High Court of KeralaSingle JudgeCivil revision petitions dismissed; enhanced la...

Jalaja Sivan v Power Grid Corporation of India Construction Area Office; Power Grid Corporation of India Construction Area Office v Jalaja Sivan

Case / Petition Number:CRP 353/2021; CRP 257/2022
Neutral Citation:/

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • V.G. Arun
Judgment Date
2024-02-16
Court Decision / Holding
The petitions were dismissed. The court held that there was no illegality or material irregularity in the impugned order and that, on careful consideration of the factors, the quantum of diminution in land value (40% for the central corridor and 20% for the outer corridor) was just and proper. The Power Grid Corporation is directed to pay the enhanced compensation fixed by the lower court within three months of receipt of this order.
Final Disposition
Civil revision petitions dismissed; enhanced land-value compensation fixed by the lower court to be paid within three months.

Parties to the Case

Appellants / Petitioners

  • Jalaja Sivan
  • Power Grid Corporation of India Construction Area Office, Kakkanad / 400/220 KV Substation, Kumarpuram Pallikara, Ernakulam

Respondents

  • Power Grid Corporation of India Construction Area Office, Kakkanad (now in PAO/400, 220 KV Substation, Kumarapuram P.O., Pallikara, Kochi 682 303) represented by Deputy Manager
  • The Special Tahsildar (LA) Power Grid Corporation of India Ltd., Chevarambalam, Kozhikode (now in Kakkanad P.O., 682 030)
  • State of Kerala represented by District Collector, Ernakulam, Kochi 682 031
  • Kerala State Electricity Board represented by Chairman and Managing Director, KSEB Ltd., Thiruvananthapuram 695 001
  • Jalaja Sivan (as respondent in CRP 257)

Legal Representation & Advocates

Counsels for Petitioners

  • • P.T. Jose (for Jalaja Sivan)
  • • Millu Dandapani (for Power Grid Corporation)

Counsels for Respondents

  • • R. Harishankar (for Power Grid Corporation)
  • • P.T. Jose (for The Special Tahsildar (LA))
  • • S. Ashitha
  • • Althaf P.A.
  • • Abey Augustine

Case Synopsis & Summary

This is a consolidated decision of the Kerala High Court in two Civil Revision Petitions (CRP Nos. 353/2021 and 257/2022) arising from the common order of the VI Additional District Judge, Ernakulam in O.P. (Electricity) No.515 of 2013. The petitioner in CRP 353, Jalaja Sivan, challenged the computation of compensation for trees felled and the diminution in land value caused by the laying of 400 kV transmission lines across her property in Koovappady, Ernakulam. The court below rejected the claim for enhanced compensation for trees, accepting mainly an Advocate Commissioner’s report and a solitary witness, and held that the contemporaneous valuation by the Corporation (and the commission reports Ext. C2/C2(a)) justified an enhancement of Rs. 4,10,404 for land-value diminution but denied further compensation for trees due to lack of independent evidence. The petitioner pressed for higher compensation for trees and greater diminution in land value, while the Corporation contended the enhancement was excessive and challenged the basis of Ext.A7 and the extant percentages. The Court evaluated the factors laid down in KSEB v. Livisha (2007) 6 SCC 792, including situs, distance of the line, extent of impact, and land use, and found the impugned order just and proper. The petitions were dismissed, with the Power Grid directed to pay the enhanced amount within three months of receipt of the order.

Provisions of Law Cited

Code of Civil Procedure, Section 115

Legal Doctrines & Maxims

  • KSEB v. Livisha (2007) 6 SCC 792 – factors for determining diminution in land value: situs of land, distance of high voltage lines, extent of line, nature of land and its cultivation, and its impact on use of the land.

Submissions & Arguments

Contentions of Appellants / Petitioners

The claimant contended that the court below committed illegality by denying enhanced compensation for the loss sustained due to the cutting of valuable trees, despite the Advocate Commissioner’s findings. The argument stressed reliance on the contemporaneous, independent valuation and on the Commissioner's report, which the court below discarded as it was prepared after a long interval post-notification. The claimant asserted that the extent of damage and consequent diminution in land value warranted higher compensation, and challenged the 40%/20% split adopted by the court below, urging that the entire land value be properly considered along with the trees’ value.

