Supreme Court of IndiaSupreme Court · 1997Division BenchPetition disposed of; no order as to costs.

Kamini Jaiswal v. Union of India and Ors.

Case / Petition Number:
Writ Petition (C) No. 714 of 1994
Neutral Citation:1997 (2) S.C.R. 651

Case Synopsis & Summary

Kamini Jaiswal, a practising advocate, filed a public interest petition under Article 32 of the Constitution seeking closure of high‑pressure gas pipelines laid by GAIL and ONGC until an independent inquiry by experts certifies their safety. The petition arose from a gas leak at Dhaula Kuan, Delhi, on 8 July 1993. The petitioner alleged that the DESU‑Maruti Spurline had not been laid in accordance with applicable international standards, such as ANSI/ASME B31.8 of 82, and that the terms of the contract with the pipeline contractor had not been complied with. She urged independent certification and, if necessary, closure of the pipelines until safety was established. GAIL filed a detailed reply and produced three expert reports on the DESU‑Maruti Spurline and the safety of its pipeline system. The company argued the contractor defaulted in several respects, that the leakage resulted from defective workmanship, and that it terminated the contract. A committee and a Sofregaz post‑construction survey found that tender specifications were clear and adequate, though some lapses occurred; the survey reported no alarming deficiencies in the pipeline network. GAIL highlighted that pipelines nationwide are laid to stringent standards, with corrective measures implemented, ISO 9002 certification, and safety awards. The Court held that no further directions were required and disposed of the petition, noting no cost orders, emphasizing the sufficiency of the information and measures taken by GAIL.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • A. M. Ahmadi
  • Sujata V. Manohar
  • K. T. Thomas
  • bench_type_placeholder
Judgment Date
1997-03-04
Court Decision / Holding
Petition disposed of. No further directions are required. There will be no order as to costs.
Final Disposition
Petition disposed of; no order as to costs.

Parties to the Case

Appellants / Petitioners

  • Kamini Jaiswal

Respondents

  • Gas Authority of India Ltd. (GAIL)
  • Oil and Natural Gas Corporation Ltd. (ONGC)
  • Central Pollution Control Board
  • Union of India

Legal Representation & Advocates

Counsels for Petitioners

  • • V. R. Reddy
  • • R. Sasiprabhu
  • • Gopal Singh
  • • Vijay Panjwani
  • • Ms. Manjula Gupta
  • • Ms. Niranjana Singh

Counsels for Respondents

  • • Ms. Anil Katiyar
  • • A. Subba Rao

Provisions of Law Cited

Article 32, Constitution of India, 1950

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that the high‑pressure pipelines laid by GAIL and/or ONGC are unsafe in specified locations and potentially hazardous. She seeks closure until independent expert inquiry certifies safety, arguing the DESU‑Maruti Spurline was not laid per applicable international standards (ANSI/ASME B31.8 of 82) and that contract terms were not complied with, including safeguards for gas leakage detection, automatic shutting down systems, depth of cover, and adequate separation from human settlements. She also asserts lack of clearance from the Department of Explosives and questions supervision and workmanship by the contractor.

Contentions of Respondents

GAIL responds with affidavits and three expert reports, contending that the contractor defaulted and that leakage resulted from defective workmanship. A committee identified lapses but found tender specifications clear and adequate; a Sofregaz post‑construction survey reported no alarming deficiencies and that safety measures were implemented. GAIL emphasizes extensive safety programs, global standards compliance, ISO 9002 certification, and ongoing improvements, arguing no further directions are warranted and the petition should be disposed of.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,918 words•~14 min read

In The Court Record

Kamini Jaiswal v. Union of India and Ors.

