Two forest contracts were granted to the appellant to fell a specified number of trees from government forests in Andhra Pradesh. The officer found excess felling and the Conservator of Forests imposed two penalties under Rule 29 of the Forest Contract Rules: one for loss due to illicit cutting and another penalty for breach of contract conditions, after the appellant was given an opportunity to re-enumerate the trees and inspect the coupe, which he declined. The contract was terminated under Rule 30. The State then sought recovery of the penalties. The appellant challenged the penalties in a Writ Petition; the High Court's Single Judge struck it down, but a Division Bench reversed. The matter reached the Supreme Court by certificate. The appellant contended that termination for breach should precede the imposition of penalties and that natural justice was violated. The respondents argued that the amount to be levied could be ascertained before termination and that termination was not a prerequisite for realisation. The Supreme Court held that, absent statutorily excluded natural justice, action prejudicial to another must comply with natural justice and that in this case no violation existed since the appellant was given an opportunity before final quantification, which he did not take. It explained Rule 29's two-tier penalties: grave breaches justify termination with a substantial penalty; minor breaches permit continued contracts and smaller penalties. The appeals were dismissed with costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • V. R. Krishna Iyer
  • A. C. Gupta
  • S. Fazal Ali
Judgment Date
1975-09-12
Court Decision / Holding
Appeals dismissed.
Final Disposition
Appeals dismissed

Parties to the Case

Appellants / Petitioners

  • K. Sreedhara Reddy

Respondents

  • Conservator of Forests
  • Ors

Legal Representation & Advocates

Counsels for Petitioners

  • • R. V. Pillai

Counsels for Respondents

  • • P. Ram Reddy
  • • G. N. Rao

Provisions of Law Cited

Hyderabad Forest Act, 1355F (ss. 44 and 79)Forest Contract Rules, Rule 29Forest Contract Rules, Rule 30Forest Contract Rules, Rule 31Constitution of India, Article 133(1)(a) and (b)Rule 29(1)Rule 29(2)Rule 29(3)

Legal Doctrines & Maxims

  • Principles of natural justice (audi alteram partem)
  • Opportunity to be heard
  • Stage-by-stage application of penalties under the Forest Contract Rules

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the penalty under Rule 29 should be levied only after termination of the contract for breach, and that the State's imposition violates the doctrine of natural justice because the process did not provide a fair opportunity to the appellant to challenge the findings before penalties were fixed. He argues that the sequence of investigation, quantification, and termination must be followed, and that any cessation should come only after due process and notice.

Contentions of Respondents

The respondents submit that the quantum of the penalty may be ascertained prior to termination and that termination is not a prerequisite for realisation; they argue that the contract may be terminated in grave breaches and a heavy penalty imposed, with later recovery under Rule 30. They contend that the petitioner was given a hearing before final quantification and that any procedural safeguard was adequate.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,040 words•~14 min read

