Haryana Urban Development Authority v. Saurabh Aggarwal

Case / Petition Number:
Civil Appeal No. 5877 of 2002
Neutral Citation:2004 SUPP. 4 S.C.R.

Case Synopsis & Summary

This appeal arises from a dispute over a plot allotted by the Haryana Urban Development Authority (HUDA) where the respondent, Saurabh Aggarwal, paid substantial sums but did not receive possession in a timely manner. The District Consumer Forum awarded 18% interest per annum on the deposited amounts, a decision upheld by the State Forum but reduced to 15% by the National Consumer Disputes Redressal Commission (NCDRC). The appellant challenged the NCDRC's approach, noting that interest at 18% cannot be granted uniformly irrespective of case facts and that damages or compensation must be awarded under appropriate heads if justified. The Supreme Court held that the NCDRC's blanket grant of 18% was unsustainable and set out a calibrated framework: the appellant must pay interest at 15% from the date of each deposit to the date of payment; no interest on delays prior to the offer of possession; if possession was offered on 22 July 1997, further interest stops; if any excess amounts were recovered, they must be refunded with 15% interest from the date of recovery; any further recovery beyond the original price requires permission from the Court; refunds of TDS, if any, must also carry 15% interest. The order directed recalculation within 15 days and compliance within one month, and clarified that it should not be treated as a precedent. The decision reiterates Ghaziabad Development Authority v. Balbir Singh and aligns future forum actions accordingly.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • S. N. Variava
  • A. K. Mathur
Judgment Date
2004-09-24
Court Decision / Holding
The National Commission's order awarding interest at 18% cannot be sustained; set aside. The appellant must pay interest at 15% from the date of each deposit until payment; no interest on delayed payments before the date of possession; if possession was offered by 22 July 1997, no further interest; refunds for any excess amounts recovered to be made with 15% interest; if there is a claim to recover amounts beyond the original price, the appellant may approach the Court for clarification/modification; no permission implies no extra recovery; if TDS was deducted, it must be paid with 15% interest; recalculation to be completed within 15 days and payment within 15 days thereafter; compliance report within one month; the order not to be treated as a precedent and future Forum/Commission follow Ghaziabad Development Authority v. Balbir Singh; appeals disposed of with no order as to costs.
Final Disposition
Appeals disposed of.

Parties to the Case

Appellants / Petitioners

  • Haryana Urban Development Authority

Respondents

  • Saurabh Aggarwal

Legal Representation & Advocates

Counsels for Petitioners

  • • Jai Prakash Dhanda
  • • Mrs. Raj Rani Dhanda

Provisions of Law Cited

Consumer Protection Act, 1986

Legal Doctrines & Maxims

  • Misfeasance in public office
  • Deficiency in service
  • Compensation/damages for mental agony/harassment
  • Principles laid down by Ghaziabad Development Authority v. Balbir Singh

Submissions & Arguments

Contentions of Appellants / Petitioners

HUDA contended that the National Commission erred in uniformly awarding 18% interest irrespective of case facts; argued that interest should be 15% from the date of each deposit until payment, with no interest on period before possession; excess sums recovered must be refunded with interest; any further recovery requires Court permission; the decision should not create a blanket precedent and the authority should recalculate and comply promptly.

Contentions of Respondents

Respondent’s position aligned with the lower fora’s award of interest, supported by prior ICS decisions; argued for maintenance of substantial interest on deposits until possession; relied on earlier decisions to justify the rate, which the Court later criticized as part of a broader practice.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Ghaziabad Development Authority v. Balbir Singh[2004] 5 SCC 65PositiveUsed as the guiding principle; held that 18% interest cannot be granted in all cases irrespective of facts and that damages/compensation must be case-specific and supported by findings.
Haryana Urban Development Authority v. Darsh KumarnullOverruledThe Court deprecated the practice of granting blanket 18% interest as per this prior decision, effectively limiting its applicability in light of the present judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,143 words•~10 min read

