Case Synopsis & Summary

This is a Civil Appeal filed by Jaipur Vidyut Vitaran Nigam Ltd. (and other Rajasthan Discoms) challenging the orders culminating in an interpretation of Change in Law under the Power Purchase Agreement (PPA) with Adani Power Rajasthan Ltd. The dispute centers on the Evacuation Facility Charges (EFC) notified by Coal India Limited on 19 December 2017, which respondent No.1 claimed amounted to a Change in Law entitling compensation and carrying costs. The Rajasthan Electricity Regulatory Commission (RERC) had partly allowed relief; Adani appealed to the Appellate Tribunal for Electricity (APTEL), which remanded and held that the 19 December 2017 notification would amount to a Change in Law and that compensation and carrying costs were payable, following the restitutionary principle. The Supreme Court’s analysis focuses on Articles 10.2 and 10.5 of the PPA (Change in Law) and Article 8 (Billing) to determine when and how compensation must be paid, and whether the carrying cost can be determined as compound interest. The judgment integrates precedents such as Energy Watchdog, GMR Warora, UHBVNL decisions, and Maharashtra State Electricity Distribution Co. Ltd. to reaffirm restitutionary principles and the scope of Change in Law under the PPA. Ultimately, the Court concludes that the appeal fails and the liability remains with the appellants under the agreement, and the appeal is dismissed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • M. M. Sundresh
Judgment Date
2025-05-23
Court Decision / Holding
The appeal is dismissed; the liability for compensation arising from the change in law event (EFC notification) remains with the appellants under the PPA, and the relief granted by the APTEL is not interfered with.
Final Disposition
Dismissed

Parties to the Case

Appellants / Petitioners

  • Jaipur Vidyut Vitaran Nigam Ltd.
  • Ors. (Rajasthan Discoms)

Respondents

  • Adani Power Rajasthan Ltd.
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Shyam Divan
  • • Karthik Seth

Counsels for Respondents

  • • Dr. Abhishek Manu Singhvi

Provisions of Law Cited

Electricity Act, 2003 - Section 86Electricity Act, 2003 - Section 111Electricity Act, 2003 - Section 125CPC, 1908 - Section 100PPA - Article 8 (Billing and Payment)PPA - Article 10 (Change in Law) - 10.2.1PPA - Article 10 (Change in Law) - 10.5.1(a)/(b)PPA - Article 11 (Payment mechanisms) - 11.3.4PPA - Article 11 (Payment mechanisms) - 11.8.1(iii)PPA - Article 11 (Payment mechanisms) - 11.8.3PPA - Article 13 (Restitutionary principles) - 13.2PPA - Article 13.3PPA - Article 13.4.1(i)PPA - Article 13.4.1(ii)PPA - Article 8.3PPA - Article 8.6PPA - Article 8.8

Legal Doctrines & Maxims

  • Restitutionary principle under Article 13.2 of the PPA (compensation to restore the affected party to the same economic position)
  • Contractual terms must be applied as written; courts do not rewrite contracts (Nabha Power Ltd. v. Punjab SPCL; Shree Ambica Medical Stores v. Surat People's Coop. Bank)
  • Timely payment obligations and the concept of Late Payment Surcharge (LPS) as a tool to ensure compliance
  • Law includes all statutes, regulations, orders, and notifications issued by Indian governmental instrumentalities having force of law (Energy Watchdog)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contend that the ‘change in law’ event arising from the Coal India Limited notification dated 19 December 2017 should be interpreted under the restitutionary framework of the PPA, with Article 10.2.1 emphasizing restoring the affected party to the pre-change economic position, and Article 10.5.1(ii) limiting relief to cases of interpretation change by a court or instrumentality. They argue that an unconditional carrying cost/late payment surcharge cannot automatically follow unless a supplementary bill is raised after proper adjudication, and that the APTEL’s reliance on prior decisions (GMR Warora, UHBVNL cases) is misplaced for this factual scenario. They also distinguish the present case from scenarios where a supplementary bill was raised, arguing that the liability should not be extended absent proper triggering events, and emphasize the contractual text of Articles 8, 10, 11 and 13 of the PPA to support non-rewrite of terms.

Contentions of Respondents

The respondents, led by Dr. Abhishek Manu Singhvi, submit that the issue is properly framed under Article 10.2 and 10.5 of the PPA and that precedents recognizing change in law events from instruments like CIL’s notification (and the restitutionary approach) apply, with the carrying cost and LPS being justified where the relevant notification qualifies as a change in law. They contend that the APTEL’s interpretation, reinforced by decisions in GMR Warora, UHBVNL 2019 and 2023, is correct, that the change in law event can be recognized from the date of the notification or order, and that the supplementary bill mechanism (Article 8/11) ensures proper payment, including carrying costs, where applicable. They assert that the scope of the appeal is restricted to the interpretation of 10.2 and 10.5 and that the APTEL’s factual determinations and remand orders are consistent with settled law.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (11)

Case NameCitationTreatmentExplanation
GMR Warora Energy Ltd. v. CERC(2023) 10 SCC 401PositiveThe decision is cited as establishing a binding framework for Change in Law and restitutionary principles, influencing the Court’s approach to the EFC issue.
Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd.(2019) 5 SCC 325PositiveStates that change in law events accrue from the date of the change and supports restitution under Article 13.
Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd.(2023) 2 SCC 624PositiveAffirms restitutionary treatment of carrying cost and the timing of such costs following a change in law.
Energy Watchdog v. CERC(2017) 14 SCC 80PositiveDefines ‘Law’ to include statutory instruments with force of law and the restitutionary aim.
Jaipur Vidyut Vitaran Nigam Ltd. v. Adani Power Rajasthan Ltd.(2021) 18 SCC 478PositiveAffirms the restitutionary approach to change in law in PPAs, cited to support the Court’s reasoning.
Maharashtra State Electricity Distribution Co. Ltd. v. Maharashtra Electricity Regulatory Commission(2022) 4 SCC 657PositiveReiterates that LPS and related adjustments must align with restitutionary and contract terms, not rewriting the contract.
Nabha Power Ltd. v. Punjab SPCL(2018) 11 SCC 508PositiveSupports the principle that explicit contractual terms govern and courts cannot rewrite the contract.
Shree Ambica Medical Stores v. Surat People's Coop. Bank(2020) 13 SCC 564PositiveCase cited for respecting explicit contractual terms over implied interpretations.
Priya Vart v. Union of India(1995) 5 SCC 437Mentioned OnlyMentioned in the judgment but not applied to the facts or leveraged for the decision.
MSEDCL v. MERC & Ors.(2022) 4 SCC 657PositiveReinforces restitutionary framework within PPAs and the treatment of carrying costs.
Maharashtra Pradesh Electricity Regulatory Commission caseSCC OnLine APTEL 13PositiveCited to illustrate interpretation of LPS and related provisions in appellate context.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•9,450 words•~43 min read

In The Court Record

Jaipur Vidyut Vitaran Nigam Ltd. & Ors. v. Adani Power Rajasthan Ltd. & Anr.