In The Court Record

K. Sreedhara Reddy v. Conservator of Forests and ors

770 K. SREEDHARA REDDY _V._ THE CONSERVATOR OF FORESTS AND ORS. _September_ 12, 1975 [V. R. KRISHNA IYER, A. C. GUPTA ANDS. MURTAZA FA2;AL ALI, JJ.] _H'\!derabad Forest .Act-Forest Contract_ _rules-Rule_ _29-30-3l-Whether tenni-_ _natio;z_ _vf_ _contract to precede_ i111po~ition _of_ _penc.J.ty-Natural Justice._ A B - _+-_ The appellant & Forest Contractor fell'~d trees in excess of the perrnitted number aut [1] horised by th·~ contract entered into by him with the State of Andhra Pradesh. Certain penalty was in1posed on the appellant under rule 29 of he_ Forest Contract Rules framed in exercise of the powers conferred by Hyderabad Forest Act. The Forest Officer found that the appellant felled more trees and, therefore. gave a show cause notice to the appellant. The C appellant prayed for re-enumeration of the trees given from the forest. }Ie was given an opportunity which was not availed by him to check. the stun1ps in the coupe as desired by him. Consequently, a penalty was Jev1red. Thereafter, the contract was terminated. After the termination of the contract the process for recovery of the penalty was startred. Rule 29 reads as under : + ( 1) Penalty on termination of a contract for breach of conditions :-- .., Every fore91: contract shall be in writing in the form annexed he~to D and shall contain a provision whereby the forest contractor bind~ himself to do all the duties and acts required to be done by or under the, contract, and convenants that hre. and his servants and agents shall abstain from all the acts forbidden by or under such contract. (2) The sums to be mentioned in a forest contract as payable in case of a breach of any such stipulation shall not exceed one-quarter of the total consideration to be paid by the· contractor, and shall be recoverable in accordance \Vith the provisions of the Hyderabad Forest Act 1355 F E and of this rule. Provided that where such consideration i5 not an ascertained amount the forest officer executing the contract !!-hall make an estimate of the total amount that would be payable if the contract were fully complied with, and such estimate shall be deemed to be for the purpose of this sub-rule. the total consideration to be Paid by the contractor. (3) This sum shall be realized from the contractor if the contract has been duly terminated in accordance with the provision3 of rule 30, and then only under the written order of the forest officer executins the contract." The appeIIant filed a Writ Petition in the High Court challenging the validity of the imposition of the penalty. The learned Single Judge allowed the Writ Petition but the· Division Bench allowed the appeal filed by the State. Jn an appeal by certificate, it w<i.s contended by the appellant before this Court that the termination of the contract for breach of conditions m-entioned in rule 29· should precede the impost of penalty. It was further contended that tho principles of natural justice were violated. The respondent contended that ascertaining the amount which is to be levied as a penalty need not be preceded by the t'ermination of the contract. Dismissing the appeal, HELD : 1. It is clear that in the absence of a statutory exclusion of natural justice any exercise of,power prejudicially affecting another must be in confol'· mity with the rules of natural justice. In the present case, we are satisfied F G H _<'_ •-:'.Ji. ' #### *~ **A** **B** ###### **c** **D** K. s. REDDY _v._ CONSERVATOR OF FORESTS _(!Krishna Iyer._ **J.)** 771'. **that there** **is** **no** **foundation for the grievance of the appellant on the score** **of natural justice since** **an** **opportunity** **was** **afforded to the appellant before·** **finally quantifying the penalty to** **be** **levied but the appellant did not avail** him~ self of the opportunity. (773-E-F] **2.** **On** **a** **true** **construction of** **ru1e** **29 once a Forest Authority detects** **a** **breach** **it** **must investigate** **thie,** **extent** **and** **estimate, the nature and degree** **of·** **damage caused** **bv** **the** **breach.** **If** **it** **is** **serious they must proceed to ascertain** **the** **<;um** **to** **be** **fiXed** **as** **penalty.** **In doing this, a reasonable opportunity must** **be** **given to** **the** **affected party.** **After that, the penalty shall be quantified** **and·** **the contract** **shall** **be** **tern1inated** **in** **the** **event the authorities come to the** **conclu:..