In The Court Record

Haryana Urban Development Authority v. Saurabh Aggarwal

A **B** # HARY ANA URBAN DEVELOPMENT AUTHORITY # _v._ SAURABH AGGARWAL ## SEPTEMBER 24, 2004 [S.N. VARIAVA AND A.K. MATHUR, JJ.] _Housing:_ _Interest-Rate of-Allotment of plot-Delay in handing over possessionDespite deposit of substantial amounts-District Forum awarded 18% interest p.a. on the deposited amount-Correctness of-Held: Interest cannot be granted_ @ _18% p.a. in all cases irrespective of facts-Development Authority to pay interest@ 15% p.a. from date of each deposit till date of payment-Authority will not charge interest on delayed payment prior to the date of offer of possession-If by that date the original allotment price had been paid the Authority will not be entitled to and will not charge any interest-If anything extra is recovered the Authority will repay that back to the allottee with interest thereon at 15% from the date of such wrongful ·recovery till payment-If the Authority has a claim and feels that it has to recover such amounts from the allottee, it is at liberty to approach the Supreme Court for clarification/modification of the order and if on that application it is permitted it may recover accordingly-But in the absence of any such permission it shall not recover anything extra/over and above the original allotment price-Further, if TDS amount is deducted the Authority will now pay that over to the al/ottee with interest thereon at the rate of 15% from the date it was so deposited till payment-This order shall not be taken as a precedent in any other matter as ·the order is being passed taking into account features of the case._ **The respondent was allotted a plot by the appellant-Authority. The respondent had paid substantial amounts but the possession of the plot was not delivered. The respondent, therefore, filed a complaint before the District Consumers Disputes Redressal Forum which awarded interest** @ **18% p.a. on the deposited amount. The State Consumers Disputes Redressal Forum confirmed the order of the District Forum but reduced the interest from 18% to 15%. The National Consumers Disputes Redressal Commission dismissed the Revision filed by the appellant on** c **D** **E** **F** **G** **H** 705 706 SUPREME COURT REPORTS [2004) SUPP. 4 S.C.R. A the ground that interest @ 18% had been allowed by it under similar circumstances. Hence the appeal. Disposing of the appeal, the Court B c HELD: I. The order of the National Consumers Disputes Redressal Commission cannot be sustained. It cannot dispose of the matters by confirming the award of interest in all matters irrespective of the facts of a case. It must, on facts of a case, award compensation/damage under appropriate heads if it comes to the conclusion that such an award is justified/necessary. Accordingly, the order of the National Commission is set aside. [708-B-C] _Ghaziabad Development Authority_ v. _Balbir Singh,_ (2004) 5 SCC 65, relied on. 2.1. The appellant must pay interest@ 15% from the date of each D deposit till the date of payment. The appellant will not charge interest on delayed payment prior to the date of other of possession. Thus, interest could only be charged from the date of offer of possession. If by that date the original allotment price had been paid the appellant will not be entitled to and will not charge any interest. If anything extra is recovered the appellant will repay that back to the respondent with interest thereon@ E 15% from the date of such wrongful recovery till payment. If the appellant has a claim and feels that it has to recover such amounts from the respondent, it is at liberty to approach this Court for clarification/modification of the order and if on that application it is permitted to so recover it may. But in the absence of any such permission, it shall not recover anything extra/ F over and above the original allotment price. [709-E-G) 2.2. Further, if TDS amount is deducted the appellant will now pay that over to the respondent with interest thereon at the rate of 15% from the date it was so deposited till payment. [709-H; 710-A] G 3. This order shall not be taken as a precedent in any other matter as the order is being passed taking into account special features of the case. The