Tenetowl LogoTenetowl
Landmark CasesDivision BenchPartly allowed

K. Subbarayudu and Others v. The Special Deputy Collector (Land Acquisition)

Case / Petition Number:
Civil Appeal No. 9288 of 2017; arising out of SLP(C) No. 30562 of 2016

Case Synopsis & Summary

This Supreme Court Civil Appeal arises from a Land Acquisition Act award for land acquired under the Telugu Ganga Project for Kandaleru Reservoir submersion. The Reference Court had enhanced the market value of land and trees, but the High Court dismissed the appeal due to an inordinate delay of 3,671 days in filing. The appellants contend that the delay was satisfactorily explained and seek condonation, arguing for liberal interpretation of “sufficient cause” and the aim of substantial justice, citing precedents including Yellasiri Sarojanamma’s case and the 2016 decision awarding higher compensation for pomegranate trees. They also urge parity with recent judgments in related projects (notably for pomegranate trees) and contend that denying interest for the period of delay would be inequitable while seeking solatium and other statutory benefits. The respondents argue that the delay lacks adequate explanation and that condonation was rightly refused, and they challenge applying the 2016 decision to the facts. The Court partly allows the appeal, enhancing compensation for pomegranate trees to Rs.1,500 per tree and lime trees to Rs.250 per tree, awards solatium and statutory benefits, but directs that no interest accrue for the period of delay, and parties bear their own costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • R. Banumathi
  • Kurian Joseph
Judgment Date
2017-07-19
Court Decision / Holding
The appeal is partly allowed. The compensation for pomegranate trees is enhanced to Rs. 1,500 per tree and for lime trees to Rs. 250 per tree. The claimants are entitled to solatium and other statutory benefits, and interest on the same, but they shall not be entitled to any interest during the period of delay 3,671 days. Costs to be borne by the parties.
Final Disposition
Partly allowed

Parties to the Case

Appellants / Petitioners

  • K. Subbarayudu and Others

Respondents

  • The Special Deputy Collector (Land Acquisition)

Provisions of Law Cited

Section 54, Land Acquisition Act, 1894Section 4(1), Land Acquisition Act, 1894Section 18, Land Acquisition Act, 1894

Legal Doctrines & Maxims

  • Sufficient cause is to be liberally construed to advance substantial justice; no negligence or lack of bona fide should be attributable to the appellants
  • Section 5 is to be construed liberally so as to do substantial justice
  • Equities can be balanced by denying the appellants’ interest for the period of delay
  • A pragmatic, not pedantic, approach is to be adopted in compensation for land acquisition
  • Compensation for fruit-bearing trees depends on facts and circumstances, often related to planting costs and yield basis

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that the delay of 3,671 days in filing the appeal was satisfactorily explained, and the High Court erred in not condoning it, relying on liberal interpretations of ‘sufficient cause’ and the substantial-justice objective. They cited Yellasiri Sarojanamma’s case and other precedents where delays were condoned, and urged parity in compensation, especially for pomegranate trees, referencing Civil Appeal Nos. 11404-11405 of 2016. They contended that denying interest during the delay would be inequitable and sought the grant of solatium and other statutory benefits.

Contentions of Respondents

The respondents contended that the delay was not satisfactorily explained and that the High Court properly exercised its discretion in refusing to condone the delay. They argued that the 2016 decision cannot be applied to the present facts due to the time gap and differences in circumstances, and that the enhanced compensation should not be extended beyond what the record supports.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (10)

Case NameCitationTreatmentExplanation
State of Nagaland v. Lipok AO and Others3 SCC 752PositiveCited to support liberal construction of Section 5 and the liberal, justice-oriented approach to condoning delay.
Dhiraj Singh (D) Thr. Lrs. v. Haryana State and Ors.2014 (9) SCALE 441PositiveSupports a pragmatic, non-pedantic approach to compensation and balancing equities.
Kerala State Electricity Board v. Livisha and Ors.2007 SCC 792PositiveCited for principles on compensation for fruit-bearing trees, including yield considerations.
Shaik Imambi v. Special Deputy Collector (Land Acquisition), Telugu Ganga Project11 SCC 639PositiveUsed to set/consider annual income per tree for lime trees.
Air 2007 SC 1142AIR 2007 SC 1142PositiveIllustrates yield-based compensation principles for trees.
Kapur Singh Mistry v. Financial Commission and Revenue Secretary to Govt. of Punjab and Ors.1 SCR 408PositiveSupports equitable balancing in compensation and delay considerations.
State of Haryana v. Gurcharan Singh and Anr.SCR 408PositiveCited for general equity and remedy considerations.
Yellasiri Sarojanamma’s caseN/APositiveCited as precedent for condoning delay in similar circumstances.
Peddireddy Madhava Reddy and Pidugu Seshugari Lakshmi DeviN/APositiveUsed to support compensation considerations in pomegranate tree cases.
Civil Appeal Nos. 11404-11405 of 2016CA Nos. 11404-11405 of 2016DistinguishedCourt distinguished this 2016 decision; cannot be applied due to date/circumstances.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,613 words•~12 min read

