Indsil Electro Smelts Ltd. v. State of Kerala & Others

Case / Petition Number:
WP(C).No.15167/2006(E)

Case Synopsis & Summary

Indsil Electro Smelts Ltd. challenged a demand by the Kerala State Electricity Board for reimbursement of the cost of a 12.477 km 110 kV transmission line constructed for evacuating power from its Kuthungal Hydro Electric Project. The Government issued GO (MS) No.23/90/PD (1990) outlining policy to encourage private generation, with Clause 7 stating that the transmission line to the nearest grid substation would be built by the Board as a deposit work and land required would form part of the project; metering would be supplied by the company. In 1994 a tripartite minutes meeting altered the position, and Ext.P5 (the petitioner’s standard form agreement dated 30.12.1994) incorporated Clause 9, which provides that the transmission line for four kilometers would be built by the Board at the company’s cost, and after that the Board would bear the cost as a promotional measure; the land requirement would be treated as part of the project land; a mismatch arose because the Board later insisted on choosing the line’s route, contrary to the original understanding. The Board later demanded the cost for 12.477 km plus interest, leading to Ext.P16 and revenue notices Ext.P18/19 under the Revenue Recovery Act. The petitioner challenged these actions in Article 226, arguing lack of statutory/contractual basis. The court analyzed Ext.P1, Ext.P2, Ext.P4, Ext.P5 and Ext.P16 to hold that Clause 9 supersedes Clause 7 and limits liability to four kilometers; Ext.P16 and the revenue notices were quashed. The writ petition was allowed, directing that recovery beyond the four-km limit could not stand.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K.M. Joseph, J.
Judgment Date
2009-07-08
Court Decision / Holding
The writ petition is allowed. Clause 9 of Ext.P5 overrides Clause 7 of Ext.P1, restricting the petitioner’s liability to the cost for four kilometres; Ext.P16 demand and Exts.P18–P19 revenue recovery notices are quashed. The court directed that the Government orders read into the agreement harmoniously govern the dispute, with the custody of the line’s cost falling within the four-km limit for the petitioner. The matter is resolved in favor of the petitioner by recognizing the contractual interpretation and the promotional purpose behind Clause 9.
Final Disposition
Writ petition allowed; Ext.P16 and revenue recovery notices quashed; Clause 9 prevails over Clause 7; Government orders to be read in harmony with Ext.P5.

Parties to the Case

Appellants / Petitioners

  • Indsil Electro Smelts Ltd.

Respondents

  • State of Kerala
  • Kerala State Electricity Board
  • The Dy. Tahasildar (RR), Udumbanchola, Idukki

Legal Representation & Advocates

Counsels for Petitioners

  • • Shri Joseph Vellappally, Sr. Adv.
  • • Sri Joseph Kodianthara
  • • Sri Mathews K.uthuppachan
  • • Sri T.R.Rajan

Counsels for Respondents

  • • Shri T.B. Hood, Government Pleader
  • • Shri Bejoy Chandran
  • • Sri C.K. Karunakaran (SC for KSEB)

Provisions of Law Cited

Revenue Recovery Act, Form 1 under Section 7; Form 10 under Revenue Recovery ActElectricity (Supply) Act, 1948Constitution of India, Article 226Limitation Act, 1908, Article 115Limitation Act, 1963, Article 55

Legal Doctrines & Maxims

  • Contra proferentem (ambiguous stipulations interpreted in light of operative terms)
  • Operative/recital doctrine: the operative part of a contract prevails over recitals
  • Public orders must be construed objectively with reference to the language used (Mohinder Singh Gill principle)
  • Contract read harmoniously: government orders read as part of the agreement and clauses must be reconciled (Pallikelagatha Marcar principle)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that the Board’s demand has no statutory or contractual basis. Clause 7 of GO (MS) 23/90/PD originally contemplated private liability up to the nearest grid substation, but the 1994 minutes (Ext.P4) and Ext.P5’s Clause 9 modified this to require payment by the private party only for four kilometres, with the Board bearing the balance as a promotional measure. The petitioner argues that Ext.P16 and the Revenue Recovery notices are arbitrary and contrary to the agreement/government orders; reliance is placed on judicial principles (including Mahabir Auto Stores and ABL International) to justify writ jurisdiction and to challenge the rejection of contract terms. Exhibits P1–P17, P16, P18, P19, and counter-affidavits are cited in support of the challenge.

Contentions of Respondents

The Board and Government contend that Ext.P1 orders, read with Ext.P5, govern the liability; Clause 9 was incorporated to reflect the promotional aim and to recover costs, including land and other charges, from the petitioner; the Government’s concurrence (Ext.R2) and supporting documents justify recovery; the matter, being contractual, falls within the Board’s authority and arbitration; limitation and public policy arguments are addressed with reliance on various statutory provisions and prior decisions.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (8)

Case NameCitationTreatmentExplanation
Mahabir Auto Stores v. Indian Oil Corporation(1990) 3 SCC 752Mentioned OnlyCited by counsel; not adopted by the Court as controlling in the decision.
ABL International Ltd. v Export Credit Guarantee Corporation of India Ltd(2004) 3 SCC 553PositiveUsed to support the proposition that a writ court can decide disputed questions of fact in appropriate circumstances.
Mohinder Singh Gill v. Chief Election Commissioner(1978) 1 SCC 405PositiveCited for principles on construing public orders objectively.
Pallikelagatha Marcar v. John Gothfried Sigg(1880) Indian Appeals 83PositiveCited to support interpretation that the operative part governs over recitals in contract analysis.
State of Kerala v. V.R. Kalliyanikutty(1999) 3 SCC 657Mentioned OnlyCited in context of writ maintainability/limitation but not controlling the outcome.
State of Orissa v. Damodar Das(1996) 2 SCC 216DistinguishedCourt distinguished its teachings on limitation in the present contractual/arbitration context.
Dhapai v. Dall(AIR) 1970 Allahabad 206 (FB)Mentioned OnlyCited as related authority; not central to the holding.
Union of India v. Steel Authority of India(AIR 1997 Orissa 77)Mentioned OnlyCited for comparative discussion on compensation and contract interpretation; not decisive in this judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,887 words•~32 min read

