Supreme Court of IndiaSupreme Court · 2021Division BenchAppeal dismissed. The respondent’s application ...

JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED

Case / Petition Number:
Civil Appeal No. 6145 of 2010
Neutral Citation:[2021] 4 S.C.R. 454

Case Synopsis & Summary

The respondent, a small-scale industry, held a high-tension electricity connection (325 KVA initially, later enhanced to 4,000 KVA) under an agreement with the Jharkhand State Electricity Board (Board) dated 14 April 2004. The respondent repeatedly sought load enhancements (to 1,325 KVA in 2006, to 3,500 KVA in 2006, and to 4,000 KVA in 2007). For each enhancement, fresh agreements were entered, culminating in an agreement dated 7 July 2007 for 4,000 KVA. Due to trippings and heavy load shedding, the respondent then sought reduction to 1,325 KVA on 20 September 2007. The Board rejected this on 8 November 2007, treating it as a case of determination under Clause 9B of the agreement and relying on a three-year initial period. The respondent challenged in the Jharkhand High Court, which allowed the writ petition; the Board appealed. The Supreme Court held that Regulation 9.2 of the Jharkhand Regulations, 2005 governs reductions of contract load, and that no reduction is allowed only before expiry of the initial period as per Regulation 9.2.1. The Court reasoned that the initial agreement for the purpose of reduction is the original 14 April 2004 agreement, and the subsequent 7 July 2007 agreement was an amendment, not a fresh agreement. Consequently, Regulation 9.2 applies, and the reduction could be deemed allowed. The appeal was dismissed with a direction that the respondent’s reduction be treated accordingly and entitled to consequential benefits.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • L. Nageswararao
  • Vineet Saran, J.
Judgment Date
2021-04-30
Court Decision / Holding
Appeal dismissed. The Supreme Court held that Regulation 9.2 governs reductions; reductions cannot be refused before expiry of the initial three-year period only if applicable to the initial agreement. Since the initial agreement for reduction purposes is the 14 April 2004 agreement, and the 7 July 2007 agreement was merely an amendment, the respondent’s 20 September 2007 reduction request falls under Regulation 9.2 and should be deemed allowed with consequential benefits.
Final Disposition
Appeal dismissed. The respondent’s application for reduction of contract load from 4000 KVA to 1325 KVA would be deemed to have been allowed under Regulation 9.2 of the Regulations of 2005, with the respondent entitled to all consequential benefits.

Parties to the Case

Appellants / Petitioners

  • Jharkhand State Electricity Board

Respondents

  • M/S Ramkrishna Forging Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Anup Kumar
  • • Saurabh Jain
  • • Ms. Neha Jaiswal
  • • Shivam Kumar
  • • Ms. Shruti Singh

Counsels for Respondents

  • • Navniti Prasad Singh, Sr. Adv.
  • • Devashish Bharuka
  • • Dhanjay C Pathak
  • • Vaibhav Niti
  • • Ms. Sarvshree
  • • Justine George
  • • Ms. Srishti Agarwal
  • • Ms. Taniya Bansal

Provisions of Law Cited

Electricity Act, 2003, Section 181(2)(x) read with Section 50Jharkhand State Electricity Regulatory Commission (Electricity Supply Code) Regulations, 2005 (Regulations of 2005)Regulation 9.1 (Enhancement of Contract Demand/Sanctioned Load)Regulation 9.2 (Reduction of Contract Demand/Sanctioned Load)Regulation 9.2.1 (no reduction before expiry of initial period)Regulation 9.2.2 (documents required for reduction)Regulation 9.2.3 (time-bound decision)Regulation 9.2.4 (deemed sanction if not communicated)Regulation 9.2.5 (effective date of reduction)Regulation 9.2.6 (execution of supplementary agreement)Clause 9B of the agreementClause 2(l) of Regulations (Definition of Contract Demand)initial three-year period from commencement of supply (07.07.2007)Regulation 2(l) (contract demand defined)