In The Court Record

K. Subbarayudu and Others v. The Special Deputy Collector (Land Acquisition)

CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 ## **REPORTABLE** IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## CIVIL APPEAL NO. 9288 OF 2017 {Arising out of SLP(C) No.30562 of 2016} K. SUBBARAYUDU AND OTHERS ...Appellants Versus THE SPECIAL DEPUTY COLLECTOR (LAND ACQUISITION) ...Respondent ## **O R D E R** ## **R. BANUMATHI, J.** Leave granted 2. This appeal by way of special leave under Section 54 of the Land Acquisition Act, 1894 has been preferred by the claimant assailing the judgment and order dated 12.07.2016 in L.A.A.S.M.P. No.61 of 2015 in L.A.A.S.(SR) No.12334 of 2014 passed by the High Court of Judicature at Hyderabad for the State of Telangana and the State of Andhra Pradesh by which the High Court declined to condone the delay of 3671 days in filing the appeal and dismissed the appeal. 3. A Notification under Section 4(1) of the Land Acquisition Act, 1894 was Signature Not Verified Digitally signed by JAYANT KUMAR ARORADate: 2017.08.05 issued on 01.10.1990 for acquiring land to an extent of Acs.32.77 in Reach 12:54:46 IST Reason: No.11 of Nellepalli village for foreshore submersion of Kandaleru Reservoir Page No. 1 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 under Telugu Ganga Project. After conducting the award enquiry, Land Acquisition Officer, Telugu Ganga Project, Rapur passed an award, in Award No.12/91-92 dated 30.01.1992. The award was passed after taking into account the sale statistics for the preceding three years prior to the date of notification under Section 4(1) of the Land Acquisition Act which was obtained from the Sub-Registrar, Rapur and after verification of all sales, the land value is fixed by the Land Acquisition Officer and approved by the Special Collector, Telugu Ganga Project, Nellore as per norms prescribed under the Land Acquisition Act, 1894 amended in 1984. The Land Acquisition Officer (LAO) awarded compensation for cultivable dry lands at Rs.9,000/- per acre and for cultivable waste land at Rs.7,000/- per acre. The Land Acquisition Officer also awarded compensation of Rs.50-70 for each lime tree and compensation of Rs.32 for each pomegranate tree. The land was taken possession on 02.03.1994 and compensation paid to the land owners. 4. As against compensation awarded by the Land Acquisition Officer, reference was made under Section 18 of the Act to the Senior Civil Judge, Gudur. Before the reference court, on behalf of the claimants, CW-1 was examined and Exs.A1 to A5 were marked. On behalf of the referring officer, one of its employees was examined as R.W.1 and the particulars showing the compensation awarded by the LAO, Ex.B1 was marked. The Reference Court by its judgment and order dated 06.08.2004 in LAOP No.22/1993 enhanced the market value of land from Rs.9,000/- to Rs.12,000/- for cultivable dry land Page No. 2 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 and to Rs.7000/- to Rs.10000/- for cultivable waste land per acre. Further the Reference Court fixed the market value of the trees to Rs.100/- per tree as against Rs.50/- to Rs.70/- awarded by the Land Acquisition Officer and confirmed the rate of Rs.32/- per pomegranate tree as fixed by the Land Acquisition Officer basing on the age of the trees. 5. Dissatisfied with the enhanced compensation, the appellants/claimants approached the High Court referring to the order in A.S. No.1749/2004 dated 01.03.2013 and other judgments of Andhra Pradesh High Court. However, there was a delay of 3671 days in so preferring the appeal. The High Court dismissed L.A.A.S.(MP) No.61/2015 in L.AA.S. (SR) No.12334/2014 on the ground of inordinate delay of 3671 days since the High Court was of the view that no sufficient cause was shown for the delay and held that the delay sought to be condoned was not on account of a _bona fide_ mistake but was merely intended to make gain basing on the assessment of value of pomegranate trees in the decisions of _**Peddireddy Madhava Reddy**_ and _**Pidugu Seshugari Lakshmi Devi**_ . 6. Aggrieved by the order of the High Court, the appellants are before us by way of special leave to appeal. 7. The learned counsel for the appellants submitted that the High Court failed to appreciate that the claimants have given satisfactory explanation for the delay of 3671 days in filing the appeal before the High Court and while so Page No. 3 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 the High Court has erred in declining to condone the delay. It was further submitted that in L.A.S.S.No.46/2015, the High Court was pleased to condone the delay of 3386 days in filing the land acquisition appeal suit subject to the condition that in the event, the appellants/claimants succeed in the appeal, she is not entitled to any interest in respect of the period of delay and the same approach ought to have been given in case of appellants also. In so far as the quantum of compensation, learned counsel for the appellant has relied upon the decision of this Court in Civil Appeal Nos.11404-405 of 2016 dated 29.11.2016 whereby this Court has awarded compensation of Rs.3,000/- per pomegranate tree in connection with lands acquired for Somashila Project submergence. The learned counsel for the appellant prayed that the same amount of compensation of Rs.3,000/- per pomegranate tree be awarded to the appellant. 