Hind Construction Contractors v. Maharashtra

Case / Petition Number:
Civil Appeal Nos. 483 and 1769 of 1969
Neutral Citation:[1979] 2 SCR 1147

Case Synopsis & Summary

This is a contract dispute arising from a 12-month completion requirement for constructing an aqueduct across the Alandi River. The appellant contends that time was not of the essence and that numerous hurdles—monsoon rains, poor access, rejection of materials, and administrative delays—delayed performance; rather than grant a time extension, the respondent State rescinded the contract. The trial court held time was not of the essence and awarded limited damages. The Bombay High Court did not decide whether time was essential, proceeding instead to assess mala fides and the reasonableness of the rescission, ultimately upholding the rescission and some limited relief. On appeal, the Supreme Court held that determining whether time is of the essence is a question of the contract’s intention, to be read with all clauses. It stressed that clauses permitting extensions and penalties, and waiver of the fixed period, can negate an express time stipulation. The Court emphasized that even with an express “time is of the essence” clause, other provisions may exclude that inference. It held the rescission in the present case to be illegal and wrongful, and reversed the High Court, restoring the trial court’s decree in favor of the appellant and directing refund of the security deposit and other sums, with interest and costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Y. V. Chandrachud
  • V. R. Tulzapurkar
  • A. P. Sen
Judgment Date
1979-01-30
Court Decision / Holding
Appeal allowed. The Court set aside the High Court’s common judgment and decree dated 9/10/1968 and restored the trial court’s decree. The appellant is entitled to damages consistent with work performed and refunded sums: full security deposit of Rs. 4,936 and Rs. 5,845 for work done but unpaid, plus nominal damages of Rs. 120, plus interest from the date of rescission. The High Court’s decree in FA 245 of 1962 is confirmed to the extent of dismissing that appeal. The appellant/plaintiff is awarded costs of the appeal and related proceedings.
Final Disposition
Appeal allowed; High Court judgment reversed; trial court decree restored; High Court’s decree partially affirmed; appellant awarded damages and costs; security deposit refunded.

Parties to the Case

Appellants / Petitioners

  • Hind Construction Contractors

Respondents

  • The State of Maharashtra

Legal Representation & Advocates

Counsels for Petitioners

  • • M. C. Bhandare
  • • J. S. Sinha
  • • K. J. John

Counsels for Respondents

  • • R. H. Dhebar
  • • B. V. Desai
  • • M. N. Shroff

Provisions of Law Cited

Civil Procedure Code, s. 80Clause 2 of the Conditions of Contract (Ex. 34)Clause 6 of the Conditions of Contract (Ex. 34)

Legal Doctrines & Maxims

  • Time is of the essence of the contract; the inference can be excluded by other provisions of the contract.
  • Waiver of time can render the fixed period non-fundamental; reasonable extension may be granted under contract terms.
  • Where time is not of the essence, employer may fix a reasonable time by notice; extension clauses may permit delays without forfeiture.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that the 12-month completion term was not an absolute, time‑of‑the‑essence clause. Extensions were possible under Clause 6, and the monsoon and site difficulties should have been considered. The waiver of the 12-month period was evidenced by the rescission letter (Ex. 78), and the State’s rescission was illegal and wrongful. The contract’s terms—especially penalties (Clause 2) and extension provisions—show that time was not necessarily fundamental and should be read with other clauses to determine true intent. The High Court erred by not deciding whether time was of the essence and by treating the rescission as justified without examining mala fides or the conduct of the authorities.

Contentions of Respondents

The State contended that time was expressly of the essence per Clause 2 and that the 12-month period was a fundamental term. Even with a possible extension under Clause 6, failure to complete within the specified time entitled rescission. The State argued that the appellant’s delay, despite extension requests, justified termination and forfeiture of the security deposit, and that the High Court appropriately assessed mala fides and reasonableness; the rescission was not wrongful given the practicalities and the appellant’s insufficient performance, and the penalties and extensions were effectively exercised under the contract.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Lamprell v. Billericay Union[1849] Exch 283PositiveCited to illustrate that time being of the essence can be modified by other contract terms and waivers.
Webb v. Hughes[1870] L.R. 10 Eq 281PositiveCited as authority for the principle that other contract provisions may affect whether time is fundamental.
Charles Rickards Ltd. v. Oppenheim[1950] 1 KB 616PositiveCited to support the notion that time can be non-essential when extended by contract terms and waivers.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,021 words•~28 min read