Legal Doctrines & Maxims

  • Regulations are to be liberally interpreted in favour of the consumer
  • Fair and reasonable treatment of consumers by a State instrumentality (Board)
  • The Board, as a monopoly, must act in a fair and reasonable manner and in accordance with the Regulations

Submissions & Arguments

Contentions of Appellants / Petitioners

The Board submitted that Regulation 9.2.1 prohibits reduction before expiry of the initial three-year period and that a fresh agreement for enhanced load created a definite initial period (the three years) from 07.07.2007. It argued that the 20.09.2007 reduction application falls within that period and should be treated as an attempt to determine the existing agreement under Clause 9B, not a reduction under Regulation 9.2. It contended that even if enhancements involved fresh documents, they were extensions/amendments of the initial contract and the Regulations must be read to allow such interpretation.

Contentions of Respondents

The respondent contended that the 2007-enhancement agreements for the same connection were merely extensions/amendments of the original 14.04.2004 agreement and not fresh agreements. Regulation 9.2 does allow reductions after the initial period, and 9.2.6 contemplates execution of a supplementary agreement. The respondent argued that the application dated 20.09.2007 should be treated under Regulation 9.2 as a valid request for reduction after the three-year period and thus should be allowed, including associated benefits, rather than being treated as a tentative step toward termination.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Bihar State Electricity Board, Patna and Others v. M/s. Green Rubber Industries and Others(1990) 1 SCC 731DistinguishedDistinguishable on facts; relates to minimum guarantee charge under the old Electricity Act.
Orissa State Electricity Board v. Orissa Tiles Limited(1993) Supp. 3 SCC 481DistinguishedDistinguishable on facts; related to minimum guarantee charge under older Act.
Andhra Steel Corporation Ltd. and Others v. Andhra Pradesh State Electricity Board and Others(1991) 3 SCC 263DistinguishedDistinguishable on facts; related to minimum guarantee charge.
Jharkhand State Electricity Board & Others v. Laxmi Business and Cement Company Private Limited and Another(2014) 5 SCC 236DistinguishedDistinguishable on facts; relates to minimum guarantee charge under newer framework.
[1989] 2 Suppl. SCR 275DistinguishedDistinguished Para 17 (older citation; used for context)
[1993] 2 SCR 860DistinguishedDistinguished Para 17 (older citation; used for context)
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,527 words•~21 min read