Forum/Commission will follow the principles laid down by this Court in _Ghaziabad Development Authority's case._ (710-B-C] _Ghaziabad Development Authority_ v. _Balbir Singh,_ [2004) 5 SCC 65, H relied on. B C HARYANA URBAN DEV. AUTHORITY v. S. AGGARWAL [V ARIA VA, J.) 707 CIVIL APPELLATE JURISDICTION: Civil Appeal No. 5877 of2002. From the Judgment and Order dated 18.12.2001 of the National Consumers Disputes Reddressal Commission, New Delhi in R.P. No. 229 of 2000. Jai Prakash Dhanda and Mrs. Raj Rani Dhanda for the Appellant. > The Judgment of the Court was delivered by S. N. V ARIA VA, J. : Before this Court a large number of Appeals have been filed by the Haryana Urban Development Authority and/or the Ghaziabad C Development Authority challenging Orders of the National Consumer Disputes Redressal Commission, granting to Complainants, interest at the rate of 18% per annum irrespective of the fact of each case. This Court has, in the case of _Ghaziabad Development Authority_ v. _Balbir Singh_ reported in [2004] 5 SCC 65, deprecated this practice. This Court has held that interest at the rate of 18% cannot be granted in all cases irrespective of the facts of the case. D This Court has held that the Consumer Forums could grant damages/ compensation for mental agony/harassment where it finds misfeasance in public office. This Court has held that such compensation is a recompense for the loss or injury and it riecessarily has to be based on a finding of loss or injury and must co-relate with the amount of loss or injury. This Court . E has held that the Forum or the Commission thus had to determine that there was deficiency in service and/or misfeasance in public office and that i~ has resulted in loss or injury. This Court has also laid down certain other guidelines which the Forum or the Commission has to follow in future cases. D This Court is now taking up the cases before it for disposal as per principles set out in earlier judgment. On taking the cases we find that the copies of the Claim/Petitions made by the Respondent/Complainant and the evidence, if any, led before the District Forum are not in the paper book. This Court has before it the Order of the District Forum. The facts are thus taken from that Order. In this case, the Respondent was allotted a plot bearing No. 4/13(P) Sector, Hisar on 4th April 1986. The Respondent paid substantial amounts but the possession was not delivered. Thus the Respondent filed a complaint. On these facts, the District Forum awarded interest @ 18% p.a. on the deposited amount. F G H 708 SUPREME COURT REPORTS [2004] SUPP. 4 S.C.R. A B c D E The State Forum confirmed the Order of the District Forum but reduced interest from 18% to 15%. The Appellants went in Revision before the National Commission. The National Commission dismissed the Reyision filed by the Appellants relying upon its own decision in the case of _Haryana Urban Development Authority_ v. _Darsh Kumar_ and observing that interest @ 18% p.a. has been allowed by them under similar circumstances. As has been stated in so many matters, the Order of the National Commission cannot be sustained. It cannot dispose of the matters by confirming award of interest in all matters irrespective of the facts of that ca~e. It must, on facts of a case, award compensation/damage under appropriate heads if it comes to the conclusion that such award is justified/necessary. Accordingly the Order of the National Commission is set aside. We are informed that the Appellants have offered possession on 22nd July 1997. Counsel had no instructions whether Respondent had taken possession or not. Undoubtedly the Respondent will be entitled to take possession, if he has not already taken possession. Appellants will deliver possession without demanding any further or other amounts. We are informed that the Respondent has paid a' sum ofRs.1,68,338.25. We however find from the copy of the allotment letter, filed in this Court along with the affidavit of the Estate Officer dated 29th July 2004, that a sum of Rs.1,68, 186.50 was payable. In the affidavit the following statement is made: .