Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1996Division BenchAppeals dismissed.

ISHWARLAL PREMCHAND SHAH v. STATE

Case / Petition Number:
Civil Appeal No. 6896 of 1996

Case Synopsis & Summary

This Supreme Court judgment concerns land acquisition in village Sarigam, Gujarat, where lands were acquired for the Gujarat Industrial Development Corporation (GIDC) under the Land Acquisition Act, 1894. An agreement between landowners and the GIDC governed the compensation to be awarded under Section 11(2), with an award issued by the Land Acquisition Officer on June 4, 1991, in terms of that agreement. The appellants challenged the correctness of the award, arguing it did not conform to Section 11(2) because the agreements were not executed before the Collector and were not in Form No. 14 prescribed under the Rules. The respondents contended the agreements themselves fixed compensation, and given the consent, the award could be passed under Section 11(2) without the need for Form No. 14 or separate registration of such terms. The Court analyzed the nature of Form No. 14, noting it applies when owners and persons interested appear before the Collector to express willingness to accept compensation, whereas the agreements in this case were between landowners and the GIDC for the benefit of the project. The Court concluded that the essential requirements of Section 11(2) were satisfied, even though Form No. 14 was not used, and that the award could reflect the contract terms. It reaffirmed a precedent (State of Gujarat & Ors. v. Daya Shamji Bhai & Ors.) and held that the appellants were not entitled to solatium, interest, or additional amounts under the Act when the agreements govern compensation. The appeals were dismissed without costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. RAMASWAMY
  • G. T. NANAVATI
Judgment Date
1996-03-15
Court Decision / Holding
The appeals are accordingly dismissed, but in the circumstances, without costs.
Final Disposition
Appeals dismissed.

Parties to the Case

Appellants / Petitioners

  • Ishwarlal Premchand Shah and Ors.

Respondents

  • State of Gujarat and Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • R.F. Nariman
  • • Jatin Jhaveri
  • • H. J. Javeri

Counsels for Respondents

  • • Dr. N. M. Ghatate
  • • Mrs. H. Wahi
  • • Ms. N. Mukherjee
  • • Ms. Anip Sachthey
  • • J. P. Pathak
  • • H. Munshi
  • • C. D. Singh

Provisions of Law Cited

Section 4(1)Section 5-ASection 11(2) (As applicable in State of Gujarat)Section 16Section 23(1-A)Section 23(2)Section 28Form No. 14Rules

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the award under Section 11(2) was invalid since the relevant agreements were not executed before the Land Acquisition Officer and were not in the prescribed Form No. 14. They argued Form No. 14 is required and that the agreements, executed between landowners and the GIDC, were not signed in the Officer’s presence; thus the award could not be said to be under Section 11(2) and they should be entitled to solatium, interest, and additional amounts.

Contentions of Respondents

The respondents argued that the agreements between landowners and the GIDC fixed compensation and were sufficient to pass an award under Section 11(2). They asserted Form No. 14 is not mandatory in such cases, as the agreement itself fixes the compensation, and the Land Acquisition Officer’s signature and specific Form No. 14 are not necessary where the contract governs the payment of compensation. They emphasized that Form No. 14 would apply to cases where owners and interested persons appear before the Collector to accept compensation in a prescribed form.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
State of Gujarat & Ors. v. Daya Shamji Bhai & Ors.[1995] 5 SCC 746PositiveThe Court applied the ratio from this decision to hold that once the parties have agreed under Section 11(2), the award can be passed in terms of the agreement and solatium/interest/additional amounts need not be separately awarded unless included in the contract.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,802 words•~9 min read