In The Court Record

Indsil Electro Smelts Ltd. v. State of Kerala & Others

## IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE K.M.JOSEPH WEDNESDAY, THE 8TH JULY 2009 / 17TH ASHADHA 1931 WP(C).No. 15167 of 2006(E) ------------------------------------------------- PETITIONER(S): ---------------------- INDSIL ELECTROSMELTS LTD., HAVING ITS REGISTERED OFFICE AT 49, AVANASHI ROAD, COIMBATORE, REP. BY ITS FINANCIAL ADVISOR V.NATARAJAN. BY ADV. SHRI JOSEPH VELLAPPALLY, SR. ADV. SRI.JOSEPH KODIANTHARA SRI.MATHEWS K.UTHUPPACHAN SRI.T.R.RAJAN RESPONDENT(S): --------------- 1. STATE OF KERALA, REP. BY THE SECRETARY, POWER DEPARTMENT, GOVT. OF KERALA, SECRETARIAT, THIRUVANANTHAPURAM. 2. KERALA STATE ELECTRICITY BOARD, REP. BY ITS SECRETARY, VYDYUTHIBHAVANAM, PATTOM PALACE P.O., THIRUVANANTHAPURAM. 3. THE DY. TAHASILDAR (RR), UDUMBANCHOLA, IDUKKI. R1 & R3 BY GOVERNMENT PLEADER SHRI T.B. HOOD & SHRI BEJOY CHANDRAN. SRI.C.K.KARUNAKARAN, SC FOR KSEB FOR R2 THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 18.9.2008, THE COURT ON 08/07/2009 DELIVERED THE FOLLOWING: ## W.P.(C).NO.15167/06 E ## APPENDIX IN W.P.(C). NO.15167 OF 2006 E ## PETITIONER'S EXHIBITS: EXT.P1TRUE COPY OF THE GOVERNMENT ORDER GO (MS).NO.23/90/PD DATED 7.12.1990. EXT.P2TRUE COPY OF THE GOVERNMENT ORDER GO.MS.NO.5/92/PD DATED 12.3.1992. EXT.P3TRUE COPY OF THE MEMORANDUM OF UNDERSTANDING BETWEEN INDSIL ELECTROSMELTS LIMITED AND ELECTRICITY BOARD. EXT.P4TRUE COPY OF THE MINUTES OF MEETING DATED 8.4.1994 HELD AT THE OFFICE OF MINISTER (ELECTRICITY). EXT.P5TRUE COPY OF THE AGREEMENT ENTERED INTO BETWEEN THE PETITIONER AND KSEB DATED 30.12.1994. EXT.P6TRUE COPY OF THE AGREEMENT ENTERED INTO BETWEEN KSEB AND SILCAL METALLURGIC LIMITED DATED 30.12.1994. EXT.P7TRUE COPY OF THE AGREEMENT ENTERED INTO BETWEEN KSEB AND TRAVANCORE ELECTRO CHEMICAL INDUSTRIES DATD 30.12.1994. EXT.P8TRUE COPY OF THE LETTER DATED 25.7.1998 FROM CHIEF ENGINEER TO INDSIL ELECTROSMELTS LIMITED. EXT.P9TRUE COPY OF THE LETTER DATED OCTOBER 5, 1998 ADDRESSED TO DY. CHIEF ENGINEER, KSEB ALONG WITH COPY OF THE DEMAND DRAFT. EXT.P10 TRUE COPY OF THE LETTER DATED 3.5.1999 FROM CHIEF ENGINEER TO PETITIONER. EXT.P11 TRUE COPY OF THE LETTER DATED 5.5.1999 FROM PETITIONER TO MEMBER TRANSMISSION WITH COPY TO DY. CHIEF ENGINEER ALONG WITH COPY OF THE DD FOR RS.20,55,075/=. EXT.P12 TRUE COPY OF THE LETTER DATED 27.6.2001 ADDRESSED BY CHIEF ENGINEER KSEB TO PETITIONER. EXT.P13 TRUE COPY OF THE LETTER FROM PETITIONER TO CHIEF ENGINEER TRANSMISSION SOUTH OF KSEB DATED 4.7.2001. EXT.P14 TRUE COPY OF THE LETTER FROM CHIEF ENGINEER TRANSMISSION SOUTH DATE 22.11.2001. EXT.P15 TRUE COPY OF THE COMMUNICATION DATED 28.11.2001 ALONG WITH COPIES OF THE LETTER DATED 28.11.2001 ADDRESSED TO DY. CHIEF ENGINEER ALONG WITH COPY OF A DD ENCLOSED THEREWITH. EXT.P16 TRUE COPY OF THE LETTER NO.TC2-9311/678 DATED 6.9.2005 FROM SECRETARY, KSEB TO PETITIONER. ## W.P.(C).NO.15167/2006 E EXT.P17 TRUE COPY OF THE REPRESENTATION SUBMITTED BY PETITIONER DATED 26.9.2005 TO THE SECRETARY, KSEB. EXT.P18 TRUE COPY OF THE REVENUE RECOVERY NOTICE DATED 6.6.2006 IN FORM 1 U/S.7 OF REVENUE RECOVERY ACT. EXT.P19 TRUE COPY OF THE REVENUE RECOVERY NOTICE DATED 6.6.2006 IN FORM NO.10 UNDER REVENUE RECOVERY ACT. ## ADDITIONAL DOCUMENTS: - 1) TRUE COPY OF LETTER DATED 4.6.1999 ISSUED BY THE SECRETARY, KSEB. - 2) TRUE COPY OF LETTER DATED 25.6.2005 ISSUED BY THE PRINCIPAL SECRETARY TO GOVERNMENT. ## RESPONDENTS' EXHIBITS: EXT.R2(A) TRUE COPY OF LETTER NO.TC2-9311/99/2257 FROM THE SECRETARY, KSEB TO THE PRINCIPAL SECRETARY TO THE GOVERNMENT DATED 04.06.1999. EXT.R2(B) LETTER NO.5560/B1/99/PD FROM THE PRINCIPAL SECRETARY TO THE GOVERNMENT TO THE SECRETARY, KSE BOARD DATED 25.6.2005. EXT.R2(C) TRUE COPY OF THE EXTRACT OF THE REPORT OF THE C & AG. _**// True Copy //**_ _**PS to Judge**_ ## **K.M.JOSEPH, J.** - - - - - - - - - - - - - - - - - - - - - - - - - ## WP.(C) No.15167 of 2006 - - - - - - - - - - - - - - - - - - - - - - - - - Dated this the 8th day of July, 2009 ## **JUDGMENT** Ext.P1 is a Government Order dated 7.12.1990, by which the Government of Kerala purported to enunciate its policy to encourage private participation in the generation of power. Ext.P2 dated 12.3.1992 is produced as guidelines in this direction. It is the case of the petitioner that several entrepreneurs including the petitioner responded to Ext.P1 notification. They felt that there was need for some clarification. Clause 7 of Ext.P1 order reads as follows: “The transmission line required for transferring power from the captive plant of the agency to the nearest grid substation will be built at the cost of the agency by K.S.E.Board, as a deposit work and after construction it shall be transferred to the Board without any compensation. Land required for construction of such transmission line will be considered as part of land required for the scheme. The metering equipment shall be provided by the agency at their cost at a point decided by the Board and handed over to the Board along with the transmission line, without any compensation.” Objections were raised to the same. Petitioner entered into Ext.P3 memorandum of understanding with the Kerala State Electricity Board, **WPC.15167/2006.