Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2021Division BenchAppeal disposed of.

HGR Green Life Energy Pvt. Ltd. v. Leitwind Shriram Manufacturing Pvt. Ltd.

Case / Petition Number:
Civil Appeal No. 692 of 2021
Neutral Citation:[2021] 1 S.C.R. 583

Case Synopsis & Summary

This Supreme Court appeal arises from a Development Agreement dated 10 February 2014 for a wind-farm project in Sangli District, Maharashtra, containing an arbitration clause (Clause 20) that originally provided for a three-member arbitral tribunal and referred disputes to arbitration under the Arbitration and Conciliation Act, 1996. Disputes led to a legal notice for payment and counterclaims. The respondent nominated its arbitrator, and the appellant was asked to nominate as well; subsequently, the respondent invoked Section 11(6) and the Madras High Court appointed an arbitrator on behalf of the appellant. The High Court held that since the parties had agreed to refer all disputes under the 1996 Act, it was a proper case for appointment of an arbitrator and the arbitration panel would be three members. The appellant later registered under the MSMED Act and sought resolution through the Facilitation Council, but the court noted a lack of provision for counter-claims under MSMED Act. During proceedings, both sides agreed to have the disputes adjudicated under the 1996 Act by a Court-appointed Sole Arbitrator, superseding Clause 20. The Supreme Court appointed Justice K. Kannan as Sole Arbitrator, to adjudicate all claims and counter-claims, with the proceedings to be conducted by the Madras High Court Arbitration Centre. The MSMED Act process was closed and the appeal disposed of.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Indu Malhotra
  • Ajay Rastogi
Judgment Date
2021-02-22
Court Decision / Holding
The Appeal is disposed of. Clause 20 is superseded to the extent that arbitration will be conducted by a three-member tribunal; the Court appoints Justice K. Kannan (Retd.), as Sole Arbitrator to adjudicate all claims and counter-claims arising from the Development Agreement, to be conducted by the Madras High Court Arbitration Centre; the MSMED Act facilitation proceedings are closed; all pending applications are disposed; the matter proceeds under the Arbitration and Conciliation Act, 1996.
Final Disposition
Appeal disposed of.

Parties to the Case

Appellants / Petitioners

  • HGR Green Life Energy Pvt. Ltd.

Respondents

  • Leitwind Shriram Manufacturing Pvt. Ltd.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996MSMED Act, 2006 (Micro, Small and Medium Enterprises Development Act, 2006)Section 11(6) of the Arbitration and Conciliation Act, 1996MSMED Act Sections 15 to 18Section 24 of the MSMED Act

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the High Court’s appointment of an arbitrator under Section 11(6) and the decision to refer disputes under the MSMED Act were inappropriate given the arbitration clause in Clause 20. The Development Agreement originally envisaged a three-member arbitral tribunal. During proceedings, the parties voluntarily agreed to have their disputes adjudicated under the Arbitration and Conciliation Act, 1996 by a Court‑appointed Sole Arbitrator, superseding Clause 20’s three-member panel. The MSMED Act’s Facilitation Council provisions cannot override the exclusive arbitration arrangement, and the counter-claims raised by the contractor were to be resolved through arbitration rather than the MSMED framework. The appellant seeks appointment of a single, independent arbitrator and final resolution under the 1996 Act.

Contentions of Respondents

The respondent submits that the High Court correctly held the inapplicability of MSMED Act counter-claims within its Facilitation Council process and that disputes referred under Clause 20 should be resolvable by arbitration under the 1996 Act. With the parties’ earlier nomination of their arbitrators, the High Court’s view that appointment of a sole arbitrator would promote efficient, final adjudication is supported. The respondent argues that the Court had authority to supersede the three-member clause due to the agreement to proceed with a sole arbitrator, and the arrangement should be confirmed and implemented by the Supreme Court.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,317 words•~6 min read

In The Court Record

HGR Green Life Energy Pvt. Ltd. v. Leitwind Shriram Manufacturing Pvt. Ltd.

