Gujarat Water Supply & Sewerage Board v Unique Erectors (Gujarat) (P) Ltd.

Case / Petition Number:
Civil Appeal No. 418/1989
Neutral Citation:(1989) 1 SCR 318

Case Synopsis & Summary

This Supreme Court judgment concerns an arbitration award under the Arbitration Act, 1940, arising from disputes in the Bhavnagar City Water Supply Scheme contract works. Respondent No. 1 (Unique Erectors) claimed underpayments and sought reference to arbitration under clause 30 of the contract after the State Government awarded two contracts for the Bhavnagar scheme. An arbitrator was appointed and delivered a lump-sum award in July 1985 after earlier interim findings on arbitrability. The Gujarat High Court had dismissed challenges to the award. The appellants argued that the arbitrator erred in law by not deciding/arbitrability of certain claims (and counter-claims), failed to indicate which claims were rejected or the exact amounts awarded, and that the award contained undecipherable or erroneous reasons, particularly regarding interest. They also challenged interest pendente lite and sought a reference to a Constitution Bench or a speaking award. The Court held that while reasons need not be detailed, an award should be read as a whole to discern the arbitrator’s mind, and that the matter need not be referred to the Constitution Bench. The decision also restated that the Court does not sit in appeal on the reasons but can set aside an award if there is no evidence or if a legal proposition is erroneous. The Court modified the interest awarded, determining the permissible periods and rates in light of the Interest Act, 1978 and Arbitration Act provisions, while upholding the core award on merits.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Sabyasachi Mukherji
  • S. Ranganathan
Judgment Date
1989-01-24
Court Decision / Holding
Appeals disposed of. The Court (i) affirmed the view that the award should be read as a whole with short intelligible grounds, (ii) held that the arbitrator did decide arbitrability and merits, (iii) modified the interest portion: deleted interest from 22.8.1984 to 19.7.1985, limited interest on the principal sum to 9% from 6.8.1981 to 21.8.1984, and allowed interest on the unpaid principal from the award date (19.7.1985) to payment, in accordance with the Interest Act, 1978 and the Arbitration Act, 1940, directing that the principal sum carry interest from the award date to actual payment. Overall, the appeals were disposed of in terms of these adjustments while upholding the award on merits.
Final Disposition
Appeals disposed of; the Court modified the award on interest in light of the Interest Act, 1978 and Arbitration Act provisions, while affirming the award on merits and directing payment of interest from the award date to actual payment.

Parties to the Case

Appellants / Petitioners

  • Gujarat Water Supply & Sewerage Board

Respondents

  • Unique Erectors (Gujarat) (P) Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • V.B. Patel
  • • D. Patel
  • • T.H Pandey
  • • R.P. Kapur

Counsels for Respondents

  • • Soli J. Sorabjee
  • • Atul Setalwad
  • • N.J. Mehta
  • • P. Shah
  • • S.K. Sharma
  • • S. Sharma
  • • P.H. Parekh

Provisions of Law Cited

Arbitration Act, 1940: Section 14; Section 17; Section 29; Section 30; Section 33-A; Section 8; Sections 15-17Interest Act, 1978: Section 3(1)(a)Code of Civil Procedure, 1908: Section 34

Legal Doctrines & Maxims

  • Awards should be read reasonably as a whole to discern the mind of the arbitrator (noting grounds, if intelligible)
  • The court does not sit in appeal over the arbitrator’s reasons and will only set aside an award if there is no evidence to support the conclusion or if the award rests on an erroneous legal proposition
  • Reasons for arbitration awards are desirable but not always mandatory; non-speaking awards are not per se invalid
  • Arbitrators may decide arbitrability and merit; a consent or de novo procedure can be used to resolve disputes
  • Interest pendente lite may be subject to correction under statutory provisions (Interest Act, 1978) and Arbitration Act provisions

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicant-board contended that the arbitrator committed an error of law by not deciding or disclosing arbitrability of claims/counter-claims; the award failed to indicate which claims were rejected and the amounts awarded; the basis for interest was not disclosed, and interest pendente lite violated Supreme Court precedent. It urged non-speaking awards and sought either a Constitution Bench reference or a re-issue of a speaking award, arguing prejudice from a large albeit undisclosed award against a nominal claim.