In The Court Record

Hind Construction Contractors v. Maharashtra

1147 ' The appellant entered into a contract with the respondent for the execution of a work the essential term of which was that the contract should be com- C pleted in 12 months from the commencement of the work. On the ground that the appellant had not completed the work within the stipulated time the respondent rescinded the contract. In his suit for damages for illegal and wrongful recision of the contract the appellant claimed that the date for commencement of the work was merely nominal and that in any case time was not of the essence of the contract. The D appellant also alleged that on account of several difficulties such as exce.ssive rains in the area, lack of proper road and means of approach to the site, rejec~ tion of materials on improper grounds by the Government officers, completion of the work was delayed, extension of time was wrongfully. refused by the officers of the Government, and that none of these factors had been taken into account by the Government while refusing to give extension of time, and in ultimately rescinding the contract. E Holding that time was not of the essence of the contract the trial Court de.creed the suit, but disallowed certain claims of the appellant. On appeal by both sides the High Court, without deciding the question whether time was of the essence of the contract, held thnt the recision of the contract was not arbitrary and unreasonable or unjustified. F On further appeal to this Court it was contended on behalf of the appellant that (i) the High Court was in error in not deciding the main question whether or not time was essence of the contract; and (ii) it was not the appellant's case that the recision was _mala_ _fide_ and that, therefore, the High Court erred in considering that question. Allowing the appeal, G HELD : The question whether or not time was of the essence of the contract would essentially be a question of the intention of the parties to be gathered from the terms of the contract. Even where the parties he.ve expressly provided that time is of the essence of the contract such stipulation would have to be read alongwith other provisions of the contract and such other provisions may, on construction of the contract, exclude the inference H that the completion of the work by a particular date was intended to be fundamental. For instance if the contract were to include clauses providing HIND CONSTRUCTION CONTRACTORS _v._ THE STATE OF MAHARASHTRA _/{]Jluary_ 30, 1979 [Y. V. CHANDRACHUD, C. J., V. 0. TuLZAPURKAR AND A. P. SEN, JJ.] _Contract_ _Act-Contract_ _not completed within stipulated time. No term in_ _contract making_ _tin1e,_ _the essence_ _of_ _contract-Tests for deciding_ _if_ _tin1e_ _was_ _of_ _essence._ A B 1148 SUPREME COURT REPORTS [1979] 2 s.c.R. A for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clause would be construed as rendering inefftctivc the express provision relating to the time being of the essence of the cont1act. fl155A-B] 8 c D Halsbury', Laws of England, Vol. 4 p. 1174 referred to. (1) In the instant case, having regard to the terms of the car.tract particularly the clauses pertaining to the imposition of penalty and extension of time~ time was never intended by the parties to be of the essence of the contract The letter by which the contract was rescinded clearly waived the stipulation of 12 months' period, the contractor having been allo,ved to do some more work after th< expiry of the period. [1157B] (ii) The approach adopted by the respondent and upheld by the High Court WM not correct Long before the expiry of the period of 12 months the appellant bad requested for extension of the period of completion. Even if the grounds made out by the appellant were not agreeable to the Superintending Engineer some reasonable time making it the essence of the contract ought to have been granted. Instead of making time of the essence at some stage or the other, the respondent rescinded the contract which was clearly illegal and wrongful. [ 11 ~SC] _)_ ' (iii) It was never the case of the appellant that the recision of the contract was _mala_ _fide._ The various reasons given by the appellant for delay in executing the work were put forward merely for showing that the refusal to extend time by the Superintending Engineer was unreasonable or unjustified. The question was not whether the recision of the contract was unreasonable and, E therefore, unjustified but whether the recision was wrongful and illegal. If time was not of the essence or if the stipulation as to the time fixed for completion had, by reason of the waiver, ceased to be applicable then the only course open to the respondent was to fix some time making it the essence and if within the time 110 fixed the appellant had failed to complete the work, the Jt!rC'nden.t could have rescinded the contr.o:ict. [1 l57D-G] F G D CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 483 and 1769 of 1969. Appeal from the Judgment and Ord•or dated 9/10-9-1968 of the Bombay High Court in First App,;al Nos. 844 of 1961 and 245 ot 1962. _M._ C. _Bhandare,_ _J._ S. _Sinha_ and _K._ _J._ _John_ for the Appellants. _R._ _H. Dhebar, B._ _V._ _Desai_ and _M._ _N._ _Shroff_ for the Respondent. The Judgment of the Court was delivered by TULZAPURKAR, J. These appeals by certificate of fitness granted by the High Court of Judicature at Bombay are directed against that Court's common judgment and decree dated September 9/10, 1968, passed in two cross appeals being First Appeal Nos. 245 of 1962 and 844 of 1961. j ### • I [, ] ol ~,.,' , I!IND CONSTRUCTION CONTRACTORS _V._ MAHARASHTRA 114 9 _(Tulzapurkar,_ J.) A contract for the construction of an aqueduct across the Alandi River at Mile No. 2 of the Nasik Left