In The Court Record

ISHWARLAL PREMCHAND SHAH v. STATE

A # ISHWARLAL PREMCHAND SHAH AND ORS. _v._ STATE OF GUJARAT AND ORS. MARCH 15, 1996 B (K. RAMASWAMY AND G.T. NANA VAT!, JJ.] _Land Acquisition Act, 1894: Sections 4(1), 5-A, 11(2) (As applicable in State of Gujarat), 16, 23( 1-A), 23(2) and 28-Fonn NO. 14 presc1ibed under Rules._ c _Land Acquisition-Compensation-Solatium and interest-Entitlement to-Land acquired for benefit of G.I.D.C.-Agreement betwcm land owners and beneficiary-Owners agreeing to accept compensation_ @ _Rs. 22,587 per hectare inclusive of solarium and additional benefits payable under the Act-Omtention that agrnement not as per Fann No. 14 presoibed under_ D _Ru/es-Award passed in tem1s of the agreement-Challenge to the validity of award-Claim for solatium, interest and additional benefits-Held in the_ _**circunistances it cannot be said that the essential requ/renients of section** 11(2) were not complied with-Award passed was not illegal---Fonn No. 14 would not be relevant in a case where the agreement is between the land-_ E _owners and interested pe1wns and beneficiary-in view of the clauses in the agreement land-owners held not entitled to the payment by way of solatium, interest and additional amount under the provisions of the Act._ _State of Gujarat & Ors._ v. _Daya Shamji Bhai & Ors.,_ [1995) 5 SCC 746, applied. F CIVIL APPELLATE JURISDICTION : Civil appeal No. 6896 of 1996 Etc. Etc. From the Judgment and Order dated 10.9.93 of the Gujarat High Court in S.C.A. No. 4981 of 1991. G R.F. Nariman, Jatin Jhaveri and H.J. Javeri for the Appellants. Dr. N.M. Ghatate, Mrs. H. Wahi, Ms. N. Mukherjee, Ms. Anip Sachthey, J.P. Pathak, H. Munshi and C.D. Singh for the Respondents. **H** The following Order of the Court was delivered : 510 511 JSHWARLAL PREM CHAND SHAHv. STATE Leave granted. We have heard the counsel on both sides. Notification under Section 4(1) of the Land Acquisition Act 1of1894 (for short, the 'Act') was published on August 2, 1984 acquiring the lands situated in village Sarigam, District Bulsar in Gujarat State for industrial B purpose. Possession also was taken after dispensing with the enquiry under Section 5-A. It is not necessary to dilate on the proceedings taken earlier under Article 226 of the Constitution. Suffice it to state that there was an agreement between the parties that an award could be made under Section 11(2) of the Act pursuant to which the Land Acquisition Officer on June C 4, 1991 made the award in terms of the agreement. The appellant challenged the correctness of the award by filing the writ petition which was dismissed by the High Court by the impugned order dated September 10, 1993. Thus these appeals by special leave. This Court by order dated February 28, 1994 issued notice confined D to the question whether the appellants are entitled to solatium, interest and additional amount under Sections 23(2), 28 and 23 (1-A) of the Act. The respondents have filed their counter-affidavit contending that in view of the agreements entered by the appellants on January 2, 1981 and subsequent agreement dated March 8, 1985, which have been filed as sample agreeE ments this Court, the appellants are not entitled to the payment of interest, solatium and additional amounts under the Act. Shri R.F. Nariman, learned senior counsel appearing for the appellants, contended that the award passed by the Collector is not in conformity with Section 11(2) of the Act in as much as the agreements were not F executed before the Collector and they were not in the prescribed form. He drew our attention to Form No. 14, prescribed by the Rules and submitted that as disclosed by the Form itself, such an agreement has to be executed by owner of the land in presence of the Land Acquisition Officer and has to be signed by the Land Acquisition Officer. In the present case, the agreements executed in 1985 were between the owners of G the land and GIDC for whose benefit the lands were acquir(d! They were not signed in presence of the Land Acquisition Officer nor did the Land Acquisition Officer put his signature thereon. Therefore, the award passed by the Collector cannot be said to be an award under Section 11(2) of the Act and, therefore, the appellants are entitled to payment of solatium, H 512 SUPREME COURT REPORTS (1996] 3 S.C.R. - A interest and additional benefits payable under the Act. We do not find any substance in this connection. In this case, the agreements were between the owners and the GIDC for whose benefit the lands were acquired. Even before the notification under Section 4 _WdS_ issued, the owners and the GIDC had entered into an B agreement whereby the owners had agreed to part with possession of their lands so as to enable GIDC to establish Udyog Nagar thereon. Under the said agreements, the GIDC was permitted to enjoy continuous possession of those lands till the process of acquisition under the Land Acquisition Act was to be completed. While entering into these agreements, the owners C had agreed to accept compensation @ Rs. 6,100 per acre. Thereafter, Section 4, notification was published on August 2, 1984. While the proceedings were pending before the Land Acquisition Officer, the owners and GIDC again in the year 1985 entered into separate agreements, whereunder the Corporation agreed to pay and the owners agreed to D accept compensation @ Rs. 22, 857 per hectare inclusive