Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Division BenchRevision petition allowed in part; condonation ...

Jayaraman v. Bappankoya

Case / Petition Number:
RCR.No.210/2009

Case Synopsis & Summary

Jayaraman, the tenant, challenged a Rent Control Appellate Authority order that dismissed his delay-condonation application and, consequently, the Rent Control Appeal RCA No. 4/2009. The revision petition under Section 20 of the relevant Rent Control Act argued that a delay of 192 days was caused by the counsel’s failure to promptly obtain the certified copy of the Rent Control Court order, and that the explanation should be considered under Indian Limitation Act principles. The Appellate Authority relied on Vedabai alias Vaijayantabai Baburao Patil v. Shantaram Baburao Patil (AIR 2001 SC 2582) to hold the delay inordinate and to weigh landlord prejudice against condonation, dismissing the IA and the appeal. The revision petitioner’s counsel urged that the matter could be decided on merits, potentially by imposing stringent terms, since the landlord claims a need under Section 11(3) to enable his son to run two different businesses in the premises and in the connected RCA (RCA No. 96/2008). The landlord contended that the two rooms serve distinct business purposes, and delay should not bar the merits. The High Court emphasized the tenant’s right of appeal under Section 18 of Act 2 of 1965 but allowed relief with conditions, including rent refixation and monetary payments, to restore the RCA and dispose of it expeditiously.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • PIUS C.KURIAKOSE
  • K.SURENDRA MOHAN
Judgment Date
2009-11-10
Court Decision / Holding
The High Court set aside the Appellate Authority’s order dismissing the condonation application and the RCA appeal, and allowed I.A. No. 58/2009 with conditions. It directed the revision petitioner to refix monthly rent to Rs. 1000 with effect from 1 December 2009, subject to the right to seek fair rent, and to pay Rs. 2,500 to the respondent and Rs. 500 to Kerala Medication Centre by 25 November 2009. Receipts must be produced, and the RCA is to be disposed of in accordance with law within one month after operative date. The judgment becomes operative only upon compliance with these payments." ,
Final Disposition
Revision petition allowed in part; condonation relief granted on stipulated terms; RCA restored with conditions and to be disposed of within one month after compliance; operative date contingent on payments.

Parties to the Case

Appellants / Petitioners

  • Jayaraman, S/o. Palaniandi, Room No. BP-5/27, Main Road, Balussery, Balussery AMSOM and Desom of Koyilandy Taluk

Respondents

  • Bappankoya, S/o. Ali, residing of Kinarullathil House, Balussery AMSOM Desom of Koyilandy Taluk

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri.V.V.Surendan
  • • Sri.P.A.Harish

Counsels for Respondents

  • • Sri.K.B.Sivaramakrishnan

Provisions of Law Cited

Section 20Section 11(3)Section 18Section 5 of the Indian Limitation ActAct 2 of 1965

Legal Doctrines & Maxims

  • Inordinate delay as a ground to deny condonation ( Vedabai alias Vaijayantabai Baburao Patil v. Shantaram Baburao Patil, AIR 2001 SC 2582)
  • Court may impose terms/conditions to grant relief in condonation cases
  • Right of appeal under Section 18 of Act 2 of 1965—remedy preserved even where condonation awarded

Submissions & Arguments

Contentions of Appellants / Petitioners

The revision petitioner contends that the delay explanation was not improbable and that the merits of the appeal should be examined, potentially with conditional relief. They point to the landlord’s need under Section 11(3) to enable his son to carry on different business activities from the room in question and another RCA 96/2008; since the other RCA is pending, a meritorious relief would be prejudiced only if the present RCA cannot be disposed of, and that the delay could be excused subject to strict conditions. They request restoration of RCA to file and merit adjudication with appropriate terms.