2025 INSC 770 **==> picture [68 x 68] intentionally omitted <==** ## **REPORTABLE** ## IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## **CIVIL APPEAL NO. 4336 OF 2025 (Arising out of CIVIL APPEAL DIARY NO. 26876 OF 2024)** JAIPUR VIDYUT VITRAN NIGAM LTD. & ORS. …APPELLANT(S) ## VERSUS ADANI POWER RAJASTHAN LTD. & ANR. … RESPONDENT(S) ## **J U D G M E N T** ## **M. M. Sundresh, J.** ## **1.** Admit. **2.** We have heard the learned Senior Counsel, Mr. Shyam Divan and learned Counsel, Mr. Karthik Seth appearing for the appellants and the learned Senior Counsel, Dr. Abhishek Manu Singhvi appearing for the respondent Signature Not Verified Digitally signed by ASHA SUNDRIYAL Date: 2025.05.23 16:17:00 IST Reason: No. 1, at length. All the relevant documents, including the written submissions of the parties, have been perused. **1 of 32** **Civil Appeal Diary No. 26876 of 2024** **3.** In pursuance of the Letter of Intent issued to Adani Power Rajasthan Ltd. (respondent No.1-Power Generator), on 17.12.2009, a Power Purchase Agreement (hereinafter referred to as the “ **PPA** ”) dated 28.01.2010 was entered into between appellant Nos.1, 2 and 3, who are the Rajasthan Discoms engaged in the distribution and supply of electricity, on one side and respondent No.1 on the other, for the supply of 1200 MW Aggregate Contracted Capacity at a levelized tariff of Rs.3.238 per unit. The same was duly approved by respondent No.2. **4.** While the agreement was in operation, a Notification came to be issued at the instance of M/s. Coal India Limited (hereinafter referred to as “ **CIL** ”), dated 19.12.2017, imposing a levy of Evacuation Facility Charges (hereinafter referred to as the “ **EFC** ”) with effect from 20.12.2017. Immediately, on the very next day i.e. 20.12.2017, respondent No.1 informed appellant No. 4 that the Notification dated 19.12.2017 constituted a ‘change in law’ event. The Notification dated 19.12.2017 is extracted below: **2 of 32** **Civil Appeal Diary No. 26876 of 2024** ## **“COAL INDIA LIMITED** A Maharatna Company (A Govt. of India Enterprise) ## **COAL BHAWAN** Sales & Marketing Division Ground & Floor, Premises No, 04 MAR, Plot No. AF-III, Action Area -1A Rajarhat, New Town, Kolkata - 700156 Phone: 033-71104143, Fax: 033-23244229, Website: ……………………………… CIN: L23 L09WB1973GO1028844 ## **PRICE NOTIFICATION: CIL:S&M: GM(F)Pricing 2017/ 1005 dated 19th Dec. 2017** Charge of Rs. 50 (Fifty) per tonne shall be levied as ‘Evacuation Facility Charges’ on all despatches except despatch through rapid loading arrangement. This is effective from 00:00 hour of 20" Dec. 2017. This issues with the approval of the competent authority. General Manager (M&S) Marketing & Sales **”** **5.** On its failure in eliciting a suitable reply, respondent No.1 filed a Petition bearing No.1373/2018 before the Rajasthan Electricity Regulatory Commission (hereinafter referred to as the “ **RERC** ”), invoking Section 86 of the Electricity Act, 2003 (hereinafter referred to as the “ **2003 Act** ”) read with Article 10 of the PPA. While rejecting some of the reliefs, the RERC did allow some of the other prayers sought for by respondent No.1. Against **Civil Appeal Diary No. 26876 of 2024** **3 of 32** the refusal of some of the claims, the respondent No. 1 filed an appeal before the Appellate Tribunal for Electricity (hereinafter referred to as the ## “ **APTEL** ”). **6.** The appeal under Section 111 of the 2003 Act was so made along with an application seeking condonation of delay of 332 days in filing. Another application was filed seeking to condone the delay of 236 days in re-filing the appeal. Upon hearing both sides, the aforesaid applications were allowed and, thereafter, the appeal was decided on merits. It is pertinent to note that the common order by the APTEL, dated 23.01.2023, condoning the delay on both counts, has attained finality for want of further challenge. **7.** The APTEL, _inter alia,_ held by its judgment dated 18.04.2024, after elaborately considering the submissions made by both sides, that the Notification dated 19.12.2017 would amount to a change in law, and the respondent No. 1 would be entitled to the grant of compensation from the date of the Notification, by taking note of the decision rendered by this Court in **GMR Warora Energy Ltd. v. CERC (2023) 10 SCC 401** (hereinafter referred to as “ **GMR Warora** ”) which, in turn, also placed **4 of 32** **Civil Appeal Diary No. 26876 of 2024** reliance upon the earlier decisions of this Court. While doing so, it also took into consideration, the fair submission made on behalf of the appellants that the principal issue of levy of EFC, and consequently, the date from which the respondent No. 1 would be entitled to the grant of compensation, is covered by the aforementioned judgement. Further reliance was placed on the said decision by the APTEL, for the purpose of granting carrying cost at the rate of Late Payment Surcharge (hereinafter referred to as “ **LPS** ”), on a compounding basis, which is to be reckoned from the date of the Notification. The submission made by the appellants before the APTEL that a supplementary bill is mandatory before seeking relief for the LPS was also considered and rejected. Once again, the impact of delay was argued and considered with specific reference to carrying cost. Accordingly, the following conclusion was arrived at: ## **“X.CONCLUSION** : The Appellant shall, in terms of what has been indicated hereinabove, be entitled for the benefit of the change in law event on account of evacuation facility charges from the date on which the notification, issued by Coal India Limited, was made applicable to them. The sum representing this benefit shall be paid by Respondents 2 to 5 to the appellant along with carrying cost at LPS rates. While the Appellant shall not be entitled for carrying cost (much less at LPS rates), for the delay of 332 days in filing the Appeal, they shall be given **5 of 32** **Civil Appeal Diary No. 26876 of 2024** credit for the sum of Rs.5 lakhs paid by them earlier as a condition for condoning the delay in filing the Appeal, since they are now being denied carrying cost for the said period of delay. The matter is remanded to the Respondent-Commission to compute the amounts which the Appellant is entitled to in terms of this Judgment. The Appeal is disposed of accordingly. **”** ## **8.** When the appeal was filed before this Court, it was entertained, limiting its scope only to the interpretation of Article 10.2.1 vis-à-vis 10.5 of the PPA, with specific reference to 10.5.1 (ii). The following is the order ## passed by this Court on 09.09.2024: “We have heard learned senior counsel for the parties at length. Most of the issues raised in the present matter are covered by earlier decisions of this Court in ‘GMR Warora Energy Ltd. v. CERC & Ors.’, (2023) 10 SCC 401, ‘UHBVNL v. Adani Power (Mundra) Limited’, (2023) 2 SCC 624, ‘UHBVNL v. Adani Power Limited’, (2019) 5 SCC 325 and ‘MSEDCL v. MERC & Ors.’, (2022) 4 SCC 657. We may note that the delay in refiling has been duly considered earlier by the APTEL while condoning it. The said order has attained finality. ## **The only issue which might arise for consideration in this appeal pertains to the interpretation of Article 10.2.1 vis-à-vis Article 10.5 of the PPA with specific reference to 10.5.1 (ii).** Learned senior counsel for the respondents seeks and is granted two weeks’ time to file a counter affidavit. Rejoinder affidavit shall be filed within a period of two weeks thereafter. List on 26.11.2024.” (emphasis supplied) **6 of 32** **Civil Appeal Diary No. 26876 of 2024** ## **SUBMISSIONS ON BEHALF OF THE APPELLANTS** **9.