A ## MS. KAMINI JAISWAL, ADVOCATE· ## _v._ ## UNION OF INDIA AND ORS. ## MARCH 4, 1997 ## B ## [A.M. AHMADI, CJ. SUJATA V. MANOHAR AND K.T. THOMAS, JJ.] _Constitution of India, 1950 : Article 32-Public Interest Litigatio.rt-Filed by an Advocate for closure of gas pipelines laid by GAIL and_ C _ONGC until an independent inquiry by experts is conducted and they certify and declare that these pipelines are safe for further operation-Petition resulted from actual gas leakage from the gas pipelines near Dhaula Kuan in New Delhi-Held, no further action is required in view of the detailed infonnation furnished by GAIL and the necessary preventive measures taken by it._ D The petitioner filed the present public interest petition under Article 32 of the Constitution of India. The petitioner contended that the high pressure gas pipelines laid by GAIL and/or ONGC were unsafe in certain specified places and were potentially hazardous. She prayed for the closure of the pipelines until an independent inquiry was conducted and they E certified and declared that those pipelines were safe for further operation. She contended that the pipelines had not been laid as per applicable international standards, ANSl/ASME B 31.8 of 82. The specific averments in the petition related to the DESU Maruti Spurline laid by GAIL. According to the petitioner, the terms and conditions on which GAIL had given F the contract for laying the pipeline had not been complied with. G. GAIL filed a detailed affidavit in reply to the petitioner's allegations. It also filed detailed technical material on the subject, as well as three reports of experts in connection with the laying of the DESU-Maruti Spurline and in connection with the safety of its pipeline system. GAIL submitted· that in laying tbe DESU-Maruti Spurline the contractor defaulted in many ways and the gas leakage at Dhaula Kuan was the result of defective workmanship. After that, the contract was terminated. GAIL appointed a committee to pinpoint lapses and to suggest H corrective measures. The committee noted that the specifications in the 650 651 KAMINIJAISWAL, ADV. _v._ U.O.I. tender were very clear, exhaustive and adequate to take care of the safety A aspects but some of the specifications were not taken care of by the contractor. The committee submitted a detailed report containing sugges· tions for quality compliance in totality. GAIL also carried out a post-construction integrity survey through B Sofregaz, an international agency known for its expertise in the area. It was asked to carry out investigation and report whether safe engineering practices had been followed during the construction of the existing underground pipelines. It was required to report on the stat11s of pipelines, critical areas, preventive measures, disaster management plan, remedies and recommendations. The report provided that on general C assessment there was no apparent alarming deficiency in the pipelines in respect of safe operation and safety of life and property. As regards the depth ·of cover over the pipelines, it considered it to be wen within the acceptable limit with reference to the standard followed by GAZ DE FRANCE in normal condition of operation. GAIL took action in com- D pliance with each of the recommendations contained in the Sofregaz report. It was pointed out that the expert report of Sofregaz was the outcome of a post-construction integrity survey for pipelines in and around Delhi. E GAIL pointed out that high . pressure gas pipelines owned and operated by it across the country were laid as per international standards and in fact even more stringent standards . than the international code ANSI 31.8. A detailed status report was also submitted dealing with di".erse aspects of maintenance of the pipeline network in the country. The streamlining of pipelines achieved over a period led to GAIL obtaining certification by International Organisation for Standardization (ISO 9002) and conferment of the Oil Industry Safety Award to GAIL for the year 1992-93. GAIL took important decisions to streamline the procedures in the matter of execution of works. F G ## Disposing of the writ petition, this Court HELD: No further directions are required as GAIL.has been at pains to allay the apprehensions expressed by the petition. No further . action is required in view of the detailed information furnished by GAIL H 652 SUPREME COURT REPORTS [1997] 2 S.C.R. A and the measures taken by it. [657-A-B] CIVIL ORIGINAL JURISDICTION : Writ Petition (C) No. 714 of 1994. (Under Article 32 of the Constitution of India.) B In-person for the Petitioner". V.R. Reddy, R. Sasiprabhu, (Gopal Singh) (NP), Vijay Panjwani (NP), Ms. Manjula Gupta, (Ms. Niranjana Singh) for Ms. Anil Katiyar and A Subba Rao for B.K. Prasad for the Respondents. c The Judgment of the Court was delivered by MRS. SUJATA V. MANOHAR, J. The petitioner is a practising advocate. She has filed the present petition as a public interest petition under Article 32 of the Constitution of India. The respondents are the Gas D Authority of India Ltd. (hereinafter referred to as 'GAIL'), the Oil and Natural Gas Corporation Ltd. (hereinafter referred to as 'ONGC), the Central Pollution Control Board and the Union of India. The petitioner contends that the high pressure gas pipelines laid by GAIL and/or ONGC are unsafe in certain specified places and are potenE tially hazardous. The petitioner has prayed that these pipelines should be closed until an independent enquiry by experts certifies and declares that these pipelines are safe for further operation. The petition was filed pursuant to gas leakage from a high pressure gas pipeline. of GAIL at Dhaula Kuan in Delhi on or about 8th of July, 1993. F GAIL was formed in the year 1984 for the purpose of handling natural gas related .activities. Originally ONGC had planned the HBJ pipeline which was to run from Hazira