Bank Canal of the total value of Rs. 1,07,000 /- was granted to the appellant-plaintiff (originally a partnership but later a proprietary firm of contractors) by the respondent-defendant (the State of Maharashtra) after the farmer's tender was accepted on June 17, 1955. On July 2, 1955 the Executive Engineer issned the work order to the appellant-plaintiff directing him to commence the work by July 5, 1955 intimatihg in clear terms that the stipulated date for starting the work would be reckoned from July _5,_ 1955. The formal vegular Contract in prescribed Form B-2/1 of 1955-56 (Ex. 34) containing the terms and conditions as well as the Schedules, specifications etc. was executed by the parties on July 12, 1955. A security deposit of Rs. 4,936/- was kept by the appelJ,antplaintif! with the respondent-defendaht. The period for completion of work was fiioed as 12 months from the date stipulated for commencement of the work, that is to say, it was expected to be completed on or before Ju;y 4, 1956. It appears that on the ground that the appdlarrt-plaintif! had not completed the work as expected within the stipulated time the Executive Engineer by his letter dated August 27, 1956 (Ex. 78) rescinded the said contract with effect from August 16, 1956. After serving a 'notice under s. 80 of the Civil Procedure Code the appellant-plaintiff filed a suit (being Special Civil Suit No. 23 of 1959) on August 28, 1959 in the Court of the Joint Civil Judge, Senior Division, Nasik making a claim for Rs. 65,000/- in the aggregate against the respondent-defendant alleging wrongful and illegal r~ cisio'n of the contract on the part of the respondent-defendant. The appellant-plaintiff's case was that the initial fixation of July 5, 1955 as the date for commencement of the work was nominal, that the area where the work was to be done had usually heavy rainfall rendering it impossible to carry out any work from July to November and that, therefore, it was the practice of the Public Works Department to deduct the period of monsoon in case of such type of works and that the appella'nt-plaintif! had been orally informed that this period would be deducted or not taken into account for calculating the period of 12 months under the contract and that on this assurance he had com menced the work towards the end of December 1955. His case further was that in any event time was not of the essence of the contract, that oh account of several difficulties, snch as excessive rains, lack of proper road and means of approach to the site, rejection of materials on improper grounds by Govermnent Officers, etc., over which he had no control, the completion of the work was delayed and that the extension of the time which was permissible under the contract had been wrongfully refused by the officers of the respondent-defe'ndant. Ac A B c E F G H A B c D E F G H 1150 SUPREME COURT REPOR:fS [1979.1 2 s.c.R. cording to him none of these factors had been taken into account b} the Government while refusing the extension and the contract was wrongfu1ly rescinded a'nd, therefore, the respondent-defendant was liable in damages. The total claim of Rs. 65,000/- comprised six items-(1) Rs. 4,936/- being the amount of security deposit wrongfully forfeited by the respondent-defendant, (2) Rs. 10,254/- being the amount due to him for the actual work done by him under Bill No. 1253 dated September 20, 1956 and which had not been paid for, (3) Rs. _7,3751-_ being the value of the material collected by him on the site for work but which had ree'n rendered useless on account of wrongful recision, the 4th and 5th items sounded in damages, while the last item was interest from date of recision to the date of the suit. The State of Maharashtra resisted the claim contending that time was of the essence of the contract, that the date fixed for commencement was real and not nominal and the 12 months period was fixed after all aspects of the matter had been taken into account, it was fur ther contended that the appellant-plaintiff knew the situation of the site and the so-called difficulties, that there was no excuse for him for not doing the work during the months of July to November, that the appellant-plaintiff failed to carry out the proportionate work during the periods fixed in the contract and that since the appellant-plaintifl had rendered himself incompetent to complete the work in proper time it had to rescind the contract and the recision was proper a'nd fo1 adequate reasons; it was further contended that the State was entitled to forfeit the security deposit which it did on the date when the contract was rescinded. The several items claimed by the appellantplaintiff were denied by the State. It was denied that the material of the value of Rs. _7,3751-_ remained on the site or that it was responsible for its 'non-removal from the site. Regarding items 4 and 5 the State denied its liability to pay the same as it was the appellant-plaintiff who had committed the breach of the contract. As regards the amount due under Bill No. 1253 dated September 20, 1956 for the actual work done, it was contended that the State had to deduct the amount of penalty leviable under the contract and for th~ actual cement supplied to the appellant-plaintiff and after making deductions in that behalf only a sum of Rs. 700/- would be due to the appellant-plaintiff. On a consideration of the documentary evidenee including the terms and conditions of the contract (Ex. 34) and the oral evidence ied by the parties, the learned trial Judge held that the date July 5, 1955 fixed as the date for commencement of the work was not nominal but that time was not of the essence of the contract between the c '"'', ~. _J_ . .. #### • I, .. HIND CONSTRUCTIO"I CONTRACTORS _V._ MAHARASHTRA 11 SI ( _Tulzapurkar,_ J.) parties, that the respondent-defendant (State Government) had wrongfully rescinded the contract, that the appellant-plaintiff was entitled to damages but that he had not established the two items claimed as damages and he was entitled to a nominal sum of Rs. 120/- as damages. He further h·~ld that since the recisioil of the contract was wrongful the State was not entitled to forfeit the security deposit nor levy any penalty. He accordingly decreed the appellant-plaintiff's claim m respect of refund of security deposits and as regards the amount of Bill No. 1253 dated September 20, 1956 for actual work done he held that a sum of Rs. 5,845/- only would be due to him after giving credit A B for Rs. 4,409/- due from the appellant-plaintiff to the State. He accordingly decreed the appellant-plaintiff's suit to the extent of C Rs. 10,901/- with interest thereon at 6% per annum from the date oL recision till date of suit and allowed proportionate costs to him. ##### i __Jr.• -.. ###### l Two appeals w~re preferred against the aforesaid decree of the trial court, one by the appellant-plaintiff in respect of the claims that had been disallowed (First Appeal No. 245 of 1962) and the other by the State in respect of the claims allowed against it (First App,al No. 844 of 1961). Cnriously enough the High Court did not decide the main issue that arose between the parties, namely, whether time was of the essence of the contract, as it took the view that a decision on that question was really unnecessary for disposal of the appeals. Il proceeded to decide the appeals on the assumption that time was not of the essence of the contract by considering the question whether the recision of the contract by the State could be regarded as _ma!a_ _fide_ or so unreasonable that it must in the place of the judgment of the officers concerned substitute its own judgment and hold that tho recision was wrongful. The High Court observed that even the appeLantplaintiff had not alleged any _mala_ _fide_ on the part of any of the officers of the State but had pressed into service five or six factors the non-consideration whereof by the rcspondent-defundant rendered !he recision of the contract arbitrary, unreasonable and, therefore, unjusti·fied. After discussing each one of those five or six factors the High Court held that some of them had not been proved by the appellantplaintiff while others did not head to the inference that the recision of the contraci was arbitrary, uilreasonable or unju&tified. It found that by about July 21, 1956 (vide Ex. Engineer's letter Ex. 74) the appellant-plaintiff had done only 1/3rd of the contract work and that in the circumstances the appellant-plaintiff could not hav>~ completed the work even within the next three months and, therefore, the respondent's officers had rightly rescinded the contract and, therefore, it was the appellant-plaintiff and not the respondent-defendant who had committed a breach of the contract. However, the High Court took the 17-119 SCI/79 D E F G H ~ _, ## • ~ _, if ·' l ., If( ' ~ # ' A **B** c **D** E G **H** 1152 SUPREME COURT REPORTS [1979] 2 S.C.R · .. ;icw that for such breach on the part of the appellant-plaintiff, the respondent-defendant, on a reading of the els. 2 and 3 of the Condi, tions of Contract, was not entitled both to levy compensation and also to forfeit the security deposit. Accordingly, the High Court upheld the forfeiture of the S<Ccurity deposit made by the respondent-defendant ' and while modifying the trial court's decree it confirmed it only to the extent of Rs. 5,845/-, being the amount due to the appellant-plaintiff ' for the work actually done by him under BilI No. 1253 and which had not been paid. In the result, the appellant-plaintiff's appeal was dismissed and that of the State was partly al1ow~d with appro- priate order of proportionate costs. the aforesaid course ilie respondent-defendant had without making,.time of the essence of the contract rescinded the same with effect from August 16, 1956 by a letter dated Augnst 27, 1956 (Ex. 78), wluch ;·ecision must be regarded as wrongful a'nd illegal. Secondly counsel· contended that the High Court further erred in considering the ques**tion whether the recision** **of** **the contract** **by** **the State was either** _**mala**_ _fide_ or wholly unreasonable and, therefore, unjustified. He pointed out it was not the appellant-plaintiff's case that the recision was mala fide and, according to him, the question was not whether the recision of the contract on the part of the respondent-defendant was unreason ' able, and, therefore, unjustified but whether the respondent-defendant was entitled in law to rescind the contract in the manner done when time was not of the essence of the contract. He further urge<d that the High Court had clearly erred in assuming that the appeUant-plaiBtHl ' ) ' ·, .. "" In support of the present appeal counsd for the appellant-plaintifl raised two or three contentions. In the first place he contended that the High Court was in error in not deciding the main issue whether the time was of the essence of the contract or not ? He urged that the said issue could 'no' be avoided in the manner done by the High Court, for, if time was not of the essence of the contract then just before the expiry of the 12 months' period or immediately after its expiry it was up to the respondent-defendant to gtant some reasonable time to the appellant-plaintiff for completing the work undertaken and make U1e same the essence of the contract a'nd only if the work was not completed by the appellant-plaintiff within that time the contract could have beoen rescinded on the gtmrnd that the appel!ant-plaintifi had committed a breach of a contract. According to him such course of action on the part of the respondent-dcfe"ndant was obligatory, when the initial period of 12 months was not of the essence, especially When the request of the appellant-plaintiff for extension of time was pending _)__ _j_ before the concerned officers of the Government since before the - fJ.