High Court of KeralaKerala High Court · 2009Single JudgeWrit petition allowed; Ext.P11 set aside; Gover...

K. Madhusoodanan v. State of Kerala and others

Case / Petition Number:
W.P.(C).No. 33941 of 2008

Case Synopsis & Summary

This writ petition questions the suspension of K. Madhusoodanan, an Executive Engineer (Under Suspension) in the Irrigation Department, pending an inquiry into alleged irregularities connected to anti-sea-erosion works after the 2004 tsunami. The petitioner, transferred to the Pamba Irrigation Division in 2007, faced seven charges framed by the Government on the basis of an investigation by the Finance Inspection Wing. While the Assistant Executive Engineer and the Assistant Engineer, who were suspended along with him, had their suspension revoked and disciplinary proceedings closed with a warning (Ext. P4), the petitioner’s suspension continued, and Ext. P11 declined to revoke it. The Government directed inquiries by various officers, including the Chief Technical Examiner and Chief Engineer, largely accepting the petitioner's explanations in some reports but not yielding a final mandating proof of loss or wrongdoing. The High Court held that suspension is a temporary measure to facilitate inquiry, not a punitive tool, and criticized the indefinite continuation of suspension without objective basis. It directed the Government to pass fresh orders revoking the suspension within a month and to complete the inquiry within a year, with appropriate consideration of the suspension period, thereby allowing the petitioner to be reinstated subject to the outcome of the disciplinary process.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • V. Giri
Judgment Date
2009-04-06
Court Decision / Holding
The writ petition is allowed. Ext. P11 is set aside. The Government is directed to pass fresh orders on the revocation of the suspension within one month and to revoke the petitioner’s suspension with effect from the date of the fresh order. The Government shall conduct a fresh inquiry as deemed fit and ensure its completion within one year from the date of the fresh order, with due consideration to the period during which the petitioner was suspended.
Final Disposition
Writ petition allowed; Ext.P11 set aside; Government directed to revoke suspension and conduct the inquiry with a defined timeline; period of suspension to be treated appropriately in final disciplinary action.

Parties to the Case

Appellants / Petitioners

  • K. Madhusoodanan, Executive Engineer (Under Suspension), PIP (CADA) Division, Chengannur

Respondents

  • State of Kerala, represented by the Additional Chief Secretary, Water Resources Department, Government Secretariat, Thiruvananthapuram
  • Chief Engineer, Irrigation and Administration, Public Office, Thiruvananthapuram
  • Chief Technical Examiner, Finance Department, Bank Employees Union Building, Thiruvananthapuram

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. George Poonthottam (Adv.)

Counsels for Respondents

  • • Smt. Sudhadevi, Government Pleader

Provisions of Law Cited

Kerala Civil Services (Classification, Control and Appeal) Rules, 1960, Rule 22Right to Information Act, 2005

Legal Doctrines & Maxims

  • Suspension should not transform itself as a punishment but be a measure to facilitate an enquiry.
  • Suspension should be resorted to only when necessary and not as a norm.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that the seven charges against him differ from those against the other suspended officers; many charges relate to tampering with records for anti-sea erosion works, but the related charges against others were largely dropped. He asserts that several reports (Ext. P5, P6) do not establish loss or illegality, and that the Chief Engineer’s report largely accepts his explanations. The Government’s reliance on these materials to sustain indefinite suspension is unjustified, especially since Ext. P11 has not been properly considered. The petitioner seeks revocation of suspension and a fresh, fair enquiry with materials properly assessed, arguing for prompt action and reasonable finalisation within a year.

Contentions of Respondents

The Government argues that the gravity and number of charges necessitate continued suspension to protect public interests and ensure integrity during ongoing inquiries. Ext. P11 reflects the Government’s view that suspension should not be revoked given the seriousness of the allegations. While not denying that materials existed, officials emphasize that the Chief Technical Examiner’s findings do not compel reversal and that further enquiry is warranted. The Government maintains discretion under Rule 22 of the Kerala Civil Services Rules and points out that the disciplinary process should be completed without compromising governance and loss recovery considerations. It contends that revoking suspension prematurely could undermine the inquiry’s efficacy.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Surendran K. v. Government of Kerala and others2008(3) ILR Kerala 587PositiveCited to support the proposition that suspension should be used only when necessary and not as a norm, and that there must be fairness and material basis before prolonging suspension.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,112 words•~10 min read

