Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Single JudgeAppeal dismissed; remand order upheld; no subst...

Joseph, Libiston and Mathew v. Thomas s/o Mathew Kuzhikuthiyani

Case / Petition Number:
FAO No. 9 of 2004

Case Synopsis & Summary

This is a first appeal from an order remanding a suit arising from O.S. No. 91/1999 before the Munsiff, Idukki, involving a dispute over a road (C schedule) claimed to be formed by dedication and providing access to A and B schedule properties. The plaintiff-respondent, Thomas, sought a perpetual injunction restraining the defendants from erecting a gate at the northern end of the plaint C schedule road that connects to Murikkassery–Karimban road. The plaint A and B schedule lands are private, non-patta lands cultivated by the plaintiff, who claims exclusive possession and income. The defendants (appellants) rely on a contention that the C schedule road was constructed using portions of their land and as such is a private road, not necessarily dedicated. The trial court dismissed the suit, holding no proof of dedication. On appeal, the Sub Court remanded to the trial court, holding that absence of a sketch/plan prevented satisfactory disposal and that evidence required resettlement with a plan. The Kerala High Court, while acknowledging the complexity of land lay-out in Idukki and the need for accuracy, ultimately upheld the remand, dismissing the appeal as no substantial question of law arose, and required the parties to appear on 03.08.2009 for further proceedings. The judgment contains extensive discussion on whether the remand was warranted and how evidence should be rendered in a plan and survey context.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • V. Ramkumar
Judgment Date
2009-07-07
Court Decision / Holding
Dismissed. The High Court upheld the remand order, indicating that there was no substantial question of law arising for consideration in the appeal, and that the trial court should be provided with an opportunity to obtain a plan and further evidence to resolve the controversy regarding the lie of the properties and the nature of the C schedule road. The judge emphasized that remand was justified to enable a more satisfactory determination and that the appellate court should not substitute for the trial court in such factual matters.
Final Disposition
Appeal dismissed; remand order upheld; no substantial question of law arises in the appeal. The case is remanded to allow for a detailed plan and further evidence to resolve the lie and ownership of the pathway.

Parties to the Case

Appellants / Petitioners

  • Joseph
  • Libiston
  • Mathew

Respondents

  • Thomas s/o Mathew Kuzhikuthiyani

Legal Representation & Advocates

Counsels for Petitioners

  • • N. L. Krishnamoorthy
  • • K. Lakshminarayanan

Counsels for Respondents

  • • S. M. Prasanth

Provisions of Law Cited

Order XLIII Rule I(u) CPCOrder XLI Rule 23 CPCOrder XLI Rule 23A CPCSection 107 CPC

Legal Doctrines & Maxims

  • Title cannot pass by admission.
  • Remand should be avoided unless absolutely essential to protect the interests of justice.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that the suit was only for injunction and did not pray for a declaration, thus the question of title or origin of right on the pathway should be treated narrowly. They contended that there was direct access from plaint A schedule property to the public road, and that Ext. C2 does not PROBABILISE a conclusion of dedication. They asserted that there was a prior sale of a portion of the plaintiff’s land to the second defendant for constructing the road, and the C schedule road was formed largely on the defendants’ land, not by dedication. They urged that remand was unnecessary; the appellate court should avoid remand and decide on evidence already available, citing Sundaresan Nair (2) and India Army & Police Equipment v. Kanodia Brothers to restrict remand and rely on existing evidence.

Contentions of Respondents

The respondent-plaintiff contended that the C schedule road resulted from dedication by adjoining landowners and was the only motorable route to A and B schedule lands. He argued that the trial court failed to appreciate the nature of the road—whether by dedication or by private agreement—and that the missing plans/commissioned sketches impeded a proper adjudication. The respondent relied on historical access and the necessity of a detailed plan to determine topography and location of the properties, and supported the remand order to allow Advocate Commissioners to prepare a plan that could resolve the dispute between the parties.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Narayanan v. Kumaran2004 (4) SCC 26PositiveCited to explain that verified pleadings may be required for questions of law in a case; used to justify the petition procedure for framing questions of law.
Sundaresan Nair v. Dr. Krishnankutty Nair2007 (2) KHC 414DistinguishedQuoted by the appellant to argue against remand; the court did not follow this principle and endorsed remand based on facts.
India Army & Police Equipment v. Kanodia Brothers1968 KLT SN 19DistinguishedCited to argue against remand in some contexts; the court ultimately did not adopt that limitation, sustaining remand.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,613 words•~12 min read

