High Court of KeralaSingle JudgeDismissed

Hind Erectors v. Travancore Titanium Products Ltd and others

Case / Petition Number:WP(C) No. 42205 of 2022

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • VIJU ABRAHAM
Judgment Date
2023-08-11
Court Decision / Holding
Writ petition dismissed. The court held that the dispute stems from a contractual relationship and is not amenable to writ relief; the petitioner may pursue civil court relief. The period during which the writ petition was pending will be excluded in calculating the period of limitation if the petitioner approaches the civil court.
Final Disposition
Dismissed

Parties to the Case

Appellants / Petitioners

  • Hind Erectors

Respondents

  • Travancore Titanium Products Limited, represented by General Manager, Kochuveli, Thiruvananthapuram – 695021
  • Manager (Commercial) Travancore Titanium Products Limited, Kochuveli, Thiruvananthapuram – 695021
  • Head of Department, Commercial Department, Travancore Titanium Products Limited, Kochuveli, Thiruvananthapuram – 695021

Legal Representation & Advocates

Counsels for Petitioners

  • • Treesa Manjila
  • • Meera Ramesh
  • • E. Adithyan

Counsels for Respondents

  • • Latha Anand, SC

Case Synopsis & Summary

The petition arises out of a contractual dispute between Hind Erectors (the petitioner) and Travancore Titanium Products Limited (the 1st respondent) along with the other respondents. The petitioner, the successful tenderer for a turnkey project to supply and install a 6.2 m ID sulphuric acid tank, argues that the work could not start during the shutdown period due to lack of clearance or intimation from the respondents and that there was a sharp rise in steel prices (approximately 80-60%) during the tender period, making completion unaffordable. The work order was issued on 30.11.2020, with a completion window of 105 days and security deposit/ execution of a performance agreement mandated under clause 10 of Ext.P2. The petitioner failed to remit the security deposit and to execute the performance agreement, and subsequently sought cancellation of the order (Ext.P3) citing price escalation. Ext.P15–P16 show the work was re-tendered and the later contract awarded to another contractor, with respondents incurring an additional cost of Rs. 3,66,202/-, recovered from the petitioner’s running bills (Ext.P22). Respondents contend the matter is purely contractual and must be adjudicated in civil court; the petitioner claims no delay on its part and challenges the penalties. The court dismisses the writ petition, holding the dispute arises from private contract and should be addressed in civil court; it also notes that the writ period will be excluded for limitation if civil action is pursued.

Provisions of Law Cited

Clause 10(3) read with Clause 5 of Ext.P2 Work OrderClause 10(5) of Ext.P2 Work OrderClause 10(6) of Ext.P2 Work OrderExt.P2 Work Order (Tender/Contract) Clauses

Legal Doctrines & Maxims

  • Writ jurisdiction is not a forum for adjudication of contractual disputes; such disputes lie in civil court.
  • In contract disputes, issues must be adjudicated by a competent civil court; writ petitions are not a proper remedy for private contractual disputes.
  • Time spent in a writ petition shall be excluded while calculating the period of limitation if the party pursues civil action subsequently.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that there was no clearance to start during the shutdown period and no intimation from the respondents. The order anticipated quick execution but the respondents failed to grant permission or provide timely clearance. The petitioner argues that the significant rise in steel prices affected feasibility and that the work was put to retendering. It asserts there was no deliberate delay on its part and that the contractual dispute involves private law; therefore, challenge through writ should be entertained, or the respondents’ authority to recover penalties should be reviewed. The petitioner emphasizes the contract terms (Ext.P2) and the failure to remit security deposit and execute the performance agreement as critical default points. The writ petition challenges the charges and seeks relief against recovery from running bills.