Contentions of Respondents

The respondents argued that the arbitrator properly decided arbitrability within the scope of the contract and proceeded claimwise; the grounds, though not elaborately stated, were sufficient when read with the preamble; the High Court’s conclusions were correct in sustaining the award; the award did not require a full speaking judgment and the grounds were intelligible; the decision complied with the contract and applicable law.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Indian Oil Corporation Ltd. v. Indian Carbon Ltd.[1988] 3 SCC 36PositiveCited to support the standard that the Court does not re-weigh evidence but may consider whether the award is based on a legal proposition that is erroneous or on no evidence.
Municipal Corporation of Delhi v. Miss Jagan Nath Ashok Kumar & Anr.[1987] 4 SCC 497PositiveCited for the meaning of the term 'reasonable' and the standard of reasonableness in evaluating awards.
Executive Engineer (Irrigation) Balimela and Ors. v. Abhaduta Jena & Ors.[1988] 1 SCC 418PositiveCited regarding the permissible periods for interest pendente lite and the scope of awarding interest.
State of Orissa & Ors. v. Construction India[1987] Supp. SCC 709PositiveCited in the context of interest and procedural considerations in arbitration.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,929 words•~23 min read

In The Court Record

Gujarat Water Supply & Sewerage Board v Unique Erectors (Gujarat) (P) Ltd.

