High Court of KeralaSingle JudgeDisposed of

Kanakamma and Others v. State of Kerala and Others

Case / Petition Number:WP(C).No. 586 of 2014 (W)

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K. Vinod Chandran
Judgment Date
2015-02-03
Court Decision / Holding
The writ petition is disposed of. The court directs the respondents (2nd and 3rd) to expedite recovery proceedings and conclude them within three months from today.
Final Disposition
Disposed of

Parties to the Case

Appellants / Petitioners

  • Kanakamma
  • Ammukutty Amma
  • Sajeev
  • Sajith

Respondents

  • State of Kerala
  • District Collector, Kollam
  • Tahsildar (RR), Kollam
  • Commissioner for Workmen's Compensation & Deputy Labour Commissioner, Kollam
  • Sri. Baiju Ambalakkara, Kottarakkara

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri O.V. Maniprasad
  • • Sri Saju J Panicker

Counsels for Respondents

  • • Sri R. Renjith (Government Pleader)
  • • Sri Praveen K. Joy
  • • Sri T.A. Joy

Case Synopsis & Summary

The petitioners, legal heirs of a deceased workman, challenge the non-recovery of an award amount under the Workmen’s Compensation Act. Ext. P1 records an award of Rs. 2,80,350 with 12% simple interest (from 20-11-2004) by the Workmen’s Compensation Commissioner, Kollam, in WC Case No. 50/2005, which was issued in relation to an industrial injury of the deceased employee. The petitioners sought enforcement via the Revenue Recovery Act, 1968, arguing that recovery of such amounts falls within the special recovery machinery under the revenue act, and that recovery was initiated promptly, evidenced by RTI disclosures (Ext. P4) showing a show-cause to the fifth respondent and a statement that an appeal had been filed before the High Court. The Industrial Tribunal’s notification as the Employees’ Compensation Commissioner and the subsequent execution steps (29-08-2011 and in 2013) form the factual matrix. The fifth respondent contends limitation bars recovery, relying primarily on a Full Bench decision (Perumbavoor Municipality v. Assistant Engineer). The petition questions whether the manner of recovery should be governed by the Revenue Recovery Act or by other statutory limits, asserting that recovery has proceeded despite a pending appeal. The High Court ultimately disposed of the petition, directing that the recovery proceedings be expedited and concluded within three months.

Provisions of Law Cited

Revenue Recovery Act, 1968 (Kerala) — Section 71Employees' Compensation Act, 1923 — Section 31Limitation Act, 1963 — Article 137Right to Information Act (RTI) (as referenced)

Legal Doctrines & Maxims

  • Public revenue due on land doctrine
  • Recovery under the Revenue Recovery Act rather than civil decree; limitation determined by statute under which recovery is sought.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contend that the Workmen's Compensation Award (Ext. P1) ought to be recoverable through the Kerala Revenue Recovery Act, 1968, and that revenue recovery proceedings were initiated promptly, with RTI evidence (Ext. P4) showing action and the possibility of an appeal pending in the High Court. They argue that the prior order of the Workmen's Compensation Commissioner creates a duty to recover, and that limitation should not bar proceedings since recovery steps were commenced within the statutory framework; they emphasize that the Industrial Tribunal’s notification does not alter the applicability of the Revenue Recovery Act to the recovery process.