Contentions of Respondents

The landlord argues the delay was inordinate and unsupported by concrete evidence; condonation would prejudice the landlord as it would undermine timely resolution. He emphasizes that the past conduct and affidavits do not substantiate the delay, and urges the Court to uphold the Appellate Authority’s dismissal of the delay application and the appeal, maintaining that eviction merits and business projections should precede any delay-relief.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Vedabai alias Vaijayantabai Baburao Patil v. Shantaram Baburao Patil and othersAIR 2001 SC 2582PositiveCited to support the proposition that delay in condonation can be inordinate and prejudice to the landlord may justify denying condonation.
Collector, Land Acquisition Anantnag and another v. Mst.Katiji and othersAIR 1987 Supreme Court 1353Mentioned OnlyReferenced among precedents governing limitation up to which the court may exercise discretion; not central to the ultimate disposition.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,274 words•~6 min read

In The Court Record

Jayaraman v. Bappankoya

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE PIUS C.KURIAKOSE & THE HONOURABLE MR. JUSTICE K.SURENDRA MOHAN TUESDAY, THE 10TH NOVEMBER 2009 / 19TH KARTHIKA 1931 RCRev..No. 210 of 2009() -----------------------RCA.4/2009 of ADDL.DISTRICT COURT, KOZHIKODE RCP.36/2007 of MUNSIFF COURT, QUILANDY .................... REVISION PETITIONER/ APPELLANT/RESPONDENT: ----------------------------------------- JAYARAMAN, S/O.PALANIANDI, ROOM NO. BP-5/27, MAIN ROAD, BALUSSERY, BALUSSERY AMSOM AND DESOM OF KOYILANDY TALUK. BY ADV. SRI.V.V.SURENDRAN SRI.P.A.HARISH RESPONDENT(S)/ RESPONDENT/PETITIONER: ------------------------------------- BAPPANKOYA, S/O.ALI, RESIDING OF KINARULLATHIL HOUSE, BALUSSERY AMSOM DESOM OF KOYILANDY TALUK. ADV. SRI.K.B.SIVARAMAKRISHNAN FOR R THIS RENT CONTROL REVISION HAVING COME UP FOR ADMISSION ON 10/11/2009, THE COURT ON THE SAME DAY PASSED THE FOLLOWING: ## **PIUS C.KURIAKOSE & K.SURENDRA MOHAN, JJ. -----------------------R.C.R.No. 210 OF 2009 ------------------------** Dated this the 10[th ] day of November, 2009 ## **O R D E R** Pius C.Kuriakose, J. Under challenge in this revision filed under Section 20 by the tenant is the order of the Rent Control Appellate Authority dismissing the application for condonatiin of delay caused in the matter of filing the appeal and also the consequent judgment of the Appellate Authority dismissing the Rent Control Appeal itself. The delay caused in the matter of filing the appeal was 192 days. The delay was sought to be explained by the tenant by stating that the task of obtaining certified copy of the order of the Rent Control Court was entrusted by him to his counsel, who defended him before the Rent Control Court and that communication regarding the obtainment of copy of the order was not received by him from the office of the counsel. The landlord filed objection to the application for condonation of delay contending inter alia that the explanation offered is not genuine. The petitioner did not adduce any evidence in support of his RCR.No.210/2009 2 application for condonation of delay. It appears that it was conceded by the petitioner that the application can be decided on the basis of the affidavits filed by the parties. The Appellate Authority was not inspired by the explanation offered by the petitioner. The Appellate Authority referred to the judgment of – the Supreme Court in Vedabai alias Vaijayantabai Baburao Patil v. Shantaram Baburao Patil and others (AIR 2001 SC 2582) and found that in the instant case the delay was inordinate and therefore, the consideration that condoning the delay will cause prejudice to the landlord was to be taken into account. Accordingly, the Appellate Authority held that the no sufficient case was made out by the tenant for condoning the delay and dismissed the I.A. and consequently the appeal also. 2. We have heard the submissions of Sri.P.A.Harish, learned counsel for the revision petitioner and Sri.K.B.Shivaramakrishnan, learned counsel for the respondent. Sri.Harish submitted that the adjudication of the Rent Control Appeal on its merit may be facilitated atleast by imposing terms on the revision petitioner. He pointed out that the need projected by the landlord in the context of sub section (3) of RCR.No.210/2009 3 Section 11 was that the landlord's son wants to carry on business not only in the petition schedule premises, but also another room which was subject