to Babrala and Jagdishpur for supply of gas to the fertilizer and power plants enroute. This pipeline was taken over by GAIL from ONGC in the conceptualisation stage itself. G Subsequently, GAIL added additional pipelines and spurline to the HBJ pipeline. ONGC had also laid around 680 kms. of pipelines in various locations of the country such as the Gujarat region, Assam region, Bombay region, K.G. Basin, Cauvery basin etc. All these pipelines were transferred to GAIL during the period 1994-95. According to GAIL, a health check of all these lines was carried out when it took over these pipelines. After H the check, necessary corrective action which included replacement of some .. ## KAMINIJAISWAL,ADV. _v._ U.O.I. [MRS. SUJATA V.MANOHAR,J.] 653 of the pipelines was also taken by GAIL both from the safety point of view as well as operational point of view. As of now, GAIL operates a total of 2974.856 kms. of pipelines. · The petitioner has contended that the ·pipelines have not been laid as per applicable international standards ANSl/ASME B 31.8 of 82. The specific averments in the petition relate to the DESU- Maruti Spurline laid B by GAIL which admeasures about 35 kms. According to the petitioner, the terms and conditions on which GAIL had given the contract for laying this pipeline have not been complied with. She contends that gas leakage detection and automatic shutting down system has not been provided. Tele supervisory system is not provided. Gas pipeline was required to be buried C at least 1.5 meters below the ground. But the gas pipeline has not been so laid. The gas pipeline was required to be laid keeping adequate distance from human settlements but this has also not been done and lastly she contends that GAIL has not obtained clearance from the Department of Explosives. She has alleged lack of experi,ence, lack of supervision . or control by GAIL officials and mismanagement by GAIL so that the con- D tractors have used sub-standard material and bad workmanship in laying the pipeline in violation of the safety guidelines. This resulted in gas foakage from this pipeline at Dhaula Kuan on 8th July, 1993. GAIL has filed a detailed affidavit in reply to these allegations. It E has laid before us three reports of experts in connection with the laying of the DESU-Maruti Spurline as also in connection with the safety of its pipeline system. GAIL has also furnished to us detailed technical material in connection with the allegations made by the petitioner. F GAIL has submitted that it had decided to lay the DESU-Maruti Spurline which is a short line by using their in-house experience. They had given a contract for the laying of this pipeline stipulating all the necessary conditions ensuring safety of the system. The contractor, however, defaulted in many ways while laying this pipeline. Ultimately GAIL was compelled to terminate his contract. There is an arbitration pending be- G tween Gail and the contractor in .connection with the defective workmanship and the termination of the contract. GAIL contends that it was this defective workmanship which led to the gas leakage at Dhaula Kuan. In connection with this accident GAIL set up a committee consisting of the Additional Director, Oil Industry Safety Directorate and two GAIL of- H 654 (1997] 2 S.C.R. ## SUPREME COURT REPORTS A ficers not connected with the project to report on the investigation of the failure of the DESU-Maruti pipeline at Dhaula Kuan. This report was placed before us. The committee has reported that (a) the area near Dhaula Kuan being rocky normal mode of trenching using explosives was not possible due to close proximity to traffic/habitations. Hence manual B rock cutting had to be done. Consequently, against the tender specifications of 1.5 meter soil cover, about 1.0 meter cover could be achieved. (b) The space constraints with dense traffic near Dhaula Kuan restricted the use of conventional pipe lowering machinery for extended hours. ( c) Necessary and sufficient details of existing utilities like underground cables, pipes were not available from civic authorities. ( d) On excavation of the C leakage affected area, it was observed that the bottom of the pipeline was found to be resting on a cable. ( e) Inspection of buried pipeline route revealed soil settlement at various locations near Dhaula Kuan Park Area after heavy rains. This caused accumulation of stagnant water in some areas. One of the factors noted by the committee was that none of the D persons associated with supervision of the job were aware about the existence of a cable underneath the pipe. Hence the HDPE Sheet which is normally placed between the pipeline and the cable had not been placed. We need not examine at length the various facts found by the committee as leading to that accident. What is more important, GAIL set E up an internal committee to pin-point the lapses and to suggest corrective measures. This committee's report is also produced before us. The committee noted that the specifications in the tender were clear, exhaustive and adequate to take care of the safety aspects. However, some of the specifications as set out in the report were not taken care of by the contractor. It F noted that some of the construction activities may not have been inspected by GAIL personnel or the inspection report may not represent the real status of the activity. The committee has commented upon trenching work and the fact that the cover of the pipe was at some places even less than 1.0 meter although the tender specification was 1.5 meters. This may be on account of the rocky soil and the prohibition on the use of explosives on G account of the vicinity of the area to habitation. It commented on the defects in the inspection reports. It was also pointed out that thickness of the compacted padding on top of pipe corrosion coating should have been at least 150 MM. Padding