8. _Per contra_ , supporting the judgment of the High Court, the learned counsel for the respondent submitted that reason for inordinate delay of 3671 days was not satisfactorily explained and the High Court rightly exercised its discretion in declining to condone the delay. Insofar as the judgment in Civil Appeal Nos.11404-11405 of 2016 is concerned, it is submitted that the said order relates to Somashila Project submergence of which the award was of the year 1999 and the same cannot be applied to the present case. 9. Heard the learned counsel for the parties at some length. Perused the impugned judgment and considered the documents and other materials Page No. 4 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 placed on record. 10. The High Court dismissed the claimants’ appeal mainly on the ground of delay of 3671 days in filing the appeal. On perusal of records, it is seen that the appellants have explained the reason for the delay in filing the appeal stating that they have entrusted the relevant papers to their co-villager namely, viz., Pullaiah who is well-conversant with the court proceedings and the said Pullaiah has also taken steps to engage an advocate at Hyderabad and the said Pullaiah informed that the appeal was filed and left for Kuwait to eke out his livelihood. Thus the appellants/claimants were under the impression that the appeal has been filed. The claimants have further stated that when they inquired the said Pullaiah, he informed them that he went to the house of Sri Jaganmohan Raju, Advocate and he learnt that the said Advocate is no more and expired in 2012 itself and on enquiry with the clerk of the said advocate, he learnt that no appeal has been filed and this has caused a delay of 3671 days in filing the appeal. The High Court rejected the explanation given by the appellants on the ground that there are contradictions between the affidavit filed by the said Pullaiah and the stand of the claimants and being not satisfied with the reason for the delay of 3671 days in preferring the appeal, the High Court dismissed the appeal. 11. Before the High Court, the appellants relied upon _**Yellasiri Sarojanamma’s**_ case, in L.A.S.S. No.46 of 2015, in which the High Court Page No. 5 of 10 ## CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 condoned the delay of 3386 days in filing the land acquisition appeal suit subject to the condition that in the event, the appellant/claimant thereon succeed in appeal, she is not entitled to any interest in respect of the period of delay. The appellants contended that the same approach ought to have been adopted in the case of appellants also. Insofar as, the reliance placed upon by the claimants in L.A.S.S. No.46/2015, the High Court seems to have brushed aside the contention of the appellants on the puerile ground that the relevant fact situation in the said case is not forthcoming in the said order. In our view, the High Court was not right in adopting a different yardstick in the case of the appellants in not condoning the delay. 12. The term “sufficient cause” is to receive liberal construction so as to advance substantial justice, when no negligence, inaction or want of _bona fide_ is attributable to the appellants, the Court should adopt a justice-oriented approach in condoning the delay. In _**State of Nagaland v. Lipok AO and Others**_ (2005) 3 SCC 752: 2005 (4) JT 10, it was held as under:- “Section 5 is to be construed liberally so as to do substantial justice to the parties. The provision contemplates that the court has to go into the position of the person concerned and to find out if the delay can be said to have been resulted from the cause which he had adduced and whether the cause recorded in the peculiar circumstances of the case is sufficient”. 13. With the acquisition of lands, the lifeline of the agriculturist is lost. There may be omission on the part of the claimants to adopt extra vigilance; but same need not be used as a ground to depict them with negligence or want of Page No. 6 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 _bona fide_ . In case of acquisition of lands of agriculturists, the courts ought to adopt a pragmatic approach to award just and reasonable compensation and not pedantic in their approach. In _**Dhiraj Singh (D) Thr. Lrs. Etc. Etc. v. Haryana State and Ors. Etc. Etc.**_ 2014 (9) SCALE 441, it was held as under:- “15. Equities can be balanced by denying the appellants’ interest for the period for which they did not approach the Court. The substantive rights of the appellants should not be allowed to be defeated on technical grounds by taking hyper technical view of self-imposed limitations. In the matter of compensation for land acquisition, we are of the view that approach of the Court has to be pragmatic and not pedantic.” 