___ expiry of the initial period. He contended that instead of adopting ' ~ J;ii ... \, .. **B** 'r ""' . •• _>_ _+_ ~ _(_ l!IND CONSTRUCTION CONTRACTORS _V._ MAHARASHTRA 1153 _(Tulz.apurkar,_ !.) could no.t have completed the work even within the next three months and, therefore, the contract was rightly rescinded by the respondentdefendant. He, however, fairly stated that even if this Court held in his favour that the recision was wrongful and, therefore, the respondent-defendant had connnitted a breach he would merely press for th~ restoration of the decree passed by the trial Court and not press any other item forming the subject-matter of the original claim in the suit. On the other hand, counsel for the respondent-defendant sought _to_ support the judgment P.nd decree of the High Court on both the grounds first that time was of the essence of the contract having regard to the express provision contained in cl. (2) of the "Conditions of Contract" and, therefoP", on appellant-plaintiff's failure to complete **the** **san1e** **\Vithin** **the** stipula~cJ **thne the recision of the contract** **\Vas** legal and justified and secondly, that even if time was not of the essence of the contract, having regard to the circumstances the Hish Court rightly came to the conclusion that the recision of the contrnct by the respondent-defendant could not be regarded as unreasonable or unjustified and that, thernfore, the appellant-plaintiff being in breach the security deposit had been rightly forfeited. The first question that arises for our consideration, therefore, is whether time was of the essence of the contract that was executed between the parties on July 12, 1955 (Ex. 34). It cannot be di•puted that question whether or not time was of the essence of the contract would essentially be a question of the intention of the parties to be gathered from the terms of the contract. The contract in the instant case is for the construction of an aqueduct across the Alandi River at Mile No. 2 of the Nasik Left Bank Canal and unquestionably 12 months' period commencing from the date of the commencem~rrt of the work had been specified within which the construction had to b~ completed by the appellant-plaintiff. Indisputably, in the work order dated July 2, 1955 the Executive Engineer had directed the appellantplaintiff to commence the work by July 5, 1955 intimating in clear terms that the stipulated date for starting the work would be reckoned !i:om July 5, 1955. Both the trial court as well as the High Court have found that mentioning of July 5, 1955 as the date for starting the work was not nominal but was real date intended to be acted upon by the parties. It is, therefore, clear that 12 months' period mentioned for the completion of the work was to expire on July 4, 1956. The question is whether this period of 12 months so specified in the con tract was of the essence of !he contract or not ? On the one hand, counsel for the a~JX'.llant·plaintiff con~~nded that the contract being analogous to a buildmg contract the period of 12 months would **not** **A** **ll** **c** **D** **F** **G** **B** " ' . A B c D E F G 1154 SUPREME COURT REPORTS [1979] 2 S.C.R. ordinarily be of the essence of the contract as the subject-matter there· of was not such as to make completion to time essential, that an agreement to complete it within reasonable time would be implied and that reasonable time for completion would be allowed. On the other hand counsel for the respondent-defendant contended that time had been expressly made of the essence of the contract and in that behalf reliance was placed upon cl. (2) of the "Conditions of Contract" where not only time was stated to be of the essence of the contract on the part of the contractor but even for completion of proportionate works specific periods had been specified and, therefore, the appellantplaintiff's failure to complete the work within the stipulated period entitled the respondent-defendant to rescind it. In the latest 4th edn. of Halsbury's Laws of England in regard to building and engineering contracts the statement of law is to be found in Vol. 4, Para 1179, which runs thus : " 1179. _Where time_ _is_ _of the essence of the contract._ The expression time is of the essence means that a breach of the condition as to the time for performance will entitle the innocent party to consider the breach as a repudiation of the contract. Exceptionally, the completion of the work by a specified date may be a condition precedent to the contractor's right to claim payment. The parties may expressly provide that time is of the essence of the contract and where there is power to determine the contract on a failure to complete by the specified date, the stipu1atio'n as to time will be fundamental. _Other provisions_ _of_ _the contract may, on the_ _construction_ _of_ _the_ _contract, exclude_ _an_ _inference that the_ _completion_ _of the works by a particular date_ is fundamenta~ _time_ _is_ _not_ _of_ _the essence where a sum_ _is_ _payable_ _for_ _each_ _week that the work remains incomplete after the date fixed,_ _nor where the parties contemplate a postponement_ _of_ _com-_ _pletion._ _Where time has not been made_ _of the essence_ _of the con-_ _tract or, by reason_ _of waiver, the time fixed has ceased to be_ _applicable, the employer may by notice_ _fix_ _a reasonable time_ _for_ _the completion_ _of_ _the work and dismiss the contractor_ _on a failure_ _to_ _complete by the date_ _so_ _fixed."