material should have been graded soiVsand and/or other materials containing no gravel, rock or lumps of hard soil. H Such padding material has not been observed at various points during the ## KAMIN! JAISWAL, ADV. _v._ U.0.1. [MRS. SUJATA V. MANOHAR,J.) _655_ inspection. The report is a very detailed report setting out other defects A also. It has made various suggestions;· some of the suggestions being that (1) GAIL should deploy third party - Inspecting Agency for such activities of pipe laying; (2) That GAIL should supervise and monitor the activities on the third party inspecting agency and the activities of the contractor in respect of the compliance of tender specification; (3) That no deviation B should be permitted by Engineer Incharge; (4) Necessary formats should be developed to ensure total conformity to the specification requirements; (5) GAIL Engineers and Supervisors should be given training programmes and (6).GAIL should have own quality audit cell for overviewing the quality compliance in totality. c GAIL also carried out a post-construction integrity survey through Sofregaz, an international agency known for its expertise in this area. Sofregaz was asked· to carry out investigation and report whether safe engineering practices have been followed during construction of the existing underground pipelines; (2) to ascertain whether the pipeline has been· D laid as per standard construction specification/codes and to review the _QNQC_ procedures, namely, welding procedure specifications, material specifications, coating and cathodic protection and to recommend modifications/improvements wherever required. It was also required to carry out other detailed examinations as set out in its terms of reference. E It was also, inter alia, asked to identify potential possible hazardous situations and measures to control quickly any leak/burst etc. It was required to report on the status of pipeline, critical areas, preventive measures, disaster management plan, remedies and recommendations. Sofregaz report sets out that on its general assessment there was no apparent alarming deficiency in the pipelines with respect to safe operation and F safety of life and property. GAIL shouid, whoever, take action to attend to the points listed in the minutes of the discussions for further improvement of long term safety of the pipelines. It also said that based on the survey of th depth of cover ,over the pipelines to the extent observed, it considers it to be well wi~hin the acceptable limit with reference to the standard G . followed by GAZ DE FRANCE in normal condition of operation. As such it was not necessary to undertake further lowering of the pipeline from the .present state of cover to the extent observed. The detailed point-by-point action plan of Sofregaz and the action consequently taken by GAIL In connection with each of the recommendations has been set out in detail as H 656 SUPREME COURT REPORTS [1997] 2 S.C.R. A Annexure 2 to the report of Sofregaz. GAIL has pointed out that the expert report of Sofregaz is the outcome of a post-construction integrity survey for pipelines in and around Delhi. A technical survey by an independent agency was considered necessary in view of the fact that the Delhi pipeline network was the first urban and sub-urban gas distribution system executed· B by GAIL. A decision to have such a survey through international competitive bidding by an experienced international company was· taken on 22.6.1993 even prior to the occurrence of the gas leak at Dhaula Kuan. The . cost of such technical audit is part of the approved cost of the project itself. A detailed status report has also been submitted dealing with diverse C aspects of maintenance of the pipeline network in the country. It deals with the health check of the pipelines taken over from ONGC and the operation and maintenance control of the entire pipeline system in the country. The streamlining of procedures achieved over a period has led to GAIL obtaining certification by international Organisation for Standardization (ISO D 9002) and conferment of the Oil Industry Safety Award to GAIL for the year 1992-93. GAIL has also pointed out that high pressure gas pipelines owned and operated by it across the country are laid as per international standards and in fact GAIL has prescribed even more stringent standards than the international code ANSI 31.8. It has annexed a comparative table E in which, _inter alia,_ the minimum cover of a pipe under ANSI is 75 ems. while GAIL has prescribed 75 ems. to 1.5 meters. GAIL has also taken the following important decisions to streamline the procedures in the matter of execution of works : F - (i) To have a 3-layer polythene coating which has a higher resistance to handling damage; - (ii) To execute the work with an overall consultancy by third party agency with backup consultant; G - (iii) To have inspection both during procurement as well as construction by third party agencies along with the check inspecting agency in addition to an audit group of GAIL consisting of persons from a project other than the particular projects being audited; and H - (iv) To provide all future pipeline systems with optical fibre cable KAMINI JAISW AL, ADV. _v._ U.O.I. [MRS. SUJATA V. MANO HAR, J.] 657 links to the various nodal points to ensure safe communication. A Looking to the detailed information furnished by GAIL and the measures taken by it as set out in the material which is disclosed by GAIL, we do not think any further action is now required to be taken by this Court. GAIL has been at pains to allay the apprehensions expressed by the petitioner. Looking to the material on record, we do not think that any B further directions are required. The petition is accordingly disposed of. There will be no order as to costs. J.N.S. Petition disposed of. -I
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.