Contentions of Respondents

The respondents submit that the petitioner did not complete the work despite multiple opportunities and that the contract was terminated on 07.06.2021; retendering ensued, incurring Rs. 3,66,202 as additional cost, which was recovered from the petitioner’s running bills (Ext.P22). They argue the dispute is contract-based and cannot be resolved through writ petition; civil court is appropriate, citing decisions of the Supreme Court (State of U.P. v. Bridge & Roof Co. (India) Ltd; Kerala State Electricity Board v. Kalathil). The respondents contend the petitioner failed to remit security deposit and to execute a performance agreement, and the matter must be adjudicated under private law, not writ jurisdiction.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
State of U.P. and others v. Bridge & Roof Company (India) Ltd(1996) 6 SCC 22Mentioned OnlyCited by respondents to support the proposition that contractual disputes fall within civil court, not writ jurisdiction.
Kerala State Electricity Board and another v. Kurien E. Kalathil and others(2000) 6 SCC 293Mentioned OnlyCited to support the civil court jurisdiction for contractual disputes; used as authority for approach, not overruled or distinguished.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Hind Erectors v. Travancore Titanium Products Ltd and others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **`IN THE HIGH COURT OF KERALA AT ERNAKULAM`** ## **`PRESENT`** ## **`THE HONOURABLE MR.JUSTICE VIJU ABRAHAM`** ``` FRIDAY, THE 11[TH] DAY OF AUGUST 2023 / 20TH SRAVANA, 1945 ``` ``` WP(C) NO. 42205 OF 2022 ``` ## **`PETITIONER:`** ``` HIND ERECTORS, REPRESENTED BY MANAGING PARTNER AJAYAKUMAR GHOSH GANGADHARAN, S/O GANGADHARAN, AGED 65 YEARS, DEVASWOM BUILDING, FIRST FLOOR, POST BOX NO: IV KARUNAGAPPALLY -690518, KOLLAM(DIST), KERALA, INDIA ``` ``` BY ADVS. TREESA MANJILA MEERA RAMESH E.ADITHYAN ``` ## **`RESPONDENTS:`** - **`1 TRAVANCORE TITANIUM PRODUCTS LIMITED REPRESENTED BY GENERAL MANAGER, KOCHUVELI, THIRUVANANTHAPURAM - 695021`** - **`2 MANAGER (COMMERCIAL) TRAVANCORE TITANIUM PRODUCTS LIMITED, KOCHUVELI, THIRUVANANTHAPURAM - 695021`** - **`3 HEAD OF DEPARTMENT, COMMERCIAL DEPARTMENT, TRAVANCORE TITANIUM PRODUCTS LIMITED, KOCHUVELI, THIRUVANANTHAPURAM - 695021 BY ADV LATHA ANAND, SC`** ``` THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 11.08.2023, ``` ``` THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ``` WP(C) No.42205 of 2022 2 ## **VIJU ABRAHAM, J.** **................................................................. W.P.(C) No.42205 of 2022 .................................................................** Dated this the 11[th] day of August, 2023 ## **JUDGMENT** The above writ petition is filed seeking a direction to the 2[nd] respondent not to seize the additional charges of Rs.3,66,202/- from the running bills as per Ext.P21. 2. Petitioner is a partnership firm who was the successful tenderer in the tender floated as per Ext.P1 and Ext.P2 work order was issued in favour of the petitioner. By Ext.P3 the petitioner made a request for cancellation of Ext.P2 work order on the ground that there was an increase of 60% in the steel price during the last five months. By Ext.P4 the 2[nd] respondent issued a reply informing that the work order was received on 30.11.2020 and they had to complete the work within 60 days period and now there is a delay of almost five months and therefore they requested the petitioner to supply the materials at the earliest, remit security deposit and execute agreement immediately, failing which they will be arranging the work with other sources at the petitioner’s risk and cost. Petitioner submits that there is no delay on his part and he has in fact approached the site representative for proceeding with the supply and erection work. Essentially the contention of the petitioner is that no permission was granted by the respondent company and they were informed that the WP(C) No.42205 of 2022 3 work could not be started during the shut down period as they did not get any clearance or intimation from the respondents. It is also contended that the cost of steel has increased roughly 80% after the tender quotation period making it unaffordable for the petitioners. Later by Ext.P15 the work was re-tendered and thereafter Ext.P16 letter was issued wherein it is intimated that after the cancellation of the work order issued in favour of the petitioner the work was retendered whereby the company incurred an additional expense of Rs.3,66,202/- and the petitioner was directed to remit the said amount towards additional cost involved in executing the aforesaid work by another contractor. Petitioner by Ext.P17 requested to relieve of this penalty amount. Thereafter as is evident from Ext.P22 the amount of Rs.3,66,202/- towards additional cost involved in executing the aforesaid work through another contractor was deducted from the running bill of the petitioner. 3. A detailed counter affidavit has been filed by the respondents mainly contending that the petitioner has not completed the work despite repeated requests from the respondents and contract was ultimately terminated as per communication dated 07.06.2021 specifically informing the petitioner that the work would be undertaken at the risk and cost of the petitioner. Even after the said communication, the petitioner was given opportunities to comply with the contractual obligation but the petitioner did not avail any of the WP(C) No.42205 of 2022 4 said opportunities to complete the work. Consequently the termination of contract was confirmed and the same was informed to the petitioner as per Ext.P14 communication. Subsequently, the additional expenses incurred by the respondents for execution of the work was quantified and informed the petitioner vide Ext.P18 communication and since the petitioner failed to pay the same, the amount was deducted from the running bill of the petitioner as early as on 03.10.2022 as is evident from Ext.P22 ledger. The tender invited was for “the supply, installation of sulphuric acid tank of size 6.2 m ID x 2.5 metres height on turnkey basis” . Though