Contentions of Respondents

The corporation argued that the enhanced diminution in land value and the 9% interest thereon were excessive. It contended that Ext. A7 and the Commission reports were misused; drawing of lines does not completely bar agricultural activities, and the proposed percentages were unfounded. It asserted that the land may be used for cultivation, small structures, and other activities, and that the court below misapplied evidence and relied on a limited comparison. It argued that the impairment caused by the corridor was not as severe as claimed and that the order should be upheld as just and legal under Section 115 CPC.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
KSEB v. Livisha[(2007) 6 SCC 792]PositiveThe court adopted the factors laid down in KSEB v. Livisha for calculating diminution in land value due to laying of high-tension lines.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Jalaja Sivan v Power Grid Corporation of India Construction Area Office; Power Grid Corporation of India Construction Area Office v Jalaja Sivan and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT** **THE HONOURABLE MR.JUSTICE V.G.ARUN** **FRIDAY, THE 16[TH] DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945** **CRP NO. 353 OF 2021** **AGAINST THE ORDER/JUDGMENT OPELE 515/2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM** ## **REVISION PETITIONER/S:** JALAJA SIVAN AGED 55 YEARS W/O.SIVAN, EETTUNGAPPADI, CHERANELLUR, KOOVAPPADY VILLAGE, KUNNATHUNADU BY ADV P.T.JOSE ## **RESPONDENT/S:** 1 POWER GRID CORPORATION OF INDIA CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400, 220KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI 682 303, REP.BY DEPUTY MANAGER 2 THE SPECIAL TAHASILDAR (L.A.) POWER GRID CORPORATION OF INDIA LTD., CHEVARAMBALAM, KOZHIKODE, NOW IN KAKKANAD P.O.682 030 3 STATE OF KERALA REP.BY DISTRICT COLLECTOR, ERNAKULAM KOCHI 682 031 4 KERALA STATE ELECTRICITY BOARD REP.BY CHAIRMAN AND MANAGING DIRECTOR, KSEB LTD., THIRUVANANTHAPURAM 695 001 BY ADV R.HARISHANKAR ## **OTHER PRESENT:** SR.GP.PREETHA K.K.SC FOR KSEB A.ARUNKUMAR THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON 20.12.2023, ALONG WITH CRP.257/2022, THE COURT ON 16.02.2024 DELIVERED THE FOLLOWING: CRP Nos.353/2021 & 257/2022 -2- ## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT** **THE HONOURABLE MR.JUSTICE V.G.ARUN** **FRIDAY, THE 16[TH] DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945** **CRP NO. 257 OF 2022** **AGAINST THE ORDER/JUDGMENT OPELE 515/2013 OF VI** **ADDITIONAL DISTRICT COURT, ERNAKULAM** ## **REVISION PETITIONER/S:** POWER GRID CORPORATION OF INDIA CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY, KAKKANAD, COCHIN - 682 030, PRESENTLY AT CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION, KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM REPRESENTED BY ITS SENIOR GENERAL MANAGER, PIN - 683565 BY ADV MILLU DANDAPANI ## **RESPONDENT/S:** 1 JALAJA SIVAN AGED 64 YEARS W/O SIVAN, EETTUNGAPPADI, CHERANALLOOR, KOOVAPADY VILLAGE , KUNNATHUNADU TALUK, ERNAKULAM DISTRICT, PIN - 683544 2 THE SPECIAL TAHSILDAR (LA) POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM, KOZHIKODE, PIN - 673017 BY ADVS. P.T.JOSE S.ASHITHA(K/000357/2018) ALTHAF P.A.(K/000535/2022) ABEY AUGUSTINE(K/000923/2022) **THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD** **ON 20.12.2023, ALONG WITH CRP.353/2021, THE COURT ON 16.02.2024 DELIVERED THE FOLLOWING:** CRP Nos.353/2021 & 257/2022 -3- ## **ORDER** Dated this the 16[th] day of February, 2024 These revision petitions are filed challenging the common order passed by the Additional District Judge-VI, Ernakulam in O.P. (Electricity) No.515 of 2013. The original petition was filed by the revision petitioner in CRP No.353 of 2021 (hereinafter called 'the claimant'), being dissatisfied with the compensation awarded towards the damage and loss sustained due to the drawing of 400 KV lines across her property by the Power Grid Corporation of India Ltd (hereinafter called 'the Corporation'). The essential facts are as under; The claimant is in ownership and possession of landed property having an extent of 3.96 Ares in Sy.No.39/18-2 of Koovappady Village in Kunnathunadu Taluk. The land was cultivated with various yielding and non-yielding trees. CRP Nos.353/2021 & 257/2022 -4- According to the claimant, to facilitate drawing of the lines and smooth transmission of power, large number of trees were cut from her property. The drawing of high tension lines rendered the land underneath and adjacent to the lines useless, resulting in diminution of the value of the property. In spite of the huge loss suffered by the claimant, only an amount of Rs.13,679/was paid as compensation towards the value of yielding and non-yielding trees cut. Surprisingly, no compensation was granted for diminution in land value. Hence, the original petition was filed, seeking enhanced compensation towards the value of trees cut and diminution in land value. 