·. F G H "The interest on the amounts deposited by the respondent has been adjusted on 25.5.1998 for an amount ofRs.2,49;829.65 at the interest rate of 15% p.a." Counsel had no instructions and could not explain what were the amounts due from the Respondent which are supposed to have been adjusted. As stated above Respondent has paid more than what he was bound to pay. Also neither before the District Forum or the State forum or the National Commission and even in the Appeal Memo before this Court is there a claim that Appellants have to recover amounts from the Respondent. When the dispute has been subjudice the Appellants are bound to put before the Court/ Forum not just their defence but also their claim/counterclaim, if any. Without permission of Court the Appellants cannot set at naught awards of the Forum by raising, ·outside Court, demands against the Respondents. It HA RY ANA URBAN DEV. AUTHORITY v. S. AGGARWAL [VARIAVA, J.] 709 A must be remembered that the Appellants were to deliver possession within a reasonable time. They do not offer possession till 22nd July 1997. As can be seen from the Order of the District Forum possession was not being offered because development work had not taken place. As they were not in a position to deliver possession they cannot expect parties like the Respondent i.e. allotees to keep on paying installments to them. In such cases i.e. where Appellants are not in position to deliver possession they cannot charge interest on delayed payments till after they offer possession. Clause 6 of the letter of allotment also so provides. It reads as follows: "6. The balance amount i.e. Rs.1,26,139/50 of the above tentative price of the plot/building can be paid in lump sum without interest within 60 days from the date of issue of the allotment letter or in six equal instalments. The first instalment will fall due after the expiry of one year of the date of issue of this letter. Each instalment would be recoverable together with interest on the balance price at 10% interest on the remaining amount. The interest shall, however accrue from the date of offer of possession." B c D Thus, interest could only have been charged from date of offer of possession. As we are unable to understand and Counsel has no instructions to be able to explain why extra payment has been collected and/or what adjustments are purported to have been made, we direct that Appellants shall now recalculate in the manner set out hereunder. In this case, Appellants mu~t pay interest at l 5% from date of each deposit till date of payment. They will not charge interest on delayed payments prior to 22nd July 1997. Ifby that date the original price of Rs.1,68, 186.50 had been paid they will not be entitled to and will not charge any interest. If anything extra is recovered they will 'repay that back to the Respondent with interest thereon at 15% from the date of such wrongful recovery till payment. We, however, clarify that if Appellants have a claim and fee 1 that they have to recover such amounts from Respondent, they are at liberty to approach this Court for clarification/ modification of the Order and if on that application they are pennitted to so recover they may. But in the absence of any such permission, they shall not recover anything extra/over and above the allotment price ofRs.1,68, 186.50. Further, if TDS amount is deducted they will now pay that over to the Respondent with interest thereon at the rate of 15% from date it was, so E c 710 A B c SUPREME COURT REPORTS [2004) SUPP. 4 S.C.R. > deposited till payment. Such recalculation to be made within I _5_ days from today and the amounts found due and payable to the Respondent to be paid to him within 15 days thereafter. A compliance report to be filed in this Court within one month from date. A copy of the recalculation to be annexed to the compliance report. We clarify that this Order shall not be taken as a precedent in any other matter as the order is being passed taking into account special features of the case. The Forum/Commission will follow the principles laid down by this Court in the case of _Ghaziabad Development Authority_ v. _Balbir Singh_ (supra) in future cases. > With these observations, the Appeal stands disposed of with nO'order as to costs. v.s.s. Appeals disposed of.
End of Judgment Record
Browse All Supreme Court of India (2004) Decisions
2004-05-26