matter of another RCA (RCA No.96/2008). Since that RCA is pending, the landlord will not be able to accomplish the projected need unless that RCA is also disposed of in favour of the landlord. Sri.Shivaramakrishnan would quickly respond to the above submission of Sri.Harish saying that it is not the same business which is proposed to be conducted by the landlord's son in these two rooms. Separate businesses are proposed to be conducted in these two rooms. Therefore, if the room which is subject matter of the present Rent Control Revision is got vacated, it will be possible for the landlord's son to carry on one of the proposed businesses. Sri.Shivaramkrishan further submitted that idea of preferring the appeal against the order of the Rent Control Court struck the tenant only at a later stage. As soon as the decision of the Rent Control Court was known, the tenant approached the landlord and sought for three months time to vacate the premises. The landlord very graciously allowed seven months time. Now the landlord is cheated by the tenant. No indulgence RCR.No.210/2009 4 be shown to such a tenant, so submitted by the learned counsel. 3. We have very anxiously considered the rival submissions addressed at the Bar. We have kept in mind the judicial precedents governing exercise of jurisdiction by this court under Section 5 of the Indian Limitation Act including the judgment of the Supreme Court in Collector, Land Acquisition Anantnag and another v. Mst.Katiji and others (AIR 1987 Supreme Court 1353). After all, the defeated tenant has a right of appeal under Section 18 of Act 2 of 1965. Even though the petitioner did not adduce any evidence to substantiate the explanation offered by him for condoning the delay, we are of the view that his explanation that his counsel (or the counsel's clerk) did not promptly informed him about the obtainment of certified copy of the order of the Rent Control Court is not improbable. At any rate, it is clear to our mind that the revision petitioner did not receive intimation even if the same was sent by the counsel's office on time. At the same time, we find some merit in the submission of Sri.Shivaramakrishnan that the averments in the affidavit sworn to by the tenant in support of his application for RCR.No.210/2009 5 condonation of delay were not specific. Under the above circumstances, we are of the view that relief can be given to the petitioner only on stringent terms. We notice that current monthly rent of Rs.500/- being paid by the revision petitioner to the landlord is far below the rent which the building may fetch if the same is let out today. Under the above circumstances, we decide that one of the conditions to be imposed for granting relief to the petitioner is refixation of monthly rent prospectively subject to the right of either sides to move the competent court for fixation of fair rent. Accordingly, we decide the RCR issuing the following directions: 1). The order of the Rent Control Appellate Authority dismissing I.A. No.58/2009 as well as its judgment dismissing the appeal in RCA No.4/2009 are set aside. 2). I.A. 58/2009 will stand allowed and RCA will stand restored to file subject to the following conditions; i). Monthly rent payable by the revision petitioner for the subject building will stand refixed tentatively with effect from 1[st] December, 2009 at Rs.1000/- per RCR.No.210/2009 6 month. This refixation is without prejudice to the right of either of the parties to move the competent court for fixiation of fair rent. ii). The Revision Petitioner shall pay a sum of Rs.2,500/- to the respondent either directly or through the respondent's counsel in this court on or before 25/11/2009. iii). The Revision Petition shall pay a sum of Rs.500/- to the Kerala Medication Centre within the same time limit. iv). Receipts against the two payments mentioned above shall be produced by the revision petitioner before the Rent Control Appellate Authority. 3). The present judgment setting aside the order dismissing the application for condondation of delay and restoring the appeal will become operative only if the two payments are made within the time limit. Once it is noticed that the above order has become RCR.No.210/2009 7 operative, the Appellate Authority will restore the appeal and dispose of the RCA in accordance with law at the earliest. It will be ensured that the RCA is disposed of finally within one month thereafter. **PIUS C.KURIAKOSE,JUDGE** **K.SURENDRA MOHAN, JUDGE** dpk
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.