** Notwithstanding the aforesaid order passed on 09.09.2024, the learned Senior Counsel and learned Counsel appearing for the appellants, made elaborate submissions on the other issues as well. It is submitted that the delay has occasioned only due to the fault of respondent No.1 through the litigation process and, therefore, what is to be applied is Article 10.5.1 (ii). The APTEL was wrong in condoning the delay by allowing the applications filed by respondent No.1. There is no basis for awarding carrying cost at the rate of LPS, and the APTEL ought not to have awarded the same as the LPS is granted only when there is a delay in the payment of a supplementary bill. The learned Senior Counsel placed substantial reliance on the PPA to contend that it is respondent No.1 who did not raise the supplementary bill at the earliest point of time, as mandated under Article 8 of the PPA. The decision rendered by this Court in **GMR Warora (** _**supra**_ **)** does not apply to the case of respondent No.1, considering that in the said case, a supplementary bill was indeed raised. Unless a demand is raised, there is no question of payment that would arise, as there is a clear **Civil Appeal Diary No. 26876 of 2024** **7 of 32** distinction between the liability to pay, as against an obligation to pay. In support of his contention, the learned Senior Counsel has also placed reliance upon the decision of this Court in **Prem Cottex v. Uttar Haryana** **Bijli Vitran Nigam Ltd., (2021) 20 SCC 200.** ## **SUBMISSIONS ON BEHALF OF THE RESPONDENTS** **10.** The learned Senior Counsel Dr. Abhishek Manu Singhvi appearing for the respondent No. 1, submits that there exists a preliminary objection as arguments have been made by the appellants beyond the scope of not only the present appeal but also the order, dated 09.09.2024, of this Court. The issues sought to be raised by the appellants have already been settled by this Court in not only **GMR Warora (** _**supra**_ **)** but also in two other decisions of this Court in **Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd., (2019) 5 SCC 325** (hereinafter referred to as “ **UHBVNL 2019** ”) and **Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd., (2023) 2 SCC 624** (hereinafter referred to as “ **UHBVNL 2023** ”). **8 of 32** **Civil Appeal Diary No. 26876 of 2024** **11.** There is no question of raising a supplementary bill earlier, in view of the definite stand taken by the appellants on the notification made by respondent No.1 on 20.12.2017. It is nobody’s case that the appellants were going to honour the bill if raised at the earliest point of time, as contended by them. The APTEL itself has held that respondent No.1 is not entitled to carrying cost for the period of delay in filing the appeal. The orders passed on that count have attained finality. The appellants are making a futile attempt at reopening the issues which are closed. Thus, it is a fit case where the appeal has to be dismissed with costs, particularly when appropriate orders have been passed by the RERC in pursuance of the order of remand made by the APTEL. **12.** Before we deal with the submissions made by the parties, we deem it appropriate to discuss and elaborate on the scope of appeals under the 2003 Act. ## **SCOPE OF APPEALS UNDER THE ELECTRICITY ACT, 2003** **13.** Whenever a statute provides for an appeal, a Court is expected to restrain itself to the contours of the powers conferred under it. The nature and status **Civil Appeal Diary No. 26876 of 2024** **9 of 32** of the Court loses its significance as it only draws its powers from the statute alone, and not beyond. After all, judicial restraint and sobriety, when consciously restricted by the Legislature, forms an integral part of the duties and functions of the Court. ## **Section 111 of the 2003 Act** **“111. Appeal to Appellate Tribunal** .— (1) Any person aggrieved by an order made by an adjudicating officer under this Act (except under Section 127) or an order made by the Appropriate Commission under this Act may prefer an appeal to the Appellate Tribunal for Electricity: Provided that any person appealing against the order of the adjudicating officer levying any penalty shall, while filing the appeal, deposit the amount of such penalty: Provided further that where in any particular case, the Appellate Tribunal is of the opinion that the deposit of such penalty would cause undue hardship to such person, it may dispense with such deposit subject to such conditions as it may deem fit to impose so as to safeguard the realisation of penalty. (2) Every appeal under sub-section (1) shall be filed within a period of fortyfive days from the date on which a copy of the order made by the adjudicating officer or the Appropriate Commission is received by the aggrieved person and it shall be in such form, verified in such manner and be accompanied by such fee as may be prescribed: Provided that the Appellate Tribunal may entertain an appeal after the expiry of the said period of forty-five days if it is satisfied that there was sufficient cause for not filing it within that period. (3) On receipt of an appeal under sub-section (1), the Appellate Tribunal may, after giving the parties to the appeal an opportunity of being heard, pass such orders thereon as it thinks fit, confirming, modifying or setting aside the order appealed against. **10 of 32** **Civil Appeal Diary No. 26876 of 2024** (4) The Appellate Tribunal shall send a copy of every order made by it to the parties to the appeal and to the concerned adjudicating officer or the Appropriate Commission, as the case may be. (5) The appeal filed before the Appellate Tribunal under sub-section (1) shall be dealt with by it as expeditiously as possible and endeavour shall be made by it to dispose of the appeal finally within one hundred and eighty days from the date of receipt of the appeal: Provided that where any appeal could not be disposed of within the said period of one hundred and eighty days, the Appellate Tribunal shall record its reasons in writing for not disposing of the appeal within the said period. (6) The Appellate Tribunal may, for the purpose of examining the legality, propriety or correctness of any order made by the adjudicating officer or the Appropriate Commission under this Act, as the case may be, in relation to any proceeding, on its own motion or otherwise, call for the records of such proceedings and make such order in the case as it thinks fit. **”** ## **Section 125 of the 2003 Act** **“125. Appeal to Supreme Court** .—Any person aggrieved by any decision or order of the Appellate Tribunal, may, file an appeal to the Supreme Court, within sixty days from the date of communication of the decision or order of the Appellate Tribunal, to him, on any one or more of the grounds specified in Section 100 of the Code of Civil Procedure, 1908 (5 of 1908): Provided that the Supreme Court may, if it is satisfied that the appellant was prevented by sufficient cause from filing the appeal within the said period, allow it to be filed within a further period not exceeding sixty days. **”** ## **Section 100 of the Code of Civil Procedure, 1908** **“100. Second appeal** .— (1) Save as otherwise expressly provided in the body of this Code or by any other law for the time being in force, an appeal shall lie to the High Court from every decree passed in appeal by any Court subordinate to the High Court, if the High Court is satisfied that the case involves a substantial question of law. **11 of 32** **Civil Appeal Diary No. 26876 of 2024** (2) An appeal may lie under this section from an appellate decree passed _ex-_ _parte_ . (3) In an appeal under this section, the memorandum of appeal shall precisely state the substantial question of law involved in the appeal. (4) Where the High Court is satisfied that a substantial question of law is involved in any case, it shall formulate that question. (5) The appeal shall be heard on the question so formulated and the respondent shall, at the hearing of the appeal, be allowed to argue that the case does not involve such question: Provided that nothing in this sub-section shall be deemed to take away or abridge the power of the Court to hear, for reasons to be recorded, the appeal on any other substantial question of law, not formulated by it, if it is satisfied that the case involves such question. **”** **14.