of solatium and additional benefits payable under the Act. These agreements d nly signed were presented before the Collector. On being satisfied about the voluntary nature of the said agreements, the Collector passed an award in terms of those agreements. Under these circumstances, it cannot be said that the essential requirements of sub-section (2) of Section 11, as applicable in the E State of Gujarat, was not complied with. Moreover, Form No. 14 as such would not be relevant in a case where the agreement is between the owners and interested persons on the one hand and the body for which the land is being acquired on the other hand. Form No. 14 would apply to a case where the owners and the persons interested in the land appear before the F[Collector and express their willingness to accept an agreed amount ][as ] compensation. In such cases, the agreement is required to be executed in the prescribed Form No. 14. Therefore, even though in the present case the agreements were not in the prescribed form, there being no prescribed form for a case like this, the award cannot be said to be illegal or void. G The owners have agreed in 1985 as under : H , ## H "This agreement is being done in pursuance of the consent agreement that has been arrived at on 27,12,1980 between Shri Hitendra @ Gautam Prem Shankar Oza of the first part and the Gujarat Industrial Development Corporation of the second part since the _j_ 513 ISHWARLAL PREMCHAND SHAH _v._ STATE price of the land that has been given under the said agreement has A been fixed at . Rs. 22,857 (Rupees twenty two thousand eight hundred fifty seven only) per hectare inclusive of solatium and additional land compensation by way of its consent price. This agreement is thus being done for that limited purpose. The date of possession and other terms and conditions mentioned in the B agreement done on 27.12.80 shall remain the same." It is true that on determination of compensation under sub-section (1) for the land acquired, Section 23(2) enjoins to award, in addition to the market value, 30% solatium in consideration of compulsory nature of acquisition. Equally, the Parliament having taken notice of the inordinate C delay in making the award by the Land Acquisition Officer from the date of notification published under Section 4(1) till passing the award under Section 11, to off-set the price pegged during the interregnum, Section 23(1-A) was introduced to award an amount calculated@ 12% per annum on such market value, in addition to the market value of the land, for the D period commencing on and from the date of the publication of Section 4(1) notification to the date of award of the Collector or date of taking possession of the land whichever is earlier. Under Section 28, interest was directed to be paid on the excess compensation at the rate specified therein from the date of taking possession of the land to the date of deposit into court of such excess compensation. These three components are in addition E to the compensation determined under Sub-section (1) of Section 23. They intended to operate in different perspectives. One for compulsory acquisi' tion, the other for the delay on the part of the Land Acquisition Officer in making the award and the third one for deprivation of the enjoyment of the land from the date of taking possession till determination of the F compensation. The 3 components are in addition to the determination of market value under sub-section ( 1) of Section 23. They are not integral to determination of compensation under sub-section (1) of Section 23 but in addition to, for the circumstances enumerated hereinbefore. In a private sale between a willing vendor and a willing vendee, parties would arrive at consensus to pay and receive consolidated consideration which would form G the market value of the land conveyed to the vendee. For public pnrpose, compulsory acquisition under the Act gives absolute title under Section 16 free from all encumbrances. Determination of the compensation would be done under Section 23(1) on the basis of market value prevailing as on the date of the publication of the notification under Section 4(1). It would, H 514 [1996] 3 S.C.R. ## SUPREME COURT REPORTS - A therefore, be open to the parties to enter into a contract under Section 11(2), without the necessity to determine compensation under Section 23(1) and would receive market value at the rates incorporated in the contract signed under Section 11(2) in which event the award need not be in Form 14. B This Court in _State of Gujarat & Ors._ v. _Daya Shamji Bhai & Ors.,_ [1995] 5 SCC 746 had considered the similar contentions and held that once the parties have agreed under Section 11(2) of the Act, the Land Acquisition Officer has power nnder Section 11(2) to pass the award in terms thereof and that the award need not contain payment of interest, solatium C and additional amount unless it is also part of the contract between the parties. The same ratio applies to the facts in this case. In view of the above clauses in the agreements the appellants are not entitled to the payment of additional amounts by way of solatium, interest and additional amount under the provisions of the Act. D The appeals are accordingly dismissed, but in the circumstances, without costs. T.NA. Appeals dismissed.
End of Judgment Record
Browse All Supreme Court of India (1996) Decisions
1996-08-16