In The Court Record

Joseph, Libiston and Mathew v. Thomas s/o Mathew Kuzhikuthiyani

## IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE V.RAMKUMAR TUESDAY, THE 7TH JULY 2009 / 16TH ASHADHA 1931 FAO.No. 9 of 2004() ------------------AS.55/2001 of SUB COURT,KATTAPPANA OS.91/1999 of MUNSIFF COURT, IDUKKI .................... ## APPELLANTS/RESPONDENTS/DEFENDANTS:- ----------------------------------------------------- 1. JOSEPH AGED 70, S/O. THOMAS, MUNDIYANKAL HOUSE, KARIMBAN KARA, UPPUTHODE VILLAGE, UDUMBANCHOLA TALUK. 2. LIBISTON AGED 35 YEARS, MUNDIYAMKAL HOUSE, KARIMBAN KARA, UPPUTHODE VILLAGE, UDUMBANCHOLA TALUK. 3. MATHEW, AGED 47 YEARS, MUNDIYAMKAL HOUSE KARIMBAN KARA, UPPUTHODE VILLAGE, UDUMBANCHOLA TALUK. BY ADV. MR. N.L.KRISHNAMOORTHY MR. K.LAKSHMINARAYANAN RESPONDENT/APPELLANT/PLAINTIFF:- -------------------------------------------- THOMAS S/O. MATHEW KUZHIKUTHIYANI HOUSE, KARIMBAN KARA, UPPUTHODU VILLAGE, UDUMBANCHOLA TALUK. ADV. MR. S.M.PRASANTH THIS FIRST APPEAL FROM ORDERS HAVING BEEN FINALLY HEARD ON 07/07/2009, THE COURT ON THE SAME DAY PASSED THE FOLLOWING: F.A.O. NO. 9/2004 : 2 : ORDER ON I.A. NO. 95/2004 IN F.A.O. NO. 9/2004 ## DISMISSED 07.07.2009 sd/- **V. RAMKUMAR, JUDGE.** ## V. RAMKUMAR , J. ========================== F.A.O. No. 9 of 2004 ========================== Dated this the 7[th] day of July, 2009. ## **JUDGMENT** Defendants 1 to 3 in O.S. No. 91 of 1999 on the file of the Munsiff's Court, Idukki are the appellants in this appeal filed under Order XLIII Rule I(u) C.P.C. The challenge is against the order of remand passed by the Sub Court, Kattappana in A.S. No. 55 of 2001. The following are the questions of law supplied subsequently by means of a verified petition as necessitated by the decision in Narayanan v. Kumaran – 2004 (4) SCC 26:- - 1.When the suit is merely for injunction without a prayer for declaration whether the question of title or the origin of right on the pathway arises for consideration? - 2.Whether the points for which the remand is made really arise for consideration in the suit? - 3.When admittedly the appellants are using 'C' schedule property as the pathway which is the access to their residence, has not the Lower Appellate Court gone wrong in casting the burden on the appellants? - 4.Whether there are any circumstances coming under Order XLI Rule 23 and 23A which would warrant a remand? F.A.O. No. 9/2004 : 2 : 2. The aforesaid suit filed by the respondent herein was one for a perpetual injunction restraining the defendants from putting up a gate at the northern end of the plaint C schedule road which joints the MurikkasseryKarimban road. 3. The case of the plaintiff can be summarised as follows:- The residential property of the plaintiff is situated to the north of the Murikkassery-Karimban road. The petitioner has two other plots of land situated to the south of the said Murikkassery-Karimban road. They are the plaint A and B schedule properties. The plaint A schedule property is at a distance of about 25 metres from the said road. The plaint B schedule property is further to the south of the plaint A schedule property and situated at a distance of about 50 metres. The plaint B schedule property was obtained by the petitioner about 33 years prior to the institution of the suit. Both plaint A and B schedule F.A.O. No. 9/2004 : 3 : properties are non-patta lands which have been fully cultivated by the plaintiff who is appropriating the income therefrom by keeping exclusive possession and enjoyment of the same. There was an old pathway about 3 feet wide starting from Murikkassery-Karimban public road and proceeding southwards. About 10 years prior to the institution of the suit, the said pathway was widened to a motorable road having a width of about 10 feet. The said road was constructed by utilising the portions of the plaint A and B schedule properties. Likewise, the defendants and other property owners on either side of the road had also contributed portions of their properties for the formation of the road. The plaint C schedule is the road, thus, formed. It is by way of dedication that the plaint C schedule road was formed. Except the plaint C schedule road, there is no motorable road to the plaint A and B schedule properties. The defendants are also using the plaint C schedule road for having access to their house. The properties are comprised F.A.O. No. 9/2004 : 4 : in Survey No. 1/1 of Upputhode village. On 16.04.1999, at about 10 a.m., the defendants came to the plaint C schedule road with some workers for digging ditches for the construction of concrete pillars for installing a gate at the northern end of the plaint C schedule road. Even though the said attempt was foiled by the timely intervention of the plaintiff, the plaintiff apprehends that the defendants will translate their intention into action. Hence the suit. 4. The suit was resisted by defendants 1 to 3 contending inter alia as follows:- The suit is not maintainable. The plaintiff has to prove the extent of A and B schedule properties. The plaint C schedule