In The Court Record

K. Madhusoodanan v. State of Kerala and others

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE V.GIRI** **MONDAY, THE 6TH APRIL 2009 / 16TH CHAITHRA 1931** **WP(C).No. 33941 of 2008(N)** **----------------------------------------** ## **PETITIONER(S):** **----------------------** **K.MADHUSOODANAN, EXECUTIVE ENGINEER (UNDER SUSPENSION) PIP (CADA) DIVISION, CHENGANNUR TC.36/574-1, KRISHNA KRIPA ERA 42, PALKULANGARA JN., THIRUVANANTHAPURAM-8.** **BY ADV. MR.GEORGE POONTHOTTAM** ## **RESPONDENT(S):** **-------------------------** **1. STATE OF KERALA, REP.BY THE ADDITIONAL CHIEF SECRETARY, WATER RESOURCES DEPARTMENT, GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM.** **2. CHIEF ENGINEER, IRRIGATION AND ADMINISTRATION, PUBLIC OFFICE, THIRUVANANTHAPURAM.** **3. CHIEF TECHNICAL EXAMINER, FINANCE DEPARTMENT, BANK EMPLOYEES UNION BUILDING, THIRUVANANTHAPURAM.1** **GOVERNMENT PLEADER SMT.SUDHADEVI FOR R1 TO 3** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 06/04/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** ## **W.P.(C) NO.33941/2008** ## **APPENDIX** ## **PETITIONERS EXHIBITS** ## **P1:- COPY OF THE REPORT ON INSPECTION CONDUCTED IN THE OFFICE OF THE EXE. ENGINEER, IRRIGATION DIVISION, KOLLAM BY THE FINANCE INSPECTION WING.** ## **P2:- COPY OF THE G.O.(RT) NO.926/07/WRD DT. 12.7.07.** **P3:- COPY OF THE MEMO OF CHARGES DT. 16.11.07 ALONG WITH STATEMENT OF ALLEGATIONS.** **P4:- COPY OF THE G.O.(RT) NO.210/08/WRD DT. 15.2.08.** **P5:- COPY OF THE ENQUIRY REPORT NO.6933/FIWPC1/06/FIN DT. 25.11.06.** **P6:- COPY OF THE REPORT NO.VIG 2/1562/07 DT. 24.1.08.** **P7:- COPY OF THE JUDGMENT IN WPC. NO.9093/08 DT. 18.3.08.** **P8:- COPY OF THE RELEVANT PAGES OF THE NOTE FILES OBTAINED BY THE PETITIONER UNDER RIGHT TO INFORMATION ACT.** **P9:- COPY OF THE REMARKS OF THE PRINCIPAL SECRETARY, FINANCE DEPT. NO.31390/FIWPF1/08/FIN. DT. 28.4.08.** **P10:- COPY OF THE RELEVANT PAGES OF THE NOTE FILES OF THE GOVERNMENT NO.19573/GW2/07/WRD OBTAINED UNDER THE RIGHT TO INFORMATION ACT.** **P11:- COPY OF THE GO(RT) NO.118/08/WRD DT. 30.4.08.** **P12:- COPY OF THE G.O.9RT) NO.398/07/WRD DT. 22.3.07.** **P13:- COPY OF THE G.R.(RT) NO.640/07/WRD DT. 10.5.07.** **P14:- COPY OF THE REPORT ALONG WITH TE ENCLOSURES OBTAINED UNDER THE RIGHT TO INFORMATION ACT.** ## **TRUE COPY** **P.S. TO JUDGE** **TSS** ## **V.GIRI** ## ---------------------------------------------- ## **W.P.(C)No.33941 of 2008** ----------------------------------------------- **Dated this the 6[th] day of April, 2009.** ## **JUDGMENT** The petitioner is aggrieved by Ext.P2 order, by which he was suspended from service pending enquiry as also Ext.P11 order passed by the Government declining to revoke his suspension, in spite of a motion made by the petitioner in this regard. 2. The petitioner is an Executive Engineer in the Irrigation Division. He was transferred to the Pamba Irrigation Division (CADA), Chengannur as the Executive Engineer on 23.3.2007 and he was working as the Executive Engineer, Irrigation Division, Kollam from 12.5.2005 to 23.3.2007. The Finance Department (Inspection Wing) had conducted an inspection in the office of the Executive Engineer, regarding the alleged irregularity in the anti sea erosion works that followed the Tsunami attack on 26[th] December, 2004. A report was submitted by the Inspection Wing. The Executive Engineer (petitioner), Assistant Executive Engineer and an Assistant Engineer were placed under suspension on the basis of Ext.P1 ## **W.P.(C)No.33941 of 2008** :: 2 :: recommendation. The charges levelled against the Assistant Executive Engineer and the Assistant Engineer are identical, viz., that they have removed/tampered the entry in the letter of credit proposal for the anti sea erosion work, the M book and bill to enable a contractor to obtain the amounts at an early date and had, therefore, cheated the Government. 3. Ext.P3 is the memo of charges issued to the petitioner, along with the statement of allegations. Seven charges have been levelled against him. He submitted his detailed reply to the charges. The Government will have to take a final decision as to whether to go on with the enquiry or drop the same. 4. In the meanwhile, as evidenced by Ext.P4 order dated 15.2.2008, the Government not only decided to revoke the suspension of the Assistant Executive Engineer and the Assistant Engineer, who were suspended along with the petitioner as per Ext.P2, but also decided to drop the proceedings against them and close the file with a warning. ## **W.P.