** **2** hereinafter referred to as the Board. It is the further case of the petitioner that on the strength of the objections raised by the persons who have responded to Ext.P1, a meeting was called by the then Minister for Electricity. It was attended by the Chairman of the Board, Member (Technical), Chief Engineer (Civil)(Plg. & R), representative of the petitioner and two other agencies. Ext.P4 is produced as the minutes of the meeting. In Ext.P4, clause 3 reads as follows: “iii) Charges to be levied for transmission line to be erected for evacuation of power. It was felt that the earlier decision modified asking the private entrepreneur to construct the line upto 4 kms. The balance may be constructed at the cost of Electricity Board as promotional measure.” Petitioner entered into Ext.P5 agreement with the Board. Clause 9 of Ext.P5 being crucial is extracted hereunder: “The transmission line required for transferring power from the power house to the nearest grid substation and/or other locations as suggested by the KSEB upto a length of 4 (four) Km shall be built by the KSEB at the cost of company, as a deposit work and the balance constructed by the KSEB at its cost as a promotional measure for encouraging the private entrepreneurs for generation of power. After construction of the line for the company by KSEB it shall be transferred to the KSEB without any compensation. Land required for **WPC.15167/2006.** **3** construction of such transmission line will be considered as part of land required for the project as per conditions as elaborated under clause (6) above and the metering equipment as per the specifications of KSEB shall be provided by the company at their cost at a point in the generating station as approved by the KSEB and handed over to the KSEB along with transmission line; without any compensation.” It is the case of the petitioner that once it was decided that the major portion of the cost of construction of the line was to be met by the Board itself, then the Board had also insisted that they must be given the liberty to choose the place to which the transmission line must be erected. That is, whereas the Government Order originally contemplated transmission line to be constructed from the project to the nearest sub station, in the agreement the Board insisted that it should be given liberty to choose the place to which the transmission line is to be drawn, and that is how clause 9 came to be incorporated, is the case of the petitioner. Exts.P6 and P7 are the agreements executed with other agencies. It is stated that both these agreements provide that the transmission line is to be constructed by the Board and the agencies would be required to meet the cost of transmission line for the first 4 km. Petitioner contends it set up Hydro Electric Project at Kuthungal incurring an investment of more than Rs.55 Crores. It is pointed **WPC.15167/2006.** **4** out that the nearest sub station to Kuthungal was at Sengulam and that the transmission line if drawn from Kuthungal to Sengulam would be traversing 6 - 7 kms. But the department decided, it is stated, that the power evacuated from Kuthungal must be received at Neriyamangalam. Ext.P8 dated 25.7.1998 is produced as the communication from the Chief Engineer to the petitioner referring to clause 9 and requesting petitioner to remit Rs.213.8 Lakhs as work deposit amount, which was stated to be preliminary estimation cost of 4 km line. Petitioner remitted the amount. It is further stated that the tender for the construction of the 110 DC line from Kuthungal to Neriyamangalam was floated and finalized at 136% above the PAC. Petitioner was called upon pay Rs.20,55,075/- as proportionate tender excess for construction of 4 km vide Ext.P10, which also the petitioner remitted. It is stated that the transmission line was completed by the end of May, 2001. Transmission of power commenced on 1.6.2001. By Ext.P12 dated 27.6.2001 petitioner was called upon to remit the additional amount of Rs.21.94 Lakhs towards the proportionate cost payable by the petitioner for the transmission line for the first 4 kms. Petitioner pointed out vide Ext.P13 that the petitioner was not liable to pay the said sum. The Department persisted with the demand vide Ext.P14. Petitioner points out that petitioner paid the said sum on 28.11.2001 and has produced Ext.P15 in **WPC.15167/2006.** **5** support thereof. It is while so petitioner received Ext.P16 communication from the Secretary of the Board. In Ext.P16, after referring to Ext.P1 Government Order and Ext.P5 agreement, it is stated as follows: “The Board vide letter dated 4.6.1999 had requested the Government to approve the proposal of recovery of the cost of the transmission line and interest thereon. The Government vide letter dated 25.6.2005 had conveyed Government's concurrence to the proposal of KSE Board to recover the cost of12.477 Km of transmission line constructed for the evacuation of power generated at Kuthungal HE Project and interest thereon from your company.” Petitioner was asked to remit a sum of more than Rs.22 Crores and the break up of the aforesaid sum is given as follows: “Rs. |_____________________________________________________________|_____________________________________________________________| |---|---| |Labour cost|3,49,27,137| |Material cost|1,97,80,849| |Storage charges|31,64,936| |Tree-cutting compensation paid so far|1,54,82,202| |Land acquisition cases so far|97,69,753| |Anticipated future payment of Tree-cutting|| |and Land Acquisition|1,50,00,000| |Development charges|1,96,24,975| |Departmental charges|2,47,27,469| **WPC.15167/2006.** **6** **Total** 14,24,77,321 Less amount remitted by M/s.Indsll 2,56,29,075 **Balance amount due** 11,68,48,246 **Calculation of total amount due** Balance amount due 11,68,48,246 Less anticipated future payment of Tree-cutting and Land Acquisition 1,50,00,000 Balance 10,18,48,246 Interest @ 18.5% per annum on the balance amount from 17.7.1999 to 16.7.2005. 11,30,51,553 **Sub Total** 21,48,99,799 Add future payment of Tree-cutting and Land Acquisition 1,50,00,000 **GRAND TOTAL** 22,98,99,799” Petitioner requested vide Ext.P17 letter dated 26.9.2005 to withdraw the letter. Exts.P18 and P19 notices under the Revenue Recovery Act are issued demanding a sum of Rs.22,98,99,799/-. Petitioner challenges Exts.P16, P18 and P19. 2. First respondent, State has filed a counter affidavit, wherein it is inter alia stated as follows: 3. The Board had incurred a huge loss iin constructing 110 KV double circuit line for the evacuation of power from Kuthungal Hydro Electric Project. It is stated that Ext.P1 Government order is made part of **WPC.15167/2006.