In The Court Record

JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED

454 SUPREME COURT REPORTS [2021] 4 S.C.R. 454 [2021] 4 S.C.R. ## A JHARKHAND STATE ELECTRICITY BOARD AND OTHERS v. ## M/S RAMKRISHNA FORGING LIMITED (Civil Appeal No. 6145 of 2010) B APRIL 30, 2021 ## **[L. NAGESWARA RAO AND VINEET SARAN, JJ.]** - _Electricity: Jharkhand State Electricity Regulatory_ - _Commission (Electriity Supply Code) Regulations, 2005 – Regns.9.1, 9.2 – On 14.04.2004, the respondent, small scale industry entered_ - C _into an agreement with Board for High Tension connection of 325 KVA load – Thereafter, on 14.03.2006, respondent applied for enhancement of load from 325 KVA to 1325 KVA, which was sanctioned – On 26.12.2006, respondent again applied for enhancement of load from 1325 KVA to 3500 KVA which was also_ - D _sanctioned by Board – On a further request of respondent, on 07.07.2007, the load was again enhanced to 4000 KVA – Due to continuous load shedding, which was affecting machineries, respondent decided to reduce load from 4000 KVA to 1325 KVA – However, the application to that effect was rejected treating it to be a case of determination of agreement, and quoting the Clause 9B_ - E _of the agreement which provided that the agreement could not be permitted to be determined prior to the completion of initial period of three years from 07.07.2007 and that the respondent will have to pay the minimum guarantee charges and other charges, even if the respondent decides to terminate the agreement – Respondent_ - F _successfuly filed writ petition before High Court – Board filed instant appeal – Held: Chapter 9 of the Regulations of 2005 deals with the enhancement and reduction of contract demand/sanctioned load – Regn.9.1 deals with enhancement of contract demand/sanctioned load, whereas Regn.9.2 deals with the reduction of contract demand/ sanctioned load – Regn.9.2.6 of the Regulations of 2005 provides_ - G _for execution of a supplementary agreement for reduction of contract demand/sanctioned load of the consumer – If the Regulations provide for contract load to be varied even through a written communication, then in all fairness, though fresh agreements may have been executed at the stage of enhancement of load of the_ - H 454 455 JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED _same electricity connection, the same cannot be treated as anything but an extension/amendment or modification of the initial agreement granting the electricity connection, which in the present case would be the agreement dated 14.04.2004 – Thus, even though the consumer may have been required to sign fresh agreements for each enhancement of load, but the enhancement being for the same electricity connection which still continues, it would merely be amendment of the initial agreement – This would also be in consonance with the provisions of the Regulations of 2005, which have to be liberally interpreted in favour of the consumer – The Board was wrong in treating the application of the respondent for reduction of load to be that for determination of the agreement under Clause 9B of the agreement, which application, in fact, ought to have been considered under Regn. 9.2 of the Regulations of 2005 – The agreement to be considered in the present case is the initial agreement dated 14.04.2004 and not the subsequent agreement dated 07.07.2007._ A B C D ## **Dismissing the appeal, the Court** **HELD : 1. After the initial agreement dated 14.04.2004, which came into effect from 16.04.2004 whereby the contract demand of 325 KVA was allowed in favour of the respondent, the Jharkhand State Electricity Regulatory Commission in exercise of power conferred by Section 181(2)(x) read with Section 50 of the Electricity Act, 2003, framed the Jharkhand State Electricity Regulatory Commission (Electricity Supply Code) Regulations, 2005, which came into effect from 28.07.2005. [Para 5][459-F-H]** **2.1 The communication dated 08.11.2007 of the Electrical Superintending Engineer of the Board, refusing the prayer of the respondent for reduction of load showed that the application of the respondent for reduction of load was rejected in terms of Clause 9(B) of the agreement, treating the date of commencement of the agreement to be 7/12.07.2007 and only by considering the provision of determination of the agreement, which could not have been without giving notice of less than 12 calendar months. It is clear that the said communication/order does not consider the provisions of the Regulations of 2005 with regard to reduction of load, but only treats the application for reduction of load to be an** E F G H 456 SUPREME