) A B GUJARAT WATER SUPPLY & SEWERAGE BOARD _v._ UNIQUE ERECTORS {GUJARAT) (P) LTD. & ANR. JANUARY 24, 1989 [SABYASACHI MUKHARJI AND S. RANGANATHAN, JJ.) _Arbitration Act,_ _1940:_ _Sections_ _14, 17,_ _29,_ _30 and 33-Award-_ _Setting aside_ _of-No evidence_ _to_ _support conclusion-Based on_ _legal_ _proposition which is erroneous-Award of arbitrator to be read reason-_ _ably_ _as_ _a whole--Unreasoned award-Effect_ _of-Error apparent on_ C _face_ _of award-What is-interest pendente lite-Cannqt be_ _granted-_ _interest for period between_ _date_ _of award and_ _date_ _of decref!_ _can_ _be_ _allowed in cases governed by Interest Act,_ _1978._ D _Interest Act,_ _1978:_ _Section 3(1)(a)-Arbitration proceedings-_ _grant of interest bY Court._ _Wor¢s_ _&_ _Phrases._ _'reqsonable'-Meaning of._ In 1978 the State Government undertook the construction of the E '·Bhavnagar City Water Supply Scheme', and on 12th January, 1979, two contracts in respect thereof were awarded to respondent No. 1. On 29th March, 1981, respondent No. 1 filed a civil suit with regard to measurements recorded by the Deputy Engineer and alleged underpayments- On 14t!t June, 1981, he gave notice to the State Government and the petitioner Board requesting for reference of the d.isputes to an F arbitrator as provided for under clause 30 of the Agreement, and gave notice under section 8 of the Arbitration Act, 1940 calling upon the petitioner tO'concur in the appointment of one Sbri G.G. Vaidhya. On 6th August, 19,81 respondent No_ 1 filed a civil miscellaneous application for appoin~ent of the said Sbri G. G. Vaidhya as the sole ar.bi.tr.ator. after withdrawing th.e _civil suit. The petitioner contended . g tl!!lt the application_ was not maintainable. The Civil Jµdge however . aPP'!in.t~!_I the s;ti.d Stu.i. G.G. Vaidbya as sole arbitrlltor. The arbitrl!tor g!frll !l!l illtetjm !l"\Vl!!'cl h,!llcling thllt only two ~lllin_ts were not arbitrllble ~ a, ~n.'-1 t!t;::::~::::~::: :::::·ti!~ !IP~.!. w~~~r aP~ H was filed in this Court. This appelll was, however, disposed of by con- ·. 318 GUJARAT WATER SUPPLY BOARD _v._ UNIQUE ERECTORS 319 sent on 30th November, 1983 to the effect that a retired Secretary, A •.+ Public Department who was at that time sitting member of the peti tioner-Board be appointed as the sole arbitrator to decide all the disputes between the parties- On 8th July, 1985, this sole arbitrator made a lump sum award. The Civil Judge directed that the decree he passed in terms of the award, rejecting the objections of the petitioner. B The High Court by a common judgment dismissed the two appeals -:.::. of the petitioner challenging the award. ~ In the appeals to this Court by special leave, it was.contended: (1) that the arbitrator had committed an error of law in not deciding or disclosing his mind about the arbitrability of the claims or counter- c claims, (2) in the award no basis or indication was given as to which claim was rejected, and further what amount was awarded as claim and c).; what amount towards element of interest, (3) there was an error apparent on the face of the award inasmuch as the basis on which interest had been awarded had not been disclosed and whether the interest has D been ·awarded from the date of the institution of the proceedings, (4) that the granting of interest pendente lite was contrary to the decision of this Court and ( 5) that the non-speaking award had resulted in great prejudice to the petitioner inasmuch as against the claim of Rs.I lakh, #### x Rs.57 lakhs had been awarded. Rs.57 lakhs had been awarded. E Disposing of the appeals, the Court, ' HELD: l(a) There is a trend in modern times that reasons should he stated in the award though the question whether the reasons are ~ necessary in ordinary arbitration awards is pending adjudication by the Constitution Bench of this Court. Even if it be held that it is obligatory F for the arbitrator to state reasons, it is not obligatory to give any detailed judgment. l325E] l(b) An award ~f an arbitrator should be read reasonably as a whole to find out the implication and the meaning thereof. Short intelligible indications of the grounds shall be discernible to find out the G mind of the arbitrator for his action. l325F] ~ l(c) The Court does not sit in appeal over the award and review the reasons. The Court can set aside the award only if ii is apparent from the award that there is no evidence to support the conclusion or if the award is based upon any legai proposition which is erroneous. [325G-H I H 320 SUPREME COURT REPORTS [1989] 1 S.C.R. A _Indian Oil Corporgtion Ltd._ v. _Indian Corbon Ltd.,_ [1988] 3 SCC #### + 36, regerred to. B c 1 ( d) It is one thing to say that an award is unintelligible and it is another thing to say that the award was bad because it was a nonspeaking award. [326F] In the instant case, the arbitrator, in pursuance to the order of this Court had to decide which of the disputes were arbitrable and which were not. Reading the award along with the preamble, it appears clear that the arbitrator had decided the arbitrability and the amount which he has awarded was on the points which were arbitrable. In such circumstances it will not ™; in consonance with justice to refer the matter to the Constitution Bench or to await the disposal of the point by the Constitution Bench. [326B, G] 2. Reasonableness as such of an award unless per se preposterous or absurd is not a matter for the Court to consider. Appraisement of D evidence by the arbitrator is ordinarily not a matter for the Court. It is difficult to give an exact definition of the word 'reasonable'. The word 'reasonable' has in law, prima facie meaning of reasonable in regard to those circumstances of which the actor, called upon to act reasonably, knows or ought to know. The award in the instant case cannot be condemned as unreasonable. [327C-D] E _Municipal Corporation_ _of_ _Delhi_ v. _Mis._ _Jagan_ _Nath_ _Ashok_ _Kumar_ _&_ _Anr.,_ [1987] 4 SCC 497 referred to. 3. The grant of interest pendente Ute is however one infirmity in. the award which is apparent on the face of the award which in the .. --4! F interest of justice should be corrected. [327E] ' -1 _Executive Engineer (Irrigation) Balimela and_ _Ors._ v. _Abhaduta_ _Jena_ _&_ _Ors.,_ [1988] 1 SCC 418 and _State of Orissa_ & _Ors._ v. _Construc-_ _tion India,_ [1987] Supp. SCC 709 referred to. G In the instant case, April 2, 1984 is the date of the reference to arbitration, on August 22, 1984 the arbitrator entered upon the reference. July 8, 1985 is the date of the award and July 19, 1985 the,l.. date of publication of the award. The latter date should be taken as the date of the award. Since the reference to arbitration was made after the commencement of the Interest Act, 1978 the arbitrator under section H 3(1)(a) of the said Act was entitled to award interest from August 6, GUJARAT WATER SUPPLY BOARD _v._ UNIQUE ERECTORS [MUKHAR.ll, J.J 321 1981 till August 21, 1984. He could not have awarded interest for the period from August 22, 1984 till the date of publication of the award viz. July 19, 1985. l327G-H; 328A] 4. So far as interest for the period from the date of the award (July 19, 1985) till the