** **7** Ext.P5 agreement and hence Clause 7 is to be read as part of the agreement of the parties. Reference is made to Clause 6 of Ext.P5 agreement. It is stated that compensation amounting to Rs.2,52,51,955/- was already paid by the Board towards tree cutting and land acquisition cases and so many cases for tree cutting compensation are pending in various courts. It is stated that other projects were not materialised though agreement was executed with other agencies. It is stated that original proposal was to construct 15 kms of transmission line for evacuation of power. On actual execution of the work, length of line was 16.477 kms, that is the Board had constructed 12.477 kms of line. It is stated that in the report of the Comptroller and Auditor General of India for the year ended 31[st] March, 2003 it was observed that the decision to incorporate a provision in the agreement deviating from the prescribed guidelines resulted in undue benefit of Rs.8.79 Crores to the private entrepreneurs. It is further stated that since the Board has to bear the cost of transmission line for the balance as per the agreement, the Board has requested Government sanction to recover the cost borne by Board and its interest thereon. The Government vide letter dated 25.6.2005 conveyed concurrence for the proposal. The Board is borrowing money for its capital expenditure from the financial institutions and incurring huge amount towards interest, and it has invested Rs.11,68,48,246/- for the construction **WPC.15167/2006.** **8** of the balance portion of the said line during 2000-2001. Reference is made to Clause 23 of the agreement providing for recovery of the amount in any manner including under the Revenue Recovery Act. It is stated that the recovery is based on the approval granted by the Government. The Board has not agreed for the construction of transmission line required for a private entrepreneur at Board's expenditure. It is stated that when there is a contract between parties, demand made in terms of the contract need not be sourced to any statutory provision. It is stated that law of limitation is not applicable. 4. A counter affidavit is filed on behalf of the second respondent inter alia stating as follows: Reference is made to Clause 9 of Ext.P1 order besides other provisions. It is stated that Ext.P1 order is made part of Ext.P5 agreement and therefore Clause 7 of Ext.P1 is to be read as part of the agreement. Ext.P4 minutes is stated to be only a minutes and not a part of Ext.P1 order by amending the same and it is also stated that it is not part of the agreement. Reference is made to Clause 6 of Ext.P5 agreement. It is stated that the Board has already paid compensation towards tree cutting and land acquisition expenses in a sum of Rs.25251955/- and several other cases are pending in various other courts claiming compensation for tree cutting. **WPC.15167/2006.** **9** The original proposal was for 15 kms. Reference is made to the report of the Comptroller and Auditor General of India. It is stated that the Board has not agreed for the construction of the transmission line required for a private entrepreneur at Board's cost. It is stated that the agreement was executed based on clause 21 of the Government order and that Government Order forms part of Ext.P5 agreement and the parties are bound to obey and act in accordance with the terms and conditions stipulated in the Government Order. Reliance is placed on Clause 23. There is also reference made to the Board borrowing money from financial institutions and incurring huge amount towards interest. It is stated that the principle of transferring the line to the Board without any compensation is adopted for all deposit works. 5. Thereafter an additional counter affidavit is filed inter alia stating as follows: There is a denial of the allegation of the petitioner that the claim is barred since the work of transmission line was over on 27.5.2001. It is stated that for the purpose of laying the transmission line vast areas of land were acquired and trees were cut. Disputes relating to compensation are pending in various courts. Reference is made to Clauses 6 and 9 of Ext.P5 agreement to contend that all lands acquired for the project are to be paid for by the petitioner. Tree cutting compensation is stated to be **WPC.15167/2006.** **10** incidental to acquisition of land and the right to draw the line. It is stated that the final determination of the dues is not complete and various claims under these heads are still pending before various courts. Separate clauses cannot be taken in isolation for determining limitation. It is stated that the petitioner has not performed the requirements at paragraph 7.3.2 (Power tunnel). It is stated that the petitioner has been seeking extension for doing the above work and payments and settlement of accounts under various clauses of the agreement are on going and will subsist through out the duration of the agreement. The limitation cannot decided without detailed examination of the underlying facts, which is normally not contemplated under Article 226, it is stated. It is also stated that there is no question, which cannot be decided by the Arbitrator contemplated under clause 25 of the agreement. It is stated that the period of limitation will start only with the contractual obligation is broken, which commenced on 26.9.2005, when the petitioner for the first time communicated its refusal to pay and the breach being continuing, the period of limitation has not set in. It is stated therefore that Exts.P18 and P19 revenue recovery action is well within the period of limitation. It is stated that any charges, which are due towards the construction of the line is a continuing liability. Demand is purely in terms of the contract and dues to the Board include all plausible overhead and **WPC.15167/2006.