** **sion** **that** **the breach is grave enough for that drastic** **step.** **Once the contract'** **is** **termir.atcd** **the** **last procedure is realisation which can** **in** **no case** **be** **before·** **the** **termination** **of** **the contract.** **[7741-I,** **775** **AMB.]** CIVIL APPELLATE JURISDICTION: Civil Appeals Nos. 814-815 of 1968. From the Judgment and Order dated 7th September, 1966 of the· Andhra Pradesh High Court in Writ Appeal Nos. 71 and 72 of 1964· respectively. _R._ _V._ _Pillai,_ for the appellant. _P._ _Ram_ _Reddy_ and G. _N. Rao,_ for the respondents. The Judgment of the Court was delivered by KRISHNA IYER, J. A forest contractor-the appellant-who had allegedly excess felled trees beyond the permitted number under two contracts entered into by him with the State of Andhra Pradesh, was **E** directed by the Conservator of Forests-the first respondent-to suffer two levies. One item represented the loss sustained by the State on account of the illicit cutting and the other was a penalty imposed under r. 29 of the Forest Contract Rules (for short, the Rules) issued in exercise of the powers conferred under ss. 44 and 79 of the Hyderabad Forest Act, 1355F (for short, the Act). The factual story out of which the legal controversy springs may be narrated in simple terms. Admittedly, the appellant was granted two forest contracts to fell and remove a specific number of trees from government forest, iri accordance with the Act and the Rnles. The· Contracts were of two years' duration ending with 31st December 1960. It was found by the Forest Officers that the appellant contractor had felled more trees and so he was given a notice calling for his explanation about this detected breach of condition. In C.A. 814 of 1968 such notice was issued on June 25, 1960 but no explanation was forthcoming. So the Conservator determined the amount representing the loss caused by the unauthorised cutting of trees. On July 22, 1960 the District Forest Officer informed the appellant that the Conservator of Forest, who is the appropriate authority under the Rules, had fixed Rs. 11,426/- as representing the loss sustained by Government and Rs. 11,250/- as penalty under r. 29. The contractor, thereupon, prayed for re-enumeration of the ~ ~~ #### '~ **F** **G** **H** 772 SUPREME COURT REPORTS [1976] 1 S.C.R. trees cut from the forest by his application, dated foly 30, 1960. He was informed by the forest authori~ics, by communication dated August 24, 1960 to check the stumps in the coupe as desired by the petitioner before September 15, 1960. This opportunity was also not availed of by the appellant. Consequently, the Conservator levied a penalty, as earlier proposed. Thus there were two items (i) the loss caused by illicit cutting; (ii) the penalty imposed under the rules for breach of conditions of the contract. There were three small amounts of fine also, all together resulting in a sum of Rs. 23,088.00. Eventually, the contract was terminated on December 28, 1960 under r. 30 of the Ru!es. Long later, in January 1962, the amount stated above was sought to be realised by revenue recovery process by the Tahsildar, by his attachment order, dated January 8, 1962. Thereupon a writ petition was filed by the appellant challenging the demand. He succeeded before the lear11ed Single Judge but a Division Bench, in appeal carried by the State, reversed this order and the appellant has invoked the jurisdiction of this Court under Art. 133(1) (a) and (b) of the Constitution. Jn C.A. 815 of 1968 a similar excess felling by the same contractor was detected by the concerned officials and notice was issued to the appellant to explain how he had felled 255 trees in excess of the contractual figure. The appellant denied the illicit felling whereupon a date was fixed for checking the coupe in his presence, as requested by him. The contractor however did not avail himself of the opportunity so afforded despite a second date for inspection being fixed to suit his convenience. Eventually the Conservator of Forests fixed the loss sustained by government on account of the illicit felling ·of trees and also the penalty for breach of the conditions of the con· tract. This was done on October 16, 1960 and the appellant was asked to pay the sum by notice dated October 28, 1960. On the same date, the lease was also terminated. Long later, on January 9, 1962 proceedings for realisation of the amounts were initiated by the Tahsildar. This step