_ (Emphasis supplied) ' ' H It will be clear from the aforesaid statement of law that even where the parties have expressly provided that time is of the essence of the contract such a stipulation will have to be read along with other ' ' ' HIND CONSTRUCTION CONTRACTORS _v._ MAHARASHTRA 1155 _(Tulzapurkar,_ _J.)_ provisions of the contract and such other provisions ma.y, on construction of the contract, exclude the inference that the completion -0f the work by a particular date was intended to be fundamentJl, for instance, if the contract were to include causes providing for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken rel!'ains unfinished on the expiry of the time provided in the contract suLh clauses would be construed as rendering inctiective the express pro~'sion relating to the time being of the essence of contract. The emphas1' 'd portion of the aforesaid statement of law is based on _Lamprell_ v. _Billericay_ _Union('), Webb_ v. _Hughes(')_ and _Charles Rickards Ltd._ v. _Oppen-_ _heim_ ( [3] ). It is in light of the aforesaid position in law that we will have to consider the several clauses of the contract Ex. 34 in the case. The material clauses in this behalf are els. 2 and 6 of the "Conditions of Contract" which run as follows : "Clause 2 :-The time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be reckoned from the date on which the order to commence work is given to the contractor. The work shall throughout the stipulated period of the contract be proceeded with, with all due diligence (time being deemed to be of the essence of the contract on the part of the contractor) and the contractor shall pay as compensation an amount equal to one per cent or such smaller amount as the Superintending Engineer (whose decision in writing shall be final) may decide, of the amount of the estimated cost of the whole work as shown by the tender for every day that the work remains uncommenced, or unfinished, after the proper dates. And further to ensure good progress during the execution of the work, the. contractor shall be bound, in all cases in which the time allowed for any work exceeds one month, to complete. t of the work in t of the, time t of the work in t of the time t of the work in t of the time" . "Cfause 6 :-If the contractor shall desire an extension of the time for completion of the work on the ground of his having been unavoidably hindered in its execution or (1) [184913 Exch 283 at 308. (2) [1870] L.R. 10 Eq 281. (3) [ 1950] l KB 616, A B c D p G H ' \" **A** **B** 1156 SUPREME COURT REPORTS [1979] 2 s.c.R. on any other ground, he shall apply in writing to the Executive Engineer before the expiry of period stipulated in the tender or before expiry of 30 days from the date on which he was hindered as aforesaid or on which the cause for asking for extension occurred, whichever is earlier and the Executive Engineer, may if in his opinion there arc reasonable grounds for granting an extension, grant such extension as he thinks necessary or proper. The decision of the Executive Engineer in this matter shall be final." Two aspects emerge very clearly from the aforesaid two clauses, In the first place under cl. 6 power was conferred upon the Executive Engineer to grant extension of time for completion of ~e work on reasonable grounds on an application being made by the contractor (appellant•plaintifI) in that behalf; in other words, in certain contingencies parties had contemplated that extension of **D** time would be available to the contractor. Such a provision would clearly be inconsistent with parties intending to treat the stipulated period of 12 months in cl. 2 as fundamental. Similarly, in cl. 2 itself provision was made for levying and recovering penalty _I_ compensation from the appellant-plaintiff at specified rates during the period the work shall remain unfinished after the expiry of the fixed **E** date. Such provision also excludes the inference that time ( 12 months period) was intended to be of the essence of the contract. Further with regard to the provision that is to be found in c!. 2 whereunder a time schedule for proportionate work had been set out (namely, t of the work in t of the time, t of the work in t of the time and ! of the work in i of the time ), the evidence of the F Superintending Engineer Pandit (D.W. 1) is very eloquent. In para 13 of his deposition this is what he has stated : **G** "In the agreement (Ex. 3· ~) the rate of work is based on the valuation tth time mentioned means tth in 12 months. The suit contract is for Rs. 1,07,000/-. Hh work means the work of about Rs. 27,000/-. IL is not possible to do the work of Rs. 27,000/- in tth time as the days were rainy. This was not reasonable." The witness in para 12 of his deposition has also given the following, admission :**B** "It is not specifically mentioned in the agreement (Ex. 34), that the suit work was urgent and that it was to be completed within 12 months. In this agreement (Ex. 34) HIND CONSTRUCTION CONTRACTORS _V._ MAHARASHTRA 1 I 5 7 _(Tulzapurkar,_ _l.)_ there are the clauses of imposing a penalty and extension A **of** **time."