** Under Section 111 of the 2003 Act, the APTEL is vested with all the powers that can possibly be exercised by the Regulatory Commission. In other words, it is the final Court of fact and law. **15.** However, under Section 125 of the 2003 Act, the powers expected to be exercised by this Court is circumscribed and controlled by the _pari materia_ provision contained under Section 100 of the Code of Civil Procedure, 1908 (hereinafter referred to as “ **the CPC** ”). Thus, it is axiomatic that an appellant has to raise a substantial question of law, which if the Court finds to be in existence, shall accordingly frame it in whatever manner it deems fit and proper, and put it to the other side to respond. It is for this Court to **12 of 32** **Civil Appeal Diary No. 26876 of 2024** ultimately consider the existence of a substantial question of law and if it does so, answer it accordingly. We will only clarify that there is no bar for this Court to add any number of substantial questions of law even after framing one earlier, in which case the respondents will have to be given due notice of the same. **16.** Section 100 of the CPC, after its amendment in the year 1978, consciously concerns itself with a question of law which shall be substantial in nature. Therefore, a mere question of law would not be sufficient enough to entertain an appeal under Section 125 of the 2003 Act. Added to that, it should be such that the substantial question of law, if answered in the affirmative in favour of the appellant, shall have the effect of reversing the decision of the APTEL. While deciding a substantial question of law, this Court shall do so, based upon the findings of fact rendered by the APTEL, unless by way of an exception, a perversity is found thereunder. In a case where a finding is rendered contrary to the records, without assigning any reason, and/or on a total misconception of the fact seen apparently on the face of the record, may in a given case, give rise to a substantial question **13 of 32** **Civil Appeal Diary No. 26876 of 2024** of law. Suffice it is to state that a substantial question of law has to be framed by this Court in exercise of the power under Section 125 of the 2003 Act and, thereafter, to be answered accordingly. **17.** In the facts of the instant case, we have indeed framed only one substantial - question of law vide order dated 09.09.2024, as aforementioned. Though we did permit the appellants to raise all the other issues and considered them as not feasible, the fact remains that they do not constitute substantial questions of law. ## **DISCUSSION** **18.** The issue with respect to change in law over a notification issued by a public authority and the resultant date to be reckoned has indeed attained finality pursuant to the judgments delivered by this Court in **GMR Warora** **Energy Ltd. (** _**supra**_ **)** , **UHBVNL 2019 (** _**supra**_ **) and UHBVNL 2023** ## _**(supra)**_ . ## **GMR Warora Energy Ltd. v. CERC (2023) 10 SCC 401** - **“95.** For appreciating the rival submissions, we will have to construe the term “Law”, which has been defined in the PPAs, which reads thus: ## **“ “Law” means, in relation to this Agreement, all laws including Electricity laws in force in India and any statute, ordinance,** **Civil Appeal Diary No. 26876 of 2024** **14 of 32** **regulation, notification or code, rule, or any interpretation of any of them by an Indian Governmental Instrumentality and having force of law and shall further include all applicable rules, regulations, orders, notifications by an Indian Governmental Instrumentality pursuant to or under any of them and shall include all rules, regulations, decisions and orders of CERC and MERC.”** **96.** Perusal of the definition of the term “Law” itself would clearly show that the term “Law” would mean all laws including Electricity laws in force in India and any statute, ordinance, regulation, notification or code, rule, or any interpretation of any of them by an Indian governmental instrumentality and having force of law. **It would further reveal that the term “Law” shall also include all applicable rules, regulations, orders, notifications by an Indian governmental instrumentality and shall also include all rules, regulations, decisions and orders of CERC and MERC.** **97.** In any case, the issue as to what would amount to “Law” is no more res integra. This Court, in _Energy Watchdog_ [ _Energy Watchdog_ v. _CERC_ , (2017) 14 SCC 80 : (2018) 1 SCC (Civ) 133] , has observed thus : (SCC p. 131, para 57) “ _57_ . Both the letter dated 31-7-2013 and the revised Tariff Policy are statutory documents being issued under Section 3 of the Act and have the force of law. This being so, it is clear that so far as the procurement of Indian coal is concerned, to the extent that the supply from Coal India and other Indian sources is cut down, the PPA read with these documents provides in Clause 13.2 **that while determining the consequences of change in law, parties shall have due regard to the principle that the purpose of compensating the party affected by such change in law is to restore, through monthly tariff payments, the affected party to the economic position as if such change in law has not occurred.** Further, for the operation period of the PPA, compensation for any increase/decrease in cost to the seller shall be determined and be effective from such date as decided by the Central Electricity Regulation Commission. This being the case, we are of the view that though change in Indonesian law would not qualify as a change in law under the guidelines read with the PPA, change in Indian law certainly would.” **98.** The aforesaid view of this Court taken in _Energy Watchdog_ [ _Energy Watchdog_ v. _CERC_ , (2017) 14 SCC 80 : (2018) 1 SCC (Civ) 133] has been approved by a Bench of three learned Judges of this Court in _Adani Rajasthan_ **Civil Appeal Diary No. 26876 of 2024** **15 of 32** _case_ [ _Jaipur Vidyut Vitaran Nigam Ltd._ v. _Adani Power Rajasthan Ltd._ , (2021) 18 SCC 478] and also followed by this Court when the two linked matters out of this batch of appeals were decided by this Court in _Maharashtra State Electricity Distribution Co. Ltd._ v. _Adani Power Maharashtra Ltd._ [(2023) 7 SCC 401] **It cannot be denied that CIL is an instrumentality of the Government of India and its orders, insofar as price of fuel is concerned, are binding on all its subsidiaries.** *** **100. As discussed hereinabove, the term “Law” would also include all applicable rules, regulations, orders, notifications issued by an Indian governmental instrumentality.** **101. It would thus be clear that all such additional charges which are payable on account of orders, directions, notifications, regulations, etc. - issued by the instrumentalities of the State, after the cut off date, will have to be considered to be “change in law” events. The generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date.** *** **111. Undisputedly, EFC was imposed by CIL vide its Circular dated 19-122017.** **112. As already discussed hereinabove, CIL is an instrumentality of the - State. It is thus clear that, on the cut off date, there was no requirement of EFC, which has been brought into effect only on 19-12-2017. As such, the circular of CIL dated 19-12-2017 would also amount to “change in law”.