drove the contractor to move a writ petition, which shared the fate, at the single Judge's level and in appeal, of the sister writ petition already adverted to. In the same manner he has moved this Court in appeal, by certificate. Two points were urged by Mr. R. V. Pillai, learned counsel for the appellant, one relating to the loss assessed and sought to be realised by the State under the two contracts on account of excess felling, the other relating to the imposition of penalty under r. 29 and its validity. The first point docs not survive because in both the writ petitions which were disposed of together by a common judgment the learned Single Judge rejected the contention with the observation 'I find no substance in the arguments advanced in this behalf ... No provision was brought to my notice which disentitles the government to collect those items'. If the appellant had been aggrieved by the negation of his plea under this head he should have challenged it in A B c D E F ~ G -~-,... # ' H _y_ ... ~ -~-,... appeal which he did not. Thus the matter has become final and he cannot, in this Court, revive it at all. There is only a single question that therefore deserves our consideration. K. s. REDDY _v._ CONSERVATOR OF FORESTS _(Krishna_ _Iyer,_ **J.)** 773 Was the penalty in the two cases imposed validly ? The learned Single Jndge held, on a study of rr. 29 and .31 that the impost was illegal for reasons which we find difficult to accept. The Division Bench, in appeal, disagreed with the learned Single Judge for reasons which are unclear although our conclusion concurs with theirs. The rules regnlating the consequence of a breach of the conditions of forest contracts were originally promulgated in Urdu in the Hyderabad State but we have been handed up the Manual of Civil Laws, Andhra Pradesh, which contains those mies in English. Rule 29(3) reads sligl1tly obscurely but, in the absence of the original Urdu rules, we have to make-do with the English version. There are two types of penalties which we may conveniently designate as 'major' and 'minor', in the contemplation of the Forest Rules. Rule 29 deals with the major penaliies while r. 31 relates to minor penalties. Where the breach of the conditions of the contract coillffiitted by the forest contractor is serions, tile contract itself is to be terminated and a substantial penalty is to be imposed which 'shall not exceed one quarter of tile total consideration paid by the contrac**tor'.** If the breach is of lesser significance, then the autilority may not propose to terminate the contract on account tilereof bu, may recover a portion of the 'whole penalty provided for in r. 29' not exceeding Rs. 100/-. In short, if the contravention is grave, the contract is cancelled and a heavy penalty imposed but if the breach is inconsequential tile contract continues but a lighter penalty is imposed. 1n the present case it is apparent that the authorities term'. nated the contract and it is equally clear tllat tile breach was serious. Rilie 31 which deals witll trivial breaches and lighter penalties is inapplicable. The only question then is whether the exercise of the power to impose a penalty under r. 29 has been (a) in compliance with natural justice; and (b) in fulfilment of the conditions precedent for the exercise of the power. The facts we have set out earlier make it clear that an opportunity had been afforded in the case of botii the contracts before finally quantifying the penalty to be levied but the contractor did not avail hinlself of the opportunity. While it is clear that in the absence of a statutory exclusion of natural justice any exercise of power prejudicially affecting another must be in conformity with the rules of natural justice, we are satisfied that in the prc•ent case there is no foundation for the grievance of tile petitioner on this score. 