COURT REPORTS [2021] 4 S.C.R. - A **application for determination of the agreement. [Paras 9, 11] [463-B; 464-A-C]** **2.2 Chapter 9 of the Regulations of 2005 deals with the enhancement and reduction of contract demand/sanctioned load. Regulation 9.1 deals with enhancement of contract demand/** B **sanctioned load, whereas Regulation 9.2 deals with the reduction of contract demand/sanctioned load. Just as the consumer has the liberty of getting its load enhanced under Regulation 9.1, the reduction of contract demand/sanctioned load can also be prayed for and decided in terms of Regulation 9.2. The proviso to Regulation 9.2.1, no doubt, provides that no reduction of load** C **shall be allowed before expiry of the initial period of agreement, which is three years in the present case. The question would be whether the initial agreement is to be considered for such purpose, or the subsequent agreements. [Paras 12, 13] [464-C-F]** - D **3. Regulation 9.2.6 of the Regulations of 2005 provides for** - **execution of a supplementary agreement for reduction of contract demand/sanctioned load of the consumer. Similarly, for enhancement of load also, even if a fresh agreement may have been executed between the parties, the same could be treated** - E **as nothing but a supplementary agreement of the initial agreement by which the electricity connection was granted for a particular load. Clause 2(l) of the Regulations also defines “contract demand” to be demand mutually agreed in the agreement** _**or agreed through other written communication**_ **, meaning thereby that for variation of the contract demand execution of a fresh** - F **agreement is not essential and the same can be done otherwise also by mere written communication. [Para 14][464-F-H]** **4. The Jharkhand State Electricity Board (‘the Board’) is a monopoly supplier of electricity which has laid down its own terms and conditions, regarding which the consumer has no say or choice** G **but to sign on the dotted lines, if it wants of get electricity load varied for running its industry. The Board is an instrumentality of the State. It has to be fair and reasonable. If the Regulations provide for contract load to be varied even through a written** H 457 JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED **communication, then in all fairness, though fresh agreements may** A **have been executed at the stage of enhancement of load of the same electricity connection, the same cannot be treated as anything but an extension/amendment or modification of the initial agreement granting the electricity connection, which in the present case would be the agreement dated 14.04.2004. On the** B **dictates of the Board, the consumer may have been required to sign fresh agreements for each enhancement of load, but the enhancement being for the same electricity connection which still continues, it would merely be amendment of the initial agreement. This would also be in consonance with the provisions of the Regulations of 2005, which have to be liberally interpreted in** C **favour of the consumer. [Para 15][465-A-D]** **5. The Board has gone wrong in treating the application dated 20.09.2007 of the respondent for reduction of load to be that for determination of the agreement under Clause 9B of the agreement, which application, in fact, ought to have been considered under Regulation 9.2 of the Regulations of 2005. The agreement to be considered in the present case is the initial agreement dated 14.04.2004 and not the subsequent agreement dated 07.07.2007. [Para 16][465-D-F]** _Bihar State Electricity Board, Patna and Others v. M/s. Green Rubber Industries and Others_ **(1990) 1 SCC 731 : [1989] 2 Suppl. SCR 275;** _Orissa State Electricity Board v. Orissa Tiles Limited_ **(1993) Supp. 3 SCC 481 : [1993] 2 SCR 860;** _Andhra Steel Corporation Ltd. And Others v. Andhra Pradesh State Electricity Board and Others_ **(1991) 3 SCC 263 : [1991] 2 SCR 624;** _Jharkhand State Electricity Board & Others v. Laxmi Business and Cement Company Private Limited and Another_ **(2014) 5 SCC 236 : [2014] 3 SCR 453 – distinguished.** ## **Case Law Reference** D E F G **[1989] 2 Suppl. SCR 275 distinguished Para 17 [1993] 2 SCR 860 distinguished Para 17** H 458 SUPREME COURT REPORTS [2021] 4 S.C.R. - A **[1991] 2 SCR 624 distinguished Para 17 [2014] 3 SCR 453 distinguished Para 17** CIVIL APPELLATE JURISDICTION : Civil Appeal No. 6145 of 2010. B From the Judgment and Order dated 23.07.2008 of the High Court Jharkhand at Ranchi in W.P. (C) No. 6651 of 2007. Anup Kumar, Saurabh Jain, Ms. Neha Jaiswal, Shivam Kumar, Ms. Shruti Singh, Advs. for the Appellants. Navniti Prasad Singh, Sr. Adv., Devashish Bharuka, Dhanjay C Pathak, Vaibhav Niti, Ms. Sarvshree, Justine George, Ms. Srishti Agarwal, Ms. Taniya Bansal, Advs. for the Respondent. The Judgment of the Court was delivered by ## **VINEET SARAN, J.