Supreme Court of IndiaSupreme Court · 1973Division BenchPetition dismissed; detention upheld and order ...

Joydeb Gokai v. State of West Bengal

Case / Petition Number:
Writ Petition No. 39 of 1972
Neutral Citation:[1973] 1 S.C.C. 115

Case Synopsis & Summary

Joydeb Gokai, detained under the West Bengal Prevention of Violent Activities Act, 1970, challenged his detention under Article 32 before the Supreme Court. The District Magistrate, Burdwan, issued an order directing detention on the ground that the petitioner’s acts—threatening to kill a person and displaying anti‑Naxalite slogans—would prevent the public from pursuing ordinary activities and disturb public order. After the case progressed, the Government of West Bengal approved the order and referred the case to the Advisory Board, whose opinion supported detention. The petition raised two main challenges: first, that ground No. 1 of the grounds of detention—the threat to kill in response to the alleged refusal to erase anti‑Naxalite slogans—was irrelevant to the statutory definition of ‘acting in any manner prejudicial to the maintenance of public order’ under sec. 3(2)(d); and second, that there was undue delay in confirming the detention beyond the three‑month limit. The Court held that the offence defined in Sec. 506 IPC, namely a threat to commit an offence punishable with death or imprisonment for life, can fall within the expression ‘acting in any manner prejudicial to the maintenance of public order’ under sec. 3(2)(d). It also held that the order of confirmation was passed within three months from arrest, so the delay contention failed. Deb Sadhan Roy and Ujjal Mandal were followed. The petition was dismissed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • J. M. Shelat
  • I. D. Dua
  • H. R. Khanna
Judgment Date
1972-07-24
Court Decision / Holding
Petition dismissed.
Final Disposition
Petition dismissed; detention upheld and order of detention sustained.

Parties to the Case

Appellants / Petitioners

  • Joydeb Gokai

Respondents

  • State of West Bengal

Legal Representation & Advocates

Counsels for Petitioners

  • • S. Lakshminarasu

Counsels for Respondents

  • • G. L. Itukhoty
  • • Sukumar Basu

Provisions of Law Cited

West Bengal (Prevention of Violent Activities) Act, 1970 – Section 3(1); Section 3(2)(d); Section 3(3)Indian Penal Code – Section 506Constitution of India – Article 32

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicant contends that ground (1) of detention—the threat to kill in response to the alleged refusal to erase anti‑Naxalite slogans—is irrelevant to the statutory definition of ‘acting in any manner prejudicial to the maintenance of public order’ under sec. 3(2)(d); and that there was undue delay in the confirmation beyond three months. The detention cannot be sustained on an extraneous ground, and the period beyond three months must not be allowed to render detention illegal. The petition argues for strict adherence to the three‑month confirmation window and for severance of any invalid ground.

Contentions of Respondents

The respondents defend detention as valid under sec. 3(2)(d), arguing that a threat to kill constitutes an act prejudicial to public order and that the offence falls within the ambit of the Act when linked to the disturbance of public order; they rely on the Advisory Board’s opinion and maintain that confirmation within three months was timely, given statutory prerequisites.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Deb Sadhan Roy v. West Bengal[1972] I.S.C.C. 308PositiveThe Court followed Deb Sadhan Roy to support that the legality of detention hinges on timely action after the Advisory Board’s opinion within the three‑month period.
Ujjal Mandal v. West Bengal[1972] I.S.C.C. 456PositiveThe Court followed Ujjal Mandal for the principle that confirmation of detention within three months keeps detention legal, with continued detention contingent on the Board’s opinion.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,653 words•~8 min read