** Having regard to the aforesaid material on recor;;, particularly the <:lauses in the agreement pertaining to imposition of penalty and extension of time it seems to us clear that time (12 months period) was never intended by the parties to be of the essence of the contract. Further from the correspondence on the record, particularly, the letter (Ex. 78) by,which the contract was rescinded it does appear that the stipulation of 12 months' period was waived, the contractor having been allowed to do some more work after the expiry of the period, albeit at his risk, by making the recision effective from August 16, 1956. Once either of the aforesaid conclusions is reached it would be difficult to accept the High Court's finding that the recision of the contract on the part of the respondent-defendant was proper and justified on the basis that the same was neither shown to be mala fide nor unreasonable. It must be observed that it was never the case of the appellant-plaintiff that the recision of the contract on the part of the respondent-defendant was _ma/a_ _fide._ Counsel for the appellantplaintiff further pointed out and, in our view, rightly that the five or six factors, namely, ( 1) the contract having been given at the threshold of monsoon, the period of monsoon ( 4 months) ought not to have been reckoned, (2) absence of proper road and approach to the work site during the rainy season and a couple of months there· after, (3) unreasonable rejection by the Government Officers _of_ material brought on the site, which material was later on allowed to be used, ( 4) difficulty in procuring labour due to malarious climate at the site, (5) delay in issuing quarry permit and (6) extra time taken for doing extra work that was entrusted ought to have been taken into account_:_were put forward by the appellant-plaintiff merely for the purpose of showing that the refusal to extend the time by the Superintending Engineer although recommended by the S.D.O. and Executive Engineer was unreasonable and not for showing that the ·recision of the contract was unreasonable or unjustified. In our view, the question would not be whether the recision of the contract was unreasonable and, therefore, unjustified but whether the recision of the contract in the circumstances of the case was wrongful and illegal. If time was not of the essence of the contract or if the stipulation as to the time fixed for completion had, by reason of waiver, ceased to be applicable then the only course open to the, respondent' defendant was to fix some time making it the essence and if within the' time so fixed the appellant-plaintiff had failed tr ~.omplete the B c **D** F G R A B c 0 E G H 1158 SUPREME COURT RHPORT5 [1979 I 2 S.C.R. work the respondent-defendant could have rescinded the contract. The High Court has taken the view that the contract was rightly rescinded by the. respondent-defendant because by about July 21, 1956 _(vide_ letter Ex. 74). the appellant-plaintiff had done work of the value of Rs. 35,000/- as against the tender value of Rs. 1,07,000/-, that is to say, only I/3rd of the total work had been completed and, therefore, even though time was not of the essence of the contract, the appellant-plaintiff, in the circumstances, could not have completed the work even within the next three months. In our view, this approach adopted by the respondent-defendant and upheld by the High Court is not correct. Long' before the expiry of the period of 12 months the appellant-plaintiff had by his letter dated June 6, 1956 (Ex. 68) requested for extension of period of completion up to the end of December, 1956; this request was repeated by another letter dated June 23, 1956 (Ex. 69). May be the reasons or grounds on which the request was made may not have appealed to the Superintending Engineer but some reasonable time making it the essence ought to have been granted. In this behalf it may be stated that the S.D.O. by his letter (Ex. 69) had recommended extension upto December 1956 as sought while by his letter dated June 23, 1956 (Ex. 70) addressed to the Superintending Engineer, the Executive Engineer had recommended that extension of time up to October 30, 1956 may be granted to the appellant-plaintiff with clear intimation that if he failed to complete the work by then, the maximum penalty allowable under cl. 2, namely, 10% of the cost of the work will be inflicted on him, but the recommendation did not receive approval of the Superintending Engineer. It appean; that the appellant-plaintiff had an interview with the Superintending Engineer on August 24, 1956 when a written representation (Ex. 99) was handed over and the whole position was sought to be explained to the Superintending Engineer but within three days of the interview by the letter dated August 27, 1956 (Ex. 78) the contract was rescinded and the full security deposit was fof'feited to Government. It will thus appear clear that though time was not of the essence of the contract, the respondent-defendant did not fix any further period making time the essence directing the appellant-plaintiff to complete the work within such period; instead it nscinded the contract straightaway by letter dated August 27, 1956. Such recision on the part of the respondent-defendant was clearly illegal and wrongful and thereby the respondent-defendant committed a breach of contract, with the result that there could be no forfeiture of the security deposit. In our view, therefore, the trial court was right in coming to the conclusion that the appellant-plaintiff was entitled to a rdund of their full security deposit of Rs. 4,936/- as also ' ' ' ' .. _ .,_,HIND CONSTRUCTION CONTRACTORS V. MAHARASHTRA • 1159 _(Tulzapurkar,_ _J.)_ to Rs. 5845/- being the balance of their Bill No. 1253 dated September 20, 1956 for work actually done by them and not paid for and nominal damages of Rs. 120/-. The appellant-plaintiff was also entitled to interest on the aforesaid sums and costs of suit as directed by the trial court. **A** In the result we allow the appeal, set aside the common judgment **B** and decree in F.A. No. 844 of 1961 passed by the High Court and rnstore that of the trial court. The appellant-plaintiff will get costs of this appeal as also costs of F.A. No. 844 of 1961. The High Court's decree dismissing F.A. No. 245 of 1962 is confirmed. **P.B.R.** _Appeal_ _allowed._
End of Judgment Record
Browse All Supreme Court of India (1979) Decisions
1978-08-16

