High CourtDivision BenchAppeal allowed.

HOTEL AND RESTAURANT KARAMCHARI SANGH v. GULMARG HOTEL

Case / Petition Number:Civil Appeal No. 5371 of 2005

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Arijit Pasayat
  • C. K. Thakker
Judgment Date
2006-06-08
Court Decision / Holding
Appeal allowed. The High Court’s quashment of the Labour Commissioner’s certificate is set aside; the certificate for recovery is restored. There will be no order as to costs.
Final Disposition
Appeal allowed.

Parties to the Case

Appellants / Petitioners

  • Hotel and Restaurant KaramcharI Sangh

Respondents

  • Gulmarg Hotel
  • M/s Gulmarg Hotel and Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • Anuvrat Shanna
  • • Sanjay Kumar Singh
  • • M.P. Shorawala

Counsels for Respondents

  • • S. Wasim A. Qadri
  • • Pradeep Misra

Case Synopsis & Summary

This Supreme Court appeal concerns the interpretation and application of the Uttar Pradesh Industrial Peace (Timely Payment of Wages) Act, 1978. The appellant, a workers’ union, challenged the Allahabad High Court’s quashing of a Deputy Labour Commissioner’s certificate directing recovery of wages amounting to Rs. 60,810.76 from the respondent employer under the 1978 Act. The core issue revolves around when the “default” amount must be assessed for maintainability: at the time of filing the complaint or at the time of adjudication. The Labour Commissioner had issued the certificate after finding that the wage-bill in default exceeded Rs. 50,000, and the proceedings were instituted when the claim value exceeded that threshold. The High Court held the proceedings were not maintainable because, at the time of adjudication, the amount in default did not exceed Rs. 50,000. The Supreme Court reversed, holding that the determinative date is the date on which the claim is lodged, to preserve the Act’s objective of providing prompt relief to workers and to prevent abuse by partially paying to slip below the threshold. The Court reaffirmed that the Act is beneficial, designed to assist workers rather than adjudicate entitlement disputes, and it does not replace but supplements the Payment of Wages Act, 1936. It distinguished Modi Industries Ltd. v. State of UP and Ors. and permitted restoration of the Labour Commissioner’s certificate.

Provisions of Law Cited

Uttar Pradesh Industrial Peace (Timely Payment of Wages) Act, 1978 – Section 3(1) (recovery of wages as arrears of land revenue)Section 3(1) of the ActSections 5 and 6 of the ActPayment of Wages Act, 1936 (as context)

Legal Doctrines & Maxims

  • The Act is a beneficial piece of legislation intended to aid workers; the purpose is to secure timely payment of wages and maintain industrial peace.
  • The Labour Commissioner’s role is to assist workers in recovering wages rather than adjudicate any dispute over entitlements; where liability is disputed, parties may approach the regular forum.
  • The Act does not substitute the Payment of Wages Act but supplements it in a limited manner for big establishments with wage-bills exceeding Rs. 50,000.
  • Avoiding the legislative intent by making premature part-payments to reduce the default below Rs. 50,000 would defeat the Act’s purpose; thus the determinative date must be the filing date to preserve efficacy.

Submissions & Arguments

Contentions of Appellants / Petitioners

Appellant unions contend that the determinative date for maintaining the complaint under the UP Act is the date on which the claim is lodged, so that even if part payment reduces the later default below Rs. 50,000, the certificate can still be issued to secure wages due to workers. The Act is intended to safeguard industrial peace and to provide prompt relief, not to adjudicate disputed entitlement. Modi Industries Ltd. was distinguished and the Act should be interpreted as supplementary to the Payment of Wages Act, 1936, designed to secure wages for the workforce as a whole.

Contentions of Respondents

Respondents argued that maintainability must consider the date on which adjudication occurs, not merely when the complaint was lodged, since subsequent payments can alter the default amount and affect jurisdiction. They relied on Modi Industries Ltd. to contend that proceedings cannot issue a certificate if the amount in default is not sustained beyond the Rs. 50,000 threshold at adjudication. They maintained that the Labour Commissioner’s role is advisory or preparatory, and disputes over entitlement must be resolved in a regular forum.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Modi Industries Ltd. v. State of UP. and Ors.[1994] I SCC 159DistinguishedThe Court distinguished Modi Industries as not controlling the issue, noting differences in factual and legal circumstances relevant to maintainability under the UP Act.
State of Uttar Pradesh v. Basti Sugar Mills Co. Ltd.AIR 1961 SC 420PositiveCited to illustrate the analogous principle that the Labour Commissioner’s powers aim at preventing breaches of industrial peace and that the inquiry is of a limited, non-adjudicatory nature, with parties still free to pursue regular remedies.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against HOTEL AND RESTAURANT KARAMCHARI SANGH v. GULMARG HOTEL and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