'The substantial issue is as to whether the termination of the contract for breacl;t of conditions should precede the impost of penalty. According to Shri Pillai, that is the meaning of r. 29 read in the light of r. 30( 3). There is seeming varbal support for this contention but a closer scrutiny pricks the bubble. Rule 29 may well be read at this 8tage : ###,. ## I r- --J-. **A** **B** **c** **D** **E** **F** **G** ''29. (1) Penalty on termination of a contract for breach of **H** conditions. Every forest contract shall be in wntmg in the form annexed hereto and shall contain a provision whereby the 774 SUPREME COURT REPORTS [1976] 1 S.C.R. forest contractor binds himself to do all the duties and acts required to be done by or under the contract, and covenants tltat he and his servants and agents shall abstain from all the acts forbidden by or under such contract. (2) The sums to be mentioned in a forest contract as payable in case of a breach of any such stipulation shall not exceed one-quarter of the total consideration to be paid by the contractor, and shall be recoverable in accordance with the provisions of the Hyderabad Forest Act 1355 F .and of this **rule** : Provided that where su.ch consideration is not an ascertained amount the forest officer executing the contract shall make an estimate of the total amount that would be payable if the contract were fully c;omplied with, and such estimate shall be deemed to be,. for t.he purpose of this sub-rule, the total consideration to be paid by the contractor. ( 3) This sum shall be realized from the contractor if the contract has been duly terminated in accordance with the provisions of rule 30, and then only under the written order of the forest officer executing the contract." :Shri Ram Reddy, for the respondent, urges that ascertaining the amount which is to be levied as a penalty need not be preceded by 1he termination of the contract. Indeed, according to him, it is only if there is an investigation of the nature of the breach, the quantum .of loss inflicted .on the State and other circumstances that a decision as to whether the contract should be terminated or not can be taken. If it is found that the breach of condition be wilful and the damage substantial, the penalty will be imposed under r. 29 and a decision will be taken for termination of the contract. However, the sum fixed as penalty shall not be realised from the contractor until th~ .contract has been duly terminated in accordance with the provisions of r. 30. This is because you cannot keep a contract alive and claim that a grave breach of conditions has been committed. That would be too inconsistent a stance for the State to adopt. It is true that the termination of the contract under r. 30 is a condition precedent to _realisation_ of the penalty from the contractor but realisation is ·different from imposition. The forest authorities quantify and impose the penalty. The revenue authorities as well as the forest authorities adopt the various steps prescribed in r. 30(3) for realisation of the sum. In the present case it was the Tehsildar who sought to realise the penalty and he did this after the contract was terminated. Indeed, r. 30(3) uses the expression 'recover' which is in consonance with 'realise' in **r.** 29(3). We think that the true meaning of rr. 29 and 30, read together, is that the forest authorities must move from stage to stage in the following manner. Once they detect a breach, they must investigate to understand and estimate, the nature and degree of damage caused :by tbe breach. If it is serious, they must proceed to ascertain the **A** **B** # **1** ###### **c** ##### D • **E** **F** _y_ **G** ~ **-i-** **.-1** **H** **.-1** # ' K. s. REDDY _v._ CONSERVATOR OF FORESTS _(cKrishna_ _Iyer,!.)_ 775 sur.1 to be fixed as penalty. In doing this, a reasonable opportunity must be given to the affected party. After that the penalty shall be quantified and the contract shall be terminated, in the event of the authorities coming to the decision that the breach is grave enough for that drastic step. Once the contract is terminated, the last procedure is realisation which can in no case be before the termination of the contract. The realisation of the penalty may be in one or other of the ways set out for recovery under r. 30. Cf course, if the breach is of a venial nature, r. 31 is attracted, the contract is continued and only a small portion of the penalty envisaged in r. 29 is collected. ##### - _,;_ ~ **)r** ~ ##### + • • _**A**_ **i)** The view we have taken of the scheme of the rules leaves us in no doubt that the order of penalty is right and the judgment of the Division Bench is correct in the conclusion and the appeals, in the **C** result, must fail. The circumstances are such that the litigation is purely induced by the obscure official translation of r. 29 from Urdu to English with an obvious omission o[ 'not'. This and the other attendant features of the case persuade us to direct that the parties shall bear their costs throughout. **V.M.K.** _Appeals dismissed._
End of Judgment Record
Browse All Supreme Court of India (1976) Decisions
1975-12-18