** **11** ancillary amounts incurred for laying the transmission line. It is stated that the provisions of the Electricity (Supply) Act are incorporated into the agreement by reference. Any clause in Ext.P5 agreement at variance with the public policy cannot take precedence over public policy. There is no public interest in giving any concession to the petitioner at the cost of public revenue. It is stated that the entire generation is for the use of the petitioner. Entering into Ext.P3 before Ext.P4 minutes is stated to be relevant. The non-translation of Ext.P4 into a Government Order also evidences the fact that Ext.P1 governs the field. Clause 9 has to be read in the context of the Government Orders. The agreement has to be incorporated harmoniously and therefore the terms of the Government Order regarding the petitioner having to bear the entire cost of setting up the transmission line is to be read as an essential part of the condition of the agreement. It is stated that the petition under Article 226 may not be allowed to be converted into adjudication on merits. It is stated that Government Order (Ext.P1) must be read as part of the agreement as the said document is referred to in the agreement. It is stated that the petitioner has neither resorted to the alternate remedy or any remedy under the Revenue Recovery Act and that it has rushed to this court when efficacious alternate remedies are available. **WPC.15167/2006.** **12** 6. Under a memo by the learned counsel, letter dated 4.6.1999 issued by the Board and letter dated 25.6.2005 issued by the Government are produced. The Board has also produced Exts.R2(a) and R2(b)letters. Ext.R2(c) produced is the extract of the report of the Comptroller and Auditor General for the year ended 31.3.2003. 7. I heard learned Senior Counsel for the petitioner Sri. Joseph Vellappally and Sri.C.K.Karunakaran for the Board besides the learned Government Pleader. 8. Learned Senior counsel reiterates the facts. He would submit that the action of the Board is unsustainable. He would point out that the impugned demand is based neither on a statute nor does it have any support from a contractual provision. He pointed out that Clause 7 in Ext.P1 order was expressly modified by the tripartite minutes dated 8.4.1994 and it was the amended clause which was incorporated as clause 9 in Ext.P5, standard form agreement. It is contended that the action of the Board and the Government of Kerala is illegal and unreasonable. Reliance is placed on the decision of the Apex Court in **Mahabir Auto Stores v. Indian Oil Corporation** ((1990) 3 SCC 752). Support is sought to be derived from the decision of the Supreme Court in **ABL International Ltd.** **WPC.15167/2006.** **13** **v. Export Credit Guarantee Corporation of India Ltd** . ((2004) 3 SCC 553) for the proposition that a writ petition is indeed maintainable to resolve the dispute in this case. He would refer me to the various documents which I have already referred to to contend that the understanding between the parties with reference to the documents including Ext.P5 agreement was that the petitioner would be liable to pay the amounts in respect of 4 kms. He pointed out that Clause 7 of Ext.P1 provides that the transmission line to the nearest grid sub station is to be built at the cost of the agency as a deposit work by the Board and the land required for the construction of such transmission line will be considered as part of the land required for the scheme. He would therefore contend that if the matter is decided with reference to Clause 7, petitioner would have been liable only for the cost of the line upto the nearest grid station. It is pointed out that even the Government or the Board are not seeking to go by the terms of the contract but are relying on the report of the Comptroller and Auditor General. The demand is neither based on the agreement nor even on Ext.P1 policy. The action is arbitrary. It is pointed out that the writ will lie as the revenue recovery proceedings are barred as the civil suit would patently not lie on account of limitation ( **State of Kerala v. V.R. Kalliyanikutty** ((1999) 3 SCC 657)). It is pointed out that the final payment was demanded vide **WPC.15167/2006.** **14** Ext.P12 dated 27.6.2001 and paid vide Ext.P15 dated 28.11.2001. It is also contended that the State and the Board have sought to supplement the reasons for raising the demand in the additional counter affidavit and in oral arguments and which is impermissible in law. Reliance is placed on the decision of the Apex Court in **Mohinder Singh Gill v. Chief Election Commissioner** ((1978) 1 SCC 405), (wherein the Apex Court referred to the following observations of Bose, J., in Gorghandas Bhanji) “Public orders, publicly made, in exercise of a statutory authority cannot be construed in the light of explanations subsequently given by the officer making the order of what he meant, or of what was in his mind, or what he intended to do. Public orders made by public authorities are meant to have public effect and are intended to affect the actings and conduct of those to whom they are addressed and must be construed objectively with reference to the language used in the order itself.” Reliance is also placed on the principle of Contra Preferentem. Learned Senior Counsel relies on the decision of Privy Council in **Pallikelagatha Marcar v. John Gothfried Sigg,** (1880 Vol.VII Indian Appeals 83) wherein the court dealing with the question of construction of an ambiguous stipulation in a deed held inter alia as follows: **WPC.15167/2006.** **15** “The construction of an ambiguous stipulation in a deed may undoubtedly be governed or qualified by a recital; but on the other hand if the intention of the parties is clearly to be collected from the operative part of the instrument, that intention is not to be defeated or controlled because it may go beyond what is expressed in the recital.” 