** D 1. The respondent is a small scale industry. For running its industry, it had a contract demand/sanctioned load of electricity of 4000 KVA from the appellants-Jharkhand State Electricity Board (for short ‘the Board’). The request of the respondent for reduction of such sanctioned load to 1325 KVA having been refused, the respondent filed a writ petition before the High Court of Jharkhand, which has been allowed. Aggrieved E by the said judgment of the High Court, this appeal has been preferred by the Board. 2. The brief facts, relevant for the present case, are that the respondent, which is a small scale industry, had entered into an agreement with the Board on 14.04.2004 for High Tension (H.T.) connection of F 325 KVA load. The respondent thereafter applied for enhancement of load from 325 KVA to 1325 KVA, which was allowed by the General Manager-cum-Chief Engineer of the Board on 14.03.2006. The respondent again applied for enhancement of load from 1325 KVA to 3500 KVA, which was sanctioned by the Board on 26.12.2006. On a G further request of the respondent, the load was again enhanced by 500 KVA to 4000 KVA. For each enhancement of load, fresh agreements to that effect were entered into between the respondent and the Board, the last one being on 07.07.2007 for supply of 4000 KVA load. The respondent alleges that after the enhancement of load, it was facing major trippings as well as continuous load shedding which was affecting H 459 JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.] the costly machineries and, therefore, the respondent decided to reduce the load from 4000 KVA to 1325 KVA. Accordingly, the respondent filed an application, on 20.09.2007, before the authority of the appellantsBoard for such reduction. Vide its order dated 08.11.2007, the Electrical Superintending Engineer rejected the said application of the respondent for reduction of load from 4000 KVA to 1325 KVA informing the respondent that from the date of enhancement of supply of load, an agreement (dated 07.07.2007) would be enforced for a period of three years and treating it to be a case of determination of agreement, and quoting the Clause 9B of the agreement, it was provided that the agreement could not be permitted to be determined prior to the completion of initial period of three years from 07.07.2007 and that the respondent will have to pay the minimum guarantee charges and other charges, even if the respondent decides to terminate the agreement. 3. Challenging the said order of the Board dated 08.11.2007, the respondent filed Writ Petition No.6651 of 2007, which has been allowed by the High Court vide its judgment dated23.07.2008, primarily on the ground that the proviso contained in Regulation 9.2.1 of the Jharkhand State Electricity Regulatory Commission (Electricity Supply Code) Regulations, 2005 (for short, ‘the Regulations of 2005’), providing for no reduction of load to be allowed by the Distribution Licensee before expiry of the initial period of agreement was discriminatory, arbitrary and against the public policy. Challenging the aforesaid judgment, this appeal has been filed. 4. We have heard Shri Anup Kumar, learned counsel appearing for the appellants and Shri N.P. Singh, learned Senior Counsel appearing for the respondent, assisted by Shri Devashish Bharuka, Advocate-onRecord for the respondent. 5. It is noteworthy that after the initial agreement dated 14.04.2004, which came into effect from 16.04.2004 whereby the contract demand of 325 KVA was allowed in favour of the respondent, the Jharkhand State Electricity Regulatory Commission (for short, ‘the Commission’) in exercise of power conferred by Section 181(2)(x) read with Section 50 of the Electricity Act, 2003, framed the Jharkhand State Electricity Regulatory Commission (Electricity Supply Code) Regulations, 2005, which came into effect from 28.07.2005. 6. The submission of the learned counsel for the appellants-Board, is that in terms of Regulation 9.2.1 of the Regulations of 2005, which A B C D E F G H 460 SUPREME COURT REPORTS [2021] 4 S.C.R. - A relates to the reduction of contract demand/sanctioned load, no reduction of load could be allowed before the expiry of the period of agreement which, according to the appellants, would be 07.07.2007 when a fresh agreement was executed for enhanced load of 4000 KVA. Learned counsel for the appellants has thus submitted that the application for reduction of load filed by the respondent on 20.09.2007, which was well - B within the period of three years from 07.07.2007, was rightly rejected by the Board vide its order dated 08.11.2007, as it was in conformity with the provisions of the Regulations of 2005. 