Haryana State Industrial and Infrastructure Development Corporation Ltd. & Ors. v. Deepak Aggarwal & Ors.
Case Synopsis & Summary
The Supreme Court settles a critical interpretive dispute arising from a batch of Civil Appeals and SLPs relating to Section 24(1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act) and the erstwhile Land Acquisition Act, 1894 (LA Act). The central issue is the meaning of the word “initiated” in Section 24(1) of the 2013 Act, in the context of land acquisition proceedings under the LA Act. The appellants (Party A) contend that initiation occurs when a Section 4(1) notification under the LA Act is issued and published, enabling preliminary steps and entry for survey. The respondents (Party B) argue initiation occurs only on a Section 6 declaration that the land is required, asserting reliance on decisions such as Babu Barkya Thakur and M/s. Fomento Resorts. The Court traces the legislative history, noting Section 114 saving, and Section 6 of the General Clauses Act, and surveys the precedents (Indrapuri Griha Nirman Sahakari Samiti; VKM Kattha Industries; Ambica Quarry Works; Chandavarkar Sita Ratna Rao; Offshore Holdings; Shiv Kumar; Jilubhai Nanbhai Khachar; Narmada Bachao Andolan; Laxman Lal; Maharashtra Vidarbha Irrigation Development Corpn.). It ultimately holds that initiation for Section 24(1) is the publication of the Section 4(1) notification, with LA Act provisions applying for compensation, and 2013 Act provisions governing compensation only when applicable.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- C. T. Ravikumar
- A. M. Khanwilkar
- Abhay S. Oka
- Judgment Date
- 2022-07-28
- Court Decision / Holding
- For purposes of Section 24(1) of the 2013 Act, the LA Act proceedings shall be treated as initiated on publication of a Section 4(1) notification; if Section 24(1)(a) applies, proceedings continue under the LA Act; however, for the determination of compensation, the provisions of the 2013 Act shall apply.
- Final Disposition
- The appeals are disposed by holding that for the purposes of Section 24(1) of the 2013 Act, the LA Act proceedings are initiated on publication of the Section 4(1) notification; when Section 24(1)(a) applies, the proceedings continue under the LA Act; the determination of compensation is governed by the 2013 Act to the extent applicable. Other issues to be considered on merits in separate proceedings or benches as already listed. New Delhi; 28 July, 2022; J. (C.T. Ravikumar), J. (A.M. Khanwilkar), J. (Abhay S. Oka).
Parties to the Case
Appellants / Petitioners
- Haryana State Industrial and Infrastructure Development Corporation Ltd. & Ors.
Respondents
- Mr. Deepak Aggarwal & Ors.
Provisions of Law Cited
Legal Doctrines & Maxims
- Ex visceribus actus
- Notwithstanding / non-obstante clause
- Interpretation should subserve the legislative intent of the Act (purposive construction)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants contend that land acquisition proceedings under the LA Act are initiated with the publication of the Section 4(1) notification; this initiation triggers subsequent steps and allows the 2013 Act to apply to compensation, while preserving the LA Act for the mechanics of the process. They rely on Indrapuri Griha Nirman Sahakari Samiti Ltd. and VKM Kattha Industries to support the Section 4(1) initiation view, and sustain their position against the respondents’ Section 6-based initiation argument by citing Babu Barkya Thakur and Fomento Resorts.
Contentions of Respondents
The respondents contend that initiation occurs upon the Section 6 declaration that land is required, arguing that Section 4(1) is only a preliminary formality. They rely on Babu Barkya Thakur, M/s. Fomento Resorts, and related decisions to argue that Section 6 marks initiation; they also invoke Articles 21 and 300-A to challenge delays and seek broader protections.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (13)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Indrapuri Griha Nirman Sahakari Samiti Ltd. v. State of Rajasthan | [(1975) 4 SCC 296] | Positive | Cited as authority that land acquisition proceedings commence with the notification under Section 4 of the LA Act. |
| V.K.M. Kattha Industries (P) Ltd. v. State of Haryana | [(2013) 9 SCC 338] | Positive | Used to support initiation at Section 4(1) notification as the starting point. |
| Babu Barkya Thakur v. State of Bombay & Ors. | (AIR 1960 SC 1203) | Positive | Cited for the proposition that Section 4 initiation is the starting point for proceedings. |
| M/s. Fomento Resorts & Hotels Ltd. v. Gustavo Ranato Da Cruz Pinto & Ors. | [(1985) 2 SCC 152] | Distinguished | Held initiation after Section 6; distinguished for purposes of Section 24 interpretation in this judgment. |
| Chandavarkar Sita Ratna Rao v. Ashalatha S. Guram | [(1986) 4 SCC 447] | Positive | Cited for non-obstante clause interpretation on override effects. |
| Maharashtra Vidarbha Irrigation Development Corpn. v. Mahesh & Ors. | [(2022) 2 SCC 772] | Distinguished | Earlier view distinguished; the decision not controlling for the Section 24(1) interpretation here. |
| Ambica Quarry Works v. State of Gujarat | [(1987) 1 SCC 213] | Positive | Supports purposive interpretation aligning with 2013 Act’s twin aims. |
| Offshore Holdings Private Ltd. v. Bangalore Development Authority | [(2011) 3 SCC 139] | Positive | Cited for contextual interpretation i.e., ex visceribus actus. |
| Shiv Kumar and Anr. v. Union of India and Ors. | [(2019) 10 SCC 229] | Positive | Used to illustrate limits of Section 4(1) notification validity and cure by Section 6. |
| Jilubhai Nanbhai Khachar v. State of Gujarat | [(1998) 11 SCC 175] | Positive | Cited for Article 21 vs Article 300-A considerations in property rights. |
| State of M.P. v. Narmada Bachao Andolan | [(2011) 7 SCC 639] | Positive | Supports view on Article 21/300-A interplay and property rights. |
| Laxman Lal (Dead) Through LRs. & Anr. v. State of Rajasthan | [various] | Positive | Cited in context of initiation and section 4 precedents. |
| Ambica Quarry Works v. State of Gujarat | [(1987) 1 SCC 213] | Positive | Repeated entry to purposive construction. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Haryana State Industrial and Infrastructure Development Corporation Ltd. & Ors. v. Deepak Aggarwal & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.