Supreme Court of IndiaSupreme Court · 1997Division BenchAppeal allowed; High Court's decision reversed.

Himachal Pradesh Nagar Vikas Pradhikaran v. M/s Aggarwal & Co.

Case / Petition Number:
Civil Appeal No. 635 of 1997

Case Synopsis & Summary

The case concerns a dispute between Himachal Pradesh Nagar Vikas Pradhikaran (appellant) and M/s Aggarwal & Co. regarding escalation charges claimed by the contractor for works executed under an agreement that had been referred to arbitration at the High Court's direction. The Arbitrator concluded that the delay lay with the respondent’s Executive Engineer and awarded a 25% increase over tendered rates for all works performed after 21 May 1989, a quantity later implemented by the court as a rule of the Court. In implementing the award, the department deducted the cost of materials supplied by the SDA and calculated a net sum payable to the respondent. The appellant contends that the 25% escalation is tied to tendered rates for the works and not to the prices of raw materials supplied by the Department; since cement and steel were supplied by the Department at schedule rates, the department should bear the cost of any increases, and the award cannot be read to require payment for escalated materials. The High Court of Himachal Pradesh accepted the contractor’s position and directed payment of the disputed amount. The Supreme Court, however, allowed the appeal, holding that neither the contract’s Clause 10 nor the award supports paying escalation on materials supplied by the Department; the very object of escalation is to compensate for open-market price increases borne by the contractor, and here the materials were supplied by the Department, not procured by the contractor. The appeal is allowed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • G. T. Nanavati
Judgment Date
1997-01-27
Court Decision / Holding
Appeal allowed; High Court order directing payment of escalation amounts set aside; contractor not entitled to 25% escalation on materials supplied by the Department; award finality preserved; appeal allowed without costs.
Final Disposition
Appeal allowed; High Court's decision reversed.

Parties to the Case

Appellants / Petitioners

  • Himachal Pradesh Nagar Vikas Pradhikaran

Respondents

  • M/s Aggarwal & Co.

Legal Representation & Advocates

Counsels for Petitioners

  • • Rajesh Srivastava
  • • Ujwal Banerjee
  • • H.K. Puri

Counsels for Respondents

  • • S.B. Upadhyay

Provisions of Law Cited

Section 47 of the Civil Procedure Code

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that 25% escalation relates to tendered rates for the works and does not apply to rates of raw materials supplied by the Department. Cement and steel were supplied by the SDA at schedule rates irrespective of the delay; escalation on materials would shift the burden to the Department. Since the materials were not procured by the contractor, the award cannot be construed to provide payment for escalation for those items. The High Court’s direction to pay the disputed amount is therefore unwarranted.

Contentions of Respondents

The respondent argues that the Arbitrator found delay by the Executive Engineer and awarded 25% more than the normal rate; once the award has become final, it cannot be interfered with. The decision in P.M. Paul v. Union of India supports entitlement to escalation where the award provides for it. The 25% escalation reflects increased costs incurred in performance and should be paid; to deny it would amount to modifying the award post-finalisation.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
P.M. Paul v. Union of India[1989] Supp. 1 SCC 368PositiveCited to support the proposition that escalation costs may be payable where the award contemplates escalation and that final awards can include such escalation; used to argue for upholding the concept of escalation in the relevant context.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,256 words•~6 min read

In The Court Record

Himachal Pradesh Nagar Vikas Pradhikaran v. M/s Aggarwal & Co.