In The Court Record

Joydeb Gokai v. State of West Bengal

714 JOYDEB GOKAI _v._ STATE OF WEST BENGAL _July_ 24, 1972 (J. M, SHELAT, I. D. DUA AND H. R. KHANNA, JJ.] _West Bengal_ _(Prev.enti'.on_ _of_ _Violent Activities)_ _Act_ (19 _of_ 1970), _s.3(1)_ (2) _(d) mtd_ _(3)-Threct_ _lo_ _kill_ _a person and disturbing public_ _order-if_ _valid ground_ _of_ _detention-Period_ h~ithin _which c·onfinnation_ _of_ _order_ _of detention_ _by_ _State_ _Govemmcnt_ _should be passed._ Section 3(2) (d) of the West Bengal (Prevention of Violent Activities) Act, 1970, amongst other things, provides that the committing of any ot1ence punishable with imprisonment for a term extending lo 7 years or more, where the commission of such offence disturbs or is likely to disturb public order would be within the definition of the expmsion "acting in any manner prejudicial to the maintenancb of public l'lrder". In pursuance of un order under s. 3 (I) and ( 3) of the Act, the petitioner '"as arreste<,I on August 6, 1971, wi:h a view to preventin1. him tr.1m acting in any manner prejudicial to the maintenance of public ordrr. One of the grounds furnished to him was that he threatened to kill a person on account of his refusal to rub out the anti-naxalite slogan.• ~·r.i.tten on the wall of his house, that the threat terrorised the oommon public and as such they could not pur" ue their normal avocations, and thal he disturbed public order. The State Government donfirmed tee order on October 28, 1971, after receipt pf the opinion of the Advisory lloard. (Dismissing the petition under Art. 32 Challenging the order o( tWention. HELD : (1) Under s. 506 I.P.C., a threat to commit an offence !)unishablc with death or imprisonment for life shall be punishable witt unprison1nent of either description for a term which may extend to 7 years. Hence the ground furnished was not extraneous or irrelevant since the petitioner had committed an offence enumerated in s. 3(2) (d) and there was di'turbance of public order. [716A-Cl (2) There was no delay in pas<ing the order of confirm1tion, aince it wao passed before the expiry of three months from .he date of <.ktention. [716H] _Deb Sadhan_ _Ro,v_ v. _West Bmgcl,_ [1972] l S.C.C. 308 and _Ujjal Mandal_ v. _West_ _Bengal,_ [1972] I S.C.C. 456. followed, A B ## c D F ORIGINAL JURISDICTION : Writ Petition No. 39 of 1972. G Petition under Article 32 of the Constitution of India fo~ the enforcement of fundamental rights. _S._ _Lakshminarasu,_ for the petitioner. _G._ _L._ _!t{ukhoty_ and _Sukumar Basu,_ for the respondent. The Judgment of the Court was delivered by H Shelat, J. The District Magistrate, Burdwan, passed the order impugned in this petiti6n on July 14, 1971 directing the A ## c D E F G H JOYDEB v. WEST BENGAL _(She/at,_ _J.)_ _115_ petitioner's detention under sub-sec. ( 1) read witli sub-sec. (3) of sec. 3 of the West Bengal (Prevention of Violent Activities') Act, being President's Act XIX of 1970, on the ground that such detention was necessary "with a view to preventing him from acting in any manner prejudicial to the maintenance of public order". In pursuance of the order the petitioner was arrested on August 6, 1971 when he was furnished, as required by the Act, the grounds of detention. 'There is no disput that >.onsequent upon the passing of th~ said order the Government of W.est Bengal and the other relevant authorities under the Act duly took all consequential steps, such a,, the reporting to and obtaining the Government's order of approval, reporting to the Central Govrrunent, disposal of the petitioner's representation, referring the. petitioner's case to the #### Advisory 1loard and obtaining its opinion etc., within the rea pcctive times prescribed by the Act.· Two grounds questioning the validity of the said order and the detention thereunder were, however, urged by Mr. Lakshmi narasu, appearing for the petitioner _amicus_ _curiae._ The first wa.• that the first ground in the grounds of detention was irrelevant and therefore vitiated the entire order. The second was that there was undue delay in the confirmation by the State Government of the detention ordoc and the continuance of detention thereunder after the expiry of three months of detention. The first ground in the grounds of detention runs as follows : "That on 7-2-71 at 13-30 hours you and your associates had been to the house of Shri Bibhuti Bhusan Ghosh of Ranchi Dhowrah, Police Station Kulti, and asked him to rub [out) the anti-naxalite slogans written on the wall of his house. Being refused you threatened to k'.11 him. Your such act terrorised the common public and as such they could not pursue the normal avoca tions of life. Moreover, it disturbed public order." The question is whether threat to kill the said Bibhuti BhWll.ll Ghosh amounted to '·acting in any manner prejudicial to-the maintenance of public order" as defined in sec. 3(2)(d) of the Act. Cl. ( d) amongst other thin~ provides that committing any offence punishable with death or imprisonment for life or imprisonment for a term extending to seven years or more, where the commission of such offence disturbs or is likely to disturb public order, would fall within the said definition of the expres ~ion "acting in any manner prejudicial to the maintenance of public order". Sec. 506 of the Penal Code providi:s that a threat to 716 SUPREME COURT REPORTS [1973] 1 S.C.lt cause death or grievous hurt or to cause an offence . punishable with death or imprisonment for life shall be punishable with imprisonment of either description ·for a term which may extend to seven years or with fin" or both. That being so, the offence said to have been committed by the petitioner clearly was one of the offences enumerated in cl. (d) of sec. 3(2) of the Act. Ground No. (1 ) further alleges that the threat to kill the said Ghosh administered to him on account of his refusal to rub out the anti-na.xalite slogans written on the wall of his hoµse "terror#### ised the common p~ blic and as such they could not pursue the normal avocations of )ife" and furthennore, disturbed public order. This assertion, coupled with the satisfaction of the other requirement of cl. (d) of sec. 3(2), namely, 'the committal of the offence of threatening to kill, would bring the act 'in question within the expression "acting in any manner prejudicial to the maintenance of public· order" as defined in sec. 3 (2). It cannot, #### therefore, be argued that ground No. ( 1) was extraneous or irrelevant to the objects set out in sec. 3 of the Act ·and in respect of which a valid order -,f detention could be made under #### the Act. The second· contention also is not such as can be sustained. There is no dispute that the petitioner was arrested on August 6, 1971 and the order of confirmation and the impugned detention thereunder beyond the period of three months was passed by the State Government on October 28, 1971, that is within three months from the date of his arrest. Counsel, however. argued that though the decision of this Court have laid doWll that such an order of confirmation has to be passed within three months from the date of arrest, the appropriate Government has to pass such an order as soon as possible and cannot delay in doing so until the expiry of three months. In _Deb_ _Sadhan Roy_ v. _West_ _Bengal_ (1), a case under the President's Act XIX of 1970, this Court laid down that it was essential that the appropriate Government should take positive action on the report of !he Advisory Board, which action alone would determine whether the deten· #### tion was to be terminated or continued, that it would, therefore, _prima_ _facie,_ appear that that action should be taken ;immediately after the receipt of the opinion of the Board, or at any rate, within three months from the date a person was detained, and that failure to confirm or extend the period within three months would result in the detention becoming illegal, the moment the three months period elapsed without any such confirmation This decision, thus, makes it clear that the legality of a deten### tion _order or the detention thereunder would not be affected ii an order of confirmation is passed before the expiry of three [1972] I S.C.C. 308. A B # c t D E F G H A B # c D E JOYDEB _v._ WEST BENGAL _(She/at,_ /.) 717 months from the date of detootion. Similarly, in _Ujjal_ _Mandal_ v. _West Bengal('),_ Mathew, J., speaking for the Court, observed at page 459 of the report as follows : "To put the matter in a nut-shell : the State Gov-. emment has poweir under the Act to detain a person without trial beyond a period of three months, but limited' to a period of on year. That power the State Government may exercise on receij>t of the opinion of the Board that there is sufficient cause for the detention. When the State Government receives that opinion, it has stil: the option to exercise the power and to con· #### tinue the detention beyond the period of three months or not. Confirmation is the exercise of the power to continue the detention after the expiry of three months. Unless that power is exercised within the period of three months from the date of detention, the detention after the expiry of that period would be without the authority of the law." Therefore, if the order of confirmation has been passed, as it has been done in the present case, within three months' time from the date of arrest, neither the legality of the detention order nor the continued detention thereunder is affected. Both the contentions raised by counsel thus having failed. the petition also must fail and is consequently dismissed. V.P.S. _Petition_ _dismissed._ (I) [1972] IS.C.C. 456.
End of Judgment Record
Browse All Supreme Court of India (1973) Decisions
1972-12-01