work order was issued to the petitioner on 20.11.2020 and as per clause 10(3) read with clause 5 of Ext.P2 work order the work was agreed to be completed within 105 days of the issuance of work order and as per clause 10(5) the petitioner was required to remit 5% of the contract value as security deposit within 15 days from the date of issue of the work order and also as per clause 10(6) the petitioner was bound to execute a performance agreement within 15 days of the remittance of the security deposit and start the work immediately after remitting the security deposit, the petitioner failed to remit the security deposit and to execute the performance agreement, instead the petitioner vide Ext.P13 requested to cancel the work order citing increase in the price of steel. Ultimately the work was re-tendered and Ext.R1(e) work order was issued to the new contractor and the said contractor WP(C) No.42205 of 2022 5 completed the work and the additional cost involved in executing the work through the said contractor was calculated as Rs.3,66,202/which was directed to be deposited by the petitioner and due to the failure on the part of the petitioner to make the deposit, the same was recovered from the running bills. It is contended that the default was absolutely on the petitioner and they failed to fulfil the contractual obligation. The respondents have also taken a contention that the issues raised in the writ petition cannot be adjudicated in a writ proceeding since the issues arise essentially out of a contractual relationship between the petitioner and the respondents and it will fall within the realm of private law and therefore the reliefs sought for by the petitioner cannot be granted in this proceedings. To substantiate their contentions, they rely on the judgments of the Supreme Court in _**State of U.P. and others v. Bridge & Roof Company (India) Ltd, (1996) 6 SCC 22**_ and _**Kerala State Electricity Board and another v. Kurien E. Kalathil and others, (2000) 6 SCC 293**_ and therefore the petitioner if aggrieved by any of the proceedings initiated by the respondents as part of the contract, they have to approach the competent civil court. 4. I have heard the rival contentions of both the parties. 5. The specific contention of the respondents is that the petitioner failed to execute the work as per the conditions in the work order despite the several chances given and it is thereafter the work order WP(C) No.42205 of 2022 6 was cancelled and the work was re-tendered at the risk and cost of the petitioner. It is the additional cost of Rs.3,66,202/- was also recovered from the running bills of the petitioner as is evident from Ext.P22 ledger. Petitioner has not challenged Exts.P9, P14 and P18 which are orders regarding the cancellation of the work order and consequential recovery of the loss due to re-tendering of the work. Even otherwise, admittedly the said dispute arising out of a contract and the matter in issue can be adjudicated only by a competent civil court after adducing evidence and the same cannot be adjudicated in a writ proceedings. Therefore the writ petition is dismissed. It is made clear that if the petitioner chooses to approach the Civil Court to adjudicate the claim, the time during which this writ petition was pending before this Court will be excluded while calculating the period of limitation. Sd/- ## **VIJU ABRAHAM** **JUDGE** cks WP(C) No.42205 of 2022 7 ## **`APPENDIX OF WP(C) 42205/2022`** ``` PETITIONER EXHIBITS ExhibitP1EXHIBIT P 1 TRUE COPY OF THE TENDER FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 22.09.2020 ExhibitP2TRUE COPY OF THE WORK ORDER AWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 30.11.2020. ExhibitP3TRUE COPY OF THE LETTER INTIMATION DATED 19.04.2021 FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT. Exhibit P4TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 20.04.2021 Exhibit P5TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 22.04.2021 Exhibit P6TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 05.05.2021 Exhibit P7TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 06.05.2021 Exhibit P8TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 12.05.2021 ``` ``` Exhibit P9TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 07.06.2021 ``` ``` Exhibit P10TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 08.06.2021 Exhibit P11TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 11.06.2021 ``` WP(C) No.42205 of 2022 8 ``` Exhibit P12TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 17.06.2021 Exhibit P13TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 18.06.2021. ``` ``` Exhibit P14TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 23.06.2021. Exhibit P15TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 26.06.2021 Exhibit P16TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 18.07.2022 Exhibit P17TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 30.07.2022 Exhibit P18TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE 1ST RESPONDENT TO THE PETITIONER DATED 16.09.2022 ``` - `Exhibit P19 TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE PETITIONER TO THE 3RD RESPONDENT DATED 16.09.2022` - `Exhibit P20 TRUE COPY OF THE LETTER INTIMATION FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 19.09.2022` - `Exhibit P21 TRUE COPY OF THE DETAILED` - `REPRESENTATION FORWARDED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 07.12.2022.` ``` Exhibit P22TRUE COPY OF THE LEDGER DATED 16.12.2022 . ``` ``` RESPONDENT EXHIBITS ``` ``` Exhibit R1(a)True copy of the letter dated 04.05.2021 issued by the 2nd ``` WP(C) No.42205 of 2022 9 ||`respondent to the petitioner`| |---|---| |`Exhibit R1(b)`|`True copy of the letter dated`| ||`13.05.2021 issued by the petitioner`| ||`to the 1st respondent`| |`Exhibit R1(c)`|`True copy of the letter dated`| ||`07.06.2021issued by the 2nd`| ||`respondent to the petitioner`| |`Exhibit R1(d)`|`True copy of the letter dated`| ||`12.06.2021 issued by the petitioner`| ||`to the 2nd respondent`| |`Exhibit R1(e)`|`True copy of the work order dated`| ||`07.09.2021 issued to M/s.Deepak`| ||`Engineering Works`|