** *** **117.** For considering the rival submissions, it will be apposite to refer to the following articles, which are almost common in most of the PPAs: “11. _Billing and payment_ .— **==> picture [22 x 9] intentionally omitted <==** 11.3. _Payment of monthly bills_ .— *** 11.3.4. In the event of delay in payment of a monthly bill by any procurer beyond its due date, a late payment surcharge shall be payable by the procurer to the seller at the rate of two (2) per cent in excess of the applicable **Civil Appeal Diary No. 26876 of 2024** **16 of 32** SBAR per annum, on the amount of outstanding payment, calculated on a day-to-day basis (and compounded with monthly rest), for each day of the delay. **==> picture [22 x 9] intentionally omitted <==** ## 11.8. _Payment of supplementary bill_ .— 11.8.1. Either party may raise a bill on the other party (“supplementary bill”) for payment on account of: ( _i_ ) Adjustments required by the Regional Energy Account (if applicable); ( _ii_ ) Tariff payment for change in parameters, pursuant to provisions in Schedule 5; or ( _iii_ ) Change in law as provided in Article 13 and such bill shall be paid by the other party. *** 11.8.3. In the event of delay in payment of a supplementary bill by either party beyond one month from the date of billing, a late payment surcharge shall be payable at same terms applicable to the monthly bill in Article 11.3.4.” **118.** A perusal of Article 11.3.4 of the PPA would reveal that in the event of delay in payment of a monthly bill by any procurer beyond its due date, a late payment surcharge shall be payable by the procurer to the seller @ of 2% in excess of the applicable State Bank Advance Rate (“SBAR” for short) per annum, on the amount of outstanding payment, calculated on a day-to-day basis (and compounded with monthly rest), for each day of the delay. Article 11.8 of the PPA deals with payment of supplementary bill. It enables either party to raise a supplementary bill on the other party for payment on account of certain events. Clause ( _iii_ ) of Article 11.8.1 of the PPA deals with “change in law” as provided in Article 13. It requires the bill to be paid by the other party. Article 11.8.3 of the PPA also provides that in the event of delay in payment of a supplementary bill by either party beyond one month from the date of billing, a late payment surcharge shall be payable at same terms applicable to the monthly bill in Article 11.3.4. *** **120.** It could thus be seen that this Court in _Adani Power_ [ _Uttar Haryana Bijli Vitran Nigam Ltd._ v. _Adani Power Ltd._ , (2019) 5 SCC 325 : (2019) 2 SCC (Civ) **Civil Appeal Diary No. 26876 of 2024** **17 of 32** 657] has held that insofar as the “operation period” is concerned, compensation for any increase/decrease in revenues or costs to the seller is to be determined and effected from such date as is decided by the appropriate Commission. It has further been held that the compensation is only payable for increase/decrease in revenue or cost to the seller if it is in excess of an amount equivalent to 1% of the letter of credit in aggregate for a contract year. **It has been held that restitutionary principles apply in case a certain threshold limit is crossed. It has been held that an inbuilt restitutionary principle compensates the party affected by such “change in law” and the affected party must be restored through monthly tariff payment to the same economic position as if such “change in law” had not occurred.** **121.** From the perusal of para 9 of _Adani Power_ [ _Uttar Haryana Bijli Vitran Nigam Ltd._ v. _Adani Power Ltd._ , (2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657], **it would also be clear that in case the “change in law” happens to be by - way of adoption, promulgation, amendment, re enactment or repeal of the law or “change in law”, it has to be effected from the date on which such change occurs.** **122.** In this respect, it will also be apposite to refer to the following observations of this Court in _Maharashtra State Electricity Distribution Co. Ltd._ v. _Maharashtra Electricity Regulatory Commission_ [(2022) 4 SCC 657] : (SCC pp. 719-20, paras 173-78) “ _173_ . APTEL correctly found that: ( _Maharashtra Pradesh Electricity Regulatory Commission case_ [ _Maharashtra State Electricity Distribution Co. Ltd._ v. _Maharashtra Pradesh Electricity Regulatory Commission_ , 2021 SCC OnLine APTEL 13], SCC OnLine APTEL para 13) ‘ _13_ . … On the contrary, there is _a conscious exclusion regarding any suo motu change in the rate to be applied while calculating LPS_ , it being incorrect to argue on the assumption that the contract permits automatic change in system.’ _174_ . This Court is unable to accept Mr Singh's submission that the conclusion of APTEL that LPS is not tariff is erroneous. The meaning of the expression tariff has to be considered, and has rightly been considered by APTEL in the context of the relevant provision of the power purchase agreements. The dictionary meaning of tariff may be charge. However, in Article 13 of Stage 1 and Article 10 of Stage 2 power purchase agreements, tariff means monthly tariff and tariff adjustment consequential to change in law, is of monthly tariff in respect of supply of electricity. **Civil Appeal Diary No. 26876 of 2024** **18 of 32** _175_ . As argued by the respondent power generating companies appearing through Mr Rohatgi, Mr Singhvi, Mr Mukherjee and Ms Anand respectively, LPS is only payable when payment against monthly bills is delayed and not otherwise. _**176**_ **. The object of LPS is to enforce and/or encourage timely payment of charges by the procurer i.e. the appellant. In other words, LPS dissuades the procurer from delaying payment of charges. The rate of LPS has no bearing or impact on tariff. Changes in the basis of the rates of LPS do not affect the rate at which power was agreed to be sold and purchased under the power purchase agreements. The principle of restitution under the change in law provisions of the power purchase agreements are attracted in respect of tariff.** _177_ . LPS cannot be equated with carrying cost or actual cost incurred for the supply of power. The appellant has a contractual obligation to make timely payment of the invoices raised by the power generating companies, subject, of course, to scrutiny and verification of the same. Mr Mukul Rohatgi has a point that if the funding cost was so much lesser than the rate of LPS, as contended by the appellant, the appellant could have raised funds at a lower rate of interest, made timely payment of the invoices raised by the power generating companies, and avoided LPS. _**178**_ **. The proposition that courts cannot rewrite a contract mutually executed between the parties, is well settled. The Court cannot, through its interpretative process, rewrite or create a new contract between the parties.** The Court has to simply apply the terms and conditions of the agreement as agreed between the parties, as observed by this Court in _Shree Ambica Medical Stores_ v. _Surat People's Coop. Bank_ [(2020) 13 SCC 564] , para 20, cited by Ms Divya Anand. This appeal is an attempt to renegotiate the terms of the PPA, as argued by Ms Divya Anand as also other counsel. It is well settled that courts cannot substitute their own view of the presumed understanding of commercial terms by the parties, if the terms are explicitly expressed. The explicit terms of a contract are always the final word with regard to the intention of the parties, as held by this Court in _Nabha Power Ltd._ v. _Punjab SPCL_ [(2018) 11 SCC 508 : (2018) 5 SCC (Civ) 1] , paras 45 & 72, cited by Ms Anand.” (emphasis in original) **123.