9. Per contra, Sri. C.K.Karunakaran would contend that any dispute between the parties has to be referred to arbitration by the Government. Reliance is placed on the decision of this court in O.P.No.32432 of 2002 between the same parties. In the said judgment a learned Single Judge of this court dealing with the claim for compensation by the petitioner itself took the view that when the parties have agreed for resolution of the dispute, they are bound by such clause contained in the agreement and cannot approach this court under Article 226 for resolving such remedies in the agreement and it was directed that it is for the petitioner to seek reference of the matter to the Government in terms of Clause 25 of the agreement. It is pointed out that the said judgment was confirmed in W.A. 2920 of 2002 and the petitioner has to avail the remedy provided in Ext.P5. It is further contended that this case does not come within the three established circumstances in which a writ would lie even in the teeth of alternate remedies. It is stated that this court cannot effectively **WPC.15167/2006.** **16** adjudicate the matter specially so when an effective alternate remedy is available. It is further contended that the bar of limitation is not attracted in this case as Ext.P5 is an agreement which spans the entire duration of the contracted terms and no clause can be taken in isolation and the bar of limitation pleaded. Period of limitation will begin to run if at all from the date of completion of the last of the terms of the agreement, which date has not yet arrived. It is stated that in this case dispute arose only on 26.9.2005, the date when the petitioner has categorically denied any liability and therefore the revenue recovery proceedings are within time. Reliance is placed on the decision reported in **State of Orissa v. Damodar Das** ((1996 2 SCC 216) to contend that limitation in cases where matters have to be arbitrated upon commences from the date when the cause of action for arbitration accrues. After referring to Clauses 6 and 9, it is contended that the petitioner has to pay for the land needed for drawing the transmission line and the dispute regarding compensation payable for such lands are pending adjudication before various courts and therefore there is no question of limitation. Reliance is also placed on the Full Bench decision of the Allahabad High Court in **Dhapai v. Dall** (AIR 1970 Allahabad 206 (FB)) and the decision of the Orissa High Court in **Union of India v. Steel** **WPC.15167/2006.** **17** **Authority of India** (AIR 1997 Orissa 77). In these decisions courts have taken the view that the word 'compensation' in Article 115 of the Limitation Act, 1908 (corresponding to Article 55 of the Limitation Act, 1963 denotes the sum of money payable or damage caused to him by the breach of the contract. In other words, it cannot be restricted to a claim of unliquidated damages, but is used in a very wide sense and includes a claim for payment of a certain sum. It is contended that Ext.P4 would not make any difference to Ext.P5 agreement. There is no mention of Ext.P4 in Ext.P5 while Exts.P1 and P2 Government Orders are made parts of Ext.P5 agreement. The intention of the contracting parties is clear that Exts.P1 and P3 were to be part of Ext.P5 agreement. It is stated that Government can only give directions as contemplated under the Electricity Act, 1910 and the Electricity (Supply) Act, 1948 and Ext.P4 cannot be treated as such a statutory direction. Exts.P1 and P2 being executive action issued in accordance with Article 166(1) of the Constitution of India cannot be altered by Ext.P4 minutes. The Comptroller and Auditor General is a constitutional authority to go into the accounts of the Board and has a constitutional duty to point out areas where public revenue/monies have not been properly realized. It is stated that the argument of the petitioner based on investment of over Rs.55 Crores cannot be accepted as it is a purely a **WPC.15167/2006.** **18** captive plant of the petitioner and petitioner has an amount in excess of Rs.125 Crores and the petitioner has 23 years of operation period remaining. The Board has suffered huge loss, it is stated. The Board would lose more than Rs.25 Crores, it is stated, if the petitioner succeeds. The plea of Contra preferentem, which is not pleaded, would not apply. The Board also points out that the decisions in **Mahabir Auto Stores Case** and ABL International Ltd's Case cannot apply. 10. Ext.P1 is a Government Order dated 7.12.1990 providing for the terms and conditions for setting up of hydel scheme by private agencies. Clauses 7 has already been extracted. Clause 20 reads as follows: “20. In case of any dispute or difference of opinion between the agency and the Kerala State Electricity Board, the matter would be referred to the Government and their decision shall be final.” Ext.P2 provided for further guidelines. Undoubtedly, there was a memorandum of understanding between the petitioner and the Board dated 24.8.1992. Thereafter, on 8.4.1994 there appears to have been a meeting attended by the Minister and officials of the Board. Clause 3, as already noted, was among the clauses incorporated in the minutes indicating that earlier decision was modified asking the private entrepreneurs to construct **WPC.15167/2006.