Contentions of Respondents

The fifth respondent contends that the claim is barred by limitation and relies on a Full Bench decision (Perumbavoor Municipality v. Assistant Engineer) to argue that the manner of recovery under Revenue Recovery Act does not convert the dues into public revenue on land with that immunization from limitation. They also point to the pending appeal and deposit issues, suggesting that these facts impede immediate recovery.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Perumbavoor Municipality v. Assistant Engineer2015 (1) KLT 95DistinguishedThe Full Bench decision discussed whether notification under Section 71 of the Revenue Recovery Act would render dues as public revenue due on land. The present case concerns recovery under the Revenue Recovery Act and the petitioners seek recovery as public revenue; the court held this decision not applicable to the current context, distinguishing it on the ground that the present case involves recovery under the Revenue Recovery Act rather than treating the dues as land-based public revenue.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Kanakamma and Others v. State of Kerala and Others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT:** ## **THE HONOURABLE MR.JUSTICE K.VINOD CHANDRAN** ## **TUESDAY, THE 3RD DAY OF FEBRUARY 2015/14TH MAGHA, 1936** ## **WP(C).No. 586 of 2014 (W)** **--------------------------------------** ## **PETITIONERS:** ## **--------------------** **1. SMT.KANAKAMMA, AGED 48 YEARS** - **W/O.LATE THULASEEDHARAN , RESIDING AT VATTAKKATTU THEKKATHIL THATTARKONAM P O, KOLLAM DISTRICT.** **2. AMMUKUTTY AMMA, AGED 80 YEARS M/O.LATE THULASEEDHARAN , RESIDING AT VATTAKKATTU THEKKATHIL THATTARKONAM P O, KOLLAM DISTRICT.** **3. SAJEEV, AGED 26 YEARS S/O.LATE THULASEEDHARAN , RESIDING AT VATTAKKATTU THEKKATHIL THATTARKONAM P O, KOLLAM DISTRICT.** ## **4. SAJITH, AGED 24 YEARS** - **S/O.LATE THULASEEDHARAN , RESIDING AT VATTAKKATTU THEKKATHIL THATTARKONAM P O, KOLLAM DISTRICT.** **BY ADVS.SRI.O.V.MANIPRASAD SRI.SAJU J PANICKER** **RESPONDENTS:** - **-----------------------** ## **1. STATE OF KERALA,** - **REPRESENTED BY ITS SECRETARY TO GOVERNMENT REVENUE DEPARTMENT, GOVERNMENT SECRETARIAT THIRUVANANTHAPURAM-695001.** **2. THE DISTRICT COLLECTOR, KOLLAM-691001.** **3. THE TAHSILDAR (RR), TALUK OFFICE, KOLLAM-691001.** **4. THE COMMISSIONER FOR WORKMEN'S COMPENSATION & DEPUTY LABOUR COMMISSIONER, KOLLAM-691001.** ## **5. SRI.BAIJU,** ## **AMBALAKKARA, KOTTARAKKARA P O, KOLLAM-691506.** **R1-4 BY GOVERNMENT PLEADER SRI.R.RENJITH R5 BY ADVS. SRI.PRAVEEN K. JOY SRI.T.A.JOY** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 03-02-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **PJ** ## **WP(C).No. 586 of 2014 (W) -------------------------------------** ## **APPENDIX** ## **PETITIONER(S)' EXHIBITS -------------------------------------** - **P1:TRUE COPY OF THE JUDGMENT DTD 29/6/2011 IN WCC NO 50/2005 OF THE 4TH RESPONDENT** - **P2:TRUE COPY OF THE INTIMATION OF JUDGMENT BY THE 4TH RESPONDENT DTD 29/6/2011 TO THE 5TH RESPONDENT** - **P3:TRUE COPY OF THE APPLICATION DTD 31/7/2013 SENT UNDER THE RIGHT TO INFORMATION ACT** - **P4:TRUE COPY OF THE REPLY DTD 3/8/2013 GIVEN BY THE 4TH RESPONDENT** - **P5:TRUE COPY OF THE REQUEST FILED BEFORE THE CHIEF MINISTER OF KERALA BY THE PETITIONERS** **RESPONDENT(S)' EXHIBITS** **---------------------------------------** **NIL.** ## **/ TRUE COPY /** **P.S. TO JUDGE** **PJ** ## **K.VINOD CHANDRAN, J** - - - - - - - - - - - - - - - - - - - - W.P.(C).No. 586 of 2014 - - - - - - - - - - - - - - - - Dated 3[rd] February, 2015 - - - - - - - - - - - - - - - - - - - - - - - - ## **JUDGMENT** The petitioners are aggrieved with the non recovery of the amounts as specified in the judgment of the Commissioner For Workmen's Compensation at Ext.P1. Admittedly, at present, the Industrial Tribunals are notified as the Employees Compensation Commissioner and in the present case, the Industrial Tribunal, Kollam. 