7. Per contra, learned Senior Counsel appearing for the respondent has submitted that the agreement was initially entered into on 14.04.2004 C and thereafter even though technically fresh agreements may have been executed for enhancement of load of the respondent, but the same were only extension/amendment of the initial agreement dated 14.04.2004, and the terms of each of these agreements were identical, with the only change being that of the increased contracted load. It has been contended - D by the learned Senior Counsel for the respondent that the Regulations do not permit execution of a fresh agreement in case of enhancement of load, and the enhancement agreements would merely be supplementary agreements in continuation of the initial agreement dated 14.04.2004 and cannot be treated as fresh agreement because it is the same electricity connection, which was granted by the agreement dated 14.04.2004, in - E which there have been amendments from time to time for increase of load, and merely executing a fresh agreement for enhancement of load cannot be termed as fresh agreement for the purpose of Regulations of 2005. It has, thus, been submitted that the application of the respondent for reduction of load dated 20.09.2007 has to be treated as after a period - F of three years from the date of initial agreement dated 14.04.2004 and thus, the application of the respondent ought to have been allowed and/ or should be deemed to be allowed in terms of the provisions of Regulations of 2005. In this regard, reliance has been placed on Regulations 2(l), 9.1 and 9.2 of the Regulations of 2005. - G 8. For the ready reference, the relevant provisions of the Regulations of 2005 are reproduced below:- - _**“2. Definitions. 2.1** In these regulations, unless the context otherwise requires:_ - _(a)….._ H 461 JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.] _(b)….. (c)….._ A _……..._ _**(l) “Contract Demand”** means demand in Kilowatt (KW) or Kilo Volt amperes (KVA) or H.P (Horse Power) mutually agreed_ B _between the Distribution Licensee and the consumer as entered into agreement or agreed through other written communication._ _(m)….._ **==> picture [31 x 11] intentionally omitted <==** C ## _**9. Enhancement and Reduction of Contract Demand/ Sanctioned Load. –**_ ## _**9.1Enhancement of Contract Demand /Sanctioned Load**_ _**9.1.1** The application for enhancement of Contract Demand/_ D _Sanctioned Load shall be made in the prescribed form and in the manner as specified in new service connection in Clause 5 of these Regulations._ _**9.1.2** The application for enhancement of load shall be disposed of in the manner and within the time frame as_ E _prescribed for new service connection in Clause 6.2.11 of these Regulations._ _**Provided** that the application for enhancement of Contract Demand/Sanctioned Load may be outright rejected by the distribution licensee if the consumer is in arrears of licensee’s_ F _dues and the same have not been stayed by a court of law or the Commission._ ## _**9.2 Reduction of Contract Demand/Sanctioned Load. -**_ _**9.2.1** The application for reduction of Contract Demand/ Sanctioned Load shall made in the prescribed form specified_ G _for the new service connection._ _**Provided** that no reduction of load shall be allowed by the Distribution Licensee before expiry of the initial period of agreement._ H 462 SUPREME COURT REPORTS [2021] 4 S.C.R. A _**9.2.2** The application for reduction of load shall be accompanied by-_ _(i) Details of modification, alteration and removal of electrical installation with completion certificate and test report of the Licensed Electrical contractor._ B _(ii) Any other reason for reduction of load_ _(iii) Details of generator if any installed by the consumer with safety clearance certificate from competent authority as applicable._ C D E F G _**9.2.3** The Distribution Licensee shall consider the application verify the same and communicate in writing its decision on reduction of Contract Demand/Sanctioned Load in writing within 30 days of the application._ _**Provided** that if the distribution licensee rejects or refuses the reduction of Contract Demand/Sanctioned Load it shall do so after affording the consumer reasonable opportunity of being heard in the matter and after communicating in writing the reasons for such refusal._ _**9.2.4** If the