** This Court has clearly held in _Maharashtra State Electricity Distribution Co._ [ _Maharashtra State Electricity Distribution Co. Ltd._ v. _Maharashtra_ **Civil Appeal Diary No. 26876 of 2024** **19 of 32** _Electricity Regulatory Commission_ , (2022) 4 SCC 657] **that the DISCOMS have a contractual obligation to make timely payment of the invoices raised by the power generating companies, subject to scrutiny and verification of the same.** This Court has rejected the contention that the funding cost was much lesser than the rate of LPS. This Court has reiterated the proposition that the courts cannot rewrite a contract which is executed between the parties. This Court has emphasised that it cannot substitute its own view of the presumed understanding of commercial terms by the parties, if the terms are explicitly expressed. It has been held that the explicit terms of a contract are always the final word with regard to the intention of the parties. **124.** As already discussed hereinabove, Article 11.8 of the PPA entitles either party to raise a supplementary bill on the other party on account of “change in law” as provided in Article 13 and such bills are required to be paid by the either party. Article 11.8.3 of the PPA specifically provides that in the event of delay in payment of a supplementary bill by either party beyond one month from the date of billing, a late payment surcharge shall be payable at the same terms applicable to the monthly bill in Article 11.3.4. Article 11.3.4 of the PPA specifically provides a late payment surcharge to be paid by the procurer to the seller @ of 2% in excess of the applicable SBAR per annum on the amount of outstanding payment calculated on day-to-day basis (and compounded with monthly rest), for each day of the delay. *** **126. It is thus clear that this Court has reiterated in** _**Adani Power (Mundra)**_ **[** _**Uttar Haryana Bijli Vitran Nigam Ltd.**_ **v.** _**Adani Power (Mundra) Ltd.**_ **, (2023) 2 SCC 624 : (2023) 1 SCC (Civ) 31] that once carrying cost has been granted, it cannot be urged that interest on carrying cost should be calculated on simple interest basis instead of compound interest basis. It has been held that grant of compound interest on carrying cost and that too from the date of the occurrence of the “change in law” event is based on sound logic. It has been held that it is aimed at restituting a party that is adversely affected by a “change in law” event and restore it to its original economic position as if such a “change in law” event had not taken place.** **127. The argument that there is no provision in the PPAs for payment of compound interest from the date when the “change in law” event had occurred, has been specifically rejected by this Court.** **128.** In view of this consistent position of law and application of restitutionary principles and privity of contractual obligations between the parties as **20 of 32** **Civil Appeal Diary No. 26876 of 2024** contained in the PPAs, we do not find that the view taken by the learned APTEL with regard to carrying cost warrants interference. *** **177.** It is further to be noted that this Court in _Uttar Haryana Bijli Vitran Nigam Ltd._ v. _Adani Power Ltd._ [(2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657], **has specifically observed that the “change in law” events will have to accrue from the date on which rules, orders, notifications are issued by the instrumentalities of the State. Even in spite of this finding, the DISCOMS are pursuing litigations after litigations.** **178. We find that, when the PPA itself provides a mechanism for payment of compensation on the ground of “change in law”, unwarranted litigation, which wastes the time of the Court as well as adds to the ultimate cost of - electricity consumed by the end consumer, ought to be avoided. Ultimately, the huge cost of litigation on the part of DISCOMS as well as - the generators adds to the cost of electricity that is supplied to the end consumers.”** (emphasis supplied) ## **Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power (Mundra) Ltd. (2023) 2 SCC 624** **“20. It is clear that the restitutionary principles encapsulated in Article 13.2 would take effect for computing the impact of change in law.** We see no reason to interfere with the impugned judgment [ _Adani Power (Mundra) Ltd._ v. _CERC_ , 2021 SCC OnLine APTEL 67] , wherein it has been held by the Appellate Tribunal that Respondent 1 Adani Power had started claiming change in law event compensation in respect of installation of FGD unit along with carrying cost, right from the year 2012 and that it has approached several fora to get this claim settled. Respondent 1 Adani Power finally succeeded in getting compensation towards FGD unit only on 28-3-2018, but the carrying cost claim was denied. The relief relating to carrying cost was granted to Respondent 1 Adani Power by the Appellate Tribunal vide order dated 13-42018 [ _Adani Power Ltd._ v. _CERC_ , 2018 SCC OnLine APTEL 5] which was duly tested by this Court and upheld on 25-2-2019 [ _Uttar Haryana Bijli Vitran Nigam Ltd._ v. _Adani Power Ltd._ , (2019) 5 SCC 325 : (2019) 2 SCC (Civ) 657]. **Once carrying cost has been granted in favour of Respondent 1 Adani Power, it cannot be urged by the appellants that interest on carrying cost should be calculated on simple interest basis instead of compound interest** **Civil Appeal Diary No. 26876 of 2024** **21 of 32** **basis. Grant of compound interest on carrying cost and that too from the date of the occurrence of the change in law event is based on sound logic. The idea behind granting interest on carrying cost is not far to see, it is aimed at restituting a party that is adversely affected by a change in law event and restore it to its original economic position as if such a change in law event had not taken place.** **21.** In the instant case, Respondent 1 Adani Power had to incur expenses to purchase the FGD unit and install it in view of the terms and conditions of the environment clearance given by the Ministry of Environment and Forests, Union of India, in the year 2010. For this, it had to arrange finances by borrowing from banks. The interest rate framework followed by scheduled commercial banks and regulated by Reserve Bank of India mandates that interest shall be charged on all advances at monthly rests. **In this view of the matter, Respondent 1 Adani Power is justified in stating that if the banks have charged it interest on monthly rest basis for giving loans to purchase the FGD unit, any restitution will be incomplete, if it is not fully compensated for the interest paid by it to the banks on compounding basis.** **22. We are of the opinion that interest on carrying cost is nothing but time value for money and the only manner in which a party can be afforded the benefit of restitution in every which way.** In the facts of the instant case, the Appellate Tribunal was justified in allowing interest on carrying cost in favour of Respondent 1 Adani Power for the period between the year 2014, when the FGD unit was installed, till the year 2021. **There was no justification for the Central Commission to have excluded the period between 2014 and 2018 and grant relief from the date of the passing of the order i.e. from 28-32018** [ _Adani Power Ltd._ v. _Uttar Haryana Bijli Vitran Nigam Ltd._ , 2018 SCC OnLine CERC 8] **to 2021** ; nor is there any logic to such a segregation of timelines, particularly when Respondent 1 Adani Power was prompt in raising a claim on the appellants and pursuing its legal remedies. **23. We are not persuaded by the submission made on behalf of the appellants that since no fault is attributable to them for the delay caused in determination of the amount, they cannot be saddled with the liability to pay interest on carrying cost; nor is there any substance in the argument sought to be advanced that there is no provision in the PPAs for payment of compound interest from the date when the change in law event had occurred.