583 [2021] 1 S.C.R. 583 **==> picture [184 x 8] intentionally omitted <==** A v. LEITWIND SHRIRAM MANUFACTURING PVT. LTD. (Civil Appeal No.692 of 2021) February 22, 2021 B ## **[INDU MALHOTRA AND AJAY RASTOGI, JJ.]** _Arbitration and Conciliation Act, 1996 – Appellant-contractor and Respondent had entered into a agreement to set up a Wind Farm Project – Agreement contained an arbitration clause (Clause 20) – Disputes between the parties – Respondent invoked arbitration under Clause 20 of the agreement, and nominated its arbitrator, with request to Appellant to make nomination of its arbitrator – Appellant failed to do so – Subsequently, Respondent filed petition u/s.11(6) of the 1996 Act before the High Court, requesting the Court to appoint an arbitrator on behalf of Appellant in terms of Clause 20 of the agreement – High Court took the view that since the parties had in their agreement agreed to refer all their disputes under the 1996 Act, it was a fit case for appointment of arbitrator and that the agreement provided for a three-member arbitral tribunal – Respondent having already nominated its arbitrator, the Appellant was directed to appoint an arbitrator, and it was further directed that on such nomination, the two arbitrators would appoint the presiding arbitrator – Appeal before Supreme Court by AppellantContractor – During proceedings before Supreme Court, the parties agreed to have their disputes adjudicated under the Arbitration & Conciliation Act, 1996 by a Court-appointed Sole Arbitrator – Accordingly, the Supreme Court appointed a former Judge of the Madras High Court, as the Sole Arbitrator._ C D E F CIVIL APPELLATE JURISDICTION : Civil Appeal No. 692 of 2021. From the Judgment and Order dated 16.09.2020 of the High Court of Judicature at Madras in Original Petition No. 300 of 2019. G Ms. Shweta Sharma, Diggaj Pathak, Ravi Raghunath, Ms. Aakashi Lodha, Sanyat Lodha, Advs. for the appearing parties. H 583 584 SUPREME COURT REPORTS [2021] 1 S.C.R. A The following Order of the Court was passed: ## **ORDER** Leave granted. 1. The present Civil Appeal has been filed by the Appellant- B Contractor to challenge the Order dated 16.09.2020 passed on an Application filed under Section 11 of the Arbitration and Conciliation Act, 1996 by the Madras High Court in Original Petition No. 300 of 2019. - 2.The Appellant and the Respondent had entered into a - C Development Agreement dated 10.02.2014 to set up a Wind Farm Project in Sangli District in Maharashtra, which contained an arbitration clause. Clause 20 of the Agreement reads as : ## **“20. Governing Law and Jurisdiction and Service of Process** D **….** - c) All disputes, differences and claims or any non-payment concerning the project work hereby created and / or touching this presents, arising out of or in relation to anything contained herein shall be referred to arbitration to be held at Chennai, under the provisions of Arbitration and Conciliation Act, 1996 (inforce from - E time to time). The arbitration panel shall consist of three arbitrators, one arbitrator shall be appointed by each party and the arbitrators so appointed shall appoint the presiding arbitrator. The parties here to shall duly observe any interim award/s or direction/s of the arbitration tribunal and the award in pursuance to arbitration shall - F be final and binding on the parties hereto. The arbitration proceedings shall be in English language.” 3. Disputes arose between the parties with respect to claims raised by the Appellant-Contractor, which led to issuance of a legal notice dated 21.04.2018 seeking payment of outstanding dues of Rs. 3,26,08,545/-. G 4. The Respondent _vide_ letter dated 21.01.2019 rejected the allegations in the notice, and contended that the Contractor had failed to provide services as agreed under the Development Agreement. It was further contended that the Appellant-Contractor was liable to refund an amount of Rs.10,26,00,000/- with Interest @ 15% p.a., and pay liquidated H damages of Rs. 1,54,00,000/- to the Respondent-Company. 