A # HOTEL AND RESTAURANT KARAMCHARI SANGH _v._ MIS. GULMARG HOTEL AND ORS. JUNE 8, 2006 [ARJJIT PASAYAT AND C.K. THAKKER, JJ.] B _Labour Laws:_ \. _Uttar Pradesh Industrial Peace (Timely Payment of Wages) Act, 1978Section 3-Recovery of wages in certain industrial establishments as arrears_ C _of land revenue-Complaint for recovery of wages amounting to more than Rs. 60, 000-Subsequent payment of a part of claim by employer leaving the claimed amount less than Rs. 50,0001-Maintainability of the complaintAuthority held the complaint as maintainable as at the initiation of the complaint the claimed amount was more than Rs. 60,000-Jn Writ Petition High Court_ D _held that the date of adjudication is the determinative date for deciding maintainability of the complaint-Held: The determinative date for deciding maintainability of the complaint, is the date on which the claim is lodgedOtherwise, the very purpose of the Act i.e. to give help to the workers, would be defeated._ E Appellant filed a complaint under Uttar Pradesh Industrial Peace (Timely Payment of Wages) Act, 1978 for recovery of more than Rs. 60,000 towards wages. Respondent No. 1 objected to the same on the ground that the authority had no jurisdiction to entertain_ the complaint, as a part of the amount claimed had been paid subsequently and the amount payable was less than Rs. 50,000/-. The authority held that at the time of initiation F of the proceedings, the amount was admittedly more than Rs.50,000; that merely because a part of the amount claimed had been paid subsequently, that cannot affect the jurisdiction of the concerned authority to issue a certificate of recovery. Respondent-employer filed a writ petition wherein it was held by High Court that the proceedings were not maintainable as G at the time of adjudication, the amount in default did not exceed Rs. 50,000/-. Hence the present appeal. Allowing the appeal, the Court 17 H 18 SUPREME COURf REPORTS [2006] SUPP. 3 S.C.R. A HELD: 1. Uttar Pradesh Industrial Peace (Timely Payment of Wages) Act, 1978 is a beneficial one intended to give help to the workers who are not being paid their wages. The Assistant Labour Commissioner was justified in taking the view that the determinative date for deciding maintainability of the complaint under the Act, is the date on which the B claim is lodged. Otherwise, the very purpose of the enactment would be defeated. 123-B; 22-Fl _Modi Industries Ltd._ v. _State uf UP. and Ors.,_ fl994J I SCC 159, distinguished. 2. The Act does not supplant or substitute the Payment of Wages C Act, 1936, but supplements the said Act, in the limited area, viz., where the establishment, (i) produces, processes, adopts or manufactures some articles, (ii) where there is a default in the wage-bill of the entire such establishment and (iii) where such wage-bill exceeds Rs.50,000/-. The object of the Act is not so much to secure payment of wages to individual D workmen but to prevent industrial unrest and disturbance of industrial peace on account of the default on the part of the establishment in making payment of wages to their workforce as a whole. [21-B-DJ 3. Under the Act, the Labour Commissioner acts to assist the workmen to recover their wages which are admittedly due to them but E are withheld for no fault on their behalf. He does not act as an adjudicator if the entitlement of the workmen to the wages is disputed otherwise than· on frivolous or _prima facie_ untenable grounds. When the liability to pay the wages is under dispute which involves investigation of the questions of fact and/or law, it is not the function of the Labour Commissioner to F adjudicate the same. In sucllI cases, he has to refer the parties to the appropriate forum. The 1:xercise of the powers by the Labour Commissioner does not prevent either party from approaching the regular forum for the redressal of its grievance. (21-G-H; 22-A-BI _State of Ullar Pradesh_ v. _Basti Sugar Mills Co. Ltd,_ AIR (1961) SC G 420, relied on. CIVIL APPELLATE JURISDICTION: Civil Appeal No. 5371 of2005. From the Judgment and Order dated 16.01.2004 of the High Court of Allahabad in W.P. No. 375 (MIS) of2001. H HOTEL AND RESTAURANT KARAMCHARI SANGH v. GULMARG HOTEL [PASA YAT, J.] J 9 Anuvrat Shanna, Sanjay Kumar Singh and M.P. Shorawala for the A Appellant. S. Wasim A. Qadri and Pradeep Misra for the Respondents. The Judgment of the Court was delivered by **B** **ARIJIT PASA YAT, J.