THAKUR PRASAD SAO ETC. v. THE MEMBER. BOARD OF REVENUE & ORS.

These ten appeals arise from writ petitions challenging the licensing regime for outstill shops under the Bihar & Orissa Excise Act, 1915. The licensees, who held licences for manufacturing and retail sale of country liquor in Singhbhum district, argued that what was granted to them was merely a license to retail on their premises and not an exclusive privilege under section 22, nor beyond the reach of section 30. They sought refunds of deposits and damages for loss of anticipated profits, and in the second batch sought reductions of licence fees on grounds of speculative bidding; in the third batch they argued refund of sums charged as consideration for licences to grant exclusive privileges. The State contended that the outstill system confers an exclusive privilege to manufacture and supply country liquor within the area, i.e., a monopoly within the meaning of section 22(1)(d); The High Court had held otherwise. The Supreme Court held that the outstill licences for manufacturing and selling country liquor within the specified area are an exclusive privilege under section 22(1)(d), not a simple retail licence under section 30. It held that the licences continued in force with no right to compensation under Section 44, and that the State could frame rules and collect fees as consideration for the exclusive privilege. The court dismissed all appeals with costs, directing instalment recovery over three years for those able to furnish security.

1975-12-04

Gorelal Dubey v. The State of Madhya Pradesh and Others

This case concerns a dispute over limestone exploitation in Madhya Pradesh under competing mineral classification regimes. Gorelal Dubey (applicant) sought a quarry lease for limestone designated as a minor mineral under the Madhya Pradesh Mineral Rules, 1961, while Ram Chander Badri Prasad Gaur (respondent No. 3) sought a mining lease for limestone as a major mineral under the Central Rules, 1960, with the Central Government initially concluding that the appellant’s application effectively amounted to a major-mineral request. The Madhya Pradesh High Court dismissed related writ petitions, and special leave was granted, leading to two appeals: CA 785/71 and CA 1781/75. The Parliament’s Mines and Minerals Act, 1957 and the Central Rules (1960) are contrasted with the Madhya Pradesh State Rules (1961) and the 1958 and 1961 notifications redefining limestone as a minor mineral. The Court traces the two-notification framework, emphasizing that a lease decision should be based on the quality and partition of limestone in the questioned area, and that when two distinct applications exist, the State Government must consider both and determine whether one should be a minor mineral lease or a major mineral lease. The judgment ultimately resolves the dispute by quashing the central directive and directing fresh consideration by the State, with interim royalty duties allocated per the relevant minor/major rates.

1975-10-10

HIND OVERSEAS PRIVATE LIMITED v. RAGHUNATH PRASAD JHUNJHUNWALLA AND ANR.

This Supreme Court judgment addresses whether a private limited company, formed in 1956 by two family groups for iron and steel business, can be treated as a partnership for the purposes of winding up under Section 433(f) of the Companies Act, 1956. The two groups — RPJ (Raghunath Prasad Jhunjhunwalla) and his family, and the VD J group (V. D. Jhunjhunwalla) along with M.P.J. — held control through a two-family shareholding structure (1875 vs 3125 shares). Allegations arose that, despite formal corporate structure, management and day-to-day control were concentrated in one group, with the other group being ousted from directorship and access to books, ostensibly creating a de facto partnership. The Calcutta High Court dismissed the winding-up petition, but the Division Bench allowed it, holding that the company was in substance a partnership and the just and equitable clause justified winding up. The Supreme Court, however, reverses that view, stressing that the just and equitable remedy is a last resort and must serve the interests of the company and all shareholders, not merely the petitioning party. While English authorities like Yenidje and Ebrahimi are persuasive, Indian conditions require a careful, contextual application. The Court reviews the facts: there was no substratum dissolution, no irreparable mismanagement, and there were procedural remedies within the company’s articles. It concludes that the petition for winding up should not succeed and dismisses the petition, preserving the corporate form and the rights of all shareholders.

1976-02-24

Pandurang Dnyanoba Lad v. Dada Rama Methe & Ors.

Pandurang Dnyanoba Lad v. Dada Rama Methe & Ors concerns whether the abolition of Inams in the merged territories terminated the landlord-tenant relationship and extinguished a tenant's right to purchase land under the Bombay Tenancy and Agricultural Lands Act, 1948. Lad, the appellant, owned land classified as Huzur Sanadi Inam and was challenged by tenants who were declared purchasers under the Tenancy Act. The Bombay Merged Territories Miscellaneous Alienations Abolition Act, 1955 abolished all alienations with effect from an appointed date and provided occupancy rights for erstwhile Inam lands (sections 4–9) and a protection clause (section 28) preserving the operation of the Tenancy Act to the extent not inconsistent. The appellant argued that abolition ended the landlord-tenant relationship and that the tenants lost the right to purchase. The respondents contended that the Tenancy Act rights remained intact; Section 32 of the Tenancy Act grants a right to purchase on the tillers' day, and Section 32G fixes the price; Section 32G(6) ensures the purchase right persists even where land is re-granted under abolition with non-transferability conditions. The Court held that the abolition act did not extinguish the landlord-tenant relationship, and Section 32 remained applicable to pre-existing tenancies; the rights of tenants to purchase were preserved. The appeal was dismissed. The decision clarifies that the abolition act aimed to remove intermediaries, not evict tillers, and that existing tenancy protections remain intact.