** **22 of 32** **Civil Appeal Diary No. 26876 of 2024** **24. The entire concept of restitutionary principles engrained in Article 13 of the PPAs has to be read in the correct perspective. The said principle that governs compensating a party for the time value for money, is the very same principle that would be invoked and applied for grant of interest on carrying cost on account of a change in law event.** Therefore, reliance on Article 11.3.4 read with Article 11.8.3 on the part of the appellants cannot take their case further. Nor does the decision in _Priya Vart case_ [ _Priya Vart_ v. _Union of India_ , (1995) 5 SCC 437] have any application to the facts of the present case as the said case relates to payment of compensation under the Land Acquisition Act and the interest that would be payable in case of delayed payment of compensation.” (emphasis supplied) ## **Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd. (2019) 5 SCC 325** **“9. It will be seen that Article 13.4.1 makes it clear that adjustment in monthly tariff payment on account of change in law shall be effected from the date of the change in law** [ _see_ sub-clause ( _i_ ) of clause 4.1] **, in case the change in law happens to be by way of adoption, promulgation,** _**amendment**_ **, re-enactment or repeal of the law or change in law. As opposed to this, if the change in law is on account of** _**a change in interpretation of law**_ **by a judgment of a Court or Tribunal or governmental instrumentality, the case would fall under sub-clause (** _**ii**_ **) of clause 4.1, in which case, the monthly tariff payment shall be effected from the date of the said order/judgment of the competent authority/Tribunal or the governmental instrumentality.** What is important to notice is that Article 13.4.1 is subject to Article 13.2 of the PPAs. **10. Article 13.2 is an in-built restitutionary principle which compensates the party affected by such change in law and which must restore, through monthly tariff payments, the affected party to the same economic position as if such change in law has not occurred. This would mean that by this clause a fiction is created, and the party has to be put in the same economic position as if such change in law has not occurred i.e. the party must be given the benefit of restitution as understood in civil law.** Article 13.2, however, goes on to divide such restitution into two separate periods. The first period is the “construction period” in which increase/decrease of capital cost **23 of 32** **Civil Appeal Diary No. 26876 of 2024** of the project in the tariff is to be governed by a certain formula. However, the seller has to provide to the procurer documentary proof of such increase/decrease in capital cost for establishing the impact of such change in law and in the case of dispute as to the same, a dispute resolution mechanism as per Article 17 of the PPA is to be resorted to. It is also made clear that compensation is only payable to either party only with effect from the date on which the total increase/decrease exceeds the amount stated therein. **11.** So far as the “operation period” is concerned, compensation for any increase/decrease in revenues or costs to the seller is to be determined and effected from such date as is decided by the appropriate Commission. Here again, this compensation is only payable for increase/decrease in revenue or cost to the seller if it is in excess of an amount equivalent to 1% of the Letter of Credit in aggregate for a contract year. **What is clear, therefore, from a reading of Article 13.2, is that restitutionary principles apply in case a certain threshold limit is crossed in both sub-clauses (** _**a**_ **) and (** _**b**_ **). There is no dispute that the present case is covered by sub-clause (** _**b**_ **) and that the aforesaid threshold has been crossed. The mechanism for claiming a change in law is then set out by Article 13.3 of the PPA.** *** **13.** A reading of Article 13 as a whole, therefore, leads to the position that subject to restitutionary principles contained in Article 13.2, the adjustment in monthly tariff payment, in the facts of the present case, has to be from the date of the withdrawal of exemption which was done by administrative orders dated 6-4-2015 and 16-2-2016. The present case, therefore, falls within Article 13.4.1( _i_ ). **This being the case, it is clear that the adjustment in monthly tariff payment has to be effected from the date on which the exemptions given were withdrawn.** This being the case, monthly invoices to be raised by the seller after such change in tariff are to appropriately reflect the changed tariff. On the facts of the present case, it is clear that the respondents were entitled to adjustment in their monthly tariff payment from the date on which the exemption notifications became effective. This being the case, the restitutionary principle contained in Article 13.2 would kick in for the simple reason that it is only after the order dated 4-5-2017 [ _Adani Power Ltd._ v. _Uttar Haryana Bijli Vitran Nigam Ltd._ , 2017 SCC OnLine CERC 66] that CERC held that the respondents were entitled to claim added costs on account of change in law w.e.f. 1-4-2015. This being the case, it would be fallacious to say that the respondents would be claiming this restitutionary amount on some general principle of equity outside the PPA. Since it is clear that this amount of **24 of 32** **Civil Appeal Diary No. 26876 of 2024** carrying cost is only relatable to Article 13 of the PPA, we find no reason to interfere with the judgment of the Appellate Tribunal. **”** (emphasis supplied) **19.** Notwithstanding the aforesaid clear pronouncements of this Court, we would like to throw a little more light on what constitutes a ‘change in law’ event, in view of the persuasive submissions made by Mr. Shyam Divan, the learned Senior Counsel appearing for the appellants. **20.** While Article 10 of the PPA, with specific reference to Article 10.2, deals with application and principles for computing impact of change in law, Article 10.5, being a facet of Article 10.2 of the PPA, concerns itself with tariff adjustment payment on account of change in law. Article 10.2 and Article 10.5 of the PPA are extracted as below: ## **“** 10.2 _Application and Principles for computing impact of Change in Law_ 10.2.1 While determining the consequence of Change in Law under this Article 10, the Parties shall have due regard to the principle that the purpose of compensating the Party affected by such Change in Law is to restore through monthly Tariff Payment, to the extent contemplated in this Article 10, the affected Party to the same economic position as if such Change in Law has not occurred. *** 10.5 _Tariff Adjustment Payment on account of Change in Law_ **25 of 32** **Civil Appeal Diary No. 26876 of 2024** l0.5.1 Subject to Article 10.2, the adjustment in monthly Tariff Payment shall be effective from: (i) the date of adoption, promulgation, amendment, re-enactment or repeal of the Law or Change in Law; or (ii) the date of order/ judgment of the Competent Court or tribunal or Indian Governmental Instrumentality, if the Change in Law is on account of a change in interpretation of Law. 10.5.2 The payment for Change in Law shall be through Supplementary Bill as mentioned in Article 8.8. However, in case of any change in Tariff by reason of Change in Law, as determined in accordance with this Agreement, the Monthly Invoice to be raised the Seller after such change in Tariff shall appropriately reflect the changed Tariff. **”** **21.