** Challenge in this appeal is to the order passed by a learned Single Judge of the Allahabad High Court allowing the Writ Petition filed by respondent No. I (hereinafter referred to as the 'employer'). The High Court by the impugned order quashed the order passed by the Deputy Labour Commissioner, Lucknow Region, Lucknow. The said authority C had issued a certificate for recovery of Rs.60,810.76 from respondent No.I in term~ of Uttar Pradesh Industrial Peace (Timely Payment of Wages) Act, 1978 (in short the 'Act'). Background facts filtering out unnecessary details are as follows: **D** On the basis of a complaint received from the appellant, the Assistant Labour Commissioner issued a notice to respondent No. I stating that it had not paid outstanding wages to the employees/workmen of the establishment amounting to more than Rs.60,000/-. The authority asked the respondent No.I-employer to show cause as to why recovery under the Act shall not be E tnade as arrears of land revenue by issuance of certificate of recovery. Respondent No. I-employer submitted a reply stating that nine employees were absconding and out of total 22 employees, 8 employees had been paid their wages and the amount to be payable was less than Rs.50,000/-. It was, therefore, submitted that the provisions of the Act cannot be applied. The Assistant Labour Commissioner considered the plea of the employer and F rejected the same by holding that the claim was instituted on 16.10.2000, notice was issued on 19.10.2000 and the response was filed on 14.12.2000. At the time of initiation of the proceedings, the amount was admittedly more than Rs.50,000/-. Merely because a part of the amount claimed had been paid subsequently, that cannot affect the jurisdiction of concerned authority to issue a certificate for recovery. The employer filed a Writ Petition before the G Allahabad High Court questioning correctness of the order. The High Court came to hold that at the time of adjudication, the amount in default did not exceed Rs.50,000/- and, therefore, proceedings were not maintainable. Reference was made to a decision of this Court in _Modi Industries Ltd._ v. _State of U.P. and Ors.,_ [ 1994] I sec 159 to hold that the certificate for H 20 SUPREME COURT REPORTS (20061 SUPP. 3 S.C.R. A recovery could not have been issued. The writ petition was accordingly allowed. In support of the appeal, learned counsel for the appellant submitted that _Modi Industries·_ case (supra) has no bearing on the subject matter of controversy. The Assistant Labour Commissioner was right in his view that B at the time the claim was lodged, the amount was admittedly more than Rs.50,000/-. By adopting a subterfuge the employer cannot in law be permitted to take away the jurisdiction of the authority to issue certificate for recovery. Learned counsel for the State, respondent No.2 and the concerned C authority-respondent No.3 supported the stand. There is no appearance on behalf of respondent No. I-employer. In order to resolve the controversy between the parties, it is first necessary to examine the provisions of the Act. As the title of the Act itself suggests it has been enacted to secure industrial peace by ensuring timely D payment of wages to the workmen. The preamble of the Act states that it is an Act to provide "in the interest of maintenance of industrial peace, a timely payment of wages in bigger industrial establishments and for matters connected therewith". The statement of objects and reasons of the Act states that delays in payment of wages of workmen lead to simmering discontent among them. Sometimes a grave threat to law and order is also forced on this account. The E provisions of the Payment of Wages Act, 1936 (in short 'Wages Act') have been found to be inadequate to ensure timely payment of wages. The incidence of disturbance of industrial peace being greater in comparatively bigger establishments, it was considered necessary to provide that if the wage bill in default exceeds Rs.50,000/-, the amount should be recoverable as arrears F of land revenue. Further, in order to curb the tendency of the employers to keep large amounts of wages in arrears, it was also necessary to make it a penal offence to be in default of a wage-bill exceeding Rs. I lakh. It will thus be clear from the preamble, the statement of objects and reasons and the provisions of the Act that, firstly the Act has been placed on G the statute book to ensure timely payment of wages by the bigger establishments, the incidence of disturbance of industrial peace being greater in such establishments on account of the default in payment of wages. Secondly, the Act deals with defaults in payment of the wage-bill of all the workmen in the establishment. It is not meant to provide a remedy for the default in payment of wages of individual workmen. That can be taken care H HOTEL AND RESTAURANT KARAMCHARI SANGH _v._ GULMARG HOTEL [PASAYA T, J] 21 ). of by the provisions of the Wages Act which provisions are found inadequate A to ensure timely payment of wages of the whole complement of workmen in an establishment. Thirdly, it is not in respect of the default in payment of every wage-bill; but only if a wage-bill exceeds Rs.50,000/- the Labour Commissioner can be approached under the Act for redressal of the grievance. Fourthly, the Act is not applicable to all establishments but only those B establishments which produce, process, adopt or manufacture some articles. It will, therefore, be evident that the Act does not supplant or substitute the Wages Act but supplements the said Act, in the limited area, viz., where the establishment, as stated above, (i) produces, processes, adopts or manufactures some articles, (ii) where there is a default in the wage-bill of the entire such establishment and (iii) where such wage-bill exceeds Rs.50,000/-. The object C of the Act as stated above is not so much to secure payment