State of Maharashtra v. Atma Ram Sadashiv Dongarwar and ors.

This appeal concerns the State’s power to levy water charges for irrigation from Navegaon Bandh Tank under the Central Provinces Irrigation Act, 1931, after vesting of proprietary rights in the State under the Madhya Pradesh Abolition of Proprietary Rights Act, 1950 and the Madhya Pradesh Land Revenue Code, 1954. The five villages around Navegaon Bandh have long depended on tank water for rice and sugarcane, with free irrigation rights recognized and recorded in the Wajib-ul-Arz. The respondents—ex-proprietors and occupancy tenants—challenged the levy, arguing their customary rights to free irrigation persisted despite vesting. The Bombay High Court held that the right to free water was a customary right recognized in the Wajib-ul-Arz and not destroyed by vesting or by the Abolition Act or the MP Code, and that the State had no competence to levy water charges. The Supreme Court, however, undertook a detailed textual and historical interpretation of the Abolition Act (sections 45–47) and the saving provisions in the MP Code (section 239). It held that the occupancy tenants and malik-makbuza acquired rights to irrigation were not merely extinguished but saved, and continued under the Code. The appeal was dismissed with costs, upholding the Court’s operative order that water charges could not be imposed on those rights.

1979-09-21

Ibrahim Khan v. M. P. State

This appeal concerns the grant of a quasi-permanent cinema licence under the Madhya Pradesh Cinemas Regulation Act, 1952, and the related Rules (1972), specifically addressing whether local objectors must be heard at the renewal stage. The third respondent, Prem Narayan, initially obtained a six-month no-objection certificate for a temporary cinema, which was renewed twice but later refused for renewal on the ground that Paras Talkies—having a permanent licence in the locality—had reopened. The State Government then granted a quasi-permanent licence on appeal. The appellants, residents of the locality, had objected to the licence on grounds including a mosque, a madrasa and a temple in the vicinity, and contended that their objections, though upheld by the licensing authority, were not heard in the appeal before the State Government; they asserted this violated natural justice. The Madhya Pradesh High Court dismissed the petition, holding the matter rested on the State Government’s subjective satisfaction and no interference was warranted. The Supreme Court, with Desai, J. and Pathak, J. concurring, upheld the dismissal of the appeal. It held that there is no statutory obligation to invite objections for a quasi-permanent or touring cinema licence at renewal, and that objections are confined to the initial no-objection stage. The court reiterated that a right to notice depends on a sustained interest and that s.5(3) provides a remedy only to a person aggrieved by a licensing authority’s refusal. The appeal was dismissed with no order as to costs.

1979-02-13

Maharashtra v. D. B. Kulkarni

Clause (2) of the contract stipulated that time was of the essence and fixed a one-year period within which the work was to be completed, with a provision for compensation at a daily rate for delays beyond the proper dates. Clause (3) empowered the Executive Engineer to rescind the contract if the contractor became liable to pay compensation, abandoned the work, or faced other specified causes, with the contractor’s security deposit forfeited and the contractor having no claim to compensation for losses. The work began in 1955 and progress was slow; the Executive Engineer demanded speed in 1956 and rejected extensions. Ultimately, after notices and deteriorating progress, the contractor was informed that the contract stood rescinded under clause (3) and the security deposit forfeited. The trial court awarded the plaintiff a refund of the security deposit; the Bombay High Court held that rescission after the due date was not valid, and hence the security deposit forfeiture was unjustified. The Supreme Court allowed the appeal, holding that rescission was well-founded and the security deposit forfeiture justified. It held that clauses (2) and (3) must be read together and that the contract continues in force until completion or abandonment; time is only a limit for compensation, not a bar to rescission when conditions of clause (3) are met. The suit was dismissed with costs in this Court to the plaintiff.

1979-11-21

Murari Lal s/o Ram Singh v. State of Madhya Pradesh

Murari Lal, accused of murdering Sonawala, was convicted under Section 302 IPC and sentenced to death. On appeal, the Madhya Pradesh High Court altered the conviction to 302 read with Section 34 IPC and reduced the sentence to life imprisonment for the other counts. In the Supreme Court, it was contended that the conviction could not rest on uncorroborated opinion evidence of handwriting and that the note found beside the dead man could not be attributed to Murari Lal, who was not matriculated. The prosecution contended that the recovered wrist-watch belonging to the deceased, coupled with a note in Hindi allegedly in Murari Lal’s handwriting found at the scene, formed a nexus with the crime. The Court held that an expert is not an accomplice and that no inflexible rule requires corroboration of handwriting expert opinions; the judge must test the reasons given by the expert and consider all other relevant evidence. Section 73 of the Evidence Act empowers the court to compare disputed writings with admitted writings, and, if warranted by the facts, the court may accept uncorroborated opinions with convincing reasons. The judgment emphasizes caution in evaluating handwriting evidence, while acknowledging that corroboration may be sought where necessary. On the facts, the two crucial circumstances were found sufficient to link Murari Lal to the offences, and the appeal was dismissed, upholding the conviction and the death sentence.