** As held by this Court in the decisions referred to _supra_ , Article 10.2.1 in the instant PPA was incorporated based on the principle of restitution. The idea of this principle is to compensate the affected party in order to restore it to the same economic position, but for the change in law. This particular provision is a substantive one, which in a normal circumstance, has to be given effect to in letter and spirit. **22.** Article 10.5 of the PPA deals with tariff adjustment payment occasioned - on account of change in law. Under Article 10.5.1 (i) of the PPA, the adjustment would start from the date of change in law. Therefore, as a matter of course, the adjustment in monthly tariff payment shall become effective from the date notified in the change in law. **26 of 32** **Civil Appeal Diary No. 26876 of 2024** **23.** Article 10.5.1 (ii) of the PPA might emerge in a factual scenario where there is an adjudication by way of an order/judgment of a competent Court - or Tribunal or an Indian Governmental Instrumentality, as the case may be. Rendering of an order/judgement would require an interpretation of law. When there is a change in the interpretation of law in rendering the order/judgement, the date of such an order/judgment would constitute a - ‘change in law’ under Article 10.5.1 (ii) of the PPA. **24.** Hence, a mere difference in the understanding of a ‘change in law’ by one party to the PPA, does not, by itself, preclude the other party from deriving - a benefit by invoking Article 10.5.1 (i) of the PPA. In other words, a different understanding would not result in a different interpretation of law, that would bar entitlement under Article 10.5.1 (i) of the PPA and, therefore, such a situation would not fall within the purview of Article 10.5.1 (ii) of the PPA. **25.** To make this position clear, Article 10.5.1 (ii) of the PPA is not applicable to the facts of the instant case since there is no change in law which has occasioned by way of an interpretation given by a Court or a Tribunal or **27 of 32** **Civil Appeal Diary No. 26876 of 2024** an Indian Governmental Instrumentality. Recognising a change in law is different from interpreting a notification as the one applicable to the parties. We are only clarifying the position that there is no change in the interpretation of law involved in the case at hand, particularly when the said issue was not before the APTEL, for which the author of the change in law should have been made a party to the proceedings, in order to defend it. The Notification, dated 19.12.2017, and its application are not in dispute. What is in dispute is whether it constitutes a change in law or not. So long as there is no interpretation on the Notification with respect to its applicability to the parties before us, Clause (ii) of Article 10.5.1 of the PPA will have no application. **26.** Article 10.5.2 of the PPA kicks in thereafter. Hence, a supplementary bill has to be raised only after due adjudication by the competent forum. Our view is fortified on a proper reading of Article 8 of the PPA. “ARTICLE 8: BILLING AND PAYMENT *** 8.3 _Payment of Monthly Bills_ **Civil Appeal Diary No. 26876 of 2024** **28 of 32** 8.3.1 The Procurers shall pay the amount payable under the Monthly Bill on the Due Date to such account of the Seller, as shall have been previously notified by the Seller in accordance with Article 8.3.4 below. 8.3.2 All payments made by the Procurer(s) shall be appropriated by the Seller in the following order of priority: i) towards Late Payment Surcharge, if any; ii) towards the earlier unpaid Monthly Bill(s), if any; and iii) towards the then current Monthly Bill. *** 8.3.5 In the event of delay in payment of a Monthly Bill by the Procurers beyond its Due Date, a Late Payment Surcharge shall be payable by such Procurers to the Seller at the rate of two percent (2%) in excess of the applicable SBAR per annum, on the amount of outstanding payment, calculated on a day to day basis (and compounded with monthly rest), for each day of the delay. The Late Payment Surcharge shall be claimed by the Seller through the Supplementary Bill. *** ## 8.6 _Disputed Bill_ 8.6.1 If a Party does not dispute a Monthly Bill, Provisional Bill or a Supplementary Bill raised by the other Party by the Due Date, such Bill shall be taken as conclusive. 8.6.2 If a Party disputes the amount payable under a Monthly Bill, Provisional Bill or a Supplementary Bill, as the case may be, that Party shall, within thirty (30) days of receiving such Bill, issue a notice (the “Bill Dispute Notice”) to the invoicing Party setting out: i) the details of the disputed amount; ii) its estimate of what the correct amount should be; and iii) all written material in support of its claim. *** 8.8 _Payment of Supplementary Bill_ **Civil Appeal Diary No. 26876 of 2024** **29 of 32** 8.8.l Either Party may raise a bill on the other Party ("Supplementary Bill”) for payment on account of: i) Adjustments required by the Regional Energy Account (if applicable); ii) Tariff Payment for change in parameters, pursuant to provisions in Schedule 4; or iii) Change in Law as provided in Article 10, and such Supplementary Bill shall be paid by the other Party. *** 8.8.3 In the event of delay in payment of a Supplementary Bill by either Party beyond its Due Date, a Late Payment Surcharge shall be payable at the same terms applicable to the Monthly Bill in· Article 8.3.5. **”** It is not in dispute that a supplementary bill is not a monthly bill. Article 8 of the PPA deals with billing and payment alone. Under Article 8.8, the other party is duty-bound to make the payment when a supplementary bill is raised due to a change in law event having occurred, as provided under Article 10 of the PPA. This can happen only after due adjudication by the competent forum, has taken place. For more clarity, one has to read Article 10.5.2 along with Article 8.8 of the PPA. It is only thereafter that Article 8.6 of the PPA might come into the picture when there exists a dispute on the quantum of amount claimed in the supplementary bill raised after the completion of due adjudication by the competent forum, on the issue pertaining to the change in law. **Civil Appeal Diary No. 26876 of 2024** **30 of 32** **27.** The incidental issue raised with respect to carrying cost at the rate of LPS has also been dealt with in the decisions referred to in **GMR Warora Energy Ltd. (** _**supra**_ **)** , **UHBVNL 2019 (** _**supra**_ **) and UHBVNL 2023** _**(supra)**_ and, therefore, any fresh consideration would only be an academic exercise. We also find that the decision relied upon by the learned Senior Counsel appearing on behalf of the appellants, have no application to the facts of the case. **28.** For the aforesaid reasons, we find absolutely no reason to interfere with the impugned judgment. Liability has been fastened upon the appellants under the agreement. The contention that the supplementary bill ought to have been raised earlier and, therefore, the payment can only be made thereafter has neither a factual basis nor a legal one. We would only point out the fact that respondent No.1 did notify the change in law event immediately on the very next day of the notification having been issued. In any case, we have been informed that in pursuance of the order of remand made by the APTEL, further orders have been passed by the RERC on 19.06.2024, which has not been challenged before this Court. **31 of 32** **Civil Appeal Diary No. 26876 of 2024** **29.** In view of the aforesaid analysis, we find no merit in this appeal. The appeal stands dismissed, accordingly. **30.** Pending application(s), if any, shall stand disposed of. **(M. M. SUNDRESH)** **…………………………. J. (RAJESH BINDAL)** NEW DELHI; MAY 23, 2025 **32 of 32** **Civil Appeal Diary No. 26876 of 2024**
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.