A. K. Roy v. Voltas Ltd.

A.K. Roy and another filed a civil appeal against an order of the Bombay High Court, arising from a writ petition challenging excise duty assessments on Voltas Limited for years 1962, 1963, 1964-66. Voltas, a manufacturer of air-conditioners and water coolers, sold 90-95% of its goods directly to consumers at list prices and also sold to wholesale dealers under agreements that fixed list prices, offered a 22% wholesale discount, and required service by dealers. Excise duty was assessed on the basis of the wholesale cash price under s.4(a) of the Central Excises & Salt Act, 1944, and later on the retail (consumer) price under s.4(b). The central legal issue was whether the real value for duty could be determined from the price paid by wholesalers after the 22% discount, i.e., a wholesale price, or whether the price should reflect the retail price when sales to consumers are dominant. The Bombay High Court held that the wholesale cash price equals the price to wholesalers after discount, and excise duty could be charged under s.4(a). The Supreme Court, in a division bench, disagreed with the narrow interpretation of wholesale sale by reference to non-arm’s-length deals; it held that the wholesale cash price must be determined from arms-length transactions and that existence of agreements with wholesalers to grant advantages does not per se negate wholesale sale, provided the transactions are at arms length and in the ordinary course of business. The Court dismissed the appeal but suspended costs. It affirmed that a wholesale market need not be physical; the key question is whether the goods themselves can be sold wholesale at a price that is cash, net of trade discounts, and free of post‑manufacture costs.