14. When the concerned court has exercised its discretion either condoning or declining to condone the delay, normally the superior court will not interfere in exercise of such discretion. The true guide is whether the litigant has acted with due diligence. Since the appellants/claimants are the agriculturists whose lands were acquired and when similar situated agriculturists were given a higher rate of compensation, there is no reason to decline the same to the appellants. Merely on the ground of delay such benefit cannot be denied to the appellants. The interest of justice would be served by declining the interest on the enhanced compensation and also on the _solatium_ and other statutory benefits for the period of delay. 15. Insofar as the compensation for the pomegranate trees, the appellants have placed reliance on the judgment of this Court dated 29.11.2016, in C.A. Nos.11404-11405 of 2016. Planting, raising and making commercial use of Page No. 7 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 fruit bearing trees is a painstaking affair and cost of the same is consistently on rise as the years are passing by which is to be kept in view. Award of compensation in relation to fruit bearing trees depends on facts and circumstances of each case. It has been held in _**Kerala State Electricity Board v. Livisha and Ors.**_ (2007) 6 SCC 792, in the following terms: “11. So far as the compensation in relation to fruit bearing trees are concerned the same would also depend upon the facts and circumstances of each case. We may, incidentally, refer to a recent decision of this Court in Land Acquisition Officer v. Kamandana Ramakrishna Rao AIR 2007 SC 1142 wherein claim on yield basis has been held to be relevant for determining the amount of compensation payable under the Land Acquisition Act, same principle has been reiterated in Kapur Singh Mistry v. Financial Commission and Revenue Secretary to Govt. of Punjab and Ors. , State of Haryana v. Gurcharan Singh and Anr. [1995] 1 SCR 408, and Airports Authority of India v. Satyagopal Roy [2002] 2 SCR 505.” 16. In the facts and circumstances of the said case, in C.A. Nos.11404-405 of 2016, considering the cost of planting and efforts involved in growing trees in general and in particular raising the pomegranate trees over the efflux of time, this Court deemed it appropriate to award Rs.3,000/- as compensation for each of the pomegranate tree. 17. However, the compensation of Rs. 3000/- per pomegranate tree, as has been awarded in the abovementioned case, cannot be made applicable to the present case, considering the fact that award of compensation by Land Acquisition Officer in the said case dated 08.03.1999, as opposed to award in the present case which is dated 30.01.1992. A period of about seven years is a considerable period to be taken note of while computing cost of planting and raising fruit bearing trees. It is obvious that seven years back a fruit bearing Page No. 8 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 tree would have fetched lesser income than it would fetch now. In the facts and circumstances of the present case and taking into consideration that the appellants were also awarded compensation for the land, we deem it appropriate to award compensation of Rs.1500/- for each pomegranate tree. 18. In so far as the lime trees are concerned, fresh limes are available throughout the year and have good market and the lime trees are earning income almost throughout the year. The Reference Court enhanced the compensation of Rs.70/- to Rs.100/- per tree as against the compensation of Rs.52/- to Rs.70/- awarded by the Land Acquisition Officer. While considering the question of awarding compensation to lime trees, in _**Shaik Imambi v. Special Deputy Collector (Land Acquisiton), Telugu Ganga Project**_ (2011) 11 SCC 639, this Court held as under:- “10. There is no specific documentary evidence in regard to the actual income from the orchard. As the reports of experts of the state government assessed the gross annual income from each tree as Rs.150-200/-, it would be appropriate to take the average thereof, namely Rs.175/- as the annual income per tree in this case. If Rs.35/- is deducted towards the cost of cultivation and other expenses as recommended by the experts, the net annual income would have been Rs.140/- per tree or Rs.1,06,540/- for 761 trees.” Applying the ratio of the above decision, Rs.250/- is awarded as the annual income per tree. Compensation of Rs.100/- per each lime tree enhanced to Rs.250/- is awarded. 19. Compensation awarded to the appellants is enhanced to Rs.1,500/- for each pomegranate tree and Rs.250/- for each lime tree. The appellants are Page No. 9 of 10 CA NO. ….. OF 2017 @ SLP (C) NO.30562 OF 2016 also entitled to all statutory benefits like _solatium_ and other benefits and interest on the same. It is further directed that the appellants shall not be entitled to any interest during the period of delay of 3671 days. The appeal is partly allowed in the above terms. Parties are to bear their respective costs. ..………………………. **J. [KURIAN JOSEPH] .………………………..J. [R. BANUMATHI]** New Delhi; **July 19, 2017** Page No. 10 of 10
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.