** **19** a line upto 4 kms and the balance to be constructed at the cost of the Board as promotional measure. Still later the actual agreement contemplated in Clause 21 in Ext.P1 was executed. In the preamble to Ext.P5 agreement reference is made to Exts.P1 and P2. It is specifically stated that it shall form part of the agreement as if incorporated therein. It is necessary to notice Clause 6 of Ext.P5, which reads as follows: “In case, the power project is to be located in area owned by private parties, company shall acquire the land from the private land owner. Any Government land required adjacent to dam works shall be got transferred through KSEB for which the company will have to pay a lease rent at the rates prescribed by the revenue authorities in Government from time to time. The lease period shall be thirty years from the date of commissioning or such other periods as mutually agreed.” In the counter affidavit of the Government, it is stated, inter alia, that based on the concurrence of the Government of Kerala, notice was issued to remit the balance amount of more than Rs.22 Crores for construction of 12.477 kms of 110 KV double circuit line. It is also relevant to notice the communication addressed by the Board as Ext.R2(a) to the Government, wherein it is inter alia stated as follows: “As per G.O.first cited (Ext.P1) the cost of transmission has to be borne by the developer. Since the Board has to bear **WPC.15167/2006.** **20** the cost of transmission for 11 Kms as per the agreement it is only proper that the cost borne by KSE Board and its interest is recovered from the energy generated over a period of 30 years.” And hence request was made to take up the work and for recovery of the cost of 11 Kms of transmission line and interest for over a period of 30 years. On the basis of the same, Ext.R2(b) was issued conveying Government's concurrence to the proposal of the Board to recover the cost of 12.477 meters of transmission line constructed for evacuation of power from Kuthungal and interest thereon from the petitioner Company. Ext.R2 (c) is produced as the objection of the Comptroller and Auditor General and the reply. It would also show that the Comptroller and Auditor General took the view that the decision to incorporate a provision (obviously Clause 9 of Ext.P5) in the agreement deviating from the prescribed guidelines resulted in undue benefit of Rs.8.79 Crores to the private entrepreneur. Thereafter reference is made to the fact that work involving actual transmission line length of 16.477 kms was completed in May, 2004 at a cost of Rs.11.35 Crores, out of which 8.79 Crores relating to 12.477 kms length was borne by the Board. It was noticed by the Comptroller and Auditor General in the audit that in respect of another agreement (Maniyar) for execution of a small hydro project entered into by the Board, the entire **WPC.15167/2006.** **21** cost of evacuation line was borne by the private agency. 11. In the reply in Ext.R2(c), it is inter alia stated that on actual execution the line length increased to 16.477 kms and that the length of the line constructed at Board's cost is 12.477 kms. The line work is completed in February, 2002. It is stated that the petitioner remitted an amount of Rs.256.29 lakhs being the cost of construction of the transmission line for 4 kms and the Board incurred 878.71 lacks towards cost of 12.477 kms. It is also noted in the answer that the decision in deviation of the general guidelines was taken with a view to encourage participation of private entrepreneurs in generation of power. It was challenged in a public interest litigation, which is pending. It is also stated that the Board has requested the Government to approve a proposal to recover the cost of 12.477 kms of transmission line and interest thereon from them and Government decision is awaited. 12. Going by the dicta of the Apex Court in ABL International Ltd.'s case ((2004) 3 SCC 553), there cannot be any doubt that a writ court can decide a disputed question of fact. It can even take oral evidence. But, unless there are extraordinary circumstances, the writ court does not decide matters requiring adducing of oral evidence. However, if a disputed question of fact can be decided with reference to the documents available, **WPC.15167/2006.** **22** as held by the Apex Court, in appropriate cases, it is open to the court to decide such disputes. In this case, a perusal of Exts.P8, P10, P12 and P14 which are all documents issued by the Board, would clearly go to show that the understanding of the parties was that the petitioner will be liable to pay the cost for putting up the transmission line upto a distance of four Kms. It is true that Ext.P1 Government Order did provide for putting up of the transmission line at the cost of the private party upto the nearest grid station. It is true that the said order is read as part of the Agreement. So also is Ext.P2 order. But, I cannot overlook the fact that in the meantime, there was a meeting as evidenced by Ext.P4. Therein, apparently, as a promotional gesture, it was decided that the transmission line need be put up only for a distance of four Kms. at the cost of the private party. It is only as a result of the same that Clause 9 of Ext.P5 came to be incorporated. It was apparently on the basis of this understanding that Exts.P8, P10, P12 and P14 were issued. The demands made thereunder, apparently came to be fulfilled. The answer of the Board to the query of the Comptroller & Auditor General would appear to make it clear that as contended by the petitioner, limiting the construction of the transmission line at the cost of the private party to 4 Kms. was a decision taken apparently pursuant to the meeting as evidenced by Ext.P4, as a promotional measure. Exts.P1 & P2 **WPC.15167/2006.