Gujarat Urja Vikas Nigam Limited v. Green Infra Corporate Wind Private Limited and Others
Case Synopsis & Summary
This is a Supreme Court judgment on tariff determination for wind energy projects in Gujarat under the Electricity Act, 2003. Gujarat Urja Vikas Nigam Limited (GUVNL) challenges four GERC tariff orders that followed the APTEL’s confirmation of earlier orders. The core issue is whether the four respondent wind projects, which did not avail accelerated depreciation (AD) under the Income Tax Act, were entitled to tariff fixation on a case-by-case basis, or were bound by a static tariff fixed in PPAs entered during the control period. The First Tariff Order (Order No. 1 of 2010) had established a levelized tariff of ₹3.56/kWh for AD-availed projects; those not availing AD could petition for separate tariffs. GUVNL contends that the 3.56 tariff applies to all wind projects in the PPAs and that shifting tariff post-signature would undermine certainty and the PPA’s terms. The respondents argue their PPAs were conditioned on tariffs applicable to non-AD projects, and they should be permitted to seek case-by-case tariffs for the project life. The Court discusses the statutory framework, the policy objectives encouraging renewable energy, and the ratio of Tarini Infrastructure to allow tariff redetermination in appropriate circumstances. It ultimately holds that the petitioners’ appeals lack merit, reinforcing tariff flexibility and policy alignment with renewables, and dismissing the appeals.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Sanjay Kumar
- Satish Chandra Sharma
- Judgment Date
- 2025-08-04
- Court Decision / Holding
- The appeals are bereft of merit and are, accordingly, dismissed. Order dated 03.02.2023 shall stand vacated. Pending applications, if any, shall also stand dismissed.
- Final Disposition
- Dismissed
Parties to the Case
Appellants / Petitioners
- Gujarat Urja Vikas Nigam Limited
Respondents
- Green Infra Corporate Wind Private Limited, New Delhi
- Vaayu (India) Power Corporation Private Limited, Daman
- Green Infra Wind Power Limited, New Delhi
- Tadas Wind Energy Private Limited, Mumbai
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
Gujarat Urja Vikas Nigam Limited (GUVNL) argued that the tariff payable to wind energy projects was fixed by the GERC under Order No. 1 of 2010 at ₹3.56 per kWh only for those projects that availed accelerated depreciation (AD) under the Income Tax Act, 1961. It contended that projects not availing AD should be determined on a case-by-case basis, and that the PPAs signed with a fixed tariff could not bind non-AD projects to the same rate for the entire 25-year life. GUVNL stressed that renewable-energy policy objectives and state policy, includingWind Power Policies, mandate flexibility in tariff to reflect changes in economics and policy. It relied on the reasoning in EMCO Limited to argue a broader entitlement to tariff review, but relied on Tarini Infrastructure Ltd. to emphasize that tariff review is possible post-PPAs when public policy and statutory provisions justify recalibration. GUVNL urged the Court to uphold a uniform tariff by enforcing the PPA-based rate irrespective of AD status, thereby maintaining consistency with contractual certainty and the statutory regime.
Contentions of Respondents
Green Infra and the other wind-energy producers submitted that the PPAs they signed with GUVNL fixed tariffs applicable to projects that had not availed AD. Since they did not claim AD, they could seek tariff determinations on a case-by-case basis before the GERC, reflecting project-specific economics. They argued that the first tariff order’s ₹3.56 rate was applicable only to AD-availed projects and that the GERC has the statutory power to redetermine tariffs in light of policy objectives, economics, and changed circumstances. They invoked Tarini Infrastructure Ltd. to support redeterminatory power post-PPAs and highlighted Gujarat wind-policy schemes and GEDA approvals to show state support for non-AD wind generation. They contended that enforcing a fixed rate from PPAs would contravene statutory tariff fixation and policy directions promoting renewable energy, fairness, and flexibility to reflect actual costs.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Gujarat Urja Vikas Nigam Limited v. EMCO Limited and another | 2016 (11) SCC 182 | Partly Overruled / Limited | Tarini Infrastructure (supra) distinguished the EMCO decision on facts; EMCO's ratio is not controlling in the present context. |
| Gujarat Urja Vikas Nigam Limited v. Tarini Infrastructure Limited and others | 2016 (8) SCC 743 | Positive | Tarini confirms the power of the GERC to redetermine tariff post-PPAs when necessary and endorses the flexibility of tariff fixation. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Gujarat Urja Vikas Nigam Limited v. Green Infra Corporate Wind Private Limited and Others
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.