sq yards) in another scheme within three months to maintain consistency with earlier judgments. The land must be used for the public purpose for which it was acquired. The appeals were disposed of with these directions under Article 142 for complete justice.

2002-11-13

Shrawan Bhadaji Bhirad and Ors. v. State of Maharashtra

Shrawan Bhadaji Bhirad and others, members of the Bhirad family, were convicted by an Additional Sessions Judge under sections 147, 148 and 307 read with section 149 IPC for forming an unlawful assembly and assaulting Ganesh Dhage with swords, causing extensive injuries and a prolonged hospitalisation. Ganesh Dhage survived and implicated the appellants, naming them in the dying/dependant statements, which were corroborated by eyewitnesses. The High Court upheld the Sessions Court’s conviction, rejecting the appellants’ contention that the victim did not know the assailants’ names and that the names were a product of enmity. In appeal, the appellants argued that their alleged involvement had no basis and was speculative. The Court emphasised that the dying declaration, though recorded after severe injuries and while the victim was in medical care, had significant content; and even if considered under Section 164 CrPC rather than as a strict dying declaration, it remained corroborated by the testimony of the eye-witnesses. The Court found overwhelming evidence on record supporting the prosecution’s case and concurred with the concurrent findings of the Sessions Judge and the High Court. Accordingly, the appeal was dismissed, bail bonds cancelled, and the appellants were to serve the remainder of their sentences.

2002-10-10

Alla China Apparao and Ors. v. State of Andhra Pradesh

Alla China Apparao and six co-accused were convicted by the trial court under Sections 302/149 and 148 of the IPC, and each was sentenced to life imprisonment, with a concurrent one-year term on the 148 IPC count and a fine. The High Court affirmed the convictions against the appellants while acquitting three others. The prosecution’s case rests on four eyewitnesses who say the deceased was attacked near his house, dragged to a wall, and slain by multiple appellants; medical and objective evidence were said to corroborate the eyewitnesses. The appellants contend that the three acquitted co-accused show the same evidence cannot justify conviction of the others; the witnesses were partisan, and there was no independent corroboration; the lack of injuries beyond what witnesses described and alleged dragging marks undermine the case; and a delay in forwarding the FIR to the Magistrate merits acquittal. The State argues the eyewitnesses were credible, corroborated by medical evidence and police findings, that non-examination of other witnesses is not fatal, and that the absence of dragging marks or blood on weapons does not negate the prosecution. The Court holds that eyewitness credibility is supported by evidence, the delay was within reasonable limits given workload, and the case remains trustworthy. The appeal is dismissed and the convictions upheld.