date of the decree is concerned, interest should be allowed for this period, on the principle that this Court can, once proceeding under sections 15 to 17 are initiated, grant interest pending the litigation before it, i.e. from the date of the award to the date of th_e decree. It may be doubtful whether this can be done in cases arising before the Interest Act, 1978 in view of the restricted scope of section 29 of the Arbitration Act. l328D-E] 5. The interest awarded by the arbitrator for the period from August 22, 1984 till the date of award is deleted; and the interest on A B c the principal sum is confined to 9% from August 6, 1981 till August 21, 1984. However, exercising powers under section 3 of tl;le Interest Act, 1978 and section 29 of the Arbitration Act, 1940, the Court directed that the principal sum or unpaid part thereof should carry interest at D the same rate from the date of the award (July 19, 1985) till the date of actual payment. l329A-B] · ~ CIVIL APPELLATE JURISDICTION: Civil Appeal No. 418, 19of1989. From the Judgment and Order dated 29.4.1988 of the Gujarat High Court.in F.A. Nos. 848-849 of 1986. V.B. Patel, D. Patel, T.H Pandey and R.P. Kapur for the Appellant. Soli _];_ Sorabjee, Atul Setalwad, N.J. Mehta, P. Shah, S.K. Sharma, S. Sharma and P.H. Parekh for the Respondents. The Judgment of the Court was delivered by E F SABY ASACHI MUKHARJI, J. This is an application for leave G to appeal under Article 136 of the Constitution from the judgment and order of the High Court of Gujarat dated 29th April, 1988. To appreciate the questions involved herein, few facts have to be emphasized. In 1978, the State Government of Gujarat undertook a scheme known as 'Bhavnagar City Water Supply Scheme'. The H 322 SUPREME COURT REPORTS [1989] 1 S.C.R. A Scheme was divided into two parts: (i) Raising Main; and (ii) Gravity Main. Raising Main was divided into two sections, namely, 10.1 k.ms. and 7.4 k.ms. steel welded pipeline. On or about 15/16th December, 1978, the State Government issued letter of approval to the bargain between the parties on certain terms. B On 12th January, 1979, two contracts were awarded to the respondent No. 1 for Rs.1,29,39,691 and Rs.94,30,435 which provided the dates of completion as February 1979 and the 3rd week of September, 1980 respectively. On 29th March, 1981 the respondent No. 1 filed the Civil Suit No. 588 of 1981 in the City Civil Court with regard to measurements recorded by the Deputy Engineer and alleged underpayments. On 4th June, 1981, the respondent No. 1 gave notice c to the State Government and the petitioner-Board requesting for reference of the alleged disputes to the arbitrator under clause 30 of the agreement. On or about 8th July, 1981 the respondent No. 1 gave notice under Section 8 of the Arbitration Act, 1940 (hereinafter called 'the Act') calling upon the petitioner to concur in the appointment of D one Shri G.G. Vaidhya. On 21st July, 1981, he withdrew the Civil Suit No. 588 of 1981. On 6th August, 1981, the respondent No. 1 filed Civil Miscellaneous Application No. 231of1981 in the Court of Civil Judge, (SD), Ahmedabad for appointment of the said Shri G.G. Vaidhya as the sole arbitrator. On 7th November 1981, the petitioner filed reply B c E F G ###### · contesting the arbitrability of the various claims made in the applica' tion and _inter alia_ contending that the application was not maintainable. On or about 15th December, 1981 the learned Civil Judge appointed Shri G.G. Vaidhya as the sole arbitrator with a direction that he should first decide as to which disputes fell within the purview of clause 30 of the agreement. On 5th May, 1982, Shri Vaidhya gave an interim award holding that the claims at S. Nos. lO(g) and 10(1) only were not arbitrable and further that the other claims were arbitrable. A petition was filed in High Court which was dismissed and then there was an application to this Court under Article 136 of the Constitution which was disposed of by consent on 30th November, 1983. The said order _inter alia_ provided that the parties had agreed to settle the matter amicably and one Shri Mohanbhai D. Patel, Retired Secretary, Public Works Department, Gujarat and at that time Sitting Member of the petitioner-Board was appointed as the sole arbitrator in place of Shri V aidhya to decide all disputes between the parties relating to the following works: "i) providing, fabricating, laying and jointing 1000 mm dia. 10,000 M long steel welded pipe line under Bhavnagar .. GUJARATWAIBRSUPPLYBOARD _v._ UNIQUE ERECTORS [MUKHARJI, J.] 323 Emergency Water Supply Scheme based on · Shetrunji A Dam-Agreement No. 5/2-1 of 1978-79. ii) providing, fabricating laying and jointing 1000 mm dia 7,400 M long steel welded pipe line under Bhavnagar Emergency Water Supply Scheme based on Shetrunji Dam Agreement No. B-2/2of 1978-79." B It was further provided that all disputes concerning the said two works in question should be referred to the sole arbitrator and the Board could also be entitled to put counter-claims before him. The consent terms also provided the following terms: c "That the arbitration proceedings shall be started de novo meaning thereby that the earlier appointment and proceedings before the Sole Arbitrator Shir G.G. Vaidhya shall be inoperative and void. That the Board shall have a right to agitate all points both D in fact and in law before the Sole Arbitrator as per the terms and conditions of the contract including the question of arbitrability within the meaning of clausse 30 of the contract. Both parties shall have a right to be representi;d by an E Advocate and/or their representatives . The expenses of arbitration shall be borne by both the parties as per rules of Government in this behalf. That both parties shall agree to extend time as and when necessary for completition of arbitration proceedings. F That a formal agreement for arbitration shall be executed betwe.en.the parties defining the scope of Arbitration. That the provisions of the Indian Arbitration Act, 1940 shall apply to the proceedings before this Sole Arbitrator." G -~ On 31st March, 1984, Shri M.D. Patel was appointed as the sole arbitrator jointly by the parties, and on 2nd April, 1984 he accepted his appointment and directed the parties to file their claim statments within 15 days. Thereafter, the respondent No. 1 filed claim to the tune of Rs.4,92,20,683 and a counter-claim to the extent of H 324 SUPREME COURT REPORTS 11989] 1 S.C.R. A Rs.26,87,217.40. On 22nd August, 1984 the parties appeared before the arbitrator after filing of claims and counter-claims. On 1st October, 1984 the petitioner filed an application before the arbitrator praying that preliminary issues be raised and decided first as to which of the disputes were arbitrable under clause 30 cif the B agreement. On 8th July, 1985, a lumpsum award was made by the arbitrator, and on 19th July, 1985 the parties were informed about the signing of the award. On the same day the award filed by the respondent No. l's Advocate which was dated 8. 