585 HGR GREEN LIFE ENERGY PVT. LTD. v. LEITWIND SHRIRAM MANUFACTURING PVT. LTD. The Respondent invoked arbitration under Clause 20 of the A Agreement, and nominated its arbitrator, with a request to the Appellant herein to make nomination of its arbitrator. 5. On 18.03.2019, the Respondent herein filed a Petition under Section 11(6) of the 1996 Act before the High Court of Madras, wherein it was prayed that the Court may appoint an arbitrator on behalf of the Appellant in terms of Clause 20 of the Development Agreement, since the Contractor had failed to do so. 6. Subsequently, the Appellant-Contractor, registered itself under the Micro, Small and Medium Enterprises Development Act, 2006 (“ _**MSMED Act**_ ”), and filed an application for resolution of disputes before the Facilitation Council, Pune established under the MSMED Act. 7. In the meanwhile, the Petition under Section 11 was taken up for hearing before the High Court, wherein it was observed that there is no provision under the MSMED Act for reference of counter-claims to the Facilitation Council, and adjudication thereof. Sections 15 to 18 of the MSMED Act provide for reference of disputes with respect to claims made by a supplier / contractor registered under the MSMED Act. Even though Section 24 of the MSMED Act gives overriding effect to the MSMED Act, it would not be applicable in this case, since there is no provision under this Act to deal with counter-claims filed against the supplier-contractor. The High Court took the view that since there is no provision for raising counter-claims under the MSMED Act, and the parties had in the Development Agreement dated 10.02.2014 agreed to refer all their disputes under the 1996 Act, it was a fit case for appointment of the arbitrator. The arbitration agreement provided for a three-member tribunal. The Applicant (Respondent herein) had already nominated its arbitrator, the Contractor was directed to appoint an arbitrator. On such nomination, the two arbitrators would appoint the presiding arbitrator. 8. The Appellant-Contractor challenged the aforesaid Order dated 16.09.2020 before this Court _vide_ Special Leave Petition (C) No. 16027 of 2020. B C D E F G During the course of the proceedings, the parties have agreed to have their disputes adjudicated under the Arbitration & Conciliation Act, 1996 by a Court-appointed Sole Arbitrator. H 586 SUPREME COURT REPORTS [2021] 1 S.C.R. A In view of the statement made by the Counsel for both parties on instructions, Clause 20 of the Development Agreement dated 10.02.2014 stands superseded to the extent that the arbitration will be conducted by a three-member tribunal. We appoint Justice K. Kannan, former Judge of the Madras High B Court, as the Sole Arbitrator to adjudicate on all the claims and counter claims made by the parties arising out of the Development Agreement dated 10.02.2014. The arbitration will be conducted in accordance with the Arbitration and Conciliation Act, 1996. The arbitral proceedings shall be conducted by the Madras High Court Arbitration Centre in accordance with its Rules. - C The appointment of the Sole Arbitrator is subject to the Declarations to be made under Section 12 of the Arbitration and Conciliation Act, 1996 with respect to independence and impartiality, and the ability to devote sufficient time to complete the arbitration. The Sole Arbitrator will be paid fees as per the Schedule of the Madras High D Court Arbitration Centre (Administrative Cost and Arbitrators’ Fees) Rules, 2017. A copy of this Order be despatched to the Madras High Court Arbitration Centre, and Justice K. Kannan (Retd.) at the following address: E “Justice K. Kannan 3/11, Lakshmi Colony, North Crescent, T. Nagar Chennai - 600017 F Mob: +91-9780008145" 9. In view of the aforesaid directions, the Application filed by the Appellant-Contractor under the MSMED Act, registered as MSFEC Case No. MH/26/M/PNE/02000 on 22.10.2020, will stand closed by the G Facilitation Council, Pune. 10. The Appeal is disposed of in the aforesaid terms. Pending applications, if any, stand disposed. H Bibhuti Bhushan Bose Appeal disposed of.
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.