(C)No.33941 of 2008** :: 3 :: 5. The Government required the Chief Technical Examiner, to conduct an enquiry, on an objection submitted by another Government contractor alleging irregularities and misuse of the Tsunami relief funds. The ante sea erosion work arranged in the Irrigation Division at Kollam, during 2004-06 also came under scrutiny. The enquiry was particularly directed at the allegation that payments were made for the anti sea erosion work from the Irrigation Division at Kollam irregularly. The Chief Technical Examiner did not agree with the said allegation on the premise that in the case of those works for which agreements were already executed, emergency works were done as an extra item and a supplementary agreement was executed for the same. The quantum of the materials used for core wall work has been taken into account depending upon the then profile of the core wall. The allegation that payment was made without the works being actually done, according to the Chief Technical Examiner, was not established. It is not known whether Ext.P5 report of the ## **W.P.(C)No.33941 of 2008** :: 4 :: Chief Technical Examiner has been finally accepted by the Government. If not, it is up to the Government to take a decision. 6. The Chief Engineer, Irrigation and Administration was called upon to submit his remarks on the charges levelled against the petitioner, taking into account the petitioner's defence in reply to the charges. He submitted a report on 24.1.2008. Ext.P6 report in this regard refers to each one of the charges, the defence taken up by the petitioner and the remarks of the Chief Engineer. The Chief Engineer has proceeded to observe that the explanation offered by the petitioner deserves to be accepted in relation to each one of the charges. The report, therefore, concludes in the following terms: _**“In such circumstances it is meaningless to make any adverse comment against him in relation to an incomplete work.”**_ 7. Pursuant to a motion made by the petitioner seeking a direction to pass orders on his application for ## **W.P.(C)No.33941 of 2008** :: 5 :: revocation of the suspension, this court directed the 2[nd] respondent Secretary to Government to consider the application for revocation of the suspension and pass orders within a time frame. A hearing note was also submitted thereafter. Ultimately, the Government, by Ext.P11 order, went on to hold that the gravity of the charges levelled against the petitioner are too high and numerous. Therefore the Government has decided, not to reinstate the petitioner in service till the entire loss sustained by the Government is finalised. Ext.P11 order has been challenged in this writ petition. 8. A counter affidavit has been filed by the Government. 9. I heard Mr.George Poonthottam, learned counsel for the petitioner and Smt.Sudha Devi, learned Senior Government Pleader. 10. Learned counsel for the petitioner submits that the charges levelled against the Assistant Executive Engineer ## **W.P.(C)No.33941 of 2008** :: 6 :: and the Assistant Engineer may not have been the same as those levelled against the petitioner. The charges related to tampering of M book and the relevant records as regards the LC Proposal for ASE works, which enabled the contractor to obtain the amount at an early date and thereby cheated the Government and violated the orders of this court. These charges were practically dropped. No doubt, separate charges were levelled against the petitioner. But, he had replied to each one of the charges and the Chief Engineer, called upon in that regard by the Government, had submitted a report, prima facie accepting the explanation given by the petitioner. May be, the Government is entitled to take a different view. But that would require, in all fairness, further materials indicating a contra position. The same is not available. There are no materials to indicate that the Government has sustained a loss. The report of the Chief Technical Examiner, Ext.P5, rejects the allegation regarding payment having been made without the works having been executed. In fact, Ext.P11 would show that ## **W.P.(C)No.33941 of 2008** :: 7 :: the report of the Chief Technical Examiner, as such, has not been taken note by the Government. There is nothing on record to show that the Government has sustained any serious loss and that the continued suspension of the petitioner is necessary to finalise the said charges. 