7 .1985 was registered as Civil Miscellaneous Application No. 144/85. Thereafter, notice was issued on the same day and served on the petitioner also on the same day. The petitioner filed objections to the award and the Objection C Petition was registered as Civil .Miscellaneous Application No. 158/85. Reply to the objections was filed by the respondent No. 1. On 17th June, 1986, however, the learned Civil Judge directed that decree be passed in terms of the award. Two appeals were filed by the petitioner. On the 29th April, 1988 the High Court by a judgment dismissed the D petition challenging the award and upheld the award. Aggrieved thereby, the petitioner has moved this Court as mentioned hereinbefore. ~· I ' .. Various grounds were urged in support of this application. It was contended, firstly, that there was an error apparent on the face of the E award and that the award was bad. It was submitted that the arbitrator had committed an error of law in not deciding or disclosing his mind about the arbitrability of claims or counter-claims, more so when the Board's application for deciding the same, was pending before the arbitrator. Before the learned Trial Judge the Board had submitted an application to the arbitrator seeking to raise a preliminary issue p regarding arbitrability of the claims. As noted by the learned Trial Judge, it appears that the third meeting specifically mentioned that the claims were placed before the arbitrator and their contentions about the arbitrability were considered. So, these issues were gone into and it appears that the parties had agreed and proceeded on the basis that the claims may be examined and it was not necessary to decide preissue of arbitrability and it was agreed that all the claims be decided # ~b claimwise. So, it cannot be said that the arbitrator had acted arbitrarily in discussing all the questions raised before him without first deciding the question of arbitrability or non-arbitrability of an issue as such. ## ~ The Court in its judgment has discussed the conduct of the H parties. It appears that the Court found that the parties themselves had -. '.J. ·.· . ' GUJARAT WATER SUPPLY BOARD _v._ UNIQUE ERECTORS IMUKHARJI;J.J 325 -----+ agreed that the arbitrator should decide claimwise and on merit. The A Court so found, and in or opinion, rightly. The arbitrator so.:proceeded. There was no error committed by the arbitrator in so oonducting himself. It was, secondlj.:, contended that out of the numerous claims before the arbitrator, some of which, according to the petitioner, were _ex facie_ not arbitrable and some were withdrawn including the claims B - ~ for interest of Rs.54,61,073 and compound interest of Rs.82,26,039 ... and in the award no basis or indication was given as to which claim was rejected and further of the amount which was awarded·as claim and what amount towards element of interest. It was, thirdly, contended that there was an error apparent on the face of the award inasmuch as -~ the basis on which interest has been awarded has not been disclosed / and whether the interest has been awarded from the date of the institu- c ti on of the proceedings. It was, fourthly, contended that granting of - )le interest _pendente lite_ was contrary to the decision of this Court. It was, lastly, contended that non-speaking award ·had resulted in great prejudice inasmuch as against the claim of Rs. I lakh, Rs.57 lakhs have been awarded. _D_ -~ The scope and extent of examination by the Court of the award made by an arbitrator has been laid down in various decisions. It hasto ~ be noted that there is a trend in modem times that reasons should be stated in the award though the question whether the reasons are necessary in ordinary arbitration awards between the parties is pending E adjudication by the Constitution bench of this Court. Even, however, if it be held that it is obligatory for the arbitrator to state reasons, it is not obligatory to give any detailed judgment. An award of an arbitrator should be read reasonably as a whole to find out the implication and the meaning thereof. Short intelligible indications of the grounds should be discernible to find out the mind of the arbitrator for F ·his action even if it ·be en joined that in all cases of award· by any arbitrator reasons have to be stated. The reasons should not only be intelligible but should also deal either expressly or impliedly with the substantial points that have been railied. Even in a case where the arbitrator has to state reasons, the sufficiency of the reasons depends upon the facts and the circumstances of the case. The Court, however, G ### ~ does not sit in appeal o':'er the award and review the reasons. The Court can set aside the award only if it is apparent from the award that there - is no evidence to support the conclusion or if the award is based upon any legal proposition which is erroneous. See the observations 'Ot lhis Court in _1ndian_ _Oil Corporation_ _Ltd._ v. _1ndian Cat'bon_ _L'tii.;_ U'9'88l _3_ SCC36. H ~. 326 SUPREME COURT REPORTS I 1989] 1 S.C.R. In the instant case, the arbitrator by virtue of the terms A mentioned in the order of this Court had to decide which of the disputes were arbitrable and which were not. It is true that the arbitrator has not specifically stated in the award that he had to decide the question of arbitrability. The arbitrator has rested by stating that he had heard the parties on the point of arbitrability of the claim and the B counter-claim. He has further stated that after 'considering all the above aspects' and 'the question of arbitrability or non-arbitrability' he had made the award on certain aspects. Reading the award along with the preamble, it appears clear that the arbitrator had decided the arbitrability and the amount he has awarded was on the points which were arbitrable. The contention that the arbitrator had not decided the c question t\f arbitrability as a preliminary issue cannot also be sus tained. A reference to the arbitrator's proceedings which were discussed in detail by the High Court in the judgment under appeal reveal that the procedure adopted by the arbitrator, i.e., that he will finally decide the matters, indicated that the parties had agreed to and the arbitrator had proceeded with the consent of the parties in deciding D the issues before him and in not deciding the question of arbitrability as a separate, distinct and preliminary issue. The arbitrator has made his award bearing all the aspects including the question of arbitrability in mind. It was contended before us that the arbitrator has made a non-speaking award. It was obliged to make a speaking award, it was submitted by terms of the order of this Court. We cannot sustain this E submission because it is not obligatory as yet for the arbitrator to give reasons in his decision. The arbitrator, however, has in this case indicated his mind. It appears to us that the point that the non-speaking award is _per se_ bad was not agitated before the High Court. We come to that conclusion from the perusal of the judgment under appeal though, however, this point has not been taken in the appellant's p appeal. It is one thing to say that an award is unintelligible and is another to say that the award was bad because it was a non-speaking award. The point taken was that the award was unintelligible and