road is lying at a lower level than the plaint A schedule property and there is no entrance from the said road either to the plaint A schedule property or to the plaint B schedule property. No portion of the plaint A and B schedule properties has been used for the construction of the plaint C schedule road. The plaintiff is not having F.A.O. No. 9/2004 : 5 : possession of the entire plaint A schedule property. In the year 1988, the 2[nd] defendant had purchased 14.50 cents of property from the plaintiff for the construction of a motorable road for the use of the 2[nd] defendant. The plaint C schedule property was, thus, constructed by utilising the portions of the said 14 ½ cents of land. The remaining extent of the said property is still under the possession of the 2[nd] defendant. The plaint B schedule property is situated about 10 s away from the plaint A schedule property. The plaint C schedule road at the place of the plaint B schedule property has been constructed entirely through the property of the 3[rd] defendant. The plaint allegation that there was a three feet wide pathway in existence and the same was widened to form the plaint C schedule road is absolutely false. Prior to the construction of the plaint C schedule road, a way starting from the public road and passing along the eastern side of the property of Alukkal Joseph was being used for having access to the F.A.O. No. 9/2004 : 6 : property of the 2[nd] defendant. The said pathway is even now in existence and it is being used by the plaintiff also. The plaint C schedule road has been constructed in the year 1990 and the plaintiff has never used the said road. It is a private road over which the plaintiff has no right. The plea of dedication as pleaded in the plaint is absolutely false. 5. On the side of the plaintiff, three witnesses were examined as PWs 1 to 3 of whom PW1 is the plaintiff himself. PW2 is a neighbour and PW3 is an assignee from the plaintiff. On the side of the defendants, four witnesses were examined as DWs 1 to 4 of whom DW1 is the 2[nd] defendant. DW2 is a neighbour and DW3 is a witness to Ext.B2 agreement for sale and DW4 is the Advocate Commissioner who submitted Ext.C2 report dated 29.11.2000. 6. The learned Munsiff, after trial, as per judgment and decree dated 28.02.2001 dismissed the suit holding that the case of the plaintiff was one of dedication and the F.A.O. No. 9/2004 : 7 : plaintiff had miserably failed to prove the said case. On appeal preferred by the plaintiff as A.S. No. 55 of 2001 before the Sub Court, Kattappana, the learned Subordinate Judge as per the impugned judgment dated 03.07.2003 set aside the judgment and decree passed by the trial court and remanded the case to the trial court after holding that even though two Advocate Commissioners had been deputed by the trial court, there was not even a sketch or plan enabling the court to decide the case satisfactorily. The lower appellate court was also of the view that the case of the plaintiff was really not dedication, but the formation of the plaint C schedule road by contributing portions of property by the adjoining owners and that there was no evidence before court to show that a portion of the plaintiff’s property was sold to the 2[nd] defendant for the specific purpose of constructing the plaint C schedule road as contended by the defendants. It is the said order of remand which is assailed in this appeal by the defendants. F.A.O. No. 9/2004 : 8 : 7. I heard the counsel appearing on either side. 8. Adv. Shri. K. Lakshminarayan, the learned counsel appearing for the appellants made the following submissions before me in support of the appeal:- It was after a careful analysis of the pleadings and evidence that the trial court came to the conclusion that the plaintiff has miserably failed to establish the dedication set up by him. The suit was only for injunction simplicitor without any prayer for declaration. The plaintiff examined as PW1 has admitted that he had sold 14 ½ cents of his property to the 2[nd] defendant. The plaintiff has further admitted that there is direct access from the plaint A schedule property to the public road on the north. Hence the observation in paragraph 15 of the judgment of the lower appellate court that the plaint A schedule property is 25 feet to the south of the public road leaving a gap in between the road and the said property, was not justified. Ext.C2 report of the Advocate Commissioner does not F.A.O. No. 9/2004 : 9 : probabalise such a conclusion. It is true that there was no sketch or plan prepared by the Advocate Commissioner. But then, that is hardly a reason for remanding the case to the trial court. As observed by this Court in **Sundaresan Nair v. Dr. Krishnankutty Nair** – 2007 (2) KHC 414 as far as possible, appellate court should avoid a remand unless it is absolutely essential to protect the interests of justice and a remand for incorporating a prayer for declaration in that case was also held unnecessary and erroneous. The apex court has also observed in **India Army & Police Equipment v. Kanodia Brothers -** 1968 KLT SN 19 that in a case where there has already been a trial on evidence before the court of first instance, the appellate power of remand should not be exercised merely because the appellate court is of the view that the parties who could lead better evidence have failed to do so. 9. I am afraid that I cannot agree with the above submissions. This is a case arising from Idukki where the F.A.O. No. 9/2004 : 10 : legal profession has not attained that much experience or acumen as could be expected from their counterparts in the urban courts. When this Court deals with a case arising from Idukki, this aspect of the matter cannot be lost sight of and the pleadings have to be approached with some amount of latitude. 10. Even I was finding it difficult to get an idea about the lie of the plaint A and B schedule properties and that of the plaint C schedule road. It appears that the Murikkassery-Karimban road which is a public road runs east-west and the land to the south of the said road is proceeding at a gradient. The plaintiff is residing in a property situated to the north of the said road. The plaintiff has two plots of land namely the plaint A and B schedule properties situated to the south of the said road. Even in the plaint, it is pleaded that the plaint A schedule property is situated at a distance of 25 s from the Karimban – Murikkassery public road. Therefore, the appellate court F.A.O. No. 9/2004 : 11 : was fully justified in assuming that in between the public road and the plaint A schedule property, there is another property. Hence, even if the plaintiff has admitted that he has direct access from the plaint A schedule property to the public road, when no portion of the plaint A schedule property actually touches the public road the alleged access, if any, could only be through the property of somebody else. For a better comprehension of the lie of the land and the topography of the geographical locations of the respective properties, it was necessary that the Commissioner who was deputed by the trial court should have submitted a plan. Without such a plan, the lower appellate court was fully justified in observing that it is not possible to decide the case in a satisfactory manner. I fully endorse the said view taken by the lower appellate court. Except pleading that a portion of the property of the plaintiff was purchased by the defendants and they constructed the plaint C schedule road for their exclusive F.A.O. No. 9/2004 : 12 : use, the document of sale, if any, was not produced before court. Merely because the plaintiff examined as PW1 has admitted that he had given a portion of his property to the defendant, it cannot be said that that is conclusive proof of transfer and that too for the purpose of constructing the plaint C schedule road. It is well settled that title cannot pass by admission. 11. The specific case of the plaintiff is that there was another pathway in the place of the plaint C schedule road and the said pathway was widened into an existing road by the adjoining owners including the plaintiff contributing portions of their properties free of cost to make the present road. If the said contention of the plaintiff as pleaded in the plaint is true, then it is not a case of dedication, as rightly observed by the lower appellate court. When the materials before the court were not complete so as to enable the court to pronounce a satisfactory judgment, the court below was fully justified in remanding the case to the trial court so F.A.O. No. 9/2004 : 13 : as to enable the plaintiff to take out a Commission who will have to submit a detailed plan showing the lie of the properties and incorporating matters which are relevant for the resolution of the controversy between the parties. Merely because the appellate court has all the powers of the trial court in view of Section 107 C.P.C., this is not a fit case where the appellate court should take additional evidence, including the appointment of a Commission and decide the matter. The trial court which is more proximate to the property in question will be in a better position to issue a Commission and dispose of the suit satisfactorily so that the parties may also get an opportunity of a forum of appeal before the lower appellate court. I, therefore, do not find any good ground to interfere with the conclusions reached by the lower appellate court as also the remit made by that court. On the facts and circumstances of the case, I do not find that the questions of law formulated by the appellant arise for consideration in this appeal. On the contrary, I am F.A.O. No. 9/2004 : 14 : satisfied that no substantial question of law arises in this appeal which is accordingly dismissed upholding the remand order passed by the appellate court. The parties shall appear before the trial court on **03.08.2009** without any further notice. Dated this the 7[th] day of July, 2009. **V. RAMKUMAR, JUDGE.** rv F.A.O. No. 9/2004 : 15 :
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.