Hindustan Construction Company Limited v Union of India & Ors.
Case Synopsis & Summary
This batch of writ petitions challenges the constitutional validity of Section 87 of the Arbitration and Conciliation Act, 1996, inserted by the Arbitration and Conciliation (Amendment) Act, 2019, and the repeal of Section 26 of the 2015 Amendment Act by Section 15 of the 2019 Amendment Act. The petitions also contest various provisions of the Insolvency and Bankruptcy Code, 2016, alleging discriminatory treatment against petitioners, who are a contractor operating against several government bodies. The petitioners argue that Section 87 creates an automatic-stay of arbitral awards upon admission of Section 34 challenges, re-introducing a mechanism that this Court, in BCCI v Kochi Cricket Pvt. Ltd. (2018), had discouraged. They contend that the 2019 amendments undermine the objects of the Act—speedy disposal and minimal court intervention—violate Articles 14, 19(1)(g), 21 and 300-A, and impair the enforcement regime and the Insolvency Code, potentially rendering them insolvent. The respondents defend the amendments as clarificatory and essential to adapt the 2015 reforms to proceedings post-23 October 2015, while preserving the Act’s policy goals. The judgment meticulously analyses UNCITRAL Model Law principles, various precedents (notably BCCI, NALCO, Fiza, Mobilox, Renusagar, and others), and concludes that Section 87 is manifestly arbitrary. The Court dismisses the petitions and disposes of the related applications, with several MA petitions allowed in terms of prayer (a).
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- R.F. Nariman
- Surya Kant
- V. Ramassubramanian
- Judgment Date
- 2019-11-27
- Court Decision / Holding
- The Court disposed of the petitions: Section 87 is struck down as unconstitutional for violating equality before law and due process; Section 26 of the 2015 Amendment Act is held to be applicable to court proceedings commenced after 23 October 2015, preserving the BCCI judgment’s effect; The 2019 Amendment Act’s removal of Section 26 and insertion of Section 87 is set aside; The 2015 Amendment Act’s changes related to Section 36 are clarified as clarificatory, and the automatic-stay doctrine is not revived; The batch of Writ Petitions is dismissed, and MA Nos. 2140-2144 of 2019 in CA Nos. 2621-2625 are allowed in terms of prayer (a).
- Final Disposition
- Writ petitions disposed; Section 87 struck down as manifestly arbitrary; Section 26 of the 2015 Amendment Act continues to apply to court proceedings established post-23.10.2015 per BCCI; 2019 Amendment Act’s Section 87 is struck down; MA Nos. 2140-2144 of 2019 in CA Nos. 2621-2625 are allowed in terms of prayer (a).
Parties to the Case
Appellants / Petitioners
- Hindustan Construction Company Limited
- M/s Patel Engineering Ltd.
- M/s Gangotri Enterprises Limited
- M/s Gammon Engineers and Contractors Private Limited
Respondents
- Union of India
- National Highways Authority of India (NHAI)
- NHPC Ltd.
- NTPC Ltd.
- IRCON International Ltd.
- Public Works Department (PWD)
Legal Representation & Advocates
Counsels for Petitioners
- • Dr Abhishek Manu Singhvi (Senior Advocate)
- • Neeraj Kishan Kaul (Senior Advocate)
- • C.A. Sundaram (Senior Advocate)
- • Nakul Dewan (Senior Advocate)
Counsels for Respondents
- • K. K. Venugopal, Attorney General for India
- • Tushar Mehta, Solicitor General of India
- • Pinky Anand, Additional Solicitor General
Provisions of Law Cited
Legal Doctrines & Maxims
- casus omissus
- two bites at the cherry (two-bites doctrine)
- per incuriam (judgments treated as per incuriam)
- manifest arbitrariness (standard of constitutional review)
Submissions & Arguments
Contentions of Appellants / Petitioners
The applicants argued that Section 87, as introduced by the 2019 Amendment Act, makes recovery contingent on a stay of money payable against arbitral awards and would thwart the objective of speedy dispute resolution under the 1996 Act and the 2015 amendments. They contended that Section 87 amounts to a retrospective change undermining BCCI v Kochi Cricket Pvt. Ltd. (2018), removes the protective framework established by the 2015 Amendment Act, and would create arbitrariness and discrimination against government entities and statutorily created bodies. They urged that Section 26 of the 2015 Amendment Act should apply to court proceedings arising from arbitral proceedings commenced before 23 October 2015, as held in BCCI; the 2019 Act’s removal of Section 26 was therefore unconstitutional. They urged re-reading Section 3(7) to exclude government bodies and argued Insolvency Code provisions cannot be weaponized for recovery in this context.