not that it was non-speaking. But there was nothing unintelligible about the award. ##### + A B c G We were invited to refer the matter to the Constitution Bench and await the disposal of this point by the Constitution Bench. The contract in this case was entered into in 1978. The proceedings for initiation of arbitration started in 1981. The matter had come up to this Court before which resulted in the order dated 30th November, 1983. Pursuant thereto, the award has been made and no grounds specifiH cally were urged though they were taken in the appeal in the High GUJARATWATERSUPPl'.YBOARDv. UNIQUEERECTORSIMUKHARJJ,J.1327 A B c D E F G A. Court in the arguments before the High Court about the award being \Jad because it is non-speaking. In those circumstances, it will not be in conson:mce with justice for us to refer the matter to the Constitution B.e.i:wh or to i\Wait the disposal of the point by the Constitution Benc!t· It was further submitted before us that the award was unreasonable <111ci thilt the arbitrator had awarded a large amount to money but the otjgi.11al cl11im W\IS not so large and as such the award was dispropoi,1io11ate. Th.is contention, as it is, it appears from the judgment of the High Court, was not urged and canvassed before the High Court. The claim and the counter-claim together in its totality, in our opinion, qoes no( make the award amount disproportionate. Reasonableness as Sl\Cll of an award unless the award is _per se_ preposterous or absurd is not <!. w.a.Her for the court to consider. Appraisement of evidence by the axl;l~(rator is ordim1rily not a matter for the court. It is difficult to give a.!\ e.l\\l.cJ <.l.efi11i(ion of the word 'reasonable'. Reason varies in its con el\\~ol).S a,cc<mling to tile idiosyncrasy of the individual and the times •rnd. U•e tjrcumstances in which he thinks. The word 'reasonable' has in law _prima facie_ meaning of reasonable in regard to those circums.tances of whi.ch the actor, called upon to act reasonably, knows or ought to kn.ow. See the observations on this point in _Municipal_ _C'!rp.Qrqtio!J. of /)efhi_ v. _Mis. ]agan Nath Ashok Kumar_ & _Anr.,_ [19871 4: ~CC 497. J,u.<\ge.d l;Jy the aforesaid yardstick the award cannot be C<?Ad.e.w.11.ie<Ji a.s u.1:i.rea.s.011a.b\e. Tu.ere. i,s, l;\o.we.ver, 9ne infirmity in the award which is apparent _9P._ t\I.e. f(lce. o~ tti.e a.wa.rcl which in ttie interest of justice as the law now stands decla.red by t\:\(s Court, we should correct, viz., the question of interest _pendente lite._ The right to get interest without the intervention of the Court and th.e powers of the court to grant interest on judgment have been examined by this Court in _Executive Engineer (Irrigation)_ _Balimela and Ors._ v. _Abhaduta Jena_ & _Ors.,_ [19881 1SCC418 which observations were also followed by this Court in _State of Orissa_ & _Ors._ v. _Construction India,_ [1987] Supp. SCC 709. In accordance with t.he principles stated therein and the facts in this case, it appears that the principal amount awarded is Rs.57,65,273. This is confirmed. In this case, 2nd April, 1984 is the date of the reference to arbitration, on 22nd August, 1984 the arbitrator entered upon the reference. 8th July, 1985 is the date of the award and 19th July, 1985, is the date of the pQblication of the award. The w.terest "a.wru:ded, ii;t. th.e W.tant case, covers three. ~~~.: ~\) 6~1'1, ..,\\l~l!.St,, 19,8J t.o 21st Aug11,st, 1984 pripr to. \l;i,e l'QJ,W;l.l,e.\\~W.e\\\ \l~ tl;i,4< Wi\J~~~\l.t\oQ, I?Wceed~ngs; (\i) ;!21\d .(\~~~~. 11!&'1. to. \~ll ~·· Ii A 328 SUPREME COURT REPORTS [1989) 1 S.C.R. 1985 _pendente lite;_ and (iii) 19th July, 1985 to 17th June, 1986 (date of award to date of decree). Having regard to the position in law emerging from the decision of this Court in _Executive Engineer (Irrigation) Balime/a_ _&_ _Ors._ (supra) and section 29 of the Arbitration Act, 1940 and section 34 of B the Code of Civil Procedure, we would modify the grant of interest in this case. The arbitrator has directed interest to be paid at 17% per annum from 6.8.1981 upto the date of decree viz., 17.6.1986. Since in this case the reference to arbitration was made after the commencement of the Interest Act, 1978, the arbitrator under section 3(1)(a) of the said Act was entitled to award interest from 6.8.1981 till 21.8.1984 C in view of this Court's decision in _Abhaduta Jena's_ case (supra). In the light of the same decision, he could not have awarded.interest for the period from 22.8.1984 till the date of the publication of the award viz. 19. 7.1985. So far as interest for the period from the date of the award (19.7.1985) till the date of the decree is concerned, the question was B not specifically considered in _Abhaduta Jena's_ case (supra) but special 0 leave had be.:n refused against the order in so far as it allowed interest for this period. We think interest should be allowed for this period, on the principle that this Court can, once proceedings under sections 15 to 17 are initiated, grant interest pending the litigation before it, i.e., from the date of the award to the date of the decree. It may be doubtE ful whether this can be done in cases arising before the Interest Act, 1978 in view of the restricted scope of section 29 of the Arbitration Act. But there can be no doubt about the court's power to grant this interest in cases governed by the Interest Act, 1978 as section 3(l)(a) which was applied by _Ahhadwa Jena_ to arbitrators will equally apply to enable this Court to do this in these proceedings. F In this connection, it is necessary to consider whether the date of commencement of the arbitration proceedings should be taken as the date of the reference or the date on which the arbitrator entered upon the reference as the date of the calculation of interest. In this case, the proceedings commenced on 2nd April, 1984 and the arbitrator entered G upon the reference on 22nd August, 1984. Having regard to the facts **and** **the circumstances** **of the case,** **it** **is** **necessary,** **in** **our opinion, to** take 22nd August, 1984 as the date. It is also necessary to consider whether the date of award should be taken as the date of its making or its publication. The award was made on 8th July, 1985 and it was published on 19th July, 1985, and, therefore, the latter date would be H taken as the date of the award. ·,4, .'x GUJARAT WATER SUPPLY BOARD _v._ UNIQUE ERECTORS [MUKHARJJ,J.[ 329 We would, however, delete the interest awarded by the arbi- A trator for the period from 22.8.1984 till the date of the award and confine the interest on the principal sum of Rs.57,65,273 to interest at 9 per cent from 6.8.1981till21.8.1984 (which has been worked out at Rs.29,82,443). However, in exercise of our powers under section 3 of the Interest Act, 1978 and section 29 of the Arbitration Act, 1940, we B direct that the above principal sum or the unpaid part thereof should carry interest at the same rate from the date of the award ( 19. 7 .1985) till the date of actual payment. The appeals are disposed of in the above terms. N.V.K. Appeals disposed of. C
End of Judgment Record
Browse All Supreme Court of India (1989) Decisions
1989-12-22