State of West Bengal v. Haresh C. Banerjee and Ors.

This appeal concerns the constitutional validity of Rule 10(1) of the West Bengal Services (Death-cum-Retirement Benefit) Rules. The Calcutta High Court had previously held the rule ultra vires the Constitution and had struck down the power to conduct a departmental inquiry against a retired employee. The Supreme Court granted special leave and noted that even if the appeal were to succeed, the benefit already due to respondent No. 1 in the High Court’s order would not be recalled; arrears would be paid by the State within the time prescribed. The sole question before the Court is the validity of Rule 10(1) and its relation to the West Bengal (Classification, Control and Operation) Rules, 1971, including sub-rule (1) of Rule 10, which governs classification and control of service. The Court observed that the issue raises a larger question of operation that could affect a large number of employees, and therefore it is appropriate to refer the matter to a larger Bench for authoritative adjudication. The matter is thus directed to be placed before a larger Bench, and the judgment does not finally decide the vires of Rule 10(1). In short, the Court stayed further adjudication on the matter of validity and opted for an expeditious reference to a larger judicial forum. The background also includes the Court’s directive in leave proceedings that arrears, if any, would be payable according to the High Court’s order, not recalled pending appellate resolution.

2004-05-05

Commissioner of Customs & Central Excise & Ors. v Charminar Nonwovens Ltd.

The case concerns the proper classification and duty liability of Floor G Coverings and Filter Fabrics under the Central Excises and Salt Act, 1944, specifically whether these goods fall under Tariff sub-headings 5703.90 (30% ad valorem) or 5703.20 (5% ad valorem). The respondent, Charminar Nonwovens Ltd., received a detention memo and a show-cause notice challenging the classification and the related duty. An appellate authority had previously upheld the assessee's classification on a similar adjudication, and the Andhra Pradesh High Court later quashed the show-cause notice on the ground that the appellate order had become final. The petitioners challenged this, arguing that classification must be decided on facts arising in each case and that new facts or changes in law may warrant re‑examination, not interference by the High Court at the show-cause stage. The Supreme Court held that classification and the determination of duty are case-specific, and even if a decision was taken earlier, further investigation can reveal new facts or a change in law requiring re‑examination. The High Court's interference at the show-cause stage was improper. The Court then set aside the High Court order and remitted the matter to the Adjudicating Authority for fresh adjudication, with similar directions to related appeals. The overarching principle is that revenue classifications are not frozen by earlier judgments and must be reconsidered as facts or law evolve.

2004-08-16

G. B. LAHOTI v. S. J. CHOURASIYA

This Supreme Court decision concerns substitution of legal heirs in a pending appeal arising from a land-lord–tenant dispute. The landlord sued for possession; the trial court decreed possession due to unlawful sub-letting. The tenant’s successor-deceased Ganesh Prasad Lahoti’s heirs sought substitution under Order XXII Rule 11 after the defendant’s death; the first substitution application Exh. 22 was rejected on a technical ground, and three further applications followed (for setting aside abatement, for condonation of delay, and for interim relief). The appellate court dismissed these on merits and on the ground of res judicata, and the High Court dismissed revisions. The Court held that the doctrine of res judicata does not bar such subsequent applications where, as in this case, there was no inaction or negligence by the heirs and the delay was explained by the circumstances—knowledge of pendency arose only after a letter from the advocate confirming hearing. The Supreme Court allowed the appeal, set aside the lower orders, and directed the lower appellate court to hear the appeal on merits in accordance with law, with an award of costs (Rs. 10,000) within three months, and a fresh deadline for a merits decision by Aug. 31, 2005. The decision clarifies substitution rights in the context of pending appeals and limits of res judicata in substitution petitions.

2004-05-05

SHAKUNTALA BAI v. NARAYAN DAS

This Supreme Court decision arises from a long-drawn eviction suit under the Madhya Pradesh Accommodation Control Act, 1961, filed for bona fide landlord’s need to carry on business in a non-residential premises. The trial court decreed eviction; during appeal, the landlord died and his heirs sought to amend the plaint to plead their own bona fide need. The tenant urged amendment of his pleadings to claim that, after the landlord’s death, the personal need ceased. The High Court dismissed the suit on the ground that after the landlord’s death the personal need could not be pursued by heirs. The Supreme Court, allowing the appeals, held that the bona fide need of the landlord must be examined as on the date of institution of proceedings, and if a decree for eviction is passed, the death of the landlord during pendency of the appeal does not invalidate the Plaintiffs’ right to defend the estate. It clarified the law: the bar under s.12(1) prevents filing the suit except on listed grounds; the need may be tested with amended pleadings after remand; the object of the Act is expeditious disposal and not perpetual litigation. Citing earlier decisions, the Court ultimately restored the trial court’s decree, set aside the High Court’s dismissal, and granted four months for eviction with an undertaking. The decision reaffirms that heirs may defend the estate where a valid eviction decree has been issued.