Contentions of Respondents
The respondents defended the 2019 Amendment Act as clarificatory in nature to unify the application of the 2015 amendments to post‑23 October 2015 arbitral proceedings and to address divergent judicial opinions. They argued that BCCI laid down the transitional framework and that the Act’s objectives remain to speedily resolve disputes with minimum court interference. They maintained that the 2019 Amendment Act does not undermine the Insolvency Code; rather, it aligns with policy considerations and the Srikrishna Committee Report. They challenged the petitioners’ interpretation of automatic-stay and asserted that the NHAI and other statutory bodies are covered by a coherent regulatory framework and that the Insolvency Code's structure remains compatible with government entities.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (19)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Hindustan Construction Co. Ltd. v. Union of India (BCCI) | (2018) 6 SCC 287 | Positive | Used as a foundational reference to discuss the impact of 2015 amendments and the object of arbitration law; the judgment confirms the need to apply amendments to court proceedings post-2015 and informs the Court’s approach in Section 87. |
| Chloro Controls (I) Pvt. Ltd. v. Seven Trent Water Purification Inc. | (2013) 1 SCC 641 | Positive | Cited to underscore alignment with UNCITRAL Model Law principles and the interpretation of Section 36 and related enforcement concepts. |
| National Aluminium Co. Ltd. v. Pressteel & Fabrications (P) Ltd. | (2004) 1 SCC 540 | Overruled | Described as per incuriam with respect to the interpretation of Section 36 and its effect on stay and enforcement. |
| National Buildings Construction Corpn. Ltd. v. Lloyds Insulation India Ltd. | (2005) 2 SCC 367 | Overruled | Followed NALCO historically but treated as per incuriam in the light of later amendments and the present judgment. |
| Fiza Developers and Intra-Trade Pvt. Ltd. v. AMCI (India) Pvt. Ltd. | (2009) 17 SCC 796 | Overruled | Referred to as per incuriam due to not considering Section 9, 35 and Part II of Section 36 in light of amended law. |
| Leela Hotels Ltd. v. HUDCO | (2012) 1 SCC 302 | Positive | Cited to support reading of Section 9 and enforcement implications consistent with modern interpretation. |
| K. Kishan v. Vijay Nirman Co. Pvt. Ltd. | (2018) 17 SCC 662 | Positive | Used to discuss pre-existing disputes and the scope of insolvency measures vis-à-vis arbitral awards. |
| Mobilox Innovations Pvt. Ltd. v. Kirusa Software Pvt. Ltd. | (2018) 1 SCC 353 | Positive | Applied to define scope of disputes and informational structure for insolvency and corporate dispute resolution. |
| Ssangyong Engineering & Construction Co. Ltd. v. NHAI | (2019) SCC Online 677 | Positive | Cited regarding the post‑2015 framework and the extent of court interference in arbitration. |
| Renusagar Power Plant Co. Ltd. v. General Electric Co. | (1994) Supp (1) SCC 644 | Positive | Referenced for historical basis on recognition and enforcement of awards and model law alignment. |
| Associated Construction v. Pawanhans Helicopters Ltd. | (2008) 16 SCC 128 | Positive | Cited to illustrate summary nature of Section 34 proceedings and the degree of deference to arbitral awards. |
| Canara Nidhi Ltd. v. M. Shashikala | (2019) SCC Online SC 1244 | Positive | Used to discuss procedural aspects of arbitral review and the nature of summary reliefs. |
| Ch K. Goody? | — | Mentioned Only | Unclear/placeholder entry for potential additional case references in the text; not central to core holdings. |
| Gulabdas & Co. v. Asstt. Collector of Customs | AIR 1957 SC 733 | Mentioned Only | Cited in general writ petition jurisprudence; not central to the key constitutional issues here. |
| Sumedha Nagpal v. State of Delhi | (2000) 9 SCC 745 | Positive | Used to illustrate judicial restraint in handling disputed factual questions in writ petitions. |
| Shri Prithvi Cotton Mills Ltd. v. Broad Borough Municipality | (1969) 2 SCC 283 | Positive | Cited for principle on judicial binding effect of earlier decisions when conditions are altered by law. |
| State of Tamil Nadu v. Arooran Sugars Ltd. | (1997) 1 SCC 326 | Positive | Used to discuss retroactive removal of basis of judgments and legislative power to amend. |
| UOI v. Parameswaran Match Works | (1975) 1 SCC 305 | Positive | Cited regarding the non-interference with cut-off date fixation unless arbitrary or discriminatory. |
| Goa Foundation v. State of Goa | (2016) 6 SCC 602 | Positive | Cited for the principle that judicial pronouncements cannot be set aside by post‑hoc legislative acts absent a valid basis. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Hindustan Construction Company Limited v Union of India & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.