2. The court below rejected the claim for enhanced compensation for the value of trees cut since no evidence in support of the claim was produced. As far as the claim for enhanced compensation towards diminution in land value is CRP Nos.353/2021 & 257/2022 -5- concerned, the court below relied on Ext.A7 document as well as Exts.C2 and C2(a) commission report and sketch. Relying on Ext.C2(a) sketch, the extent of central corridor was held to be 2.815 cents and of the outer corridor was held to be 6.445 cents. For the central corridor, 40% of the land value was granted as compensation and for the outer corridor, 20% of the land value. Accordingly, the claimant was found entitled to compensation of Rs.4,10,404/-. Dissatisfied with the quantum of enhancement, the claimant has filed CRP No.353 of 2021, whereas the Corporation has filed CRP No.257 of 2022 contending that the enhancement ordered is far in excess of the actual damage sustained. 3. Heard Adv.P.T.Jose for the claimant and Adv.Millu Dandapani for the Corporation. 4. Learned Counsel for the claimant contended that the court below committed gross illegality in refusing to grant enhanced CRP Nos.353/2021 & 257/2022 -6- compensation for the loss sustained due to the cutting of valuable trees, in spite of the Advocate Commissioner assessing and reporting the loss. The findings in the Commissioner's report were not relied on by the court below for the reason that the property was inspected much after the trees were cut. The said reasoning is flawed since the trees were cut much after issuance of notification by the Corporation and the cause of action for filing the original petition arose only on payment of the initial compensation, even later. 5. It is submitted that the court below grossly erred in granting only 40% of the land value fixed for the central corridor and 20% for the outer corridor. Considering the extent of damage sustained and the diminution in land value consequent to the drawing of lines, the court below ought to have granted compensation as claimed. CRP Nos.353/2021 & 257/2022 -7- 6. Learned Counsel for the Corporation contended that, compensation towards diminution in land value granted is exorbitant and there is no rationale in granting 9% interest on that amount. The court below also erred in relying on Ext.A7 for fixing the land value of the claimant's property. As the drawing of electric lines does not prohibit the landowner from conducting agricultural activities and putting up small structures, 40% of the land value granted for the central corridor and 20% for the outer corridor are exorbitant. 7. A careful scrutiny of the impugned order reveals that the claim for enhancement of compensation towards the value of trees cut was rightly rejected since no supporting material, other than the findings in the Advocate Commissioner's report, was made available. As found by the court below, apart from the interested testimony of a solitary witness, who CRP Nos.353/2021 & 257/2022 -8- is the claimant in some of the connected cases, no other independent witness was examined to prove the claim. It is also not in dispute that the trees were cut in the year 2011 and the commissioner inspected the property after a long period and had assessed the value of the trees on a comparison with the trees standing in the remaining property and nearby properties. Such comparison, having no scientific basis, is not sufficient to discard the contemporaneous valuation statement prepared by the Corporation. 8. As far as the diminution in land value is concerned, the factors to be taken into consideration, as laid down in _**KSEB v. Livisha**_ ## _**[(2007) 6 SCC 792]**_ are as under; “ _10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other_ CRP Nos.353/2021 & 257/2022 -9- _similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used.”_ On careful scrutiny of the impugned order, it is seen that the compensation was enhanced after taking all the above factors into consideration. The nature of the land, the cultivation therein, and the manner in which the land was affected by drawing of the lines have all been considered fixing the land value as well as the percentage of diminution. For the central corridor, 40% of the land value is granted as compensation and for the outer corridors, 20% is granted, which I find to be just and proper. As such, there is no illegality or material irregularity in the impugned order, warranting intervention by this Court in exercise of the revisional power under Section 115 of the Code of Civil Procedure. CRP Nos.353/2021 & 257/2022 -10- For the aforementioned reasons, the civil revision petitions filed by the claimant as well as the Corporation are dismissed. The Power Grid Corporation shall pay the enhanced compensation fixed by the court below within three months of receipt of a copy of this order. Sd/- **V.G.ARUN JUDGE** Scl/