11. Learned Government Pleader on the other hand supports Ext.P11. 12. No doubt, it is the right of the Government to place an employee under suspension, if such suspension is warranted. But a suspension should not transform itself as a punishment. It should only be a measure to facilitate an enquiry. Further, when there is an application for revocation and grounds are made out in support of the same, though not with technical exactitude, the Government should consider such grounds for revocation in a fairly objective manner. That does not seem to have been done in the present case. 13. May be, the charges levelled against the Assistant Executive Engineer and the Assistant Engineer were not the ## **W.P.(C)No.33941 of 2008** :: 8 :: same as those contained in Ext.P3. The charges by themselves did not give an impression of being frivolous or vexatious or extremely minor. Nevertheless, the Government has thought it appropriate not only to revoke the suspension of those persons, but also to close the disciplinary proceedings against them, with a flea bite punishment viz., warning. The wisdom behind the decision taken in Ext.P4 is not subjected to judicial review by this Court. But, nevertheless, I take note of this. 14. Ext.P5 report of the Chief Technical Engineer, though referred to in Ext.P11, does not seem to have merited a serious consideration. Ext.P6 report of the Chief Engineer giving a point by point appraisal of the charges levelled against the petitioner forwarded to the Government Secretary has not been referred to. I agree with the learned Government Pleader that it is not binding on the Government. Though it is open to the Government, as the disciplinary authority, to take a different view, after all, there must be some material gathered and available to discard the effect of Ext.P6. It is ## **W.P.(C)No.33941 of 2008** :: 9 :: open to the Government to call for such materials. That is a matter, which will be relevant at the stage of enquiry. Ext.P6 ought not to have been eschewed from consideration. 15. The decision to keep the petitioner under suspension virtually interminably; i.e., until the loss sustained by the Government is finalised, does not reflect a correct approach, nor is there any justification for the same. There must be some certainty in these matters. 16. For all these reasons, I am of the view that the Government's refusal to revoke the petitioner's suspension, in these circumstances, is not resultant upon a proper exercise of power under Rule 22 of the Kerala Civil Services (Classification, Control and Appeal) Rules, 1960. 17. That suspension should be resorted to where it is necessary and need not be adopted as a norm, in all cases, has been spoken to by the Supreme Court and by a Bench of this court on more than one occasion. Reference could be made in this regard to the decision in **Surendran K. v. Government of** ## **W.P.(C)No.33941 of 2008** :: 10 :: **Kerala and others {2008(3) ILR Kerala 587}.** If the suspension is neither necessary, nor otherwise justified, it will be appropriate that the Government servant be reinstated in service, and his services availed of in a suitable manner without the Government being compelled to dole out subsistence allowance for an interminably long time. In the result, the writ petition is allowed. Ext.P11 is set aside. The Government is directed to pass fresh orders on the application filed by the petitioner for revocation of the suspension order within one month from the date of receipt of a copy of this judgment. For the reasons mentioned above, the Government shall pass orders revoking the petitioner's suspension with effect from the date on which such fresh orders are passed. I make it clear that the observations made by me above are relevant in the context of considering an application for revocation of the suspension and the Government shall take a decision in the matter of continuance of the disciplinary action untrammelled by the observations made by me in this ## **W.P.(C)No.33941 of 2008** :: 11 :: judgment. The Government shall proceed to conduct such enquiry as is deemed fit and the same shall be completed within one year from the date on which it is ordered. The mode of treatment of the period during which the petitioner was kept under suspension shall also be considered by the Government, after finalisation of the disciplinary proceedings. Sd/- **(V.GIRI) JUDGE** sk/- **//true copy//**
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.