Pfizer Ltd. v Mazdoor Congress and ors.

Pfizer Ltd. v Mazdoor Congress and ors is a Supreme Court appeal arising from writ petitions under Article 227 challenging the Bombay High Court’s reversal of Labour Court and Industrial Court findings that Pfizer had not committed an unfair labour practice in terminating two security staff, Waman S. Surve and R.B. Sail. The matter centers on the terminations of Surve and Sail after arrests in a theft case involving Pfizer property and the company’s loss of confidence in their suitability as watch and ward personnel. The Labour Court dismissed the complaints under Section 28 of the MRTU & PULP Act, and the Industrial Court upheld that dismissal; the High Court, however, intervened in a petition under Article 227, allowing an unfair labour practice claim under Item 1(1) of Schedule IV on the grounds of undue haste and ordering reinstatement with back wages. The apex court reverses, holding that undue haste is a question of fact to be determined on evidence and that no case under Item 1(1) was pleaded or proven before the lower fora or the High Court. It stresses that new arguments cannot be introduced at the Article 227 stage absent prior pleadings and evidence. The Court restores the Labour Court’s and Industrial Court’s decisions and allows Pfizer’s appeals, clarifying the evidentiary and pleading boundaries for unfair labour practices in industrial relations law.

1996-01-09

Union of India v. S.S. Uppal and Anr.

This appeal concerns the fixation of seniority for an officer absorbed into the Indian Administrative Service (IAS) from a state civil service quota. Respondent No.1, S.S. Uppal, a Development Officer in Madhya Pradesh’s Commerce and Industry Department, was considered for IAS absorption under Rule 8(2) of the IAS (Recruitment) Rules, 1954. A panel of four officers was prepared for vacancies arising up to 1 February 1989, with Uppal placed at serial No.4, making him eligible only for the February 1989 vacancy. Although the vacancy arose earlier, he was not appointed until 15 February 1989, and on 3 February 1989 the IAS (Regulation of Seniority) Rules were amended to introduce a weightage-based method for determining Year of Allotment (YOA) for those appointed by selection. Uppal challenged Rule 2 of the 1989 Amendment Rules as ultra vires and argued his seniority should be determined by the rules in force on 1 February 1989. The Central Administrative Tribunal accepted that the vacancy occurred before the amendment, so unamended rules should apply. The Supreme Court held that seniority in the IAS is determined by the rules in force on the date of appointment, not the date of vacancy, and that weightage cannot be retrospective unless provided. It emphasized that mere inclusion in a panel does not guarantee appointment and that the Central Government may amend seniority rules from time to time. The appeal was allowed, and the Tribunal’s order set aside.

1996-03-29

Thimmappa v. Siddaramakka

Thimmappa v. Siddaramakka concerns a deed of reconveyance attached to a sale of land. The reconveyance deed provided that if the respondent vendor repaid Rs. 5,000 within eight years from the sale date (July 20, 1968), the sale deed would be executed and registered in her favor. The respondent contended she offered payment before the eight-year period expired and sought specific performance through reconveyance; the appellant allegedly refused. The trial court accepted the respondent's evidence of offer within the period; the appellate court reversed, holding time was the essence of the contract and thus the suit was barred by limitation. The Karnataka High Court then set aside the appellate decree and restored the trial court’s decree. The Supreme Court held that, unless the deed of agreement of sale fixes a date for performance, time is not necessarily the essence of the contract. It found that Thimmappa had agreed to reconveyance conditioned on repayment within eight years, and that the respondent offered payment before expiry while the appellant refused to reconvey. The cause of action arose on expiry of eight years from July 20, 1973, but the suit was filed on July 20, 1976, within the period from the date of refusal (July 19, 1976). The Court concluded the suit was not barred by limitation, dismissed the appeal, and upheld the High Court’s restoration of the trial court’s decree.

1996-11-19

STATE OF UTTAR PRADESH AND ORS. v. V.K. JAIN

State of Uttar Pradesh and Ors. v. V.K. Jain concerns the regulation of compounded entertainment tax for cinema theatres under the Uttar Pradesh Entertainments and Betting Tax Act, 1979 and related Rules. The respondent cinema proprietor sought to reduce seating capacity from 540 to 450 for the 1995-96 year and to opt for the compounded tax system under Rule 24-A. The District Magistrate rejected both applications; the Allahabad High Court quashed that rejection, holding that the District Magistrate had no power to ignore or alter the seating capacity indicated in the option application. The State appealed to the Supreme Court. The Court held that a proprietor cannot enter into a composite agreement indicating a reduced seating capacity from the maximum stated in the licence, and the District Magistrate cannot adopt any seating capacity other than the maximum in the licence for Rule 24-A purposes. To reduce seating capacity, the proprietor must approach the licensing authority under Rule 14 of the U.P. Cinematograph Rules, 1951 to amend the licence, and only then can the amended capacity be used for Rule 24-A calculations. The decision emphasizes that the maximum seats fixed in the licence, not ad hoc figures, determine the governing base for taxation and that post-composition adjustments require proper licensing amendments. The Government suggests a clarifying recast of sub-rule (4) for the post-composition period to avoid litigation.