LAXMI NARAYAN NAYAK v. RAMRATAN CHATURVEDI AND ORS.

This appeal concerns an election petition challenging the Madhya Pradesh Vidhan Sabha election from Niwadi constituency (No. 34) held in early 1985. The appellant, Laxmi Narayan Nayak, alleged that the first respondent, Ramratan Chaturvedi, engaged in corrupt practices under Sections 123(2), 123(3) and 123(3A) of the Representation of the People Act, 1951. The Madhya Pradesh High Court dismissed the petition for lack of substantiation, and Nayak challenged that decision in this Supreme Court appeal. The Court concentrates on three issues: (i) whether the nomination paper of Pratap Singh (11th respondent) was improperly rejected; (ii) whether the respondent held a meeting on 28 February 1985 at Niwadi and promised a silver shield to electors, constituting corrupt practice under Section 123(1); and (iii) whether government servants and a police officer accompanied the respondent to persuade electors and whether money was distributed. The Court reiterates that election petitions are quasi-criminal and require strict proof, including a clear element of bargaining in bribery, with reliability and corroboration of oral evidence. It critically analyzes the evidence: the nomination issue is resolved in the petitioner's favour by the High Court’s reasoning, while the alleged bribery and use of government officers fail due to inconsistencies and lack of corroboration. Ultimately, the Supreme Court upholds the High Court’s decision and dismisses the appeal with costs.