A # HIMACHAL PRADESH NAGAR VIKAS PRADHIKARAN _v._ _MIS._ AGGARWAL & CO. JANUARY 27, 1997 ## B ## [K. RAMASWAMY AND G.T. NANAVATI, JJ.] _Conttact-Execution of-Escalatio11 charges 011 material-Claimed by contractor'-He/d : Not e11titled to in view of the fact that the mate1ials were not procured by the Contractor, but were supplied by the Depmtment and the_ C _cost of mate1ials w01ked out._ _P.M. Paul_ v. _Union of India,_ [1989] Supp. 1 SCC 368, referred to. CIVIL APPELLATE JURISDICTION : Civil Appeal No. 635 of 1997. D From the Judgment and Order dated 2.5.96 of the Himachal Pradesh High Court in O.M.P. No. 626/93 in Ex. P. No. 27 of 1993. E Rajesh Srivastava, Ujwal Banerjee and H.K. Puri for the Appellant. S.B. Upadhyay for the Respondent. The following Order of the Court was delivered : Leave granted. F This appeal by special leave arises from the judgment and order dated May 2, 1996 of the Himachal Pradesh High Court Passed in O.M.P. No. 626/93 in Ex. P. No. 27/1993. The admitted facts are that the respondent had entered into an agreement with the appellant to execute certain works pursuant to which there was a dispute which was referred to the G Arbitrator, on directions of the High Court. The Arbitrator in the award dated April 25, 1992 stated as under ; H "After considering whole matter submitted to me by both the parties, both verbally and in writing I have come to this conclusions that delay lies on that part of the respondent-Executive Engineer. 582 ~·. 583 '• ' ## H.P. NAGAR VIKAS PRADHIKARAN _v._ AGGARWAL & CO. It is awarded that the plaintiffs shall be paid by the respondentA Executive Engineer an increase of 25% over and above their tendered rates for all works executed by them after the stipulated date of completion i.e. 21.5.89." The award was made rule of the Court. In implementation of the award, the appellant worked out the details, as mentioned in the letter No. B SDA(D)-Acctt-7/93-644-47 dated November 12, 1993 which reads as under: "With reference to your letter No. AV/SIM/804-93-94 dated 5.10.1993, I am enclosing herewith a cheque bearing No. 807801 dated 12.11.1993 amounting to Rs. 4,99,307 on account of payment of award announced by the Director which has been made as rule of court by the Hon'ble H.P. High Court. The details of the awarded amounts and recoveries due to be made from you are as under: Gross amount of the work done after 11th R/A Bill i.e. after 21.5.1989 onwards upto 26th _RIA_ Bill) Rs. 69,78,354.00 Less cost of material i.e. Cement/Steel supplied by the SDA on which there has been no increase in the issue rates. (-) Rs. 23,25,685.00 C D E Net amount Rs. 46,52,669.00 25% increase of Rs. 46,52669/0 as awarded by the Arbitrator. Rs. 11,63,167.00 F 'Less 2% I.= Tax on 23,263 on Rs. 11,63,167 12% S.C. on 1.-Tax Rs. 2,792.00 (-) Rs. 26,055.00 Total Rs. 26,055.00 Rs.11,37,112.00 With held on account of recoveries due to be made from you against agreement No. 52 of 1987.88. (-) Rs. 6,37,805.00 . Net payable Rs. 4,99,307.00 Please send stamped receipt. G H _{_ ' 584 _v_ # SUPREME COURT REPORTS [ 1997] 1 s. C.R. A # Yours faithfully, _r-_ (Executive Engineer (D), Shimla Development Authority, Kasumpti, Shirnla-9". B c It is seen from the contents of the letter that the appellant has deducted only the cost of the material, i.e., cement and steel supplied by the SDA on which there has been no increase in the issue. rates. After working out of the details, a sum of Rs. 4,99,307 became due to the respondent. The appellant calculated the amount actually due and payable to the respondent under the award less the income-tax and surcharge etc. and the balance amount came to be paid. But when the respondent claimed a further sum of Rs. 5,81,421, the appellant objected thereto under section 47 of the CPC. The High Court over-ruled the objection and directed payment thereof. Thus, this appeal by special leave. ,# D It is submitted by Shri H.K. Puri, learned counsel for the appellant that the enhancement of 25% is relatable to the tendered rates for the works excuted by the respondent and does not relate to the rates of raw materials supplied by the appellant. He also submitted that cement and E[steel were supplied by the Department at the schedule rates in spite of the ] delay in execution of the contract. Thus, escalation in price of raw materials supplied by the appellant the entire burden was borne by the appellant and, therefore, no extra payment could have been intended to be made under the award in respect of those items. Therefore, the High Court was not right in directing payment thereof. We find force in the contention. It F is contended by Shri Upadhyay, learned counsel for the respondent, that when the Arbitrator recorded finding that delay in execution was on account of the !aches on the part of the Executive Engineer and awarded 15% more'than the agreed normal rate, as per the contract and the award having been allowed to become final, it is not open to the appellant to deny G 25% escalation charges for the period. In other words, it amounts to interference with the award which has attained finality. In support thereof, the learned counsel relied upon paragraph 12 of the judgrnent in _P.M. Paul_ v. _Union of India,_ [1989] Supp. 1 SCC 368. Therein, the question was whether the contractor was entitled to escalated rates due to delay in H[execution ][of ][the award on the part of the Department. As seen, there is ] F "' ... _>-_ 585 H.P. NAGAR VIKAS PRADHIKARAN _v._ AGGARWAL & CO. .. no dispute on the proposition that when the award has been made awardA ing escalation charges, necessarily the increased raies of the cost of securing the material for performance of the contract are required to be . compensated by paying the amount to the extent of the escalated charges . It is seen that under Clause 10 of the contract, the appellant was required to supply the material at the rates prevailing as on the date of the execution B and it was entitled to deduct the same from the amounts payable after the execution of the contract. In other words, when the iron and cement were supplied, during the relevant period, even after the expiry of the year for which th~ award came to be made, necessarily it included the increase in . rates. It is stated that they did not charge increased rates but the rates c prevailing as on the dates and the ·amount worked out come to Rs. 23.25.785. The respondent is not entitled to 25% of the escalated costs in that behalf. The very object of awarding escalated cost was that the contractor had secured the material from the open market at the price prevailing at the relevant time and used the same for execution of the work. In view of the fact that iron and cement were not procured by the D respondent during the extended time and actual price for which they were supplied has been worked out, as detailed earlier, the respondent is not entitled to 25% more on that material supplied by the Department itself. Under these circumstances, the High Court was clearly in error in directing payment of the said amount. E c The appeal is, accordingly, allowed but in the circumstances without costs. G.N. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.