decision of the application for reduction of Contract Demand/Sanctioned Load is not communicated by the licensee within 30 days of the application, the consumer shall send a notice to the licensee requesting for disposal in the matter and if the decision is still not communicated within 15 days of the notice. The reductions of Contract Demand/ Sanctioned Load shall be deemed to have been sanctioned, from the 16th day after the issue of notice to the licensee by the consumer._ _**9.2.5** The reduction of Contract Demand/Sanctioned Load shall come into effect from the first day of the month following the month in which the reduction of load has been sanctioned or have been deemed to be sanctioned._ _**9.2.6** After the sanction of the reduction of Contract Demand/ Sanctioned Load the consumer shall execute a supplementary agreement and the licensee shall recalculate the Security Deposit excess Security Deposit if any shall be refunded by_ H 463 JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.] _way of adjustment in the minimum number of succeeding bills_ A _of the consumer.”_ _(emphasis supplied)_ 9. The communication dated 08.11.2007 of the Electrical Superintending Engineer of the Board, refusing the prayer of the respondent for reduction of load, is reproduced below:- B - _“Sub: Regarding the reduction of load from 4000 KVA to 1325 KVA in respect of M/s R.K. Forging Ltd. Conn. No. HJAP-185_ _Ref: Your letter No. R.K.F.L/III and IV 182/07-08 dated 05.10.2007._ C _With respect to the above, you have applied for reduction of C.D from 4000KVA to 1325KVA. It is to inform you that C/9B of agreement may kindly be seen._ _‘C/9B- The consumer shall not be at liberty to determine this agreement before the expiration of three years from the date of commencement of the supply of energy (4000KVA w.e.f. 12.07.2007). The consumer may determine this agreement with effect from any date after the said period on giving to the Board not less than twelve calendar months’ previous notice (this has charged not less than 6 Month Notice vide Secretary, Jharkhand State Electricity Board Notification No.5058 dated 20.08.2002) in writing in that behalf and upon the expiration of the period of such notice. This agreement shall cease and determine without prejudice to any right which then have accrued to the Board herewith provided always that the consumers may at any time with the previous consent of the Board transfer and assign this agreement to any other person and upon subscription of such transfer, this agreement shall be binding on the transferee and Board and take effect in all respects as if transferee had originally been party in place of the consumer who shall henceforth be discharged from all liabilities under or in respect thereof.’_ _Hence your request for reduction cannot be done as per agreement.”_ D E F G H 464 SUPREME COURT REPORTS [2021] 4 S.C.R. A 10. Heard learned Counsel for the parties and have carefully gone through the record. 11. From perusal of the communication dated 08.11.2007, it is clear that the application of the respondent for reduction of load has been rejected in terms of Clause 9(B) of the agreement, treating the B date of commencement of the agreement to be 7/12.07.2007 and only by considering the provision of determination of the agreement, which could not have been without giving notice of less than 12 calendar months. It is clear that the said communication/order does not consider the provisions of the Regulations of 2005 with regard to reduction of load, but only treats the application for reduction of load to be an application C for determination of the agreement. 12. Chapter 9 of the Regulations of 2005 deals with the enhancement and reduction of contract demand/sanctioned load. Regulation 9.1 deals with enhancement of contract demand/sanctioned load, whereas Regulation 9.2 deals with the reduction of contract demand/ D sanctioned load. 13. Just as the consumer has the liberty of getting its load enhanced under Regulation 9.1, the reduction of contract demand/sanctioned load can also be prayed for and decided in terms of Regulation 9.2. The proviso to Regulation 9.2.1, no doubt, provides that no reduction of load E shall be allowed before expiry of the initial period of agreement, which is three years in the present case. The question would be whether the initial agreement is to be considered for such purpose, or the subsequent agreements. 