** **23** contain various Clauses apart from Clause 7. Clause 7 of Ext.P1 runs counter to Clause 9 of Ext.P5 in so far as by Clause 9, the private party's liability is to bear the cost for the construction of the transmission line for a distance of four Kms. only under Ext.P5. It is this view which is reflected by the stand of the Board in all its correspondence as referred to. It is in this context that, as already noted, Ext.R2(a) letter came to be issued wherein it is categorically stated that the Board has to bear the cost of transmission line for a distance of 11 Kms. as per the Agreement. It is on the said basis that the Government responds by Ext.R2(b) granting sanction for the proposal. Once it is found that Clause 9 contemplated construction of the transmission line at the cost of the private party for a distance of four Kms., I would think that the reference to Clause 6 and the provisions in Clause 9 to the effect that the land required for construction of the transmission line will be considered as part of land required for the project as per conditions as elaborated under Clause 6 above and the metering equipment as per the specifications of KSEB shall be provided by the Company at their cost at a point in the generating station as approved by the KSEB and handed over to the KSEB along with transmission line, without **WPC.15167/2006.** **24** any compensation and to contend that it would mean that the writ petitioner is bound to defray the expenditure towards the cost of the land over which the transmission line had to be built irrespective of limitation as to length, appears to be clearly unsustainable being a most unreasonable view. It does not stand to reason that when the Board and the private party agreed that the latter need only defray the cost of putting up the transmission line for a distance of four Kms. and even the Government Order itself provided only for defraying the cost of constructing the transmission line only upto the nearest grid station, the parties would have understood the provision that the private party must defray the cost for the land required for construction of the transmission line as meaning that it will be liable for even defraying the cost of the land for the entire length, and that it is not limited only for the land required for construction of the line for four Kms. I have already extracted Clause 7 of Ext.P1. What was contemplated as per the same is that the transmission line from the captive plant to the nearest grid substation is to be built as a deposit work and land required for the construction of such transmission line is to be considered as part of the land for the Scheme. In fact, the last paragraph of Clause 5 of Ext.P1 appears to **WPC.15167/2006.** **25** correspond with Clause 6 of Ext.P5. Thus, even in Clause 7 of Ext.P1, the expression “land required for construction of such transmission line” would be limited to the transmission line built upto the nearest grid sub-station. When this is the position, it is clearly a most arbitrary interpretation to contend that when Clause 9 limits the liability to put the transmission line to 4 Kms. upon the petitioner, that by virtue of the provisions in Clause 9 read with Clause 6, the petitioner would be liable to meet the cost beyond 4 Kms. I would think that such an interpretation would appear to be most unreasonable and arbitrary and is essentially an attempt at wriggling out of the effect of entering into an agreement incorporating clause 9 which followed Ext.P4 meeting. The words contained in Clause 9 will clearly prevail over the provisions contained to the contrary in Exts.P1 Government Order. In other words, Ext.P1 must make way in so far as it relates to Clause 7, as far as Clause 9 of Ext.P5 Agreement provides otherwise. I undertake this exercise and arrive at the conclusions which I have mentioned both by reason of the relevant terms of Exts.P1, P2, P4 and P5 as also the unwavering perception of the Board itself of the import of the aforesaid documents, even in Exts.R2(a) and R2(c). I further note that this is a case where, in view of the stand expressed by the Government in **WPC.15167/2006.** **26** Ext.R2(b), it may not at all be appropriate to decline jurisdiction under Article 226 and relegate the petitioner for arbitration before the Government, which has already issued Ext.R2(b). The Government has also filed a Counter Affidavit. Thus, I would think that it may not be unsafe for me to conclude that the writ petitioner was liable only to bear the cost for the transmission line for a length of four Kms. I am not called upon to sit in judgment either over the wisdom or the propriety of the Board with eyes wide open entering into Ext.P5 agreement incorporating a clause like Clause 9. When the State or its instrumentality decides to enter into a contract with a specific clause, it would be arbitrary, if it seeks to act without any basis against the terms of the Agreement by which it professed itself to be bound. I am not impressed by the contention of the learned counsel for the Board that as Exts.P1 and P2 were Government Orders and they were to be read as part of Ext.P5 Agreement, they must prevail over the mere Minutes of the Meeting in which the Minister also attended it as evidenced by Ext.P4. While it may be true that in terms of Ext.P4 that Ext.P1 G.O. was not formally amended, nor a G.O. brought out, the fact remains that the Board decided to incorporate a Clause like 9, the effect of which, I have already adverted to. As much as a private party would be bound by the agreement, so must also an instrumentality of the State, be **WPC.15167/2006.** **27** bound by the terms of the Agreement. As there is no challenge to Ext.R2 (b), I am not called upon to pronounce on the same. However, I note that though a reference is made in Ext.P16 to Exts.R2(a) and R2(b), a perusal of Ext.P16 would make it clear that Ext.P16 is not issued on the basis of the approval sought vide Ext.R2(a) and concurrence granted vide Ext.R2(b). Ext.P16 is liable to be quashed and I do so. Exts.P18 and P19 being merely revenue recovery notices in consequence to Ext.P16 have no legs to stand on and they are also quashed. The writ petition is allowed as above. Sd/= **(K.M. JOSEPH, JUDGE** ) sb _**// True Copy //**_ _**PS to Judge**_
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.