1989-09-19

Aphali Pharmaceuticals Ltd. v. State of Maharashtra & Ors.

Aphali Pharmaceuticals Ltd., an Ayurvedic medicine manufacturer, challenged excise-duty liability on the product Ashvagandharist, which contains self-generated alcohol but is not a beverage. Initially treated as exempt under item 2(i) of the 1955 Act’s Schedule (renumbered as item 3(i) after the 1961 Amendment) because it was an Ayurvedic preparation containing self-generated alcohol not capable of being consumed as an ordinary alcoholic beverage. The 1962 Finance Act introduced Explanation I to the Schedule, defining “patent and proprietary” medicines by reference to the Drugs Act, 1940, with retrospective effect. A Maharashtra circular (31 May 1962) directed treating such preparations as falling under item 1 (patent or proprietary medicines) rather than item 3, and excise duties were subsequently levied and paid under protest. The appellant filed suit; the Civil Judge decreed in its favor, the High Court reversed, and this Court allowed the appeal. The Court held that Explanation I did not amend or override the Schedule’s categories, and the circular could not override the enactment; the Schedule and the Act, read with the Rules (Rules 64-66) and the Drugs Act, determine taxability. The Supreme Court restored the Civil Judge’s decree, holding the appellant was not liable under the amended schedule as interpreted. The parties were to bear their own costs.

1989-07-13

Sundarjas Kanyalal BhatiJa & Ors. v. Collector, Thane, Maharashtra & Ors.

This matter concerns judicial review of Government action under Section 3 of the Bombay Provincial Municipal Corporations Act, 1949, in the context of proposing the formation of the Kalyan Municipal Corporation by merging Kalyan, Ambarnath, Domoivali, and Ulhasnagar. Objections poured in, including from Ulhasnagar’s Sindhi community which sought to preserve its identity via the All India Sindhi Panchayat Federation. The Government undertook a draft notification under Section 3(3) and later issued a final notification excluding Ulhasnagar under Section 3(2). The Bombay High Court held that excluding Ulhasnagar while keeping contiguous areas in the proposed Corporation was arbitrary and irrational, and it directed the Government to reconsider the proposal under Section 3(3), inviting hearing for petitioners and Federation. The appellants contended that the formation of a corporation is a legislative function, thus subject to no general rules of natural justice, and that the State had complied with statutory requirements. The Supreme Court, in a Division Bench, reversed the High Court, emphasizing that judicial review aims at predictability and certainty of law, and that the procedure for forming a Corporation under Section 3 is a legislative act not bound by ordinary hearing requirements unless expressly prescribed. It criticized the High Court’s approach and held that the Government’s action was within the scheme of law, while affirming the need for proper procedure and respecting the decorum of judicial process.

1989-08-08

ATUL MATHUR v. ATUL KALRA

This appeal from the Bombay criminal proceedings concerns Section 630 of the Companies Act, where a company sought to recover possession of a flat occupied by a former employee after resignation. The leave-and-licence agreement for the flat was executed on behalf of Jenson and Nicholson (India) Ltd by the first respondent, who served as Divisional Sales Manager, under a power of attorney. The first respondent filed a civil suit asserting he was the licencee, while the company paid deposits and continued to pay licence fees. After resignation, the respondent did not vacate, was convicted under Section 630 by the Additional Chief Metropolitan Magistrate, and the conviction was upheld by the Sessions Court. The Bombay High Court, via Article 227 converted to Section 482 Cr.P.C., reversed the judgments, holding that two letters by a junior employee, Exs. 3 and 4, and the existence of a civil suit created a bona fide dispute that should be resolved in civil court rather than a criminal proceeding. The Supreme Court allowed the appeal, holding that Section 630 aims to provide speedy relief to the company, that the complaint was properly filed, and that the two letters did not establish a bona fide dispute. The Court restored the lower court judgments and granted the respondent time to vacate.