1972-12-11

PANDHARINATH SHRIDHAR RANGNEKAR v. DY. COMMR. OF POLICE, THE STATE OF MAHARASHTRA

This appeal challenges an externment order under section 56 of the Bombay Police Act, 22 of 1951, whereby Pandharinath Shridhar Rangnekar was externed from Greater Bombay and the District of Thana for a period of two years. The externment was based on allegations that his conduct had caused alarm and danger to residents, including acts of assault and robberies, and that witnesses were not willing to depose against him in public due to fear. Rangnekar contested the notice under section 59(1), arguing that the particulars were vague and that the externment extended beyond the locality of alleged unlawful activity without proper justification. He also claimed the externing authority omitting to deliver a reasoned order and the State’s failure to provide reasons in the appeal. The Bombay High Court dismissed his petition, and he carried the matter to the Supreme Court. The Court held that to activate section 56, it suffices that witnesses are unwilling to testify in public due to apprehension; full disclosure of particulars would thwart the object of externment in cases involving organized or lawless activity. The general nature of the material allegations and the limited information under section 59(1) are proper safeguards. The externment order may cover a broader area if necessary in a large, mobile city like Bombay to subserve its purpose. The appeal is dismissed, upholding the externment order as reasonable and within statutory limits.

1972-07-24

KAMINI KUMAR DAS CHOUDHURY v. STATE OF WEST BENGAL & ORS.

Kamini Kumar Das Choudhury, a Sub-Inspector in the Enforcement Branch of the Calcutta Police, was dismissed following a departmental inquiry initiated after he allegedly left his post and engaged in disobedience and alleged leakage of information regarding proposed searches. He challenged the dismissal through a petition under Article 226 of the Constitution, arguing that the departmental proceedings violated natural justice, that ill-will or mala fide influenced the decision of the Deputy Commissioner of Police, and that the Deputy Commissioner lacked the power to dismiss him. He also claimed harassment by police authorities, which compelled him to flee to the Andaman Islands in 1952. The Calcutta High Court rejected his petition on preliminary grounds (delay and lack of jurisdiction to challenge the authority’s dismissal power). The Division Bench found possible violations of natural justice but upheld dismissal largely on the ground of delay, indicating that questions of fact in departmental proceedings should not be decided in writ proceedings. The appellant then approached the Supreme Court via a certificate under Article 133. The Court, relying on Union of India v. T.R. Varma, emphasized that writ relief under Article 226 is discretionary and not intended to resolve disputed questions of fact, especially where there is significant delay. The Court ultimately dismissed the appeal, noting that extraordinary remedies may be unavailable where delay is unreasonable, and left the petitioner to pursue civil remedies if desired. The order of dismissal stands overall, with costs to be borne by the parties themselves.

1973-03-01

Hindustan Lever Ltd. v. Ram Mohan Ray & Ors.

This judgment concerns the legality of Hindustan Lever Limited’s 1966 marketing reorganisation, which reduced three divisions to two and reorganised staff on a geographical basis. Pending a reference in West Bengal under s.10 of the Industrial Disputes Act, workers filed applications under s.33A alleging adverse changes in service conditions and non-payment of October wages. The Industrial Tribunal initially ruled in the workers’ favor in the 1966-67 proceedings, while a later reference in 1969 found for the employer. The Supreme Court, in a three-judge bench, upheld both sets of awards on a holistic review of the evidence, but limited its interference with factual findings under Article 136. The Court held that the employer’s right to reorganise its business is tempered by statutory safeguards, particularly s.9A and the Fourth Schedule’s items 8, 10 and 11, but that the particular reorganisation in this case did not amount to a change in terms and conditions of service or retrenchment. It emphasized that evidence in the main reference was not part of the 33A applications and that Article 136 review does not permit re-weighing of evidence. The Court concluded that there was no change in usage adverse to workers, no retrenchment, and that there was no notice covered by s.9A; consequently, the appeals were dismissed with no costs.