of wages to individual workmen but to prevent industrial unrest and disturbance of industrial peace on account of the default on the part of the establishment in making payment of wages to their workforce as a who le. It appears that many establishments had a tendency to delay the payment of wages to their workmen and were playing with the lives of the workmen with impunity. This naturally D led to a widespread disturbance of industrial peace in the State. Hence the legislature felt the need for enacting the present statute. This being the case, the inquiry by the Labour Commissioner contemplated under Section 3 of the Act is of a very limited nature, viz., whether the establishment has made a default in timely payment of wages to its workmen as a whole when there is E no dispute that the workmen are entitled to them. The inquiry under Section 3 being thus limited in its scope, the Labour Commissioner's powers extend only to finding out whether the workmen who have put in the work were paid their wages as per the terms of their employment and within the time stipulated by such terms. If the Labour F Commissioner is satisfied that the workmen, though they have worked and were entitled to their wages, had not been paid the same within time, he has further to satisfy himself that the arrears of wages so due exceed Rs.50,000/ -. It is only if he is satisfied on both counts that he can issue the certificate in question. Under the Act, the Labour Commissioner acts to assist the G workmen to recover their wages which are admittedly due to them but are withheld for no fault on their behalf. He does not act as an adjudicator if the entitlement of the workmen to the wages is disputed otherwise than on frivolous or _prima facie_ untenable grounds. When the liability to pay the wages is under dispute which involves investigation of the questions of fact and/or law, it is not the function of the Labour Commissioner to adjudicate H 22 SUPREME COURT REPORTS [2006] SUPP. 3 S.C.R. A the same. In such cases, he has to refer the parties to the appropriate forum. The powers conferred on the Labour Commissioner under Section 3 of the Act are to prevent apprehended or present breach of industrial peace. That is why the inquiry contemplated is of a summary nature. The exercise of the said powers by the Labour Commissioner does not prevent either party B from approaching the regular forum for the redressal of its grievance. Construing a more or less similar provision of Section 3(b) of the U.P. Industrial Disputes Act, 1947 in _State of Uttar Pradesh_ v. _Basti Sugar Mills Co. Ltd.,_ AIR (I 961) SC(. 420, this Court had taken the same view. The provisions of the said Settiop 3(b) read as follows: c ## D "3. _Power to prevent strikes, lockouts, etc._ - If, in the opinion of th,. State Government, it is necessary or expedient so to do for securing the public safety or convenience or the maintenance of public order or supplies and services essential to the life of the community, or for maintaining employment, it may, by general or special order, make - provision ## (a) x xx xxx E (b) for requiring employers, workmen or both to observe for such period, as may be specified in the order, such terms and conditions of employment as may be determined in accordance with the order; ## xxx xxx" The above position was highlighted in _Modi's_ case (supra). The Assistant Labour Commissioner was justified in taking the view F that the determinative date is the date on which the claim is lodged. Otherwise, the very purpose of the enactment would be defeated. The relevant provisions i.e. sub-section (I) of Section 3 of the Act reads as follows: ## G H "3. _Recovery of wages in certain Industrial establishments as arrear of land revenue._ (I) Where the Labour Commissioner is satisfied that the occupier of an industrial establishment is in default of payment of wages and that the wage·-bill in respect of which such occupier is in default exceeds fifty thousand rupees, he may, without prejudice to the provisions of Sections _5_ and 6, forward to the Collector, a certificate under his signature specifying the amount of wages due from the industrial establishment concerned." HOTEL AND RESTAURANT KARAMCHARI SANGH v. GULMARG HOTEL [PASA YAT,.LJ 23 Though the expression used is "is in default of payment of wages" it is A relatable to the date on which the claim is lodged. Otherwise, to overcome action contemplated under Section 3(1) of the Act i.e. issuance of certificate for recovery by making a part payment to see that the amount comes below Rs.50,000/-, a crafty and unscrupulous employer can defeat the legislative intent. The act as noted above is a beneficial one intended to give help to the B workers who are not being paid their wages. The High Court completely lost sight of the relevant factors and relied on the decision in _Modi's_ case (supra) which had not decided the issue under consideration. Therefore, the order passed by the Assistant Labour Commissioner is restored and the impugned order of the High Court is quashed. The appeal C is allowed but in the circumstances there will be no order as to costs. K.K.T. Appeal allowed. ' -< -