2. The petitioners are the legal heirs of a deceased workman who was employed under the 5[th] respondent. The predecessor of the petitioners having died pursuant to an employment injury, claimants were before the Workmen's Compensation Commissioner which claim was allowed as per Ext.P1 and an amount of Rs.2,80,350/- was directed to be paid together with simple interest at the rate of 12% from 20.11.2004. In fact, the petitioners had **WP(C).586/14** 2 sought for recovery proceedings under the Revenue Recovery Act, 1968 (Kerala), since the Employees Compensation Act, 1923, by Section 31 provides for recovery of the amounts awarded by way of revenue recovery. 3. The petitioners had immediately after the Award, proceedings, initiated recovery proceedings which is evident from the communication addressed to the petitioners under the Right To Information Act produced at Ext.P4. The said communication is dated 03.08.2013. To a specific query, the Public Information Officer had informed the petitioners that as part of the revenue recovery proceedings, show cause notice was issued to the 5[th] respondent herein and that the 5[th] respondent had informed the Office that an appeal has been filed before the High Court of Kerala against the order of the Workmen's Compensation Commissioner, Kollam. It was also clarified that no amount has been deposited before 3 ## **WP(C).586/14** the Office of the Regional Joint Labour Commissioner who was the then Workmen's Compensation Commissioner. Hence, the revenue recovery proceedings were issued by the Workmen's Compensation Commissioner within three years of the Award. 4. Specifically when the Industrial Tribunal was notified, the petitioners were again before the Tribunal for initiation of revenue recovery proceedings which the Tribunal has initiated by order dated 29.08.2014. This Court had asked for a report from the Tribunal and it has been stated that in pursuance to the Execution Petition filed by the applicants in W.C.C.50 of 2005 steps have been taken for recovery on 29.08.2011. That was necessitated only since the Industrial Tribunals are now notified as the Employees Compensation Commissioner. **WP(C).586/14** 4 5. The learned counsel appearing for the 5[th] respondent would submit that the claim is barred by limitation and no proceedings under the Revenue Recovery Act, 1968 could be taken against the 5[th] respondent. The 5[th] respondent specifically relies on a Full Bench decision of this Court reported in **Perumbavoor Municipality v. Assistant Engineer (2015 (1) KLT 95)** . The only issue considered in the aforesaid decision was whether on a notification being issued under Section 71 of the Revenue Recovery Act, 1968, the amounts recoverable would get the character of public revenue due on land or not. It was declared that such notification would only enable recovery under the Revenue Recovery Act and the dues would not get the character of public revenue due on land. Hence, the limitation applicable would be governed by the terms of the specific statute, under which the amounts are levied. The said decision would not be applicable in the present case, since the petitioners seek **WP(C).586/14** 5 recovery as a 'public revenue due on land' not in form, avoiding the laws of limitation; but only by procedure sanctioned under the Revenue Recovery Act. 6. The further contention raised by the learned counsel is that the order sought to be executed, not being a decree of a Civil Court, what would apply is Article 137 of the Limitation Act, 1963 and only three years would be provided for making such an application. It is to be noticed that the petitioners had prior to Ext.P4, initiated recovery proceedings, ie, prior to 03.08.2013. the Award was dated 27.09.2011. In such circumstances, no grand of limitation could be urged against the claimant to interdict recovery under the Revenue Recovery Act. On a specific query made, it is submitted by the learned counsel appearing for the 5[th] respondent that though an appeal against Ext.P1 order was filed as early as in 2011, the same is not numbered till date since it is defective for ## **WP(C).586/14** **==> picture [7 x 9] intentionally omitted <==** want of deposit of the Award amounts. In such circumstances, it is very evident that the 5[th] respondent is evading recovery on the ground of a defective appeal. Respondents 2 and 3 shall expedite the recovery proceedings and conclude it, at any rate, within a period of three months from today. With the above observation, the writ petition is disposed of. Sd/- ## **K.VINOD CHANDRAN Judge** Mrcs //True Copy//