14. Regulation 9.2.6 of the Regulations of 2005 provides for F execution of a supplementary agreement for reduction of contract demand/sanctioned load of the consumer. Similarly, for enhancement of load also, even if a fresh agreement may have been executed between the parties, the same could be treated as nothing but a supplementary agreement of the initial agreement by which the electricity connection G was granted for a particular load. Clause 2(l) of the Regulations also defines “contract demand” to be demand mutually agreed in the agreement _or agreed through other written communication_ , meaning thereby that for variation of the contract demand execution of a fresh agreement is not essential and the same can be done otherwise also by mere written communication. H 465 JHARKHAND STATE ELECTRICITY BOARD v. M/S RAMKRISHNA FORGING LIMITED [VINEET SARAN, J.] 15. It is noteworthy that the Jharkhand State Electricity Board (‘the Board’) is a monopoly supplier of electricity which has laid down its own terms and conditions, regarding which the consumer has no say or choice but to sign on the dotted lines, if it wants of get electricity load varied for running its industry. The Board is an instrumentality of the State. It has to be fair and reasonable. If the Regulations provide for contract load to be varied even through a written communication, then in our considered view, in all fairness, though fresh agreements may have been executed at the stage of enhancement of load of the same electricity connection, the same cannot be treated as anything but an extension/ amendment or modification of the initial agreement granting the electricity connection, which in the present case would be the agreement dated 14.04.2004. On the dictates of the Board, the consumer may have been required to sign fresh agreements for each enhancement of load, but the enhancement being for the same electricity connection which still continues, it would merely be amendment of the initial agreement. This would also be in consonance with the provisions of the Regulations of 2005, which have to be liberally interpreted in favour of the consumer. 16. Reverting to the order dated 08.11.2007, which was impugned in the writ petition, we are of the opinion that the Board has gone wrong in treating the application dated 20.09.2007 of the respondent for reduction of load to be that for determination of the agreement under Clause 9B of the agreement, which application, in fact, ought to have been considered under Regulation 9.2 of the Regulations of 2005. Further, we are unable to accept the submission of the learned Counsel for the appellant that the application of the respondent for reduction of load was within the period of three years, because as we have discussed hereinabove, the agreement to be considered in the present case is the initial agreement dated 14.04.2004 and not the subsequent agreement dated 07.07.2007. 17. The judgments of this Court rendered in **Bihar State Electricity Board, Patna and Others** v. **M/s. Green Rubber Industries and Others** , (1990) 1 SCC 731, **Orissa State Electricity Board** v. **Orissa Tiles Limited** , (1993) Supp. 3 SCC 481, **Andhra Steel Corporation Ltd. and Others** v. **Andhra Pradesh State Electricity Board and Others,** (1991) 3 SCC 263 and **Jharkhand State Electricity Board & Others** v **Laxmi Business and Cement Company Private Limited and Another** , (2014) 5 SCC 236 as have A B C D E F G H 466 SUPREME COURT REPORTS [2021] 4 S.C.R. - A been relied upon by learned counsel for the parties, are distinguishable on facts, in as much as they all relate to minimum guarantee charge, and that too under the old Electricity Act of 1910, as is so in the first three cases. 18. In view of the aforesaid, we are of the opinion that the B application of the respondent dated 08.11.2007 ought to have been allowed by the Board in terms of Regulation 9.2 of the Regulations of 2005, treating the application to be beyond the period of three years from the date of the execution of the initial agreement dated 14.04.2004, by which the electricity connection of the respondent had been initially granted. C 19. While dismissing the appeal, we are not going into the question as to whether the provisions of Regulation 9.2.1 are discriminatory, arbitrary and against the public policy, as has been held by the Jharkhand High Court vide its judgment dated 23.07.2008. 20. The appeal is, accordingly, dismissed. No order as to costs. D 21. The application of the respondent dated 20.09.2007 for reduction of contract load/sanctioned load from 4000 KVA to 1325 KVA would be deemed to have been allowed under the provisions of Regulation 9.2 of the Regulations of 2005, and the respondent shall be entitled to all consequential benefits. E Devika Gujral Appeal dismissed. F G H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.